BNL - FNAL - LBNL - SLAC Progress Report on LQ Program Giorgio Ambrosio Fermilab Task Leaders: Fred...
-
Upload
timothy-gibbs -
Category
Documents
-
view
214 -
download
0
Transcript of BNL - FNAL - LBNL - SLAC Progress Report on LQ Program Giorgio Ambrosio Fermilab Task Leaders: Fred...
BNL - FNAL - LBNL - SLAC
Progress Report on LQ Program Giorgio Ambrosio
Fermilab
Task Leaders:Fred Nobrega (FNAL) – CoilsJesse Schmalzle (BNL) – CoilsPaolo Ferracin (LBNL) – StructureHelene Felice (LBNL) – Instrumentation and QPGuram Chlachidize (FNAL) – Test prep. and test
LARP Collaboration Meeting 13 Port JeffersonNov. 4-6, 2009
2005 The birth of the LQ
…
…
Some years ago … just before CM 4 …
LARP CM13 – BNL – Nov. 4-6, 2009 G. Ambrosio - Long Quadrupole
We need a successful Long Quadrupole by
the end of 2009April 2, 2005April 2, 2005
We need a successful Long Quadrupole by
the end of 2010
G. Ambrosio - Long Quadrupole 3
Long Quadrupole
Main Features:
• Aperture: 90 mm
• magnet length: 3.7 m
Target:
• Gradient: 200+ T/m
Goal:
• Demonstrate Nb3Sn magnet scale up:– Long shell-type coils
– Long shell-based structure (bladder & keys)
1st Long Quad test by the end of 2009
2nd Long Quad test in mid 2010
LQ Design Report available online at:https://plone4.fnal.gov/P1/USLARP/MagnetRD/longquad/LQ_DR.pdf
LQS01 SSL 4.3 K
Current 13.9 kA
Gradient 242 T/m
Peak Field 12.4 T
Stored Energy 473 kJ/m
LQ in LARP R&D
“S”: Shell-based support structure
“C”: Collar-based support structure
LARP CM13 – BNL – Nov. 4-6, 2009 G. Ambrosio - Long Quadrupole
Long MirrorLM023.6 m longNo bore
FNAL Core progr.
From TQS & LRS to LQS
• LQS is based on TQS
and LRS
TQS Modifications:– Added masters
– Added tie-rods for yoke & pad laminations
– Added alignment features for the structure
– Rods closer to coils
– Rods made of SS
– Segmented shell (4)
LQS with dummy Al coils
LQSD: – LQS assembled with Al coils (LBNL)– Shipped, lifted, tilted (LBNL & FNAL)– Tested at liquid nitrogen (FNAL)
6
LQSD cool down
ΔT=150 KΔT=50 K
Magnet top
Magnet bottom
LQ Coil Design & Fabrication
• Fabrication technology:– From 2-in-1 (TQ coils) to single coil fixtures (LQ)
– Mica during heat treatment
– Bridge between lead-end saddle and pole
• Coil design:– LQ coils = long TQ02 coils with gaps to
accommodate different CTE during HT
Cross-section of TQ/LQ coil
250 mceramicandbindersheet
titanium outer pole
titanium inner pole
250 m ceramic and binder sheet
500 m
250 m
250 m
125 mmica sheet
125 mmica sheet
125 m micasheet
Lead End Return End
1 2 3 4 5 6 7 8 9 10
LQ Coils Handling & Shipment
• New tooling for long coil handling and shipment– Handling: strain < 0.05%
– Shipment on rigid mandrel in shipping fixture w shock absorbers (BNL)
Shipping fixture with shock absorbers
Long Quadrupole Overview – G. Ambrosio 9LARP Collab. Mtg 10 – Port Jefferson, Apr. 23-25, 2008
Quench Protection
• Goal: – MIITs < 7.5 Temp ~ 380 K (adiabatic approx)
• Quench protection param. (4.5 K) – conservative hypothesis– Dump resistance: 60 m(extract ~1/3 of the energy; Vleads ~ 800 V)
– 100% heater coverage ( heaters also on the inner layer)
– Detection time: ~5 ms based on TQs with I > 80% ssl
– Heater delay time: 12 ms based on TQs with I > 80% ssl
Very challenging!J in copper = 2900 A/mm2
at 13.9 kA (4.3 K SSL)
Instrumentation
• Voltage taps: 13 IL + 7 OL• Two protection heaters on each layer
– Large ss strip with narrow heating areas• Successfully tested on Long Racetrack
– “Bubbles” may cause coil-heater shorts test at 4.5, and 3.0 K (1.9K at the end)
• Coil strain gauges: 4 IL– Gauges instrumented with wires
• Structure strain gauges:– Shell: 10 (two full bridges each)
– Rods: 4 (two half bridges each)Test at LN of Protection HeatersLARP CM13 – BNL – Nov. 4-6, 2009 G. Ambrosio - Long Quadrupole
G. Ambrosio - Long QuadrupoleDOE Review 09 - FNAL, July 13-14, 2009
Status Summary
• 5+ production coils are ready– Wind & cure (FNAL)– React. & Impr. (BNL & FNAL)– Instrumentation (all 3 labs)– Shipping fixtures (BNL)
• Shell-structure was tested LQSD& LQS01 was assembled (LBNL)
LQS01 ready for test (FNAL)
LQS01 Assembly
• LQS01 assembled and pre-loaded
Strain gauge readings:• on the structure (shell & rods) are on target
• on the coils are lower than expected with large scattering– Seen also in TQS models; partially caused by coil/pads sub-assembly
Should improve at cold G. Ambrosio - Long QuadrupoleLARP CM13 – BNL – Nov. 4-6, 2009
Comparison of measurements and targets
293 K y (MPa) z (MPa)
Shell measured +33 ±8 +3 ±7
Shell computed +34 +6
Pole measured -12 ±11 +14 ±17
Pole computed -49 -14
Rod measured n/a +60 ± 3
Rod computed n/a +63
G. Ambrosio - Long QuadrupoleLARP CM13 – BNL – Nov. 4-6, 2009
Test Preparation
• Quench Detection System with Adaptive Thresholds– To allow using low threshold at high current avoiding trips due to voltage
spikes at low current
– Both DQD and AQD
• Symmetric Coil Grounding– To reduce peak coil-ground voltage
• LQ needs larger dump resistance than TQ magnets (60 vs 30 mOhm)
• Reconfiguration of the Magnet Protection System– Additional Heater-Firing-Units for all LQ heaters (16)
• Modified Strain Gauge Readout System– To reduce noise and sampling time
J in copper = 2900 A/mm2
at 13.9 kA (4.3 K SSL)
All new systems tested all together two weeks ago Upgrades passed LQS01 Test Readiness Review
LQS01 Status
• LQS01 is connected to the VMTF top-head
• Electrical check-out is in progress
• Cool down start: this weekend or early next week
LARP CM13 – BNL – Nov. 4-6, 2009
Test GOALS
• Achieve target gradient 200 T/m– Compare with TQ02-series
• Understand training– Compare with TQ02-series
• Understand if limitation is due to mechanics and/or coils– Understand if changing one coil could improve “significantly”
performance for next test
• Memory after thermal cycle• Understand behavior at 1.9K
• Inner Layer “bubbles” could cause coil-heater shorts!
• Could reduce the number of usable protection heaters
LARP CM13 – BNL – Nov. 4-6, 2009 G. Ambrosio - Long Quadrupole
Present LQ FY10 plan
Notes:– Coils #14 & #15 start after LQS01 feedback
– Coil #13 delayed because of HQ coils priority
• Plan for success with budget = $1.4 M– Need contingency money in case of “problems”
LARP CM13 – BNL – Nov. 4-6, 2009 G. Ambrosio - Long Quadrupole
LQS01 Test Scenarios
1. Successful (G >= 200 T/m)
2. Limited (G < 200 T/m) by one or two coils
3. There is a flaw in all LQ coils design and/or fabrication technology
4. All coils are damaged during cooldown or testmechanics or quench protection failure, excessive pre-load, …
G. Ambrosio – Long Quadrupole 17
LQS02 (4 new coils) or LQS01b (1 or 2 new coils)
LQS01b (1 or 2 new coils), may need 3rd test
Need analysis to understand cause of limitationMay need 4 new coils (2 out of contingency)Need LQS02 and 3rd test
LARP CM13 – BNL – Nov. 4-6, 2009
G. Ambrosio - Long QuadrupoleLARP CM13 – BNL – Nov. 4-6, 2009
Conclusions
• The test of the first Nb3Sn Long Quadrupole (LQS01) is starting
• We planned the test in order to obtain as much information as possible
• The present LQ FY10 plan is based on success– May need to use contingency in case of limited
performance
Addendum
LQS01 Test Plan - I
Room temperature preparation and cool down (10 days)• Magnetic measurements (z-scan) at VMTF
1st Thermal Cycle (10 days)Test at 4.5 K
• Cold electrical checkout• Magnetic measurements• Quench training• Ramp rate study
Cool down to 3 K• Quench Training• Magnetic measurements• Ramp rate study• Temperature dependence study
Warm up to 4.5 K• Verify quench plateau at 4.5 K
LQS01 Test Plan - II
Warm up to 300 K before 2nd thermal cycle (4 days)• RRR measurements
Cool down (4 days) 2nd Cold Test (10 days)
Test at 4.5 K• Quench training Memory
Cool down to 1.9 K• Verify operation of protection heaters
– To avoid possible damage after first few quenches we will do hi-pot (coil-heaters) and low current trips to verify proper operation of heaters
• Quench Training• Magnetic measurements• Ramp rate study• Temperature dependence study
LQS01 Test Plan - III
Warm up to 4.5 K• Verify quench plateau
• Protection heater study
• Spot heater study
Warm up to room temperature (6 days)• Magnetic measurements (z-scan, use warm-finger of full length)
LARP CM13 – BNL – Nov. 4-6, 2009
1.9K Test
• “Bubbles” are a possible cause for coil-heater shortsElectric arc?
Note: we never had heaters on inner layer
“Original” & Present plans
No 3rd generation
In FY08
In FY07-08,
No ceramic binder
2N + 1R
We had delays, some parts were skipped, but we want to keep the 2009 LQ goal “it can be done, but no without pain!”
Long Nb3Sn Coils R&D
• LARP Long Racetrack (4m coils)1st LR: 90% of ssl w single shell2nd LR: 96% of ssl w segmented shell
Coils: flat, no wedges, no tight constrain on coil cross-section during heat treatment First Long Racetrack
• FNAL Long Mirror (2-4m coil)1st LM (2m coil): ~ssl w PIT strands2nd LM (4m coil): 87%* w RRP
108/127 str.Coils: cos-, with wedges, and tight
constrain on coil cross-section during heat treatment
Front view of mirror magnet
* Using heaters on outer layer