BLUE WATER BRIDGE
PORT HURON, MICHIGAN
Blue Water Bridge Plaza and Corridor Project Update Meeting 2/8/13
![Page 2: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/2.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
Current Status • Recommended Alternative identified in 2009 Record of Decision
• Reduced plaza expansion announced in December 2010
• Completion of Phase I – Black River Bridge and freeway in 2012 • Start of Joint Master Plan and Operational Analysis with BWB
Canada – begins in spring of 2013
• Phase II - International Welcome Center - construction begins in 2014
![Page 3: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/3.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
Reduced Federal Plaza Proposal
![Page 4: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/4.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
4
Land Port of Entry Portfolio
4
122 46
LPOE Facility Ownership Total Traditional Funding Mechanisms
GSA-owned 102.5* 61% GSA’s Federal Buildings Fund or Special Appropriations
GSA-leased 22.5* 13% GSA’s Federal Buildings Fund or Special Appropriations
CBP-owned 41 25% DHS Appropriations or Special Appropriations
NPS-owned 2 1% Special Appropriations
Total Facilities 168
FY2006 CBP Strategic Resource Assessments: • Reviewed facility conditions, workload, personnel forecasts
• Analyzed each port’s capacity to support the mission
• Documented present and future facility problems/challenges, and provided recommendations to address them
• Identified a $6 billion need to recapitalize the LPOE portfolio
*Ownership of Ambassador Bridge split between GSA (commercial) and the Detroit International Bridge Company (non-commercial)
122 46
122 46
![Page 5: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/5.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
• Congress has not appropriated capital funds for LPOE modernization since FY2010
• No lease prospectus authority granted for GSA-leased LPOEs
• The gap between annual appropriations and resource needs continues to grow as unmet LPOE construction, sustainment, and technology costs rise
*FY09 funding inclusive of GSA & CBP ARRA appropriations
Federal Budgetary Constraints
![Page 6: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/6.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
• CBP currently has several unfunded capital projects in design and/or construction
along the northern and southwest border
• These projects require over $1Billion in capital funding
• Additionally, a substantial allocation needed to cover the associated costs below:
1. Rent – as tenant agency, CBP is responsible for the additional shell rent and included Operation & Maintenance (O&M) costs
2. Inspection Technology – includes equipment and technology necessary for CBP to conduct inspections and perform its mission (RPMs, LPRs, NII, etc.)
3. Outfitting Costs – expenses associated with procuring furniture, security, voice/data, computer workstations and other operational set up components
4. Staffing – costs of training and employing officers and administrative personnel
Federal Budgetary Constraints
![Page 7: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/7.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
New Inspection Booths
Three stacked booths opened in May 2012
Three staggered booths opened in July 2012
![Page 8: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/8.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
Joint Master Plan and Operational Analysis with BWB Canada
• Evaluate opportunities for
efficiencies and eliminate redundancies
• Identify operational improvements on Michigan plaza
• Traffic analysis • Starting in March 2013
![Page 9: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/9.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
New Port Huron International Welcome Center
• Design to begin in June 2013
• Construction to begin in summer 2014 and completed in 2015
• BWB Aesthetic Design Guide
![Page 10: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/10.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
New Port Huron International Welcome Center
Concept from ADG
Concept from environmental study
![Page 11: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/11.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
Harker Street Connector
Constructed in fall 2012 by MDOT
To be constructed in 2013
![Page 12: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/12.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
Project Mitigation Wayfinding Signs
• City of Port Huron • $100,000 federal
and state funding
• 2013 construction
![Page 13: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/13.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
Project Mitigation Other Items
• Tourism Kiosks • CVB, Chamber of Commerce, City of Port
Huron and St. Clair County • $300,000 federal and state funding
• City of Port Huron Master Plan • $50,000 federal and state funding
![Page 14: Blue Water Bridge Plaza and Corridor - Michigan · 2/8/2013 · PORT HURON, MICHIGAN Current Status • Recommended Alternative identified in 2009 Record of Decision • Reduced](https://reader034.fdocuments.us/reader034/viewer/2022050415/5f8b518e45e1533269166ed3/html5/thumbnails/14.jpg)
BLUE WATER BRIDGE
PORT HURON, MICHIGAN
Next Steps • Welcome Center
Design & Construction • Master Plan and
Operational Analysis with BWB Canada
Questions