Project Organizational Chart
Crux Subsurface(Grouting Sub)
City and Borough of Sitka(Owner)
McMillen, LLC(Construction Manager)
Barnard Construction(General Contractor)
ASRC McGraw(Powerhouse Sub)
Southeast Earthmovers(Excavation Sub)
Blue Lake Tunnelers(Tunneling Sub)
Schmolk(Mechanical Sub)
NAES(Electrical Sub)
Generation Outage
All work in the existing tunnel and new penstock must be completed during the generation outage when the tunnel will be sealed and dewatered.
The generation outage will be scheduled during August and September 2014 so that the new intake may be submerged to allow commissioning of the generation equipment.
Construction Schedule Milestones: Planned/Actual
Construction Start 11-20-2012 / 12-03-2012
Drainage Tunnel Complete 07-01-2013 / 05-05-2013
Tunnel ex. complete 08-19-2013 / 07-24-2013
Construct Powerhouse 08-24-2014/
Construct Dam 08-24-2014/
Ready for Generation Outage 08-24-2014/
Substantial Completion 02-01-2015/