Construction QC/QA Control Charts 1 Quality control/quality assurance Control Charts Senior/Graduate HMA Course

Transcript of Block 25 Control Charts 13

Page 1: Block 25   Control Charts 13

Construction QC/QA Control Charts 1

Quality control/quality assurance

Control Charts

Senior/GraduateHMA Course

Page 2: Block 25   Control Charts 13

Construction QC/QA Control Charts 2

Control

Charts

Page 3: Block 25   Control Charts 13

Construction QC/QA Control Charts 3

Variation

- Chance Causes- Assignable Causes

Page 4: Block 25   Control Charts 13

Construction QC/QA Control Charts 4

Chance Causes

1. Everything varies2. Individuals are unpredictable3. Groups from a constant system tend to be predictable

8-31

Page 5: Block 25   Control Charts 13

Construction QC/QA Control Charts 5

Example: Chance Causes

1. People live to different ages

2. No one knows how long he or she will live

3. Insurance companies can predict the percentage of people who will live to certain ages

Page 6: Block 25   Control Charts 13

Construction QC/QA Control Charts 6

Assignable Causes

If identified -

It can be eliminated

Page 7: Block 25   Control Charts 13

Construction QC/QA Control Charts 7

Benefits of Control Charts

- Early Detection of Trouble- Decrease Variability- Establish Process Capability- Reduce Price Adjustment Costs- Decrease Inspection Frequency

Page 8: Block 25   Control Charts 13

Construction QC/QA Control Charts 8

Benefits of Control Charts

• Basis for Altering Specification Limits

• Permanent Record of Quality

• Provide a Basis for Acceptance

• Instill Quality Awareness

Page 9: Block 25   Control Charts 13

Construction QC/QA Control Charts 9

Control Chart Analysis

AASHTO

“To Develop a Quality Control/Quality

Assurance Plan for Hot Mix Asphalt”

Page 10: Block 25   Control Charts 13

Construction QC/QA Control Charts 10

1 2 3 4 5 6 7Lot Number

Upper control limit

Lower control limit

Page 11: Block 25   Control Charts 13

Construction QC/QA Control Charts 11

Data Points

Statistical Control Chart

Upper Control Limit

Lower Control Limit

Target

Value

Page 12: Block 25   Control Charts 13

Construction QC/QA Control Charts 12

Five lines on a statistical process control chart

• Target value• Warning upper control limit• Warning lower control limit• Action upper control limit• Action lower control limit

Page 13: Block 25   Control Charts 13

Construction QC/QA Control Charts 13

Upper Control Limit

Lower Control Limit

Mean

1 2 3 4 5 6 7Lot Number

Page 14: Block 25   Control Charts 13

Construction QC/QA Control Charts 14

Statistical Control Charts

Upper and Lower Warning Control Limits

UWCL = X + { 2 (s) / (n)1/2 }

LWCL = X + { 2 (s) / (n)1/2 }

Page 15: Block 25   Control Charts 13

Construction QC/QA Control Charts 15

Statistical Control Charts

Upper and Lower Action Control Limits

UWCL = X + { 3 (s) / (n)1/2 }

LWCL = X + { 3 (s) / (n)1/2 }

Page 16: Block 25   Control Charts 13

Construction QC/QA Control Charts 16

Example Problem

• Given:– Target asphalt binder content: 5.7 %– Standard deviation – 0.25 %– The rolling average is based on five data

points

Page 17: Block 25   Control Charts 13

Construction QC/QA Control Charts 17

Example Problemwarning limits

UWCL = X + { 2 (s) / (n)1/2 }

UWCL = 5.7 + { 2 (.25) / (5)1/2 }

UWCL = 5.9

Page 18: Block 25   Control Charts 13

Construction QC/QA Control Charts 18

Example Problemwarning limits

LWCL = X - { 2 (s) / (n)1/2 }

LWCL = 5.7 - { 2 (.25) / (5)1/2 }

LWCL = 5.5

Page 19: Block 25   Control Charts 13

Construction QC/QA Control Charts 19

Example Problemwarning limits

UACL = X + { 3(s) / (n)1/2 }

UACL = 5.7 + { 3 (.25) / (5)1/2 }

UACL = 6.0

Page 20: Block 25   Control Charts 13

Construction QC/QA Control Charts 20

Example Problemwarning limits

LACL = X - { 3 (s) / (n)1/2 }

LACL = 5.7 - { 3 (.25) / (5)1/2 }

UWAL = 5.4

Page 21: Block 25   Control Charts 13

Construction QC/QA Control Charts 21

Look for Assignable Cause If:

• One point is outside of control limits

• Eight consecutive points are on one side of the target value

Page 22: Block 25   Control Charts 13

Interpreting

X & R

Charts

Page 23: Block 25   Control Charts 13

2

3

4

5

6

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

Action Limit (UCL)

Warning Limit

Action Limit (LCL)

Chart

Page 24: Block 25   Control Charts 13

0

1

2

3

4

5

6

7

8

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

(UCL)

(LCL)

Range (R) Chart

Page 25: Block 25   Control Charts 13

Control ChartsRules of Thumb

Lack of Control Occurs When:

Change in , R Constant

Change in R, Constant

Change in Both & R

X

X

X

Page 26: Block 25   Control Charts 13

Sustained Shift in

2

3

4

5

6

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

Action Limit

Warning Limit

Mean Increases

Page 27: Block 25   Control Charts 13

Trend in

2

3

4

5

6

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

Production "Upward Drift"

Action Limit

Warning Limit

Page 28: Block 25   Control Charts 13

Irregular Shift in

2

3

4

5

6

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

Action Limit (UCL)

Warning Limit

Action Limit (LCL)

Page 29: Block 25   Control Charts 13

Sudden Change in R

0

1

2

3

4

5

6

7

8

9

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

(UCL)

(LCL)

Page 30: Block 25   Control Charts 13

Gradual Change in R

0

1

2

3

4

5

6

7

8

9

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

(UCL)

(LCL)

Page 31: Block 25   Control Charts 13

Irregular Shift in & R

2

3

4

5

6

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

Action Limit (UCL)

Warning Limit

Action Limit (LCL)

Page 32: Block 25   Control Charts 13

2

3

4

5

6

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50

Sample Number

% A

ir V

oid

s

Eight Points Below Target

Single Point AboveAction LimitAction Limit

Warning Limit

Lack of Control?

Page 33: Block 25   Control Charts 13

Construction QC/QA Control Charts 33