M/R Fold
• Alignment of Swashplate– Line up yellow index
– Inbd T/R horizontal
(If The swashplate is not lined up you will not be able to put in the support pole )
T/R Fold• Remove 12 OTBD RET plate bolts• Remove balance washers
– Install both on star plate and hang as they came off
• Disconnect P/C rods at pitch beam& deice• Rotate • Pad
Struts
• Main– Hyd cart. – Lower stage only.– Record exposed strut. (eliminates servicing)– Raise cargo floor to 30 inches.
Struts
• Tail– Remove tail access panel.– Record exposed strut.– Lower until no silver showing.– If tail loaded first upper stage may need to be
lowered requiring complete servicing.
Tow plates
• Remove step fairing
• Install & torque bolts on tow plate
• 1 left & 1 right
• Rotate WSPS