BLACK BEAR LAKE HYDROELECTRIC PROJECT PENSTOCK SIPHON STUDY REPORT
Transcript of BLACK BEAR LAKE HYDROELECTRIC PROJECT PENSTOCK SIPHON STUDY REPORT
~ ENGINEERING COMPANY CONSULTING ENGINEERS
BLACK BEAR LAKE HYDROELECTRIC PROJECT
PENSTOCK SIPHON STUDY REPORT
150 SOUTH WACKER DRIVE CHICAGO. ILLINOIS 60606-4288
TEL [312) 855-7000 CA8LE HARZENG CHICAGO TELEX 25-3540
BLACK BEAR LAKE HYDROELECTRIC PROJECT
PENSTOCK SIPHON STUDY REPORT
1. SCOPE
This report describes a study of a siphon to draw water from Black Bear Lake for the proposed 3.0 MW hydroelectric
project. This siphon would be used instead of a dam, which
would have raised the lake level to provide storage, and an
intake for water withdrawals. The study includes an estimate of
the project construction cost with the siphon system. The
siphon and upper penstock in this study have been sized for a 3
MW hydro plant, the proposed first stage of a potential 6.0 MW
development of the resource. A profile of the proposed upper penstock for the siphon concept is shown on Exhibit 1. The size
of the vertical shaft and lower penstock remain as sized in
previous feasibility studies for a 6.0 MW project.
2. DESCRIPTION
2.1. The use of a siphon to draw water from a lower water
source is practical to a depth up to 25 feet. Theoretically,
sta.ndard atmospheric pressure (76 cm of mercury) could raise water to a height of 33.9 feet at sea level. At the altitude of
Black Bear Lake (EI. 1687 MLLW datum) atmospheric pressure
equals about 31.9 feet of water. However, siphons are consid
ered to be practical for no more than 75% of atmospheric pres
sure. The topography of Black Bear Lake and its outlet permits
the use of a siphon to provide the intake of water for a pen
stock to the hydro plant. This penstock, can be routed in
ground about 10 feet above the existing lake elevation, thus
providing the ability to draw the lake down about 15 feet. An
-1-
intake on the siphon penstock in the lake would be located about
5 feet below this minimum drawdown elevation to provide submer
gence to reduce vortex formation and to protect the intake from
damage or clogging by ice. This submergence would also allow a
small margin for error in plant operation to prevent a brake in
the siphon action in the event that operation of the turbine
continues beyond the minimum drawdown elevation. In the design
proposed~ if the siphon action does break, it would take over an
hour to reestablish the siphon.
2.2. The proposed siphon system would consist of the fol
lowing main equipment: two vacuum pumps, electric motor driven,
rated 450 cfm at 22 inches of mercury (equals 25 feet of water)~
vacuum tank1 a seal water supply pump~ and unit heaters for a
small building enclosing the vacuum pump equipment. Piping
would consist of the connections from the penstock to the vacuum
tank, from the tank to the vacuum pumps and. for seal water,
from the lake to the vacuum pumpso Power for operation of the
siphon system equipment would be provided from the powerhouse
via an interconnection line as described in the Feasibility
Report Update 0
2.3. The proposed siphon system would be designed to
start the siphon action at any lake level down to the lowest
designed drawdown level. The vacuum tank and pumps would be
located on the high point of the upper penstock approximately
360 feet downstream from the intake. This point would be about
50 feet downstream of the location of the dam axis shown in the
February 1987 Feasibility Report Update.
-2-
The operating procedure would be as follows:
1. To fill the penstock with water, the turbine
inlet valve and by-pass valve at the powerhouse
would be closed. An air inlet valve on the
vacuum tank would be closed. The intake valve at
the vacuum pump would be opened and the pump
started to evacuate air from the tank and pen
stock. After the penstock is filled with water,
the vacuum pump intake valve would be closed and
the turbine inlet or powerhouse by-pass valve
opened. With the turbine inlet valve open, the
turbine can be started and siphoning action would
commence.
2. To dewater the penstock, the turbine would be
shut-down and the by-pass valve opened. The air
inlet valve on the vacuum tank would be opened to
allow air to enter the penstock and water to
drain toward the powerhouse and through the by
pass. The upstream portion of the penstock would
drain to the lake. Opening the air inlet valve
will break the siphon and will shut-off flow in
the penstock which eliminates the need for an
intake gate or valve at the entrance of the pen
stock.
2.4. The proposed intake would consist of a cylindrical
trashrack formed by vertical steel bars supported by horizontal,
bars bent into rings, with a horizontal flat circular plate on
top of the cylinder serving as a velocity cap. The cylindrical
intake trashrack would be welded to a miter reducing bend of 90
degrees which would be welded to the steel penstock. The intake
-3-
would be located in Black Bear Lake where the natural water
depth is 30 feet. Soundings of the lake show this depth to be
about 182 feet from the lake shore near the lake's outlet creek.
The discharge required for 3.0 MW of generating capacity is 32
cfs (with net head of approximately 1,300 feet). To obtain an
approach velocity of one foot per second the size of the cylin
drical intake would be 3'-6" in diameter and 3 feet high. Sixty
3/8 inch thick vertical bars equally spaced on the circumference
of t.he supporting rings would result in openings of 1.824" wide.
The height of the intake with miter reducing bend would be 7
feet above the center line of penstock. With a minimum submer
gence of 5 feet the maximum drawdown of the lake would be about
15 feet below the present natural lake elevation. The natural
lake is at elevation 1687 and the penstock centerline at the
miter bend would be at approximately El. 1660. This would pro
vide a lake drawdown to El. 1672.
2.5. In the Feasibility Report Update of February 1987,
the water conduit system for the 6.0 MW alternative consisted of
the following:
a) An upper steel penstock of 48 inch diameter and about
325 feet long,
b) A vertical concrete lined shaft of 48 inch diameter about 1237 feet deep, and
c) A lower steel penstock of 30 inch diameter about 2,800
feet long.
The computed total head loss for this system is 106.84 feet for
64 cfs and 33.24 feet for 32 cfs. Replacing the dam (as shown
in the feasibility report update) with a siphon will increase
-4-
the upper penstock length by 310 feet~ The increase in length
consists of 128 feet from the dam axis location to the lake bank
and 182 feet from bank into lake at penstock intake. It is
proposed that the upper penstock for the 3.0 MW siphon alterna
tive be sized to have approximately the same total head loss as
the 6.0 MW alternative (at maximum plant discharge) but without
changing the shaft and lower penstock diameterso On this basis
the diameter of the nearest standard size pipe for the upper
penstock would be 20 inches. The head loss in the 20 inch 0.00
upper penstock j 48 inch 1.0. shaft and 30 inch 0.0. lower pen
stock for 32 cfs flow is estimated to be about 76 feeto At
minimum lake Elo 1672 the net head for the plant would be 1335
feet. For future expansion of the plant to 6.0 MW, the upper
penstock would be replaced by a larger pipe, but the shaft and
lower penstock would not require change.
2.6. Approximately 182 feet of pipe would be placed under
water at the upstream end of the upper penstock. It is proposed
that this pipe be protected by dumping rock fill underwater to a
one foot thickness over the top of the pipe. A layer of rip~rap
would be placed over the rockfill. This protection would pre
vent damage to the pipe by ice with lake drawdown and possible
erosion of pipe foundation by wave action in the vicinity of the
pipe. During project operation, the lake bed adjacent to the
pipe and its p~otective material should be inspected when the
lake is drawn down and rockfill/r ip-rap placed 'if necessary. In
the event of failure of the power supply or control lines from
the powerhouse to the siphon equipment, an emergency portable
generator could be flown by helicopter to the siphon site.
2.7. The total internal volume of the water conduit sys
tem, as proposed, equals 30,607 cubic feet. With the 450 CFM
-5-
vacuum pump capacity proposed, the time required to evacuate all
air in the conduit is 68 minutes.
2.8. Black Bear Lake has not been surveyed below its water
surface~ therefore, its water volume below the surface is not
known exactly. An estimate of its volume can be made by extra
polating the reservoir area/volume curves. Extrapolation from
natural surface at EIQ 1687 to EI. 1672 gives a volume of 2650
acre-feet. Since there is some uncertainty about the under
wate~ topography, it is recommended that a usable storage of
2000 acre-ft be assumed for the 15 feet of drawdown. Based on
reservoir operation studies performed for the 3.0 MW B.W.EL.
1595 alternative (2000 acre-feet of storage) the estimated 3.0
MW siphon intake alternative average annual energy generation
would be about 18,000 MWh.
2.9. The environmental impacts of this alternative include the following:
a) Shores not previously or naturally exposed will be
exposed.
b) Fish habit will be reduced when the lake is drawn down
during winter. There may also be a drawdown during
late summer in dry years.
c) Lake outflows, by way of the creek, will be eliminated
during drawdown.
d) The distance from the Forest Service cabin to the lake
shore will increase during winter and some late summer
periods.
-6-
3. COST ESTIMATE
Based on the cost estimate for the 3.0 MW H.W.EL. 1695 Stage I alternative presented in the Feasibility Report Update,
the construction cost of the project has been estimated for the
3.0 MW generating plant with the siphon system. This estimated
cost is for the complete power generating plant but without any transmission lines from its substation. The estimated transmis
sion line costs for several options of serving load demand cen
ters are shown in Table 1II-10 on page 1II-27 of the February
1987 Feasibility Report Update. The elimination of the dam and
its replacement by a siphon system, reduces the work required in
the vicinity of Black Bear Lake which reduces mobilization and
logistics costs.
for these changes.
contractor's indirect costs have been revised
The changes in quantities for construction
consist of elimination of all dam work, revision of upper pen
stock steel, excavation, backfill and bedding, underwater place
ment of pipe and its protection. Quantities for the vertical
shaft, lower penstock, powerhouse, access roads and substation
are unchanged. Costs have been estimated for the siphon system
equipment and a small building to protect this equipment. A
summary of the estimated construction cost is shown in the table
below. A detailed estimate is shown on Exhibit 2.
-7-
Item No.
SUMMARY OF COST ESTIMATE January 1986 Price Level
Description Estimated Cost
330 331 332 333 334 335 336 353
Land & Land Rights $ 73,000 630,000
7,499,000 641,000 584,000
57,000 560,000 196,000
1,100,000
Powers tat ion & Improvements Reservoir, Dams & Waterways TUrbine & Generator Accessory Electrical Equipment Miscellaneous Mechanical Equipment Access Road Substation Equipment & Structures Mobilization & Logistics
Subtotal Direct Cost Contingency Allowances Civil 15%
Equip. 10%
Total Direct Cost Engineering & Administration 17.5% Total Estimated Construction Cost
-8-
11,340,000 1,480,000
150,000
12,970,000 2,270,000
$15,240,000
DATE MAR 06 1987 HARZA ENGINEERING COMPANY I3MWSF1284Cl FEASIBILITY ESTIMATE (LFC/RAM D) ~ROJECT 3.0 MW. HWL EL 1687. SIPHON INTAKE
ITEM DESCRIPTION QUANTITY UNIT UNIT
PRICE TOTAL PRICE
----------------------------------------------330.
LAND 8. LAND RIGHTS 1 LS 730013.00 73.000
--------------------------------------------
SUBTOTAL. PAGE 73.000
SUBTOTAL - A/c 330. LAND 8. LAND RIGHTS 73.000
., ,
ATE MAR 06 1987 HARZR ENGINEERING COMPANY 3MWSF1284Cl FEASIBILITY ESTIMATE (LFC/RAM D) ROJECT 3.0 MW. HWL.EL 1687. SIPHON INTAKE
TEM DESCR IPTION QUANTITY·UNIT UNIT
PRICE TOTAL PRICE
,-----------------------------------,---------------
330.5 MOB ILIZATION 8. LOG ISTICS 1 LS 1100000.00
._------------------------------------
;UBTOTAL. PAGE 2
SUBTOTAL - A/c 330.5 M08ILIZATION 8. LOGISTICS
1.100.000
lATE MAR 06 1987 HARZA ENGINEERING COMPANY 3M\.JSF1284C1 FEASIBILITY ESTIMATE (LFC/RAM D) -ROJECT 3.0 MW. HWL EL 1687 ~ S I PHON INTAKE
UNIT TOTAL TEM DESCRIPTIOI'l QUANTITY UN IT PRICE PRICE ._---------------------------------
331. POWERSTATION & IMPROVEMENTS
331.1 POWERHOUSE
331. 11 DIVERSION & CARE OF WATER 1 LS 350a0.00 35,000
rl 331. 12 ,-
CLEARING. HEAVY 3 AC 105a0.00 .' 31.500 \"()
331. 13 EXCAVAT I ON. TALUS 1750'CY 10.50 18.375
331. 14 FILL 750 CY 8.80 6.600
331.15 SUBSTRUCTURE CONCRETE 345 :CY 530.00 182.850
331.161 SUPERSTRUCTURE CONCRETE 65 CY 790.00 51.350
331. 162
~ MASONRY 470 SF 20.50 9.635
331. 163 ~ INSULATED METAL ~~ PANELS 3700 SF 7.05 26.085 ~~
~--------------------------------------- ~f\, UJ ;UBTOTAL. PAGE 3 361.395
ATE MAR 86 1987 HARZA ENGINEERING COMPANY 3MWSF1284Cl FEASI8ILITY ESTIMATE CLFC/RAM D) ROJECT 3.8 MW. HWL EL 1687. SIPHON INTAKE
TEM DESCRIPTION QUANTITY UNIT UNIT
PRICE TOTAL PRICE
---------------------------------------------331.164
ARCHITECTURAL TREATMENT
331. 165 STRUCTURAL STEEL
331. 166 INSULATED METAL ROOF
331.167 HVAC 8. PLUMBING
331. 168 MISCELLANEOUS METALS
331.2 STATI ON YARD
331.21 FILL
331.22 CRUSHED ROCK SURFACING
331. 23 CHAIN LINK FENCE 8. GATE
331.24 CONCRETE FOUNDATION PADS
;UBTOTAL. PAGE 4
1 LS 5558a.08 55.58a
58a88.'LB 2.75 137.588
3988 SF 6.45 25.155
1 LS 2588a.08 25.888
2888 LB 2.75 5.58a
258 CY 8.80 2.2813
68·CY 25.a8 1.588
168 LF 32.58 5.288
28.CY 54El. a8 :. 18.888
---------------
SUBTOTAL - A/c 331. POWERSTATION 8. IMPROVEMEHTS
268.355
629.750
, )
lATE MAR 06 1987 HARZA ENGINEERING COMPANY 13MWSF1284C1 FEASIBILITY ESTIMATE (LFC/RAM D) 'ROJECT 3.0 MW. HWLEL 1687. SIPHON INTAKE
ITEM DESCRIPTION QUANTITY ,UNIT
332. RESERVOIRS. DAMS. 8. WATERWAYS
332.3 WATERWAYS
332.31 INTAKE
332.311 CONCRETE - STRUCT. (BUILDING EQUIPMENT Be FOUNDATIONS) 7 CY
332.312 TRASHRACK 8. BEND 930 'LBS
332.313 BUILDING 240 SF
332.314 VACUUM PUMPS. CONTROLS. TRANSFORMER. AND MISC. EQUIPMENT 1 LS
332.315 POWER SUPPLY Be CONTROL LINES 1 LS
332.32 PENSTOCK
332.321 UPPER PENSTOCK
332.3211 EXCAVATION
332.32111 EXCAVATION. OVERBURDEN 360CY
UNIT PR ICE .'
875.00
3.70
55.50
100000.00
73500.00
13.00 ---------------------------------------------)UBTOTAL. PAGE 5
TOTAL PRICE
6.125
3.441
13.320
100.000
73.500
4.680
201.066
l()
~f'~\
~\) ~ .~ , lI'tK \ ... \'K ~f\l
rATE MAR 86 1987 HARZA EHGIHEERIHG COMPAHY 3MWSF 1284C 1 FEAS IB IL lTV ESTIMATE (LFC/RAM D) 'ROJECT 3 '.8 MW. HWL EL 1687. S I PHOH I HTAKE
TEM DESCRIPTIOI'! QUAHTITVUHIT UHlT
PRICE TOTAL PRICE
._----------------------------------------------332.32112
EXCAVATIOH. ROCK 488'CY 57.58 23.888
332.3212 BACKFILL 698 CV 16.58 11. 385
332.3213 BEDDIHG 35;CV 45.58 1.593
332.3214 COHCRETE THRUST 8LOCKS & SADDLES 6 CV 11513.88 :. 6.988
332.3215 GRAVEL FILL (FOR PEHSTOCK SUBMERGED PORTIOH) 388,:CV 42.58 , 12.758
332.3216 RIPRAP (FOR PEHSTOCK SUBMERGED PORTIOH) 288 :CV 62.88 12.488
332.322 LOWER PEHSTOCK
332.3221 EXCAVATIOH
332.32211 EXCAVATIOH. TALUS 3988 CV 19.88 74.188
.. _---------------------------------------------------
;UBTOTAL. PAGE 6 142.128
~
['-,1)
~ ~~~ . , ~~ ~,
~~ Q\
lATE MAR 136 1987 HARZA ENGINEERING COMPANY 3MWSF1284Cl FEASIBILITY ESTIMATE (LFC/RAM D) 'ROJECT 3. a MW. HWL EL 1687. SIPHON INTAKE
TEM DESCRIPTION QUANTITY:UNIT
332.32212 EXCAVATI ON. ROCK
332.3222 BACKFILL
332.3223 BEDDING
332.3224 CONCRETE THRUST BLOCKS 8. SADDLES
332.323 PENSTOCK SHAFT
332.3231 EXCAVATION
332.3232 CONCRETE LINING
332.324 TUNNEL EXCAVATION 8. SUPPORT
332.325 PENSTOCK STEEL
332.3251 UPPER SITE POWER CONDUIT
ruBTOTAL.PAGE 7
411313 CY
18aa"CY
15 CY
12413 ~ LF
73a"CY
166aLF
335aa"LB
UNIT PRICE
8.813
25.1313
985.1313 ". "
TOTAL PRICE
36.13813
45.131313
14.775
11513.1313 839.51313
213013.1313" 3.3213.131313
3.135 1132.175
6.1331.5313
r-"
lATE MAR 06 1987 HARZA ENGINEER ING COMPANY 3MWSF1284Cl FEASIBILITY ESTIMATE (LFC/RAM D) 'ROJECT 3.0 MW. HWL EL 1687. SIPHON INTAKE
TEM DESCR IPTIOH QUANTITY;UHIT UNIT
PRICE .. TOTAL PRICE
._-------------------------------------------------
332.3253 LOWER SITE POWER CONDU IT
332.326 TAILRACE & STREAM CHANNEL IMPROVEMENT
332.3261 EXCAVATIOH. TALUS
362000.LB 3.0S
1900CY 10.S0
._------------------------------------
;UBTOTAL. PAGE 8
1.104.100
19.9S0
1. 124.0S0
SUBTOTAL - A/C 332. RESERVOIR. DAMS. & WATERWAYS. 7.498.774
DATE MAR 06 1987 HARZA ENGINEERING COMPANY I3MWSF1284C1 FEASIBILITY ESTIMATE (LFC/RAM D) PROJECT 3.0 MW, HWL EL 1697, SIPHON INTAKE
ITEM DESCRIPTION QUANTITY UNIT
333. TURBINE & GENERATOr.
333.1 TURBINE Co GOVERNOR
333.2 GENERATOR
SUBTOTAL, PAGE 9
1 EA
1 EA
SUBTOTAL - O/C 333. TURBINE & GENERATOR
UNIT PRICE
39S8e8.88
253888.88
TOTAL PRICE
399,888
253,888
DATE MAR 06 1987 HARZA ENGINEERIHG COMPAHY " I3MWSF1284C1 FEASI8ILITY ESTIMATE (LFC/RAM D) PROJECT 3.0 MW. HWLEL 1687. SIPHON INTAKE
ITEM DESCR I PTI ON QUANTI TV ;UN IT
334. ACCESSORY ELECTRICAL EQUIPMENT
334.1 f:lCCESS. ELEC. EQPT. 1.LS
334.2 SUPERV'SRY CONTROLS 1 LS
334.3 COMMUN I Cf:lTI ONS l' LS
UNIT PRICE
.390000.00
.' 1250013.00
69000.00
TOTAL PRICE
390.El00
125.000
69.000
------------------------------------------------SUBTOTAL. PAGE 10 584.000
SUBTOTAL - A/C 334. ACCESSORYELECTRICALEQUIPMEHT 584.000
c' {~
~ATE MAR 1116 1987 HARZA EHGIHEERIHG COMPAHY :3MWSF1284C1 FEASIBILITY ESTIt1HE (LFCI'RAM D) -ROJECT 3.111 MW. HWL.EL 1687. SIPHOH INTAKE
:TEM DESCRIPTIOH QUAHTITY:UHIT
335. MISCELLAHEOUS MECHANICAL EQUIPMEHT
335.1 POWERHOUSE CRAHE
335.2 MISC. EQPT.
1 LS
1 LS
._------------------------------- -----
iUBTOTAL. PAGE 11
UHIT PRICE
48111111111.111111
955111.111111
SUBTOTAL - A/C 335. MISCELLAHEOUS MECHANICAL EQUIP.
TOTAL PRICE
48.111111111
9.55111
57.55111
57.55111
DRTE MAR a6 1987 HARZA EHGINEERING COMPANY " I3MWSF1284Cl FEASIBILITY ESTIMATE (LFC/RAM D) PROJECT 3.a MW. HWL EL 1687. SIPHON INTAKE
ITEM DESCR I PTI ON QUANTI TY :UH IT
336. ACCESS ROAD 1 LS
SUBTOTAL. PAGE 12
SUBTOTAL - A/c 336. ACCESS ROAD
UNIT PRICE
TOTAL PRICE
560a0a. aa.· 56a. €lea
56a.aaa
56a.aaa
~TE MAR B6 1987 HRRZR ENGINEERING COMPRNY 3MWSF1284C1 FERSIBILITY ESTIMATE (LFC/RRM D) ROJECT 3.B MW~ HWL EL 1687~ SIPHON INTRKE
TEM DESCRIPTION QURNTITY:UNIT
353. SUBSTRTION EDUIPMENT 8. STRUCTURES
353.1 TRRNSFORMERS
353.2 SWITCHES~ BRERKERS~ 8. MISCELLRNEOUS
1 ER
1 LS
UNIT PRICE
6B5BB.BB ..
135BBB.BB .
TOTRL PRICE
SUBTOTRL - n/C 353. SUBSTRTION EQUIP. 8. STRUCTURES 195~5BB