BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

35
BIOLOGICAL RESOURCES BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator

Transcript of BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Page 1: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

BIOLOGICAL RESOURCESBIOLOGICAL RESOURCES

Ken Cannon ODOT

Aquatic Biology and Fish PassageProgram Coordinator

Page 2: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Topics to Discuss:Topics to Discuss:

• Federal Endangered Species Act (ESA)• Fish passage plan approval• In-water work timing• Hydroacoustic impacts from pile

driving

• Questions & Answers

Page 3: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Mandate of the FederalEndangered Species Act (ESA)

• 1900+ listed species in the US.

• Under Section 7 of the ESA, all Federal agencies must ensure that any actions they authorize, fund, or carry out are not likely to jeopardize the continued existence of a listed species, or destroy or adversely modify its designated critical habitat.

Page 4: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Federal Nexus Federal Nexus →→ Triggers ESA Triggers ESA

• Federal Funds (FHWA)

• Federal Property (Forest Service, BLM)

• Federal Permit (USCOE)

Section 7 requires consultation with

• National Marine Fisheries Service (NMFS) and/or

• US Fish and Wildlife Service (USFWS)

(ODOT is FHWA’s non-federal representative)

Consultation is Required Before a Project is Consultation is Required Before a Project is AuthorizedAuthorized

Page 5: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

‘Take’ is Prohibited by the ESA, unless a permit has been issued through consultation with the NMFS or USFWS

• Take = “harm, harass, pursue, hunt, shoot, wound, kill, trap, capture, or collect”

• Harm = “significant habitat modification or degradation that results in death or injury”

• Harass = “significantly disrupts normal behavior patterns” including “breeding, feeding or sheltering”

Page 6: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Consultation:Consultation:

1. Biological Assessment (BA)1. Biological Assessment (BA)

• A document written by a biologist to determine the project impacts on listed species.

• Describes the project, baseline conditions, and includes an analysis of effect.

• Includes a “Finding of Effect” for listed species & designated critical habitat

Page 7: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Finding of Effect:Finding of Effect:

• No Effect (must document, but no BA needed)

• Not Likely Adverse Affect (NLAA)• Likely Adverse Affect (LAA)

• Adverse modification of critical habitat

Page 8: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

2. Biological Opinion (BiOp)2. Biological Opinion (BiOp)

• Jeopardy Analysis

• Incidental Take Statement

• Terms and Conditions

Page 9: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

• Think of the Think of the Biological Opinion Biological Opinion (permit) as a fishing (permit) as a fishing license, you must have it license, you must have it to be legal! to be legal!

• Any form of Any form of ‘take’‘take’ is is illegalillegal without a BiOp without a BiOp and accompanying and accompanying Incidental Take Incidental Take Statement.Statement.

Page 10: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Magnuson-Stevens ActMagnuson-Stevens Act

• Essential Fish Habitat (EFH) = waters and substrate necessary to fish for spawning, breeding, feeding, or growth to maturity

• Covers: coastal pelagics,ground fishPacific

salmon• Appended to the ESA BA

Page 11: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Federal ESA PermitsFederal ESA Permits

• Letter of Concurrence (LOC)

• Biological Opinion (BiOp)

• Jeopardy Opinion - Bad News

The Permit MThe Permit Mustust be on Site During be on Site During ConstructionConstruction

Page 12: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Do I Have to Write a New BA for Do I Have to Write a New BA for Each Project?Each Project?

• No… your project may fit a programmatic.

• Standard Local Operating Procedures for Endangered Species (SLOPES) Programmatic Biological Opinion

Page 13: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

ODOT’s BA Qualification ODOT’s BA Qualification TrainingTraining• July 8-9, 2009• 2-Day Training & Test• Must Be Qualified to Write or Review BA’s for

ODOT under contract• Must Maintain Qualification and renew every

3 years

To Register: Lorrie Schaefer at 503-986-3840By E-mail: [email protected]

Page 14: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Location of BA Template and Location of BA Template and GuidanceGuidance

• Electronic versions ODOT NRU Biology Publication Internet site:

http://www.oregon.gov/ODOT/HWY/GEOENVIRONMENTAL/biology.shtml

This web location has the latest versions of the ODOT BA Template, Writing Guidance, and BA Checklist to download

Page 15: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

ESA Documentation TimelineFor Construction Projects

Bid Let

Preliminary Plans (30 %)

Advanced Plans (90 %)

Plans, Specification and Estimate (PS&E)

10 mo. 9 8 7 6 5 4 3 2 1

Project Footprint

Submit Formal BA

(LAA)

Receive Biological Opinion/Take

Statement (LAA) or Letter of

Concurrence (NLAA)

Pre-consultation

Page 16: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Transmittal Process & TimelineTransmittal Process & Timeline

• BA goes to ODOT Environmental, then Action Agency (e.g., FHWA) transmits directly to Services (135 Days)

NOTE: allow an additional 2 weeks for Action Agency to transmit to Regulatory Agency

Must Program at least 150 Days into Project Schedule (from PSE Date) to Allow for ESA Timelines

Page 17: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

When You Receive the When You Receive the Permit(s)Permit(s)• Read & review all permits• Assure all BMP’s and T&C’s of permit

get into final project contract documents- ODFW In-water work period- ID no work zones on plan sheets- Include OHW elevation on plan sheets

• Work with specification writer and appropriate designer to develop final contract documents (plans & specs)

Page 18: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Implementation and Implementation and ConstructionConstruction • The process does not stop once the

permit is received

• Terms & Conditions from the permit must be reflected in the construction documents and contract (plans & specifications)

• Long-term maintenance & reporting (typically 5-years)

Responsibility of the Local Agency

Page 19: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Re-Initiation of ConsultationRe-Initiation of Consultation

• All ESA permits include a standard re-initiation clause

• Triggers for re-initiation may be listed

Page 20: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Re-InitiationRe-Initiation

• Incidental take is exceeded • New information, the action may

affect a listed species in a manner not previously considered

• The action is modified in a manner that causes an effect not previously considered

• New species listing or critical habitat designation

• Permit expiration

Page 21: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Successful Projects Involve…Successful Projects Involve…

• Effective scoping - ID critical natural resource elements- ID construction alternatives and associated costs- ID mitigation opportunities and strategies

• Understanding of the action

• Early coordination and pre-consultation with NMFS/USFWS liaisons

Page 22: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Fish PassageFish Passage

Page 23: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

• ORS 509.585 ODFW Fish Passagehttp://www.dfw.state.or.us/fish/passage/

“Must Provide Fish Passage”

Applies to streams with native, migratory fish (present & historically present)

ODFW State Fish Passage StatuteODFW State Fish Passage Statute

Page 24: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

At artificial obstructions (culvert, bridge, tide gate)

Where native migratory fish are currently or were historically present, and

When a "trigger event" will occur

OR

When the OFWC identifies an emergency location, condemns a passage site, or identifies a "priority" location

Fish Passage Must Be Fish Passage Must Be Addressed...Addressed...

Page 25: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

ODFW Statute TriggersODFW Statute Triggers

• “Culvert Triggers”: culvert extensions or repairs, slip-lining, new aprons, 50% or greater repairs, 50% removal of roadbed, extension of roadbed, new wingwalls, etc…

• “Bridge Triggers”: new bridge, replacement bridge, over 50% of existing bridge elements are cumulatively removed, replaced, filled, or added through time

Waiver & Exceptions (through ODFW)

Page 26: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Waivers–Passage would currently benefit native migratory fish–Mitigation which provides a net benefit is required–In effect until next trigger

• Exemptions–If passage would currently provide “no appreciable benefit”

–No mitigation required

–Can be revoked, in which case passage is required immediately

Waivers and ExemptionsWaivers and Exemptions

Page 27: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Fish Passage PlanFish Passage Plan

• Fish passage plan approval:

ODFW

NMFS

• Discuss early in project development

Page 28: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.
Page 29: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Fish Passage Design Fish Passage Design ConsiderationsConsiderations

• State Statute via. ODFW web site• ODOT Hydraulics Manual• ODFW Fish Passage Coordinator• ODOT–ODFW Liaisons

Where do I go for more information?

Page 30: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

In-water Work TimingIn-water Work Timing

• Know the in-water work window

• How will the in-water window effect the construction timeline?

• Applying for a variance

Page 31: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.
Page 32: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.
Page 33: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Hydroacoustic ImpactsHydroacoustic Impacts

• Pile Driving impactsVibratory hammer versus impact

hammerPile sizeSubstrate

• Attenuation technologyBubble curtains

• Monitoring

• Cost to the project

Page 34: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Bubble CurtainBubble Curtain

Page 35: BIOLOGICAL RESOURCES Ken Cannon ODOT Aquatic Biology and Fish Passage Program Coordinator.

Questions?Questions?