#BSL2015 @BAMconstruction @ferrovial @kiergroup BAM Ferrovial Kier (BFK) JV The challenges and the wins of Information Management on Crossrail at Farringdon Station

Transcript of BIM Show Live 2015: The challenges and the wins of Information Management on Crossrail at Farringdon...

#BSL2015 @BAMconstruction @ferrovial @kiergroup

BAM Ferrovial Kier (BFK) JVThe challenges and the wins of Information Management on Crossrail at Farringdon Station

1. Introduction to Crossrail Farringdon Station

2. Technology – live!

3. Implementation Process

4. BIM in action – live!

5. Q&A

Agenda

CROSRAIL PROJECT

General Overview

90km’s of

Surface Network Upgraded

21km’s of

Twin-Bore Tunnels

28Surface Station

Upgrades

8Major

Sub-Surface Stations

Farringdon Overview

West Ticket Hall

East Ticket Hall

Platform tunnel Eastbound

Platform tunnel Westbound

Farringdon Overview

Farringdon – East Ticket Hall

Farringdon – West Ticket Hall

Farringdon - Platform Tunnels

Farringdon - Platform Tunnels

Farringdon - Platform Tunnels

Interfaces

Introduction Summary

• Complex project

• Lots of site constraints

• Huge number of interfaces

PROJECT CHALLENGES

BIM SOLUTIONS

• Model for Coordination Interfaces + Stakeholders

• More robust construction planning

• Using it to visually depict status of design

• Collection of Asset Data

• CAD authoring tools and models

• Design schedules

• Work packaging

• Data management and access

• Models compare functionality

• 4D 5D 6D

• Our largest challenges

Technology

East Ticket Hall

West Ticket Hall

Running Tunnels

Barbican Station

220 Models30,000 Components

Technology

Project Information Management

Building Information Modelling

Team Structure

BIM Manager

BIM Champions

Tool Box Talks & Workshops

Rest of Work Force

BIM Forum

Parent Company

Commitment

Design Commercial Planning Quality H & S Construction

Establish Procedures/Protocols

BIM Execution PlanBIM Implementation Plan

Number of employees split by their knowledge/usage of BIM

Total employees: 295

BIM Implementation Targets

BIM Capabilities – measured for success:

AwarenessKnowledgeActive Users

5 1015 20 25 25 30 35 40 46 55

70 80

20 25 30 35 40 45 50 6075

90110

130150

20 3050

70 80 90 100

130

160

190

220

250

295

Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15

Training & Awareness

Objectives:

Number of employees split by their knowledge/usage of BIM

Total employees: 295

AwarenessKnowledgeActive Users

Current AwarenessCurrent KnowledgeCurrent Active Users

5 1015 20 25 25 30 35 40 46 55

7080

20 25 30 35 40 45 5060

7590

110130

150

20 3050

7080

90100

130

160

190

220

250

295

Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15

BIM Status 2015

Current Status:

Current status of the number of employees split by their knowledge/usage of BIM

24%

32%13%

31%

AwarenessKnowledge

Users

Rest of employees

Total employees: 295

TotalAwareness: 204Knowledge: 133User: 39Remaining: 91

BIM Status 2015

69%

45%13%

Training

Sub - Contractors

Design Consultants

• Demonstration of real benefits at Farringdon

• 3D Visualisulation

- Inerface with existing works

- BIM in action

• 4D Visulatisulations

- Platform construction

• 6D Asset data

- Examples of asset information from the model

BIM in Action

• Complex project with lots of interfaces

• Embraced BIM, with support of senior management

• 3D, 4D, 5D and 6D BIM implemented

• 69% of staff have reached minimum of “awareness”

category

Summary

• Continued roll out includes:- FieldBIM

- Full 5D roll out

- Greater granularity of 4D by site team

- Involvement of subcontractors

Summary

Any Questions?