BIM and Soft Landings –

A happy coincidence ?

Nick Nisbet, AEC3 & buildingSMART

BSRIA 26th January 2011

Page 2: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

BIM

BIM

a quick introduction

developments in the US

BIM, as we practice it here

forthcoming developments in BIM

Is it better than current practice ?

Is it a real practical benefit ?

Where are the advantages to be had ?

Page 3: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Introducing

buildingSMART

Nicholas Nisbet

Page 4: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

The Cost of Inadequate Interoperability

The Problem The cost of not addressing interoperability in US is $15bn p.a.

Probably more

Perhaps equivalent to £10/m2 in the UK

• 2/3 on Owners,

• 1/3 on Design and Construction

The Solution Think and Act Globally using International Standards

• Sharing building information

• Standard terms, properties, classification

• Common process descriptions

• Connect with related standards (geographic, supply chain)

Think and Act Locally• Extend with local data e.g.

• Provide local usage guidance

• Apply local business rulesSource: Deke Smith (Chair)

National Institute of Building SciencesNational Institute of Building Sciences

Facilities Information CouncilFac ilities Information Council

National BIM StandardNational BIM Standard

National Institute of Building SciencesNational Institute of Building Sciences

Facilities Information CouncilFac ilities Information Council

National BIM StandardNational BIM Standard

Page 5: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

buildingSMART vision

To provide a universal basis for process

improvement and information sharing in

the construction and facilities

management industries.

April 19, 2023 © AEC3 Ltd www.aec3.com5

Page 6: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

NeedIF

C U

sage

Space

Natural Asset

Linear Structure

Structure

Building

Facility / Built

Theatre / World

Sub-SystemsSystem

Level

Site

Real Property Asset

Country

State / Province

County

Installation / Region

Node

Segment

Room

Space

System

Level

Sub-Systems

Room

Water / Sea

Land / Parcel

Underground

Air / Space

Geospatial Information (GIS)

Geospatial Information (GIS)

Overlay

Overlay

Building information(Building Information Models)

Building information(Building Information Models)

Components

Components

City

Benchmarks/Comparisons for top-down work

• Portfolio • Facility • Systems/elemental • Component/Product• Materials and Constructions

Libraries/Catalogues for bottom-up work

Page 7: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

4DSchedulesLogistics

Information Delivery.

FunctionaldescriptionFunctionsCalculationsRequirementsConstraints

Knowledge databasesCompanyExternal

Rules and regulationsBldg, H&S, Planning

SimulationComfortAir, heatingLifecycle costsLight and soundInsulationUseFireEnvironmental impactLife expectancy

DescriptionInc cost estimates

SourcingProduct databasesPrice databases

FMRenting, sale and useMaintenanceWarranty

ReuseRefurbishmentDemolitionReconstruction

VRMLVisualisation3D models

Source: Lars Bjorkhaug, SINTEF . Pictures from: Selvaagbygg, DDS, Byggforsk, NBLN University of California, CIFE Stanford, Pythagoras and Oluf Granlund Yo.IAI UK Board 18/10/05

BIM softwareArch, Struct, Eng Services Civ Eng

Information DeliveryInformation Delivery

Information DeliveryInformation Delivery

ODINNobb

GranlundDDS

Lydia

dRofusFacility Composer

BARBiByggforsk

FornaxSolibri

FocusTocoman

IFC

DDSOctaga

Page 8: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Shape (explicit)

Shape (extrusions)beams, pipes, ducts, walls etc.

Shape (topology)line representations for pipe, duct, etc.

Building Elementswall, door, window, roof, stairs, etc.

Relations Between Elementsholes, chases, voids, zones

Furnitureinc. system furniture

HVAC Equipmentchillers, fans, pumps, boilers,coils, cooling towers, heaters,heat exchangers, etc..

Electrical Elementstransformers, motors, generators,switches, protective devices,power and communication outlets panels, cubicles

Fire Protection Elementssprinklers, hose reels, hydrants, wet/dry rising mains

Sanitary ElementsWC’s, urinals, baths, bidets, trapsgulleys

Spaces, Space Structurespace, storey, part, building, site

Structural analysis:structural members, boundary conditions, connections, supports, loads, etc.

Zones, Compartmentsfire, workstation, rising ducts,shafts

Structural Elementsmembers, profiles, rebars, properties, joints, features, surface

Page 9: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Systemspiping, ducting, cable, structural

Lightingfittings, rendering, photo-accuratelighting

Grids

Manholesmanholes, inspection chambers,access chambers, meter chambers,valve chambers

Controls, Instrumentssensor, actuator, controller, gauge, meter

Draughting

Time Seriestime related events

Holes and Basesholes, sleeves, packing, framing, upstands, vibration isolation

Constraintsrules, specifications, requirementstrigger conditions

Accessoriesbrackets, drop rods, steel sections, bracket assemblies, screws, bolts etc.

Environmental Impactembodied energy, CO2

Asset Managementmaintenance history, inventories

Air Handling Unit

Boiler

Pump Set[Physical

Association]

PreheaterValves

Luminaires[Spatial Association]

Helprequest, action, permit, warranty,operation

Page 10: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

30NameTitle

NameTitle

NameTitle

NameTitle

NameTitle

NameTitle

NameTitle

NameTitle

NameTitle

Actorspeople, organizations, addresses

Costingcost planning, estimates, budgets,whole life

Work Plans and Schedulesinc. nested schedules, resource allocation

Orderswork orders, change orders, purchase orders

Associated Documents

Classification

OCCS

Uniclass

External Data

Connectivityservices, structure, building

Geographical Elementsfeatures, contours, regions

Coordinate Mapping geodetic, cartesian

Page 11: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

IDM – Information Delivery Manual

Requirement & Goal Standardize on information

needed for specific tasks within the building lifecycle

Development based upon open data standards used by all

Provides requirements to software companies

To improve the construction process: Information must be available when it

is needed Quality of information needs to be

appropriate

Courtesy: Dianne Davis, AEC Infosystems

Page 12: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Geometry for energy analysis

Breakdown of geometry in IFC format shown in free neutral viewerGeometry for energy analysis relies on definition of ‘space boundaries’

Evaluation of simulation advantages for interoperable–modeled design

(MIUR – Italian Ministry of the Education, University and Research)

Page 13: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

United Kingdom

Thatcham, Birkshire RG18 3ES

Tel +44 1635 864 590

Fax +44 1635 860 673

email [email protected]

Germany

D-80634 München

Tel +49 89 1870 3223

Fax +49 89 1870 3224

email [email protected]

Air systems for safe evacuation of buildings

Page 14: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Environmental assessment

Environmental impact of building proposals (Atkins)

Applies the BRE EcoPoints methodology

Assessment of Whole Life Costing Energy assessment using the IES

VE Using an IFC 2x database to hold:

proposed designs library of construction properties. library of material properties.

Allows designers to: assess their buildings modify the materials selected.

Page 15: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Material Management

MaterialsConstructionsRates /m2 /m3 /kgCalculate

Layering Material Thickness Ventilated

Page 16: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Building Evaluation

Breakdown by

Storey

Zone

Type

Construction

Measures of Volume Mass Cost UK BRE EcoPoints … WLCC … Embodied Energy

Page 17: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Application in Practice

Real projects using 3D

BIM and IFC

Reconstruction- Office Bldg

Construction- Factory

Design- Central Train

Station

Design- Airport

Construction- Housing

Construction- Metro Station

Page 18: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Regulations

DDAATTAABBAASSEE

SSUUBBMMIISSSSIIOONN

CCAADD SSOOFFTTWWAARREE

RULE CHECKRULE CHECK

VIEW/BROWSEVIEW/BROWSE

CADCADFileFile

IFCIFCFileFile

DGN,DWG,DXFDGN,DWG,DXFFileFile

Singapore: ePlanCheckingSingapore: ePlanChecking

Automatic building regulation checking proved in Singapore Applied for planning regulations in Norway Proven for performance based regulations (Avanti programme) Approach being extended for US building codes

Page 19: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

IFC-SBEM Link (SMART Regulations)

• Link from buildingSMART to Simplified Building Energy Method for part L2 analysis

• Cuts hours of data collection and analysis to minutes

Building Monthly Energy by End Use (kWh/m2)

Page 20: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Webcam at 05.09.2006 17:49:00http://nyeahuswebcam.netpoweresolutions.no/showplace.asp

Akershus Hospital (Oslo, Norway)

Page 21: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Tromso College

Tertiary college in North Norway

Whole building design using buildingSMART principles

Using documented processes

Design process being monitored

Page 22: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Interoperability

BIM is about

re-using structured data.

Interoperability is about the

how ? - IFC

when ? - IDM

what ? - IFD

April 19, 2023 © AEC3 Ltd www.aec3.com22

Page 23: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Handover

COBie: A new approach from North America

April 19, 2023© AEC3 Ltd

www.aec3.com23

Page 24: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

20-Apr-08Engineer Reseach and

Development Center24

handover data captured and lost many times

designer creates space and equipment layouts

Equipment data captured during construction on invoices/reports

construction contractor conducts post-construction survey

wait many years to provide the survey data to the facility operator

once received, store the surveys in a boiler room

facility manager conducts separate survey to find “lost” data and finally…

hand load data into maintenance system

Handover process unchanged for over 100 years!

Page 25: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

20-Apr-08Engineer Reseach and

Development Center25

COBie

the Construction Operations Building Information Exchange format

where is COBie required? designer deliverable construction handover specification construction commissioning specs

capture data as you go design construction commissioning

easy to use spreadsheet each party adds only their part convertible to and from IFC

Page 26: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

Facility

Floor

Systems

Space

Contacts

Zones

Coordinates

Documents Attributes

Issues Connections

common

Job

Resource

Spare

build

Type(parts/warranty)

Component(serial number)

design

17-Mar-10 ERDC 2010 (c)26

COBie2

Page 27: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

20-Apr-08Engineer Reseach and

Development Center27

Facility Identification of facility(ies) referenced in a file

Floor Description of vertical levels

Space Spaces referenced in a project

Zone Functional group of spaces

Type Register Material/equipment/etc. catalog and submittal register

Component Individually named materials and equipment

System Functional group of components

what data do designers add?

Page 28: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

identify floors, roof, and site work

20-Apr-08Engineer Reseach and

Development Center30

Page 29: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

enter spaces into worksheet

20-Apr-08Engineer Reseach and

Development Center31

Page 30: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

list major building systems and zones

20-Apr-08Engineer Reseach and

Development Center32

Page 31: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

20-Apr-08Engineer Reseach and

Development Center33

Type Register Product data, submittals, warranties,

Component Serial numbers, installation dates, tags and barcodes

Spares Details of spares and spare sets

Resources Skills, tools and materials needed

Jobs PM, start-up, shut-down job steps

Documents Submittal documents etc

what data do contractors add?

Page 32: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

import designer’s type and submittal register

20-Apr-08Engineer Reseach and

Development Center34

Page 33: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

load data from schedules into ‘components’ worksheet

20-Apr-08Engineer Reseach and

Development Center35

Page 34: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

20-Apr-08Engineer Reseach and

Development Center36

Attributes Settings, measurements and configurations

Documents Logs and records, installation photos

Issues Remaining issues and hazards

Connections Confirm connections between plant systems and components

what data do commissioning teams add ?

Page 35: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

20-Apr-08Engineer Reseach and

Development Center37

COBie is an exchange format, not

specific software.

COBie data may be created manually

or through use of CADD or BIM

software.

COBie needs Product Information

conclusions

For more information:www.wbdg.org search on COBIE

Page 36: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

example sheet: Jobs

17-Mar-10 ERDC 2010 (c)38

Name Boiler Inspection - Annual

Category PM

Status Not Yet Started

TypeName Combi Boiler

Description

1. Shut down boiler - secure fuel supply and electric power. Lockout/Tagout as required.2. Inspect and clean boiler tubes.3. Check combustion chamber for air and/or gas leaks.4. Check fuel lines and connections for damage.5. Check for proper operational response of burner to thermostat controls. Adjust as required.6. Check and lubricate burner and blower motors.7. Check main flame failure protection and main flame detection scanner on boiler equipment with spark ingnition (oil burner).8. Check electrical wiring to burner controls and blower.9. Clean firebox (sweep and vacuum). 10. Check operation of control switches (i.e. steam pressure, hot water temperature limit, atomizing or combustion air proving, etc.).11. Check hot water pressure gages.12. Check condition of flue pipe, damper and exhaust stack.13. Check boiler operation through complete cycle (approximately 30 minutes). 14. Clean area around equipment.15. Complete work order time and materials. Mandatory comments required!!16. Report outstanding discrepancies to supervisor for corrective action.

Duration 120

DurationUnit minute

Start 2010-03-01T00:00:00

TaskStartUnit year

Frequency 1

FrequencyUnit year

TaskNumber B-1

Priors  

ResourceNames Cad Call Relay Switch Flame Sensors , Halide Leak Detector Kit, Boiler Certification Course

field name example value

Page 37: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

enable and enhance commissioning management and commissioning

processes ?

• the capture  of commissioning, pre-handover, handover, and post-occupation

activities

• greater control for clients of things that tend to get forgotten in the rush to

complete the build works?

enable and enhance FM and asset management?

• the three years professional aftercare process

enable and enhance the Soft Landings approach?

• ensuring that fitness for purpose doesn't get compromised by value

engineering

• reality checking design

• m&e specifications  

Page 38: BIM and Soft Landings – A happy coincidence ? Nick Nisbet, AEC3 & buildingSMART BSRIA 26 th January 2011.

No more pallets !

Questions ?

Thank you !

April 19, 2023 © AEC3 Ltd www.aec3.com40