Bill of Quantity for Barricading of Site, estimation,civil engineering, construction

download Bill of Quantity for Barricading of Site, estimation,civil engineering, construction

of 6

description

excel sheet for bill of quantity for cost analysis of construction site barrication for a height of 6m

Transcript of Bill of Quantity for Barricading of Site, estimation,civil engineering, construction

Boq for BaricadingBARRICADING SITE WITH SHEET UPTO 6m HEIGHT(BOQ for 5m Length)Sl.NoDescriptionUnitNoLengthWidth Depth Quantity1Vertical Pipes 32mmx32mmx2.6mm thk at 1m spacingRmt6636.002Horizontal Pipes 32mmx32mmx2.6mm thk at 1m spacingRmt6530.00Total (36+30) 66 m @2.44 Kg/mKg185.203SDTS ScrewsEa3030.004GI Sheet (6x5)=30 SqmSqm30.005ExcavationCum60.450.450.450.556PCC(1:4:8)Cum60.450.450.080.097Plain cement concrete(1:2:4)Cum60.300.300.300.168ScaffoldingSqm240.300.302.16

Abstract for baricadingBARRICADING WORK WITH SHEET UPTO 6m HEIGHTSl.NoDescriptionUnitQuantityRateAmountDSR Code1Hz & Vertical Hollow sections steel sections 32mmx32mmx2.6mm thkKg185.20105.4419526.1410.16.12SDTS ScrewsEa30.0045.001350.00MR3GI Sheet (6x5)=30 SqmSqm30.00300.009000.00MR4ExcavationCum0.55161.1588.112.6.15PCC(1:4:8)Cum0.094312.72393.004.1.86Plain cement concrete(1:2:4)Cum0.166404.371037.514.2.37ScaffoldingSqm2.16205.04442.894.3.1Total cost for 30 Sqm31837.64Total cost for 1 Sqm1061.25Cost for 1 Rmt6367.53Cost for 1 Rft1941.32Total cost for 320 Rft621222.22

Abstract for baricading (2)BARRICADING WORK WITH SHEET UPTO 6m HEIGHTSl.NoDescriptionUnitQuantityRateAmountDSR Code1Hz & Vertical Hollow sections steel sections 32mmx32mmx2.6mm thkKg185.2075.0013889.7010.16.12SDTS ScrewsPkt100.002.00200.00MR3GI Sheet (6x5)=30 SqmSqm30.00300.009000.00MR4ExcavationCum0.55161.1588.112.6.15PCC(1:4:8)Cum0.094312.72393.004.1.86Plain cement concrete(1:2:4)Cum0.166404.371037.514.2.37ScaffoldingSqm2.16205.04442.894.3.1Total cost for 30 Sqm25051.20Total cost for 1 Sqm835.04Cost for 1 Rmt5010.24Cost for 1 Rft1527.51Total cost for 320 Rft488803.87