ITEM DESCRIPTION QTY UNIT Bill 1 The preliminary items as set out herewith are deemed to be applied to the whole works as shown in the drawings and / or described in the Specifications and the Contractor shall allow for complying with the same and for any cost incurred in connection therewith. The amount inserted by the contractor in this section for such Preliminary items shall be deemed to be applied to the whole of the works carried out under this Contract. A INSURANCE COVERAGE To provide insurance coverage for Workmen Compensation, Contractor's All Risk including Third Party Liability, which covers the necessary requirements including the building work, in accordance with the standard provision in the said policy and also insurance for Contractor's equipment. 1.00 LOT B SAFETY REGULATIONS The Contractor shall initiate and enforce compliance of all safety measures for workmen and public. Providing adequate signage to enforce the above. 1.00 LOT C SITE SUPERVISION To provide full time site personal throughout the Contract Period. 1.00 Lot D SITE MEETING & WEEKLY REPORT 1 To organise Weekly Site Meetings, attend all meetings called by the Client and arrange the attendance of Representative of Sub-Contractors, Nominated Sub-Contractors and suppliers engaged directly under the Client. 1.00 Lot 2 To provide Weekly Site Report and submitting coloured printed site progress photographs. 1.00 Lot E SITE FACILITIES 1 SITE OFFICE To provide temporary site office facilities with table and chairs, whiteboard, proper site rules and regulations signboard. 1.00 Lot 2 GENERAL SCAFFOLDING Bill of Quantities (BOQs) - Annex B Refurbishment of Existing Blocks in UNHCR Office Malaysia Preliminaries & General Conditions Page 1

Transcript of Bill of Quantities (BOQs) - Annex B Refurbishment of ...

Page 1: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill 1

The preliminary items as set out herewith are deemed to be applied to the whole works as shown in the

drawings and / or described in the Specifications and the Contractor shall allow for complying with the

same and for any cost incurred in connection therewith. The amount inserted by the contractor in this

section for such Preliminary items shall be deemed to be applied to the whole of the works carried out

under this Contract.

A INSURANCE COVERAGE

To provide insurance coverage for Workmen Compensation, Contractor's All Risk including Third Party

Liability, which covers the necessary requirements including the building work, in accordance with the

standard provision in the said policy and also insurance for Contractor's equipment. 1.00 LOT

B SAFETY REGULATIONS

The Contractor shall initiate and enforce compliance of all safety measures for workmen and public.

Providing adequate signage to enforce the above.

1.00 LOT

C SITE SUPERVISION

To provide full time site personal throughout the Contract Period. 1.00 Lot

D SITE MEETING & WEEKLY REPORT

1

To organise Weekly Site Meetings, attend all meetings called by the Client and arrange the attendance

of Representative of Sub-Contractors, Nominated Sub-Contractors and suppliers engaged directly under

the Client. 1.00 Lot

2

To provide Weekly Site Report and submitting coloured printed site progress photographs. 1.00 Lot

E SITE FACILITIES

1 SITE OFFICE

To provide temporary site office facilities with table and chairs, whiteboard, proper site rules and

regulations signboard. 1.00 Lot

2 GENERAL SCAFFOLDING

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions

Page 1

Page 2: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions

Provide as necessary general scaffolding for the general execution of the works. Retain in

position to meet the requirements of contractors engage direct under Client and other bodies. 1.00 Lot

3 HOARDING/FENCING AND PVC NETTING

Provide painted metal hoarding/ fencing throughout the duration of the Contract Period all along

the perimeter of the site for phases of works, complete with temporary door with lock, planked

footways etc in accordance with client's approval 1.00 Lot

4 TEMPORARY SERVICES

i ELECTRICITY SUPPLY & TEMPORARY LIGHTING

Provide and maintain all necessary temporary electricity power and lighting supply for the Works and

shall periodically checked to safe and fit to be used. 1.00 Lot

ii WATER

Provide and maintain all necessary temporary water supply for the Works. Allow for all costs

involved, including any notices and applications, deposits, temporary plumbing and storage ,

shifting and adapting where so required by the Bank and pay all the charges. 1.00 Lot

iii TEMPORARY STORES

To provide and erect in approved position on or off the site, temporary stores and comply with

Authority requirements and pay all fees due. 1.00 Lot

F CLEARING / CLEANING DURING & UPON COMPLETION

1 Remove all debris, rubbish and superfluous material from the site both as it accumulates from time to

time and at completion irrespective of their sources or origins.

1.00 Lot

2 Clear the site of all temporary works, facilities, temporary structures, plant and equipment and leave the

site clears and unencumbered before handing over. 1.00 Lot

G SURVEY DRAWINGS

To prepare and submit a full site survey drawing prior to start of works. Surveyor drawing to be endorsed

and to include: 1.00 Lot

1 Boundary and fencing locations

2

All existing building setting out, their FFL and their external height (RSD, DSU and existing filing room)

3 Contour plan at 0.5m intervals (spot levels on the ground)

4 All existing above and under ground services (which includes and is not limited to, piping lines,

sewerage, water, electric, network, service holes, etc...)

5 All existing trees at a diameter of 150mm and above along with their overhang

Note : Although detail survey plan is not done prior to contract award, contractor is responsible to

capture all potential relocation, adjustments & making good based on site inspection prior to submitting

tender pricing

Page 2

Page 3: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions

H SHOP DRAWINGS

Preparation of shop drawings and mock-up (if any) in progress for the client's approval. 1.00 Lot

I AS BUILT DRAWINGS

To prepare and submit a complete set of As-Built Drawings and M&E single line drawing duly endorsed

by competent personnel within one (1) month from the issuance date of the Certificate of Practical

Completion. 1.00 Lot

J TESTING & COMMISSIONING

To conduct Testing & Commissioning of all equipment installed at site. Such works shall be carried out

by competent personnel and to submit all warranty/guarantee cards, reports on handling over date. 1.00 Lot

Bill 2

1 DEMOLITION WORKS

a. To demolish, remove and cart away all unwanted existing structure, interior & architectural component, 1 LOT

b. To touch up all necessary, prepare the ground for interior finishing work to detail drawings. 1 LOT

c. To reroute, make good and modify any services that may clash with the refurbishment works of the 1 LOT

Drawing No :

5016A/RSDDSU/REFURBISH.PLAN/TD_GS

2 CIVIL & STRUCTURAL WORKS

1 MAIN BUILDING

a. Steel Frame

i

Supply and install truss estimte size 100mm x 100mm x 5mm thick x 14.8 kg/m SHS top and bottom

chord. (Estimate total length=322 meter) 4766 KG

ii

Supply and install truss estimte size 70mm x 70mm x 3.2mm thick x 6.7 kg/m SHS diagonal member.

(Estimate total length=204 meter) 1367 KG

iii

Supply and install tie truss estimte size 100mm x 100mm x 5mm thick x 14.8 kg/m SHS. (Estimate total

length=161 meter) 2383 KG

iv

Supply and install truss estimte size 70mm x 70mm x 3.2mm thick x 6.7 kg/m SHS. (Estimate total

length=65 meter) 436 KG

v

Supply and install column estimte size 250mm x 150mm x 6.3mm thick x 30.5 kg/m RHS. (Estimate total

length=133 meter) 4057 KG

vi

Supply and install column estimte size 88.9mm diameter x 5.0mm thick x 10.3 kg/m CHS. (Estimate total

length=44 meter) 454 KG

vii

Supply and install Bracing estimte size 48.3mm diameter x 3.2mm thick x 3.56 kg/m CHS. (Estimate total

length=267 meter) 951 KG

BUILDER'S WORK

Page 3

Page 4: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditionsviii

Supply and install Purlin estimte size 120mm x 60mm x 5mm thick x 13.3 kg/m RHS. (Estimate total

length=616 meter) 8193 KG

ix Supply and instll steel plates, angle, brackets, bolt and nut 2400 KG

x Supply and install G.I Guiter as per Architect's dimension 78.4 m

xi Supply and install metal roof with PU panel as per architect detail 280 m2

xii Supply and install external perimeter metal cladding as per architect's detail m2

b. Reinforced Concrete (Main Building)

b1. Supply and Construct Ground floor structure c/w concrete grade 30 (Total estimate foot print 445.5m2)

i Soil Excavation for raft slab (Actual volume to be determine on site) 165 M3

ii To Compact Well on Existing Subsoil (1 Ton Compact Roller) 445.5 M2

iii One layer of 150mm well compacted hardcore 445.5 M2

iv One Layer of 50mm thk Lean Concrete G15 445.5 M2

v One Layer of 1.2mm thick Water Proof Membrane Sheet (including edge Slab) 475.5 M2

vi Ground Slab Concrete G30 80.8 M3

vii 9mm wire mesh with 200mm spacing (A9) (Yield Strength 485N/mm2) 1042 M2

viii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 1194 KG

ix Rough Bar 6mm Ø (Yield Strength 250N/mm2) 306 KG

c. Foundation (Main Building)

c1 Type F2 (800mm x 800mm x 250mm) (included 900 mm RC stump) ( 21 nos)

i Soil Excavation for Pad Footing Work(Actual volume to be determine on site) 18.2 M3

ii Back Filling Soil with Well Compacted(Actual volume to be determine on site) 10.4 M3

iii To Compact Well on Existing Subsoil (1 Ton Compact Roller) 13.5 M2

iv One layer of 150mm well compacted hardcore 13.5 M2

v One Layer of 50mm thk Lean Concrete G15 13.5 M2

vi Pad Footing Concrete G30 5.1 M3

vii High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 42 KG

viii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 341 KG

ix Rough Bar 6mm Ø (Yield Strength 250N/mm2) 42 KG

c2 Type F3 (1250mm x 1250mm x 350mm) (included 900 mm RC stump) ( 23 nos)

i Soil Excavation for Pad Footing Work(Actual volume to be determine on site) 53 M3

ii Back Filling Soil with Well Compacted(Actual volume to be determine on site) 31 M3

iii To Compact Well on Existing Subsoil (1 Ton Compact Roller) 36 M2

iv One layer of 150mm well compacted hardcore 36 M2

v One Layer of 50mm thk Lean Concrete G15 36 M2

vi Pad Footing Concrete G30 14.5 M3

vii High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 143 KG

viii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 775 KG

ix Rough Bar 6mm Ø (Yield Strength 250N/mm2) 46 KG

c3 Type F4 (1650mm x 1650mm x 400mm) (included 900 mm RC stump) ( 18 nos)

i Soil Excavation for Pad Footing Work(Actual volume to be determine on site) 73.5 M3

ii Back Filling Soil with Well Compacted(Actual volume to be determine on site) 42.7 M3

iii To Compact Well on Existing Subsoil (1 Ton Compact Roller) 2.8 M2

iv One layer of 150mm well compacted hardcore 2.8 M2

v One Layer of 50mm thk Lean Concrete G15 2.8 M2

vi Pad Footing Concrete G30 21.1 M3

vii High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 148 KG

viii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 974 KG

ix Rough Bar 6mm Ø (Yield Strength 250N/mm2) 36 KG

c4 Type F6 (600mm x 1050mm x 300mm) (included 900 mm RC stump) ( 1 nos)

i Soil Excavation for Pad Footing Work(Actual volume to be determine on site) 0.89 M3

Page 4

Page 5: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditionsii Back Filling Soil with Well Compacted(Actual volume to be determine on site) 0.49 M3

iii To Compact Well on Existing Subsoil (1 Ton Compact Roller) 0.63 M2

iv One layer of 150mm well compacted hardcore 0.63 M2

v One Layer of 50mm thk Lean Concrete G15 0.63 M2

vi Pad Footing Concrete G30 0.27 M3

vii High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 2 KG

viii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 19 KG

ix Rough Bar 6mm Ø (Yield Strength 250N/mm2) 2 KG

d. 1.2m height Retaining Wall Base (0.2m x 1.8m x 41.375m length)

i

Soil Excavation for Strip Footing Work (One side 1100mm, one side 2150mm)(Actual volume to be

determine on site) 126 M3

ii Back Filling Soil with Well Compacted(Actual volume to be determine on site) 98 M3

iii To Compact Well on Existing Subsoil (1 Ton Compact Roller) 80.7 M2

iv One layer of 150mm well compacted hardcore 80.7 M2

v One Layer of 50mm thk Lean Concrete G15 80.7 M2

vi Strip Footing Concrete G30 (1.95mx0.3m, length 41.375m) 24.2 M3

vii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 1214 KG

e. Wall Concrete G30 14.9 m3

i High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 463 KG

ii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 1689 KG

2 APRON

a. All Apron (Reinforced Concrete Work)

i To Compact Well on Existing Subsoil (1 Ton Compact Roller) 153.8 M2

ii One layer of 150mm well compacted hardcore 153.8 M2

iii One Layer of 50mm thk Lean Concrete G15 153.8 M2

iv One Layer of Water Proof Membrane Sheet 153.8 M2

v Ground Slab Concrete G30 (150mm Thk) 32.7 M3

vi 9mm wire mesh with 200mm spacing (A9) 356 M2

vii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 796 KG

viii Rough Bar 6mm Ø (Yield Strength 250N/mm2) 211 KG

3 NEW DISABLE TOILET

a. Ground floor structure (3.65m x 2.4m)

i To Compact Well on Existing Subsoil (1 Ton Compact Roller) 8.8 M2

ii One layer of 150mm well compacted hardcore 8.8 M2

iii One Layer of 50mm thk Lean Concrete G15 8.8 M2

iv One Layer of Water Proof Membrane 8.8 M2

v Ground Slab Concrete G30 2.05 M3

vi 9mm wire mesh with 200mm spacing (A9) 17.6 M2

vii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 78 KG

viii Rough Bar 6mm Ø (Yield Strength 250N/mm2) 17 KG

ix Column concrete G30 0.17 M3

x High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) for Column 48 KG

xi Rough Bar 6mm Ø (Yield Strength 250N/mm2) for Column 9 KG

b. Roof Structure

i Roof Beam Concrete G30 0.66 M3

ii High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 18 KG

iii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 24 KG

iv Rough Bar 6mm Ø (Yield Strength 250N/mm2) 19 KG

v Roof Slab G30 1.01 M3

vi 9mm wire mesh with 200mm spacing (A9) 17.6 M2

Page 5

Page 6: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions4 NEW TOILET

a. Ground floor structure

i To Compact Well on Existing Subsoil (1 Ton Compact Roller) 8.7 M2

ii One layer of 150mm well compacted hardcore 8.7 M2

iii One Layer of 50mm thk Lean Concrete G15 8.7 M2

iv One Layer of Water Proof Membrane Sheet 8.7 M2

v Ground Slab Concrete G30 1.55 M3

vi 9mm wire mesh with 200mm spacing (A9) 17.4 M2

vii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 66 KG

viii Rough Bar 6mm Ø (Yield Strength 250N/mm2) 15 KG

ix Column concrete G30 0.17 M3

x High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) for Column 48 KG

xi Rough Bar 6mm Ø (Yield Strength 250N/mm2) for Column 9 KG

b. Roof Structure

i Roof Beam Concrete G30 0.72 M3

ii High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 19 KG

iii High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 28 KG

iv Rough Bar 6mm Ø (Yield Strength 250N/mm2) 18 KG

v Roof Slab G30 1.06 M3

vi 9mm wire mesh with 200mm spacing (A9) 17.2 M2

5 NEW RAMP

a. RC Wall

i - Wall Concrete G30 1.1 m3

ii - High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 61 KG

iii - High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 175 KG

b. Ramp Slab

i - Back Filling Soil (Actual volume to be determine on site) 9.4 M3

ii - To Compact Well on back fill Subsoil (1 Ton Compact Roller)(Actual volume to be determine on site) 17.6 M2

iii - One layer of 150mm well compacted hardcore 17.6 M2

iv - One Layer of 50mm thk Lean Concrete G15 17.6 M2

v - Ramp Slab Concrete G30 (1.25mx0.15m, length 14m) 2.63 M3

vi - 9mm wire mesh with 200mm spacing (A9) 36.8 M2

6 STAIRCASE 1

i - Soil Excavation for Strip Footing Work (Actual volume to be determine on site) 0.16 M3

ii - To Compact Well on Existing Subsoil (1 Ton Compact Roller) (Actual volume to be determine on site) 1.6 M2

iii - One layer of 150mm well compacted hardcore 1.6 M2

iv - One Layer of 50mm thk Lean Concrete G15 1.6 M2

v - Strip Footing Concrete G30 0.16 M3

vi - High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 13 KG

vii - High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 9 KG

viii - Rough Bar 6mm Ø (Yield Strength 250N/mm2) 2 KG

7 STAIRCASE 2

i - Soil Excavation for Strip Footing Work (Actual volume to be determine on site) 0.16 M3

ii - To Compact Well on Existing Subsoil (1 Ton Compact Roller) (Actual volume to be determine on site) 1.6 M2

iii - One layer of 150mm well compacted hardcore 1.6 M2

iv - One Layer of 50mm thk Lean Concrete G15 1.6 M2

v - Strip Footing Concrete G30 0.16 M3

vi - High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 13 KG

Page 6

Page 7: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditionsvii - High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 9 KG

viii - Rough Bar 6mm Ø (Yield Strength 250N/mm2) 2 KG

8 TIMBER DECK

a. Timber Deck Foundation (Included 300mm x 300mm RC Stump)

a1. Type F5 (1700mm x 300mm x 300mm) (included 900 mm RC stump) ( 1 nos)

i - Soil Excavation for Pad Footing Work (Actual volume to be determine on site) 0.8 M3

ii - Back Filling Soil with Well Compacted (Actual volume to be determine on site) 0.4 M3

iii - To Compact Well on Existing Subsoil (1 Ton Compact Roller) 0.51 M2

iv - One layer of 150mm well compacted hardcore 0.51 M2

v - One Layer of 50mm thk Lean Concrete G15 0.51 M2

vi - Pad Footing Concrete G30 0.24 M3

vii - High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 3 KG

viii - High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 16 KG

ix - Rough Bar 6mm Ø (Yield Strength 250N/mm2) 2 KG

a2. Type F1 (700mm x 700mm x 250mm) (included 900 mm RC stump) ( 30 nos)

i - Soil Excavation for Pad Footing Work (Actual volume to be determine on site) 19.9 M3

ii - Back Filling Soil with Well Compacted (Actual volume to be determine on site) 10.8 M3

iii - To Compact Well on Existing Subsoil (1 Ton Compact Roller) 6 M2

iv - One layer of 150mm well compacted hardcore 14.7 M2

v - One Layer of 50mm thk Lean Concrete G15 14.7 M2

vi - Pad Footing Concrete G30 3.7 M3

vii - High Deformed Bar 10mm Ø (Yield Strength 460N/mm2) 52 KG

viii - High Deformed Bar 12mm Ø (Yield Strength 460N/mm2) 436 KG

ix - Rough Bar 6mm Ø (Yield Strength 250N/mm2) 60 KG

b Deck Steel Frame

i

Supply and install steel beam estimte size 150mm x 100mm x 5mm thick x 18.7 kg/m SHS. (Estimate

total length=255 meter) 4769 KG

ii

Supply and install steel beam estimte size 120mm x 60mm x 3.6mm thick x 9.72 kg/m SHS. (Estimate

total length=271 meter) 2635 KG

iii All Connection shall be 4mm Fillet weld all round m

iv Supply and instll steel plates, angle, brackets, bolt and nut 340 KG

9 Others

i To provide soil investigation report (30 nos Mackintosh Prope Test) L/S

ii To supply and construct 230mm half round perimeter drain. 44.5 m

3 EXPOSED CLAY RED BRICKS WALL AT TOILET

a.To supply & install clay red bricks wall laid in approved thin bed adhesive mortar to all horizontals &

perpends all in accordance with the manufacturer's specification.

Surface to be clean & grouting to be neatly done ready to receive waterproof clear coating finish [quote

separately]

i Toilets - Estimated Ht at 2800mmH 66 MS

Drawing No :

5016A/RSDDSU/WALL.FNSH.PLAN/TD_GS

4 FIBRE CEMENT EXTERNAL WALL W ROCKWOOL INSULATION

To supply and install 100mm thk. full height HUME Prima fibre cement wall (or equivalent) with G.I.

Metal stud internally and 12mm thk. bare finished bevelled edge fibre cement board flush on both sides

to underside of ceiling or roof level.

> Fibre Cement - PRIMA Flex or equivalent

> Rockwool - Rockwool Safe 'n' Silent Pro or equivalent

All joint to be taped, plastered and sanded smooth to receive 1 undercoat and 2 top coat paint finish.

Page 7

Page 8: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditionsi Estimated Ht at 2800mmH - 4550mmH 362 MS

Drawing No :

5016A/RSDDSU/WALL.FNSH.PLAN/TD_GS

5 WATERPROOFING

To supply and install waterproofing for floor slab using Xypex or equivalent

i Toilets & Disabled Toilet 14.5 MS

6 DOOR FRAME

To supply & install GI door frame

a D1 - Estimated size : 900mmW x 2400mmH 25 SET

b D2 - Estimated size : 1800mmW x 2400mmH 2 SET

c D3 - Estimated size : 1200mmW x 2400mmH 1 SET

d D4 - Estimated size : 1200mmW x 2400mmH 1 SET

e D5 - Estimated size : 900mmW x 2400mmH 6 SET

Drawing No :

5016A/RSDDSU/DR.WD.SCHEDULE/TD_GS

7 WINDOWS

a To supply & install Breezway Easy Screen System Naco Window and fixed glass aluminium bottom

i W1 - Size : 600mmW x 2400mmH 18 SET

ii W2 - Size : 1200mmW x 2400mmH 11 SET

iii W3 - Size : 1855mmW x 2400mmH 5 SET

iv W6 (Frosted finish) - Size : 600mmW x 600mmH 4 SET

Drawing No :

5016A/RSDDSU/DR.WD.SCHEDULE/TD_GS

b To supply and install 2 way aluminium frame sliding window with 6mm + 6mm thk laminated clear glass

i W4 - Opening Size : 1625mmW x 2400mmH 10 SET

ii W5 - Size : 900mmW x 2400mmH 1 SET

Drawing No :

5016A/RSDDSU/DR.WD.SCHEDULE/TD_GS

8 ROOF COVERING

To supply & install Ajiya Mega Rib 30 (or eqivalent) 0.47 TCT thk PU foam metal deck roof sheet with

steel sheet finish on the bottom for entire development, c/w painted GI flashing, painted hardwood fascia

and soffit for all overhangs, and other necessary fittings and accessories according to manufacturers

requirements.

i RSD DSU Main Building 575.5 MS

ii New Toilet 1 and 2 13.5 MS

iii New Disabled Toilet 12.8 MS

Drawing No :

5016A/RSDDSU/ROOF.PLAN/TD_GS

9 GUTTER AND DOWNPIPE SYSTEM

a

To supply & install Roofseal R4-type 24 or equivalent Zicalum gutter c/w GI brakets and all required

accessories, fittings and flashings according to manufacturer's recommendation.

To also supply & install stainless steel leaf mesh guard along entire gutter as indicated in the tender

drawings according to manufacturer's detail.

i RSD DSU Main Building 110 MR

ii New Toilet 1 and 2 16.5 MR

iii New Disabled Toilet 15.5 MR

Page 8

Page 9: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditionsb

To supply and install 150mm dia. UPVC rainwater downpipes to perimeter drain c/w all required

connectors, ties and brackets, and other necessary accessories. To be finished in selected paint (2

layers) according to architect's specification.

To supply and install 150mm dia. underground UPVC piping from perimeter drain to new drywell sump

and existing manhole for drainage.48 MR

cTo supply and install stainless steel full length rain chain link from gutter downspout to ground level with

5 pc interim stainless steel catch basin.3 MR

Drawing No :

5016A/RSDDSU/GUTTER.DETAIL/TD_GS

10 DRAINAGE

a

To supply and install 150mmD x 300mmW (opening) half moon concrete precasted scupper drain with

heavy duty precasted concrete drain cover with perpendicular holes to cover all exposed perimeter

drainage according to tender drawings.

127 MR

b

To supply and install interim perforated concrete underground sump (rainwater drywell) filled internally

and externally (1ft perimeter) with 20mm gravel, wrapped fully with geotextile. Drywell capacity (appx

1000mmW x 1000mmD) according to engineer's recommendation connected to rainwater and perimeter

drainage with overflow to existing manhole. C/w all necessary fittings, brackets, connectors and

accessories.

2 NOS

Drawing No :

5016A/RSDDSU/DRAINAGE.PLAN/TD_GS

11 OUTDOOR GROUND SURFACE TREATMENT

a To excavate 150mm of topsoil below deck area and fill with gravel bed at 20mm gravel size 152 MS

bTo finish all outdoor green spaces with cow grass turfing and to replace any existing ground material

with soil ensure the suitability for cow grass to grow 150 MS

c To include 100mmH concrete curb at all concrete and turfing boundaries 80 MR

Drawing No :

5016A/RSDDSU/KEYPLAN.SPECS/TD_GS

Bill 3

A PARTITIONING

Drawing No :

5016A/RSDDSU/WALL.FNSH.PLAN/TD_GS

1 GYPSUM DRYWALL INTERNAL PARTITION W ROCKWOOL INSULATION

To supply and install 75mm thk. full height gypsum wall with G.I. Metal stud internally and 12mm thk.

bare finished bevelled edge gypsum board flush on both sides to underside of ceiling or roof level.

> Gypsum - Gyproc BaseLine or equivalent

> Rockwool - Rockwool Safe 'n' Silent Pro or equivalent

All joint to be taped, plastered and sanded smooth to receive 1 undercoat and 2 top coat paint finish.

i Estimated Ht at 2800mmH - 4550mH 620 MS

2 ANTI CLIMB FENCE

To supply and install glavanised anti climb fence in selected design with galvanised, RC ground beam

and footing foundations according to manufacturers detail. All galvanised surfaces to be prepared to

receive spray painted finish with selected colours

i Boundary Fence - Estimated Ht at 3200mmH 279 MS

ID'S WORKS

Page 9

Page 10: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions3 STAIRCASE RAILING

To supply and install mild steel railing along with perforated metal sheet at 12mm perforation according

to tender design, ready to receive anti-rust undercoat and 2 top coat spray painted finished for all ramps

and staircases.

a Estimated Ht at 1200mmH 39 MS

4 ALUMINIUM COMPOSITE PANEL FIN

To supply and install 450mmW 100mm thk. full height aluminium composite panel with mild steel internal

structure in selected finishing, height to underside of ceiling or roof level, details according to

manufacturer's requirements. C/w all necessary accessories, flashings, attachments and brackets as

required by manufacturer.

a Estimated Ht at 2500mmH - 4550mmH 9 MS

B DOORS

Drawing No :

5016A/RSDDSU/DR.WD.SCHEDULE/TD_GS

1 STEEL FRAME SWING DOOR WITH 6MM INSET LAMINATED GLASS - SINGLE LEAF D1To supply and install single leaf powder coated steel framed door with 6mm inset laminated glass - with

partial frosting sticker finish

Complete with H/W door jamb, stainless steel lockset, stainless steel hinges, aluminium hydraulic door

closer and magnetic door stopper.

Inset glass to be in 6mm thk laminated glass

a Size: 900mmW x 2400mmH 25 NO

2 STEEL FRAME SWING DOOR WITH 6MM INSET LAMINATED GLASS - DOUBLE LEAF D2To supply and install double leaf powder coated steel framed door with 6mm inset laminated glass - with

partial frosting sticker finish

Complete with H/W door jamb, stainless steel lockset, stainless steel hinges, aluminium hydraulic door

closer and magnetic door stopper.

Inset glass to be in 6mm thk laminated glass

a Size: 1800mmW x 2400mmH 2 NO

3 STEEL FRAME SWING DOOR WITH 6MM INSET LAMINATED GLASS - DOUBLE LEAF D3

To supply and install single leaf powder coated steel framed door with 6mm inset laminated glass - with

partial frosting sticker finish

Complete with H/W door jamb, stainless steel lockset, stainless steel hinges, aluminium hydraulic door

closer and magnetic door stopper.

Inset glass to be in 6mm thk laminated glass

a Size: 1200mmW x 2400mmH 1 NO

4 SOLID TIMBER PANEL DOOR - SINGLE LEAF D4

To supply and install water proof solid timber panel door with selected design in selected laminate

finished.

Complete with H/W door jamb, stainless steel lockset, stainless steel hinges, aluminium hydraulic door

closer and magnetic door stopper.

a Size: 1200mmW x 2400mmH 1 NO

5 SOLID TIMBER PANEL DOOR - SINGLE LEAF D5

To supply and install water proof solid timber panel door with selected design in selected laminate

finished.

Complete with H/W door jamb, stainless steel lockset, stainless steel hinges, aluminium hydraulic door

closer and magnetic door stopper.

Page 10

Page 11: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditionsa Size: 900mmW x 2400mmH 6 NO

Drawing No :

5016A/RSDDSU/REF.CEILING.PLAN/TD_GS

C CEILING FINISHES

1 PLASTER BOARD CEILING

To supply & install suspended plaster board ceiling, 10mm thk

> Gyproc Topline or equivalent

All joint to be taped, plastered and sanded smooth to receive paint.

i All enclosed rooms 196 MS

ii Toilets 7.4 MS

iii Disabled Toilet 7.1 MS

2 PLASTER BOARD CEILING PAINTING

To paint all plaster board ceiling area with 1 undercoat and 2 finishing coats of selected colour emulsion

paint to specifications.

> Undercoat - Nippon 5200 Interior Sealer or equivalent

> Topcoat - Nippon Interior Collection or equivalent 196 MS

i All enclosed rooms 196 MS

ii Toilets 7.4 MS

iii Disabled Toilet 7.1 MS

3 OPEN CEILING PAINTING

To paint all open ceiling area (along with wiring, piping and new metal structure, if any) with 1 undercoat

and 2 spray paint finishing coats of selected colour emulsion paint to specifications.

i All open areas 253 MS

D SKIRTING

1 PVC SKIRTING

To include PVC skirting to architects selection for all interior and exterior walls.

> Dynaloc or equivalent 1 LOT

E WALL FINISHES

Drawing No :

5016A/RSDDSU/WALL.FNSH.PLAN/TD_GS

1 EXTERIOR WALL PAINT

To paint all new external wall with 1 undercoat and 2 finishing coats of selected colour paint to

specifications.

Fibre Cement / Gypsum:

> Undercoat - Nippon Timbershade or equivalent

> Topcoat - Nippon Fibercote (Fibre Cement / Gypsum) or equivalent

Also to allow for proper treatment and make good to all existing wall and column ready to receive paint.

Estimated Ht at 2800mmH - 4550mmH

Page 11

Page 12: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditionsi New building 160 MS

2 EXTERIOR WATERPROOF CLEAR COATING

To paint all external wall with double layer waterproof clear coating finish on exterior surface:

> Evercrete Top Seal or equivalent

i Toilet & Disable Toilet 66 MS

3 INTERIOR WALL PAINT

To paint all new partition & wall with 1 undercoat and 2 finishing coats of selected colour paint to

specifications.

> Undercoat - Nippon 5200 Interior Sealer or equivalent

> Topcoat - Nippon Interior Collection or equivalent

Also to allow for proper treatment and make good to all existing wall and column ready to receive paint.

Estimated Ht at 2800mmH - 4550mmH

i New building 1602 MS

ii Toilet & Disabled Toilet 66 MS

4 ANTI-RUST (STEEL)

To spray paint all railings and anti-climb fence with 1 undercoat and 2 finishing coats of selected colour

spray paint to specifications.

> Anti-rust Undercoat - Nippon MIO or equivalent

Note: Area given is one sided surface area, costing to capture entire coating 279 MS

5 SPRAY PAINT (STEEL)

To spray paint all railings and anti-climb fence with 1 undercoat and 2 finishing coats of selected colour

spray paint to specifications.

> Colourland Spray Master Zinc Rich Primer or equivalent

Note: Area given is one sided surface area, costing to capture entire coating 318 MS

6 WALL TIMBER LAMINATE

To supply and install timber grain laminate on all exposed surfaces of gypsum partition wall

> Polutec Laminates High Pressure Laminates or equivalent

i Estimated Ht at 1500mmH 14 MS

7 METAL DECK WALL CLADDING

To supply and install metal deck wall cladding c/w all required accessories in accordance to

manufacturer's requirements

> Bluescope Lysaght Concealed Flat Pan Sheet or equivalent with selected colours

Estimated Ht at 2800mmH - 4550mmH 202 MS

8 TILING

To supply and install 600mm x 300mm homogenous porcelain tile c/w edge tile capping

> MML brand or equivalent

Ht at 2100mmH

i Toilet & Disabled Toilet 48.3 MS

F FLOOR FINISHES

Drawing No :

5016A/RSDDSU/FLOOR.FNSH.PLAN/TD_GS

Page 12

Page 13: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions1 CEMENT RENDER FLOOR - POLISHED

To provide 50mm thk polished cement render

i Interior floor 445 MS

2 CEMENT RENDER FLOOR - BRUSHED

To provide 25mm thk brushed cement render finish

i Exterior floor 200 MS

3 PRECAST CONCRETE SLAB

To supply and lay 600mmW x 600mmL x 50mmD precast concrete slab 8 NOS

4 TILING

To supply and install 600mm x 300mm homogenous porcelain tiles

> MML brand or equivalent

i Toilet & Disabled Toilet 14.5 MS

5 FUSED BAMBOO DECKING

a

To supply and install waterproof fused bamboo decking with 5mm gap c/w all necessary accessories

and brackets to manufacturers recommendation.

> dassoCTECH or equivalent

i Decking 146 MS

b

To supply and install removable decking manhole access panels on timber deck according to tender

drawing for manhole and services access under the timber deck c/w all necessary frames, accessories

and brackets to manufacturers recommendation for flush and seamless finish with the rest of the timber

deck.

> dassoCTECH or equivalent

i 750mmW x 750mmL 12 NOS

ii 900mmW x 900mmD 2 NOS

G BUILD INS

1 LAMINATED PLYWOOD PANTRY COUNTERTOP AND BACKING WITH QUARTZ TABLE TOP

To build in a 600mmW x 850mmH laminated plywood pantry table top and support ready to receive

polished 50mm thk quartz tabletop

To build in 30mm thk plywood laminate table backing at 1500mmH with rounded top corners attached

securely to pantry countertop.

To supply and install 50mm thk polished quartz tabletop slab on laminated plywood countertop c/w all

necessary brackets and fittings according to manufacturer's detail.

Drawing No : 4.2 MR

5016A/RSDDSU/PANTRY.DETAIL/TD_GS

2 LAMINATED PLYWOOD UNDER SINK CLOSER AND DRAWERS

To build in laminated plywood under sink closet with 2-leaf soft close door c/w aluminium bar handle and

all necessary accessories and support

To build in laminated plywood under table drawers (4 rows) with soft close door c/w aluminium bar

handle and all necessary accessories and support

i Under Sink Closet 0.9 MR

ii Under Table Drawers 0.5 MR

Drawing No :

5016A/RSDDSU/PANTRY.DETAIL/TD_GS

3 CONCRETE TABLE TOP

Page 13

Page 14: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General ConditionsTo build in a concrete table top and support with 2 layer waterproof coating with concrete skirting.

> Evercrete Top Seal or equivalent

i Toilets 1.8 MR

ii Disabled Toilet 1.8 MR

Drawing No :

5016A/RSDDSU/KEYPLAN.SPECS/TD_GS

3 ALUMINIUM AIRCOND COMPRESSOR RACKING

To supply and install powder coated (in a range of brown) aluminium horizontal hollow bar screen in

wooden surface finish with sufficient internal racking and access for all air cond compressor according

to the tender drawings c/w all necessary accessories, support and brackets.

Estimated Size : 600mmD 60 MS

Drawing No :

5016A/RSDDSU/AC.DETAIL/TD_GS

4 ALUMINIUM LINTEL

To supply and install aluminium composite panel claded lintels with mild steel internal structure in

selected finishing, details according to manufacturer's requirements. C/w all necessary accessories,

flashings, attachments and brackets as required by manufacturer. 19 MR

Drawing No :

5016A/RSDDSU/LINTEL.DETAIL/TD_GS

H LOOSE FURNITURE

Drawing No :

5016A/RSDDSU/FURN.PLAN/TD_GS

1 PANTRY CHAIR

Polypropylene with mild steel pantry chair

a Pantry 3 NO

2 SINGLE ARM CHAIR

Water repellent fabric spring core sofa seating with solid base

a Reception Lounge 2 NO

3 2 SEATERS

Water repellent fabric spring core sofa seating with solid base

a Reception Lounge 4 NO

4 COFFEE TABLE

a Reception Lounge; Size : 900mmL x 600mmW 1 NO

5 SIDE TABLE

a Reception Lounge; Size : 450mmL x 450mmW 1 NO

6 POTTED PLANT

a

Reception Lounge;

Indoor Plant c/w designer ceramic pot; Size : 200mmW dia 1 NO

7 TABLE LAMP

a Reception Lounge 1 NO

8 THROW PILLOWS

a Reception Lounge 2 NO

Page 14

Page 15: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions

I WINDOW FINISHES

1.00 TIMBER VENITIAN BLIND

To supply & install selected 35mm wooden venetian blind (brand : maxtrack or equivalent) for

all windows 132 MS

WINDOW FINISHES TO COLLECTION : RM

J WAYFINDING & SIGNAGES

1.00 DIGITAL COLOUR PRINTED ACRYLIC SIGNAGES

To supply & install toilet sign on door (size 200mm x 200mm x 5mm thk) 3 PCS

To supply & install offices room signages (size : 150mm x 400mm x 5mm thk) 23 PCS

2.00 POWDER COATED LASER CUT METAL SIGNAGE

To supply & install powdercoated laser cut 3mm thk metal signage (size : 250mm x 250mm x

3mm thk) 10 PCS

Bill 4

A GENERAL

1 Mobilisation of equipment and machineries 1 LOT

2 Shop drawings preparation and submission 1 LOT

3 As-Built and O&M preparation and submission 1 LOT

4 Site supervision and coordination 1 LOT

5 Training and instruction to client representative/ building operator 1 LOT

6 Hacking and making good of floor/ wall finishes for conduit/ trunking/ tray installation (including

approved fire/weatherproof sealants and all neccesary)

1 LOT

B ELECTRICAL SERVICES

Note:- Contractor to inspect and visit site for exact measurement of existings services tapping

etc.1 DISMANTLING WORKS

Supply labour & tools to dismantle all the relevant existing electrical/ telecommunication/ ELV system

upon demolition & completion of the renovation works, which shall include but not limitted to the

following scopes:-

1 LOT

-

-

-

-

-

Electrical wiring

Data and telephone cabling works

ELV cabling works for card access, CCTV camera, etc

Electrical fittouts i.e. light fitting, switches, switch socket outlets, etc

ELV equipment i.e. CCTV camera, card access system, number waiting system

2 SUB-SWITCHBOARD AND DISTRIBUTION BOARD

To supply and install the following electrical switchboard and distribution boards complete with MCCB,

MCB, RCCB, surge protection device, changeover, contactors and other accessories to complete

installation:-

2.1 DB-DSU (60A TPN) 1 LOT

M&E WORKS

Page 15

Page 16: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions2.2 DB-RSD (60A TPN) 1 LOT

2.3 DB-ESS (32A 4P) 1 LOT

3 SUBMAIN CABLING WORKS

To supply, install and terminate the following submain cables complete with termination kits,earth

cables,cable tray/trunking/piping and all required. Note:- Contractor to inspect and visit site for exact

measurement of existings services tapping etc.

3.1 From existing DB-DS submain cable to DB-DSU 30 M

3.2 From existing DB-RSD submain cable to DB-RSD 30 M

3.3 From existing Generator/AMF board to DB-ESS 80 M

4 FINAL SUB-CIRCUITS

To supply and install final sub-circuits complete with earth wires in concealed uPVC conduit/ high level

trunking/in underfloor trunking (power/data)

4.1 LIGHTING AND FAN POINT - GROUND FLOOR

4.1.1 Lighting point c/w 2 x 1.5mmsq 1C Cu PVC cable c/w earth wire 182 NO

4.1.2 Outdoor Lighting point c/w 1 x 1.5mmsq 3C Cu PVC/SWA/PVC armored cable 48 NO

4.2 SMALL POWER POINT - GROUND FLOOR

4.2.1 13A SSO c/w 2 x 2.5mmsq 1C Cu PVC cable c/w earth wire (DOUBLE GANG SWITCH 13A P.P.

TABLE MOUNTED)

2 NO

4.2.2 13A SSO c/w 2 x 2.5mmsq 1C Cu PVC cable c/w earth wire (FOUR GANG SWITCH 13A P.P. TABLE

MOUNTED)

56 NO

4.2.3 13A SSO c/w 2 x 2.5mmsq 1C Cu PVC cable c/w earth wire (DOUBLE GANG SWITCH 13A P.P.

300mm from ground)

14 NO

4.2.4 13A SSO c/w 2 x 2.5mmsq 1C Cu PVC cable c/w earth wire (DOUBLE GANG SWITCH 13A P.P. @

1200MM FROM GRD)

3 NO

4.2.5 13A SSO c/w 2 x 2.5mmsq 1C Cu PVC cable c/w earth wire (TRIPLE GANG SWITCH 13A P.P. @

1200MM FROM GRD)

2 NO

4.2.6 13A SSO c/w 2 x 2.5mmsq 1C Cu PVC cable c/w earth wire (FOUR GANG SWITCH 13A P.P. @

1200MM FROM GRD)

2 NO

4.3 AC POINT - GROUND FLOOR

4.3.1 Air cond point c/w 2 x 4mmsq 1C Cu PVC cable c/w earth wire and 20A indicator type DP switch

connected to air conditioning system/indoor unit (wall mounted split unit)

22 NO

4.3.2 Air cond point c/w 2 x 4mmsq 1C Cu PVC cable c/w earth wire and 20A indicator type DP switch

connected to air conditioning system/outdoor unit (cassete split unit)

13 NO

5 ELECTRICAL FITTINGS

To supply and install the following electrical fittings c/w necessary accessories :-

5.1 GROUND FLOOR

5.1.1 SELECTED TRACK LIGHT FIXTURE 36W LED (4500 LUMENS) 6 NO

5.1.2 SUSPENDED LED LIGHTBOX (2300 LUMENS) 43 NO

5.1.3 SUSPENDED EXPOSED LED DOWNLIGHT WITH HOUSING (1600 LUMENS) 24 NO

5.1.4 CEILING RECESSED DOWNLIGHT (1200 LUMENS) 98 NO

Page 16

Page 17: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions5.1.5 IP68 OUTDOOR WALL LIGHT (1500 LUMENS) 11 NO

5.1.6 SELECTED SUSPENDED PENDANT LIGHT (4000 LUMENS) 9 NO

5.1.7 SELECTED SUSPENDED DECORATIVE SPOTLIGHT (1200 LUMENS) 20 NO

5.1.8 SELECTED DECORATIVE IP68 LANDSCAPE FLOOR RECESSED STEPLIGHT (650 LUMENS) 13 NO

5.1.9 SELECTED DECORATIVE IP68 LANDSCAPE FLOOR SPOTLIGHT (1000 LUMENS) 6 NO

5.1.10 WALL MOUNTED EMERGENCY LIGHT (RECESSED LED TYPE - 3HRS BACKUP 100 LUMENS) 12 NO

5.1.11 EXIT/KELUAR SIGNAGE (3HRS BACKUP SLIM LED) 8 NO

6 EARTHING & LIGHTNING PROTECTION

6.1 To supply and install roof lightning protection conductor mesh as per drawings c/w required

clips, saddles, brackets, accessories etc.

1 LOT

6.2 To supply and install roof lightning protection air terminal as per drawings 6 NO

6.3 To supply and install roof lightning protection down conductor as per drawings c/w required

clips, saddles, brackets, accessories etc.

1 LOT

6.4 To supply and install bi-metallic test points as per drawings 1 LOT

6.5 To supply and install pvc earth cable as per drawings c/w required trunking, accessories etc. 1 LOT

6.5 To supply and install earth bar as per drawings 3 NO

6.6 To supply and install heavy duty earth chambers as per drawings and to achieve 1 ohm 1 LOT

6.7 All other required for a complete lightning protection and earthing system. Please state:- 1 LOT

7 UNDERFLOOR TRUNKING SYSTEM

7.1 To supply and install underfloor service junction box as per drawings 36 NO

7.2 To supply and install underfloor service outlet box as per drawings 54 NO

7.3 To supply and install underfloor trunkings as per drawings 1 LOT

9 TESTING & COMMISIONING 1 LOT

10 Items not included in the above, but described in the conditions of contract, specifications and as

indicated in drawings, also required by the legislation and efficient operation of the entire installation. If

non required, please write "NIL" otherwise full details of the items to be given.

G.I Pipings for external cablings

Page 17

Page 18: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions

C COMMUNICATION SERVICES

Note:- Contractor to inspect and visit site for exact measurement of existings services tapping

etc.1 STRUCTURED CABLING

To supply and install Data Cabling for Telecommunication System, Data Network System in

concealed conduit/upvc trunking/underfloor trunking:-

1.1 Cat 6 Data Cabling/ Telephone Cabling c/w modular jack connected from network switch located at

the New Server Room to RJ45 faceplate

54 NO

1.2 Cat 6 Data Cabling/ Telephone Cabling c/w modular jack connected from network switch located at

the New Server Room to Wifi Access Point

2 NO

1.2 Interack cabling works complete with Cat6 UTP patch cord 1 LOT

1.3 Fiber cable in G.I conduit laid underground & concealed in wall from existing IT server room to new

server rack in new server room

80 M

1.4 SC ADAPTER WITH 3M OM3 SC - LC FIBRE PATCH CORD for existing fiber connection 1 LOT

1.5 Wifi Access Points/Router 2 NO

2 EQUIPMENT RACK AND NETWORK SWITCHES

2.1 NEW SERVER RACK complete with the following:

Main Equipment Rack, Main Erthernet gigabits switch (1000 Mbps), fully managed, layer 3, stackable

c/w POE function and SFP modules. (Enterprise switch), Fiber patch panels, UTP Cable Patch Panels,

wifi controller server, internet gateway, main equipment rack/ cabinet c/w ventilation fan, bracket, all

required and accessories

1 LOT

2.2 Wifi Access Points/Router 2 NO

5 TESTING & COMMISIONING 1 LOT

6 Items not included in the above, but described in the conditions of contract, specifications and as

indicated in drawings, also required by the legislation and efficient operation of the entire installation. If

non required, please write "NIL" otherwise full details of the items to be given.

6.1 Data and network connection to existing or new system 1 LOT

6.2 G.I Pipings for external cablings 1 LOT

6.3

D SECURITY SYSTEM SERVICES

Note:- Contractor to inspect and visit site for exact measurement of existings services tapping

etc.1 CCTV FIELD DEVICES

1.1 4 Mega Pixel HD IP CCTV Camera IP68 Outdoor Bullet Power Over Ethernet (POE) 4 NO

1.2 Data/Video Surge Protector c/w accessories 1 LOT

1.3 Power Surge Protector c/w accessories 1 LOT

1.4 Network Switches

1.4.1 16 ports, layer 2, managed, ethernet switch c/w POE function 1 LOT

Page 18

Page 19: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions1.5 Fiber Converters 1 LOT

3 CCTV CABLING AND INSTALLATION WORKS

3.1 CCTV point complete with Cat 6 UTP Cabling in g.i conduit c/w modular jack connected from the

network switch

3.1.1 CCTV-1 1 LOT

3.1.2 CCTV-2 1 LOT

3.1.3 CCTV-3 1 LOT

3.1.4 CCTV-4 1 LOT

3.2 Interack cabling works complete with Cat6 UTP patch cord 1 LOT

3.2 Installation and termination complete with necessary accessories at exisitng main console and pre-test

of the camera points

1 LOT

3.3 Labelling of all CCTV cables. Labels shall be provided at 30m interval along the run of the cable, and at

all bends.

1 LOT

3.4 Supply and install fiber optic cable in g.i pipings to existing CCTV System at existing reception center

security room

170 M

4 CARD ACCESS SYSTEM

4.1 Supply and install Card Access Controllers 2 NO

4.2 Supply and install Card Access Devices c/w 1.5 mm2 PVC CU. screened cables:-

i. Card Reader Unit 8 NO

ii. Exit Push Button 8 NO

iii. Breakglass 8 NO

iv. Electromagnetic Lock (600 LBS) 10 NO

4.3 Supply and install network switch/interface unit 1 LOT

4.4 Supply and install CAT6 UTP cabling from controllers to network interface unit 1 LOT

4.5 Supply and install fiber converters 1 LOT

4.5 Supply and install fiber optic cable to existing card access system at existing IT server room 80 M

4 TESTING AND COMMISSIONING

Testing and commissioning of the complete CCTV system with test report and certification 1 LOT

Testing and commissioning of the complete card access system with test report 1 LOT

5 TRAINING

Training of the clients representative for a period of 1 week on the CCTV system, and how to undertake

future moves, upgrading, and changes.

1 LOT

6 Items not included in the above, but described in the conditions of contract, specifications and as

indicated in drawings, also required by the legislation and efficient operation of the entire installation. If

non required, please write "NIL" otherwise full details of the items to be given.

6.1

6.2

6.3

E AIR-CONDITIONING SYSTEM

Page 19

Page 20: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions

1 AIR CONDITIONING UNIT

To supply material, labour, install air-cooled split unit systems c/w indoor and outdoor units, insulated

refrigerant pipings in upvc trunking, power and signal cabling in pvc conduit, drain pump, wired controller

& remote control, insulation, starters, hot dipped galvanized mild steel support and all necessary

accessories.

1.1 Ceiling Cassette c/w wired controller

1.1.1 17,100 BTU/HR 13 NO

1.2 Wall Unit c/w remote control

1.2.1 9,000 BTU/HR 20 NO

1.2.2 12,300 BTU/HR 2 NO

2 DRAIN PIPING SYSTEM

To supply and install insulated condensate drain piping with gradient in upvc trunking/concealed in

wall/slab for split units to the nearest drain point c/w insulation, pipe sleeves and all necessary

accessories to complete installation.

Cassete Units 13 NO

Wall Units 22 NO

3 TESTING AND COMMISSIONING 1 LOT

4 Items not included in the above, but described in the conditions of contract, specifications and as

indicated in drawings, also required by the legislation and efficient operation of the entire installation. If

non required, please write "NIL" otherwise full details of the items to be given.

4.1 Dismantling of existing AC systems 1 LOT

4.2

4.3

F INTERNAL COLD WATER AND SANITARY PLUMBING SERVICES

Note:- Contractor to inspect and visit site for exact measurement of existings services tapping

etc.

1 INTERNAL COLD WATER SERVICES

1.1 To supply and install all cold water distribution pipes c/w angle valves, pipe fittings, hangers, supports,

pipe sleeves fire seals and all necessary accessories for the toilets as per tender drawing

NEW TOILET 1 1 LOT

NEW TOILET 2 1 LOT

NEW DISABLED TOILET 1 LOT

NEW PANTRY 1 LOT

1.2 To supply and install all distribution pipe including tapping to existing pipe

PPR PN16 PIPING 1 LOT

SS304 PIPING 1 LOT

2 SANITARY PLUMBING SERVICES

2.1 To supply and install branch soil, waste and ventilation pipes including termination into the existing

manholes c/w floor traps, pipe fittings, brackets and all associated accessories for the toilets as per

tender drawing

1 LOT

2.2 To supply and install new gully traps 2 NO

2.3 To supply and install new inspection chamber 1 NO

Page 20

Page 21: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions3 SANITARY FITTING

Supply & Install the following fittings c/w ball valves, SS flex hose, accessories etc for the toilets as

per tender drawing:- 3.1 Pedestal Water Closets 3 NO

3.2 Sinks 1 NO

3.3 Basins 3 NO

3.4 Sink Taps 1 NO

3.5 Basin Taps 3 NO

3.6 Hand Bidet 3 NO

3.7 Floor Traps 4 NO

3.8 Shower Head 1 NO

3.9 Stainless steel grating for all sanitary floor trap & waste trap 4 NO

4 TESTING & COMMISIONING 1 LOT

5 Items not included in the above, but described in the conditions of contract, specifications and as

indicated in drawings, also required by the legislation and efficient operation of the entire installation. If

non required, please write "NIL" otherwise full details of the items to be given.

5.1

5.2

5.3

G FIRE ALARM SERVICES

Note:- Contractor to inspect and visit site for exact measurement of existings services tapping

etc.

1 FIRE ALARM DETECTION

1.1 To supply and install fire alarm devices c/w cabling

BOMBA APPROVED TYPE SMOKE DETECTOR 5 NO

BOMBA APPROVED TYPE FIRE ALARM BREAKGLASS 3 NO

BOMBA APPROVED TYPE FIRE ALARM BELL/SOUNDER 3 NO

1.2 To supply and install fire extinguisher 3 NO

1.3 To refurbish and reinstall existing fire alarm panel including all required accessories etc. 1 LOT

2 TESTING & COMMISIONING 1 LOT

3 Items not included in the above, but described in the conditions of contract, specifications and as

indicated in drawings, also required by the legislation and efficient operation of the entire installation. If

non required, please write "NIL" otherwise full details of the items to be given.

3.1

3.2

3.3

Bill 5Drawing No :

5016A/RSDDSU/FURN.PLAN/TD_GS

SYSTEM FURNITURE & OFFICE SEATING

Page 21

Page 22: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditions5016A/RSDDSU/TABLE.DETAIL/TD_GS

A SYSTEM FURNITURE

1 GENERAL WORKSTATION - RECTANGULAR

a Furniture grade plywood with timber laminate and metal frame with stainless steel leg support

Size : 1500mmL x 750mmD x 750mmHT

i Open Area Workstation 36 SET

ii Offices 16 SET

b Work station to install detachable office booth panelling on 3 sides of the general workstation. Solid

office booth seperater from ground to table top, transucent office booth seperater from table top to

1500mmH from ground according to tender drawings.

Size : 1500mmL x 750mmD x 1500mmH

i Open Area Workstation 36 SET

2 MEETING TABLE - RECTANGULAR

8 seater; Size : 2250mmL x 1125mmW x 750mmHT

a Meeting Room 2 SET

3 METAL HIGH FILING CABINET

Size : 900mmL x 450mmD x 1800mmH

a Utilities 1 4 SET

b Utilities 2 2 SET

c Filing Room 4 SET

d Storage 8 SET

B OFFICE SEATING

1 HIGH BACK ERGONOMIC MESH CHAIR

High Back Ergonomic Mesh Chair with Mesh Back and Fabric Seat c/w Arm Rest and Castor

i Offices 16 NO

ii Open Area Workstation 36 NO

2 OFFICE VISITOR CHAIR

Stackable Office Visitor Chair with Fabric Seats and Powder Coated Steel Frame

i Offices 32 NO

ii Meeting Room 16 NO

Bill 6IMPORTANT NOTE: To refer to method statement for refurbishment of roof over existing building

attached together with the tender documents for detail instruction

A BUILDER'S WORK

1 SITE PREPARATION & REMOVAL WORKS

a.To demolish, remove and cart away all unwanted existing structure, interior & architectural component,

fittings & fitments, ground works according to site condition and as per phasing and demolition plan1 LOT

NEW ROOF OVERLAY

Page 22

Page 23: Bill of Quantities (BOQs) - Annex B Refurbishment of ...

ITEM DESCRIPTION QTY UNIT

Bill of Quantities (BOQs) - Annex B

Refurbishment of Existing Blocks in UNHCR Office Malaysia

Preliminaries & General Conditionsb.To reroute, make good and modify any services that may clash with the refurbishment works of the new

roof overlay above and below ground.1 LOT

Drawing No :

5016A/RSDDSU/ROOF.REFURB/TD_GS

2 ROOF STRUCTURE REPAIR OR REPLACEMENT

a.

To assess and make good all existing structures and components required in roof overlay which

includes and is not limited to replacing faulty structural members, anti-termite treatment and anti-rust

protection, and repainting all exposed members with 1 layer undercoat and 2 layers of suitable top

coating.

> Anti-rust Undercoat - Nippon MIO or equivalent

> Top Coat - Nippon Hydro or equivalent

1 LOT

b.

All new and existing metal structures and components to include anti-rust undercoat and 2 topcoat with

suitable painted finished according to engineer's specifications:

> Anti-rust Undercoat - Nippon MIO or equivalent

> Top Coat - Nippon Hydro or equivalent

1 LOT

Drawing No :

5016A/RSDDSU/ROOF.REFURB/TD_GS

3 ROOF COVERING

To supply & install 0.55mm TCT (thick) Ajiya CL710-Clip “n” locking system Hi-Tensile metal roofing

sheets to be fixed onto Clip 710 in pre-painted hot dipped zinc coated steel with insulation and come

complete with necessary fittings and accessories or equivalent to be overlaid onto existing roofing and

cover all edges together with the existing roof with GI flashing onto hardwood timber / fibre cement

fascia board. Metal roofing and GI flashing colour to be selected.

i Cabin 205 MS

ii Services 224 MS

Drawing No :

5016A/RSDDSU/ROOF.REFURB/TD_GS

4 GUTTER SYSTEM

aTo supply & install 180mmD x 180mmW GI gutter c/w GI brakets and all required accessories, fittings

and flashings

i Cabin 60 MR

ii Services 39 MR

b

To supply and install 110mm dia. UPVC rainwater downpipes to channel to existing perimeter drain or

underground to nearest sump for main drainage c/w all required connectors, ties and brackets, and

other necessary accessories.

90 MR

Drawing No :

5016A/RSDDSU/ROOF.REFURB/TD_GS

5 CEILING WORKS

aTo repair and repaint any ceiling panel that is damaged and reinstate any services and wiring on the

underside of the roof whether it is internal of the building or external1 LOT

Page 23