BILL NR. 2 POSTGRADUATE I.C.T. RESEARCH...

43
POSTGRADUATE I.C.T. RESEARCH LABORATORIES BUILDING BILL NR. 2

Transcript of BILL NR. 2 POSTGRADUATE I.C.T. RESEARCH...

POSTGRADUATE I.C.T. RESEARCH

LABORATORIES BUILDING

BILL NR. 2

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 1 SUBSTRUCTURE

Site preparation

A Clear site of bushes, weeds, grass and undergrowths,

grub up all roots and dispose

3,039 m2 75.00 227,925.00

Excavation and Earthwork

Excavation; normal soil;

B Topsoil for preservation; average depth 150mm 2,396 m2 120.00 287,520.00

C Pits for column bases; maximum depth not exceeding

2.00m starting from stripped level 433 m3

600.00 259,800.00

D Foundation trench; width exceeding 0.30m; maximum

depth not exceeding 2.00m starting from stripped level

648 m3 550.00 356,400.00

Disposal of excavated material;

E Offsite 495 m3 350.00 173,250.00

Filling

F Backfill around foundations with material arising from

excavations; average thickness exceeding 0.25m

586 m3 300.00 175,800.00

Surface treatment;

G Pesticides; "Dieldrex 20" anti-termite solution; apply

to excavated surfaces

3,873 m2 100.00 387,300.00

Filling;

H Hardcore to make up levels; thickness 200mm; stone

granite; compacted in layers not exceeding 150mm

thick

1,313 m2 1,750.00 2,297,750.00

J Approved laterite filling to make up levels; not

exceeding 150mm thick; laterite obtained off site;

compacted to 95% B.S. compaction

374 m2 720.00 269,280.00

K Approved laterite filling to make up levels; exceeding

250mm thick; laterite obtained off site; compacted to

95% B.S. compaction

423 m3 3,550.00 1,501,650.00

TO COLLECTION 5,936,675.00

BILL NR. 02 LABORATORY BUILDING Page 2/2

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

SUBSTRUCTURE (CONT'D)

Damp proofing;

A Damp proofing; horizontal; single layer 0.26mm

polythene sheet; laid on unblinded hardcore to receive

concrete

1,362 m2 320.00 435,840.00

Concrete Work

In situ concrete

Plain; grade 10;

B Beds as blinding; thickness not exceeding 100mm 43 m3

23,500.00 1,010,500.00

Plain ; grade 20;

C Foundations; thickness 150-300mm 124 m3

25,500.00 3,162,000.00

D Steps 9 m3 25,500.00 229,500.00

E Beds; poured against unblinded hardcore; thickness

100- 150mm

204 m3 25,500.00 5,202,000.00

Reinforced; grade 20;

F Isolated foundations; thickness 150-300mm 141 m3

28,500.00 4,018,500.00

G Isolated columns 12 m3

28,500.00 342,000.00

Reinforcement for in situ concrete; Reinforcement to

BS 4449 (Provisional)

Bars; high yield steel

H 10mm diameter; in links and stirrups 6,902 kg 272.00 1,877,344.00

Bars; high yield steel

J 12-20mm diameter; straight and bent 16,104 kg 272.00 4,380,288.00

TO COLLECTION 20,657,972.00

BILL NR. 02 LABORATORY BUILDING Page 2/3

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

SUBSTRUCTURE (CONT'D)

Fabric

A Fabric; reference A142; to BS 4483; weighing

2.22kg/m2; with 300mm laps on all sides; in concrete

ground slab

1,362 m2 500.00 681,000.00

Formwork; Sawn;

Foundation and beds

B Edges of bed; not exceeding 250mm high 251 m 350.00 87,850.00

C Faces of isolated foundation; 250-500mm high 811 m 700.00 567,700.00

D Sides of column; square and rectangular in shape 151 m2

1,350.00 203,850.00

E Sides of column; circular in shape 14 m2

1,450.00 20,300.00

F Edges of steps; not exceeding 250mm high 87 m 350.00 30,450.00

Blockwork

Hollow Sandcrete Blockwork; nominal size

450x225mm high; laid stretcher bond with cement

and sand (1:3) mortar; cavities filled solid with plain

in situ concrete grade 20; Foundations;

G 225mm thick 759 m2

3,450.00 2,618,550.00

Sundries

H Form 12mm expansion joint between 150mm floor

bed and fill with celotex or similar equal and other

opproved non-porous and compressible compound17 m 1,050.00 17,850.00

Additional Works

J Allow a Provisional Sum of 1,200,000.00 for

additional works in substructure to be expanded as

directed

1,200,000.00

TO COLLECTION 5,427,550.00

COLLECTION

Collection from page 2/1 5,936,675.00

Collection from page 2/2 20,657,972.00

Collection from page 2/3 5,427,550.00

TO SUMMARY N 32,022,197.00

BILL NR. 02 LABORATORY BUILDING Page 2/4

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 2 FRAME

Concrete Work

In situ concrete

Reinforced; grade 20;

A Isolated columns 56 m3 28,500.00 1,596,000.00

B Beams 74 m3 28,500.00 2,109,000.00

Reinforcement for in situ concrete; Reinforcement to

BS 4449 (Provisional)

Bars; high yield steel

C 10mm diameter; in links and stirrups 9,788 kg 272.00 2,662,336.00

D 16-25mm diameter; straight and bent 14,682 kg 272.00 3,993,504.00

Isolated features;

E Sides of column; square in shape 747 m2 1,350.00 1,008,450.00

F Sides of column; circular in shape 32 m2 1,450.00 46,400.00

G Sides and soffits of beams; rectangular in shape 809 m2 1,350.00 1,092,150.00

TO SUMMARY N 12,507,840.00

BILL NR. 02 LABORATORY BUILDING Page 2/5

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 3 UPPER FLOOR

Concrete Work

In situ concrete

Reinforced; grade 20;

A Slabs; suspended; thickness 150-300mm 120 m3 28,500.00 3,420,000.00

B Raked suspended Slabs; suspended; thickness 100-

150mm

42 m3 28,500.00 1,197,000.00

Reinforcement for in situ concrete; Reinforcement to

BS 4449 (Provisional)

Bars; high yield steel

C 10-16mm diameter; straight and bent 24,797 kg 272.00 6,744,784.00

Formwork; Sawn;

Slabs and associated features

D Edges of suspended slabs; depth not exceeding

250mm

151 m 350.00 52,850.00

E Ditto raked suspended slabs; depth not exceeding

250mm

31 m 350.00 10,850.00

F Ditto raked suspended slabs; depth 250-500mm 56 m 350.00 19,600.00

G Soffit of suspended slab; rectangular; thickness not

exceeding 200mm; horizontal

802 m2 1,350.00 1,082,700.00

H Soffit of raked slab; sloping not exceeding 15

degrees from the horizontal

238 m2 1,350.00 321,300.00

J Edges of steps; not exceeding 250mm high 255 m 350.00 89,250.00

TO SUMMARY N 12,938,334.00

BILL NR. 02 LABORATORY BUILDING Page 2/6

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 4 STAIRCASES

Concrete Work

In situ concrete

Reinforced; grade 20;

A Staircases 8 m3 28,500.00 228,000.00

B Staircases beams 1 m3 28,500.00 28,500.00

Reinforcement for in situ concrete;

Reinforcement to BS 4449 (Provisional)

Bars; high yield steel

C 10-16mm diameter; straight and bent 1379 kg 272.00 375,088.00

Formwork; Sawn

Slabs, staircases and associated features

D Soffit of staircase; sloping not exceeding 15 degrees

from the horizontal

20 m2 1,350.00 27,000.00

E Soffit of landing slabs; thickness not exceeding

200mm; horizontal

13 m2 1,350.00 17,550.00

F Edges of landing slab; depth not exceeding 250mm 31 m 350.00 10,850.00

G Edges of staircase flights; maximum width 300mm 35 m 350.00 12,250.00

H Edges of risers not exceeding 250mm high 65 m 350.00 22,750.00

J Sides and soffits of beams; rectangular in shape 11 m2 1,350.00 14,850.00

TO COLLECTION 736,838.00

BILL NR. 02 LABORATORY BUILDING Page 2/7

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

STAIRCASES (CONT'D)

Finishes

In-situ finishings

Render; cement and sand (1:6); 15mm thick; as

specified; finish fair and smooth;

A Walls 178 m2 650.00 115,700.00

B Sloping soffits of staircase 20 m2 650.00 13,000.00

C Soffits of landings 13 m2 650.00 8,450.00

D String; not exceeding 300mm wide 18 m2 650.00 11,700.00

Beds and backings

Floors; screeded bed; 41mm thick; level and to falls;

E Landing 13 m2 1,000.00 13,000.00

F Treads; 300mm wide 61 m 500.00 30,500.00

G Ditto; risers; 165mm high 65 m 300.00 19,500.00

Vitrified Ceramic floor tiles; colour patterned;

unglazed; fixing with approved adhesive; pointing

with matching grout; floors300x300x9mm nominal

size;

H Landing 13 m2 3,100.00 40,300.00

J Treads; 300mm wide 61 m 1,550.00 94,550.00

K Ditto; risers; 150mm high 65 m 1,550.00 100,750.00

L Extra over for 50x13mm non-slip rubber insert 65 m 650.00 42,250.00

TO COLLECTION 489,700.00

BILL NR. 02 LABORATORY BUILDING Page 2/8

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

STAIRCASES (CONT'D)

Metalwork

A 50mm diameter hollow mild steel handrail welded to

balusters (measured separately)

20 m 5,200.00 104,000.00

B Ditto intermediate rails welded to balusters (measured

separately)

61 m 5,200.00 317,200.00

C 50mm diameter hollow mild steel balusters at 500mm

centres; 900mm high; one end embedded in concrete

100mm deep and other end welded to metal core rail

(measured separately)

41 nr 5,200.00 213,200.00

TO COLLECTION 634,400.00

COLLECTION

Collection from page 2/6 736,838.00

Collection from page 2/7 489,700.00

Collection from page 2/8 634,400.00

TO SUMMARY N 1,860,938.00

BILL NR. 02 LABORATORY BUILDING Page 2/9

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 5 ROOF

Concrete Work

In situ concrete

Reinforced; grade 20;

A Roof gutter; suspended; thickness 150-300mm 13 m3 28,500.00 370,500.00

B Roof Beams 67 m3 28,500.00 1,909,500.00

C Upstand Beams 87 m3 28,500.00 2,479,500.00

D Roof Slab 21 m3 28,500.00 598,500.00

Reinforcement for in situ concrete; Reinforcement to

BS 4449 (Provisional)

Bars; high yield steel

E 10-12mm diameter; in links and stirrups 6768 kg 272.00 1,840,896.00

Bars; high yield steel

F 12mm diameter; straight and bent 10152 kg 272.00 2,761,344.00

G 16mm diameter; straight and bent 13536 kg 272.00 3,681,792.00

H 20mm diameter; straight and bent 3384 kg 272.00 920,448.00

Formwork; Sawn;

J Sides and soffits of beams; rectangular in shape 945 m2 1,350.00 1,275,750.00

K Soffit of suspended slab; rectangular; thickness not

exceeding 200mm; horizontal

417 m2 1,350.00 562,950.00

L Edges of suspended slabs; depth not exceeding 250mm 260 m 350.00 91,000.00

TO COLLECTION 16,492,180.00

BILL NR. 02 LABORATORY BUILDING Page 2/10

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ROOF (CONT'D)

Structural Steelwork

Fabricated; weldeable steel; BS 4360; grade 43C,

welded fabrication and bolted site connection in

accordance with BS 449 Part 2

A Steel top and bottom members; angle ; size

75x75x6mm thick (7.34kg/m)

4052 kg 300.00 1,215,600.00

B Steel struts; angle ; size 75x75x6mm thick (7.34kg/m) 1502 kg 300.00 450,600.00

C Circular hollow section; size 350mm diameterx10mm

thick (85.20kg/m)

94 kg 300.00 28,200.00

D 25mm diameter "J" holding down bolts; 50mm long;

connecting steel trusses to base plates (measured

separately)

192 nr 405.00 77,760.00

Unframed Steelwork

E 150x50x1.50mm thick (3.50kg/m) zed purlins fixed to

steel rafters (measured separately)

880 kg 300.00 264,000.00

F Base plates; 200x200x15mm thick mild steel welded to

base of truss

12 nr 450.00 5,400.00

G Gusset plates; 450x230x10mm thick mild steel welded

to truss

672 nr 600.00 403,200.00

Fittings, connections, fixings and anchorages

H Angle cleats; 100x100x8mm thick (12.2kg/m) 88 kg 300.00 26,400.00

J 12mm sag rod; connecting zed purlins (measured

separately)

119 kg 272.00 32,368.00

K 16mm holding bolts; 50mm long; connecting angle

cleats to zed purlins (measured separately)

288 nr 280.00 80,640.00

L 18mm holding bolts; 50mm long; connecting angle

cleats to zed purlins (measured separately)

114 nr 280.00 31,920.00

Painting

Touch up primer and apply two coats of red oxide

paint to surfaces of steelwork before erection

M Steelwork 536 m2 350.00 187,600.00

TO COLLECTION 2,803,688.00

BILL NR. 02 LABORATORY BUILDING Page 2/11

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ROOF (CONT'D)

(ALL PROVISIONAL)

Woodwork

Carcassing items;

Roof members; pitched; sawn creosoeted hardwood

(black Afara) ; with nailed scarfed joints; members

fixed together with galvanized nails of appropriate

specifications

A 150x50mm rafters 1015 m 300.00 304,500.00

B 150x50mm struts and king post 1068 m 300.00 320,400.00

C 150x50mm Ceiling ties 661 m 300.00 198,300.00

D 75x50mm purlins 1442 m 245.00 353,290.00

Aluminium Roof Covering

Corrugated longspan aluminium roof sheeting of

approved colour; lapped one corrugation at sides and

150mm at ends; fixed in accordance with

manufacturer's instructions to steel zed purlins

(measured separately)

E 0.55 thick roof coverings; pitch not exceeding 50

degrees

1231 m2 2,850.00 3,508,350.00

Corrugated roofing sheet

Roofing accessories; plain sheet;

F 0.70 thick aluminium ridge capping; 600mm girth fixed

in accordance with the manufacturer's details

161 m 1,710.00 275,310.00

G 0.70 Wall flashing; 450mm girth fixed in accordance

with the manufacturer's details

234 m 1,282.50 300,105.00

H Eave flashing; 300mm girth fixed in accordance with

the manufacturer's details

234 m 855.00 200,070.00

TO COLLECTION 5,460,325.00

BILL NR. 02 LABORATORY BUILDING Page 2/12

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ROOF (CONT'D)

Paralon NT4

Single layer ‘Paralon NT4’ polyester based (180g/m2)

mineral surfaced on screeded surfaces (measured

separately); finished with aluminium paint; in

accordance with manufacturer's instruction

A Roof slab including angle fillets; over 300mm wide; to

falls and cross-falls; horizontal

417 m2 3,200.00 1,334,400.00

B Covering to upstand; girth 1650mm 171 m 5,280.00 902,880.00

C Covering to upstand; girth 1050mm 150 m 5,544.00 831,600.00

D Covering to upstand; girth 700mm 161 m 3,880.80 624,808.80

Finishes

Beds and Backings

Cement and sand (1:4); treated with approved

hardener and water-proofer; over 300mm wide

E 25mm average screeded laid to falls and cross-falls

ditto

417 m2 550.00 229,350.00

F 15mm thick screeded backing to receive paralon NT4

(measured separately)

552 m2 650.00 358,800.00

Roof drains;

G 100mm diameter uPVC pipe inserted in concretework

(measured separately)

138 m 750.00 103,500.00

H 100mm diameter uPVC bend 69 nr 650.00 44,850.00

J Fulbora, 100mm diameter 23 nr 12,345.00 283,935.00

TO COLLECTION 4,714,123.80

ROOF (CONT'D)

COLLECTION

Collection from page 2/9 16,492,180.00

Collection from page 2/10 2,803,688.00

Collection from page 2/11 5,460,325.00

Collection from page 2/12 4,714,123.80

TO SUMMARY N 29,470,316.80

BILL NR. 02 LABORATORY BUILDING Page 2/13

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 6 EXTERNAL AND INTERNAL

WALLS

Concrete Work

In situ concrete

Reinforced; grade 20;

A Beams; isolated as lintels 18 m3 28,500.00 513,000.00

Reinforcement for in situ concrete; Reinforcement to

BS 4449 (Provisional)

Bars; round mild steel

B 10mm diameter; in links and stirrups 941 kg 272.00 255,952.00

Bars; high yield steel

C 12mm diameter; straight and bent 1357 kg 272.00 369,104.00

Formwork; Sawn;

D Sides and soffits of lintels 229 m2 1,350.00 309,150.00

Blockwork

Blockwork; hollow sandcrete 450x225mm high

nominal; laid stretcher bond with cement and sand

(1:3) mortar;

E 225mm thick 2419 m2 2,950.00 7,136,050.00

F 150mm thick 247 m2 2,800.00 691,600.00

Screen wall; precast concrete blocks; 330x200mm

high nominal; bedded, jointed and pointed with

cement and sand mortar (1:3)

F 150mm thick 11 m2 3,062.00 33,682.00

TO SUMMARY N 9,308,538.00

BILL NR. 02 LABORATORY BUILDING Page 2/14

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 7 DOORS

Metalwork

Aluminium doors; high quality powder coated

anodised finish; complete with ironmongery, corner

joints, neoprene gasket system, and all necessary

fittings and accessories; factory preglazed with 6mm

tinted glazing; with and including fitting to blockwork

and/or concretework

Swing doors

A Size 2000x2100mm high (D1) 1 nr 92,400.00 92,400.00

B Size 1800x2100mm high (D2) 1 nr 85,000.00 85,000.00

C Size 1500x2100mm high (D3) 10 nr 69,300.00 693,000.00

D Size 1200x2100mm high (D4) 4 nr 55,750.00 223,000.00

Purpose made steel doors and doorframes steel

units; complete with ironmongery; anti-corrosive

finish; fixing in accordance with the manufacturer's

instructions

E Size 900x2100mm high (D5') 1 nr 65,000.00 65,000.00

Woodwork

Second Fixings;

44mm thick; doors or other approved solid mansonia

hardwood door, Complete with door frames and

matching architraves with ironmongery ; spray

polished finish

F Size 900x2100mm high (D5) 39 nr 32,500.00 1,267,500.00

G Size 750x2100mm high (D6) 35 nr 32,500.00 1,137,500.00

TO SUMMARY N 3,563,400.00

BILL NR. 02 LABORATORY BUILDING Page 2/15

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 8 WINDOWS

Metalwork

Curtain walls comprising concealed seamless

extruded aluminium sections incorporating thermal

barriers; glazing with fully drained neoprene gasket

systems fixing to structure with all necessary brackets

and bolts; reflective anodised;

A Infilled panels; flat 155x60mm mullions at 280mm

horizontal centres; 95x60mm transomes; single glazed

panels with 6mm tinted glazing

248 m2 52,000.00 12,896,000.00

Aluminium windows; bronze anodised finish;

comprising extruded aluminium sections

incorporating thermal barriers; glazing with fully

drained neoprene gasket systems fixing to structure

with all necessary brackets and bolts; supplied with ;

ironmongery, and all necessary fittings and

accessories; factory pre-glazed with 6mm tinted

glazing; complete with netting

Casement

B Overall size 3600x1350mm high (W8) 2 nr 60,750.00 121,500.00

C Overall size 1800x1350mm high (W1) 28 nr 30,300.00 848,400.00

D Overall size 1650x1350mm high (W2) 8 nr 27,750.00 222,000.00

E Overall size 1500x1350mm high (W3') 2 nr 25,320.00 50,640.00

F Overall size 1200x1350mm high (W4) 13 nr 20,250.00 263,250.00

G Overall size 750x1350mm high (W5) 24 nr 12,750.00 306,000.00

H Overall size 1500x600mm high (W3) 16 nr 11,250.00 180,000.00

J Overall size 1200x600mm high (W4') 4 nr 9,000.00 36,000.00

K Overall size 975x600mm high (W6) 10 nr 7,500.00 75,000.00

L Overall size 800x600mm high (W6') 12 nr 7,500.00 90,000.00

M Overall size 600x600mm high (W7) 13 nr 5,200.00 67,600.00

N Overall size 300x600mm high (W7') 2 nr 2,500.00 5,000.00

TO COLLECTION 15,161,390.00

BILL NR. 02 LABORATORY BUILDING Page 2/16

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

WINDOW (CONT'D)

Window Burglary Proofing

Well designed burglar proofing to opening; designed

with 6mm thick flat bar in hexagonal shape and

framed with 25x3mm thick steel flat bar steel; cast

into blockwork; finished with calcium plumbate

primer and gloss paint

A Overall size 3600x1350mm high (W8) 2 nr 17,050.00 34,100.00

B Overall size 1800x1350mm high (W1) 28 nr 8,500.00 238,000.00

C Overall size 1650x1350mm high (W2) 8 nr 7,800.00 62,400.00

D Overall size 1500x1350mm high (W3') 2 nr 7,100.00 14,200.00

E Overall size 1200x1350mm high (W4) 13 nr 5,700.00 74,100.00

F Overall size 750x1350mm high (W5) 24 nr 3,550.00 85,200.00

G Overall size 1500x600mm high (W3) 16 nr 3,150.00 50,400.00

H Overall size 1200x600mm high (W4') 4 nr 2,500.00 10,000.00

J Overall size 975x600mm high (W6) 10 nr 2,050.00 20,500.00

K Overall size 800x600mm high (W6') 12 nr 1,700.00 20,400.00

L Overall size 600x600mm high (W7) 13 nr 1,260.00 16,380.00

M Overall size 300x600mm high (W7') 2 nr 650.00 1,300.00

TO COLLECTION 626,980.00

WINDOW (CONT'D)

COLLECTION

Collection from page 2/15 15,161,390.00

Collection from page 2/16 626,980.00

TO SUMMARY N 15,788,370.00

BILL NR. 02 LABORATORY BUILDING Page 2/17

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 9 WALL FINISHES

In situ finishings

Render; cement and sand (1:6); 15mm thick; as

specified; finished fair and smooth;

Walls; over 300mm wide

A Internally including narrow width 2,535 m2 650.00 1,647,750.00

B Externally including narrow width 1,606 m2 650.00 1,043,900.00

C Isolated Column 151 m2 650.00 98,150.00

D Parapet wall 574 m2 650.00 373,100.00

Walls; screeded backing; 12mm thick; over 300mm

wide

E To receive ceramic tiles 661 m2 500.00 330,500.00

Tile, slab and block finishings

White glazed ceramic wall tiles; 150x150x6mm thick

nominal size; fixing with cement and sand mortar;

pointing with cement on screeded backing (measured

separately)

F Wall 661 m2 2,650.00 1,751,650.00

TO SUMMARY N 5,245,050.00

BILL NR. 02 LABORATORY BUILDING Page 2/18

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 10 FLOOR FINISHES

Beds

Floors exposed aggregate finishings and rough

concrete; screeded bed; 50mm thick; level and to

falls;

A Internally; corridors 717 m2 1,200.00 860,400.00

Floors; screeded bed; 41mm thick; level and to

falls;

B To receive ceramic tiles; internally 1,069 m2 1,000.00 1,069,000.00

C Ditto steps treads; 1000mm wide 235 m 1,235.00 290,225.00

D Ditto; risers; 175mm high 235 m 300.00 70,500.00

Floors; screeded bed; 30mm thick; level and to

falls;

E To receive granite tiles; internally 53 m2 1,100.00 58,300.00

Tiles, slab and block finishings

Vitrified Ceramic floor tiles; colour patterned;

unglazed; fixing with approved adhesive; pointing

with matching grout; floors 600x600x9mm

nominal size;

F Tiling; internally; over 300mm wide 1,069 m2 3,100.00 3,313,900.00

G Skirting; 100mm high 317 m 1,395.00 442,215.00

H Ditto; risers; 175mm high 235 m 313.88 73,760.63

Polished granite tiles; 20mm thick; jointing and

pointing; as specified; on screeded bed (measured

separately);

J Tiling; internally; over 300mm wide 53 m2 9,800.00 519,400.00

TO COLLECTION 6,697,700.63

BILL NR. 02 LABORATORY BUILDING Page 2/19

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

FLOOR FINISHES (CONT'D)

RAISED ACCESS FLOORS

Raised floor: 'Modular Raised Floor System

(MRFS)

‘Lindner’ or ‘Sadi’ Raised Floor System 600 x

600mm

x 38mm Calcium sulphate core covered with

'linoleum

having galvanized steel or 'aluminium as

bottom-plate

and edge 'trim on steel pedestals painted with

anti

corrosive paint plus sound absorption gaskets.

Pedestals to be fixed with adhesive on floor

A Floors, 38mm thick, 'cavity 300 high; fixing

with adhesive, 'access panels 600 x 600 with

high pressure, laminate covering; plugging.

11 m2 30,000.00 330,000.00

TO COLLECTION 330,000.00

COLLECTION

Collection from page 2/18 6,697,700.63

Collection from page 2/19 330,000.00

TO SUMMARY N 7,027,700.63

BILL NR. 02 LABORATORY BUILDING Page 2/20

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 11 CEILING FINISHES

In situ finishings

Render; cement and sand (1:6); 15mm thick; as

specified; finish fair and smooth;

A Suspended slabs 802 m2 650.00 521,300.00

B Sloping soffit of raked floor slabs 238 m2 650.00 154,700.00

Suspended ceiling;

“Armstrong” or other approved mineral fibre;

fissured panels 600x600x12mm thick in aluminium

grids; suspended with steel wires;

C Ceilings; internally 364 m2 3,250.00 1,183,000.00

Celotex ceiling board or other approved ceiling

sheets; square edge; 600x600x12mm thick;

patterned with regular edge grooves; with and

including all timber supports; paint finish; over

300mm wide

D Ceilings; internally 937 m2 2,250.00 2,108,250.00

Carcassing items;

Noggins; sawn creosoeted hardwood; with nailed

scarfed joints; members fixed together with

galvanized nails of appropriate specifications;

E 50x50mm noggins 4220 m 50.00 211,000.00

F 50x8mm ceiling strips 4220 m 40.00 168,800.00

TO SUMMARY N 4,347,050.00

BILL NR. 02 LABORATORY BUILDING Page 2/21

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 12 PAINTING AND

DECORATING

Painting

Painting render; prime and apply two full finishing

coats of emulsion paint ;

General surfaces; over 300mm girth;

A Walls; internally 2535 m2 420.00 1,064,700.00

Painting render; prime and apply one full finishing

coat of textured paint ;

General surfaces; over 300mm girth;

B Walls; externally 1606 m2 650.00 1,043,900.00

C Isolated Column 151 m2 650.00 98,150.00

D Parapet wall 574 m2 650.00 373,100.00

Soffits;

General surfaces; over 300mm girth;

E Suspended slabs 1040 m2 420.00 436,800.00

Staircase areas;

F Walls 178 m2 420.00 74,760.00

Soffits;

G Soffits of landings 13 m2 420.00 5,460.00

H Sloping soffits of staircase 20 m2 420.00 8,400.00

J String; not exceeding 325mm girth 40 m2 420.00 16,800.00

TO SUMMARY N 3,122,070.00

BILL NR. 02 LABORATORY BUILDING Page 2/22

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR 13 PLUMBING AND

MECHANICAL INSTALLATIONS

Piped Supply Systems Installations;

WATER SUPPPLY

Supply, deliver and install in trench the following

soil and waste uPVC pipes complete with jointing

materials and socket to BS4515 (PANAR ,TIGRE OR

SIMILAR APPROVED).

A 32mm diameter 300 m 900.00 270,000.00

B 25mm diameter FHR 90 m 800.00 72,000.00

C 19mm diameter 120 m 700.00 84,000.00

D 13mm diameter 90 m 500.00 45,000.00

Elbow

E 32mm Dia 30 nr 500.00 15,000.00

F 25mm Dia 20 nr 400.00 8,000.00

G 19mm Dia 60 nr 350.00 21,000.00

H 13mm Dia 270 nr 300.00 81,000.00

Reducing Elbow

J 35 x 25mm 10 nr 500.00 5,000.00

K 25 x 19mm 10 nr 450.00 4,500.00

L 19 x 13mm 20 nr 450.00 9,000.00

Equal Tee

M 32 x 32 x 32mm 20 nr 550.00 11,000.00

N 25 x 25 x 25mm 15 nr 500.00 7,500.00

P 19 x 19 x 19mm 30 nr 450.00 13,500.00

Q 13 x 13 x 13mm 35 nr 400.00 14,000.00

Reducing Tee

R 32 x 32 x 25mm 10 nr 550.00 5,500.00

S 25 x 25 x 19mm 15 nr 450.00 6,750.00

T 19 x 19 x 13mm 25 nr 400.00 10,000.00

U 19 x 13 x 13mm 30 nr 400.00 12,000.00

TO COLLECTION 694,750.00

BILL NR. 02 LABORATORY BUILDING Page 2/23

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

PLUMBING INSTALLATIONS (CONT'D)

Reducer

A 32 x 25mm 10 nr 450.00 4,500.00

B 25 x 19mm 15 nr 400.00 6,000.00

C 19 x 13mm 200 nr 400.00 80,000.00

Nipple

D 19mm 20 nr 350.00 7,000.00

E 13mm 50 nr 300.00 15,000.00

Valves

F 32mm Gate Valve 3 nr 4,500.00 13,500.00

G 19mm Gate Valve 10 nr 3,000.00 30,000.00

H 13mm Angle Valve with chrome cover plate 90 nr 2,150.00 193,500.00

J 13mm Copper Flexible connector 60 nr 1,320.00 79,200.00

K 19mm diameter Stand tap 4 nr 3,000.00 12,000.00

SOIL AND WASTE PIPEWORK

Supply, deliver and install in trench the following

soil and waste uPVC pipes complete with jointing

materials and socket to BS4515 (PANAR OR

SIMILAR APPROVED).

L 150mm 90 m 800.00 72,000.00

M 100mm 900 m 700.00 630,000.00

N 50mm 180 m 500.00 90,000.00

FITTINGS

Bends (90 Degree)

P 150mm 252 nr. 650.00 163,800.00

Q 100mm 20 nr. 550.00 11,000.00

R 50mm 120 nr. 350.00 42,000.00

TO COLLECTION 1,449,500.00

BILL NR. 02 LABORATORY BUILDING Page 2/24

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

PLUMBING INSTALLATIONS (CONT'D)

Bends (45 Degree)

A 150mm 5 nr. 650.00 3,250.00

B 100mm 15 nr. 550.00 8,250.00

C 50mm 20 nr. 350.00 7,000.00

TEES

D 150 x 150 x 150mm Wye Tee 5 nr. 750.00 3,750.00

E 100 x 100 x 100mm Wye Tee 90 nr. 650.00 58,500.00

F 50 x 50 x 50mm Wye Tee 120 nr. 400.00 48,000.00

TRAPS

G 32mm Chrome Plated Bottle Trap with 31 nr. 650.00 20,150.00

H 40mm General Purporse Tubular P-Trap 41 nr. 1,200.00 49,200.00

J 50 x 32mm Rubber Adaptor 41 nr. 500.00 20,500.00

K 100 x 50mm Reducer 5 nr. 550.00 2,750.00

L 100mm Vent Cowl 15 nr. 250.00 3,750.00

M 100mm Pan Connector 30 nr. 2,000.00 60,000.00

Socket

N 100mm 10 nr. 400.00 4,000.00

P 50mm 20 nr. 300.00 6,000.00

Q 150mm diameter Rain Water Fulbora Outletf. 42 nr. 12,500.00 525,000.00

R 150mm diameter floor drain. 3 nr. 1,750.00 5,250.00

S 50mm diameter high Quality stainless floor

drain.

36 nr. 1,200.00 43,200.00

TO COLLECTION 868,550.00

BILL NR. 02 LABORATORY BUILDING Page 2/25

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

PLUMBING INSTALLATIONS (CONT'D)

Excavate trench for the underground soil and waste

pipes not exceeding 800mm deep, 500mm wide

including back fill and disposal of spoil as directed

on site

A Trench for pipes 180 m 250.00 45,000.00

Extractor Fans

All ventilation equipments shall be of standard

specifications and of high quality, durable and fitted

with all safety devices for effective operation and

conform to Services Engineers drawings.

B Extractor fan of type G X 6 mounted on wall and

complete with electrically operated anti-back-draught

shutters

18 nr 9,000.00 162,000.00

Sanitary fittings;

Supply and deliver to site the following sanitary

wares complete with all necessary installation

and operational accessories.

C Twyford Brand wash-down white galzed close couple

Water Closet unit with horizontal outlet, P-trap or S-

trap as applicable. Ball valve Flush Master, 9 Litres

Cistern and internal overflow, Seat Cover and Pan

Connector and all necessary installation and

operational accessories.

30 nr 18,500.00 555,000.00

D Twyford white glazed Wash Hand Basin with

single tap hole, concealed bracket with fixing

clamps and centre waste bracket: Dimension 450

x 400mm. complete with pedestal. Basin Tap

shall be Piccolo basin tap with chrome-plated

pop-up waste.. Bottle trap shall be 32mm chrome-

plated with 75mm seal.

30 nr 12,500.00 375,000.00

E Single bowl single drain kitchen sink with double

tap hole, concealed bracket with fixing clamps

and centre waste bracket: Sink Tap shall be 2no.

Piccolo basin tap with chrome-plated pop-up

waste bottle trap shall be 32mm dia

1 nr 16,000.00 16,000.00

TO COLLECTION 1,153,000.00

BILL NR. 02 LABORATORY BUILDING Page 2/26

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

PLUMBING INSTALLATIONS (CONT'D)

A Chrome-plated soap dispenser for fixing in the

toilets with concealed screws.30 nr 2,000.00 60,000.00

B Screw to wall Toilet Roll Holder in stainless

steel with thief proof holder. Complete with

chrome plated fixing screws

30 nr 2,000.00

60,000.00

C Plate plain glass type toilet mirror for placement

and fixing on top of the lavatory basins. 30 nr 5,000.00 150,000.00

D Annal Spray with flexible connector and all

necessary installtion and operational accessaries.30 nr 3,500.00 105,000.00

E Construction of chamber 650x650mm with steel

cover 1 nr 7,500.00 7,500.00

FIRE FIGHTING SYSTEMS

Supply and deliver to site the following items

complete with all necessary installation and operational accessories.

F ABC Dry Chemical Powder fire extinguishers of

9kg capacity filled with Mono-ammonium

phosphate and Ammonium soleplate; with a

discharge time of 15 secs and range of 7m,

complete with indicator discharge hose and wall

hook cylinder. Finish - BLUE; Make - AMEREX

or equal. 14 nr. 12,000.00 168,000.00

G Gas/carbon dioxide fire extinguisher of 6kg

capacity for BC and Electrical fires; with a

discharge range of 7m, complete with pressure

indicator and discharge hose. 14 nr. 15,000.00 210,000.00

H 25mm condesate pipes and fittings 240 m 600.00 144,000.00

J Testing and Commissioning of the entire

installation sum 100,000.00

Builder's work in connection with plumbing and

mechanical services

K Allow a provisional sum of 200,000.00 for builder’s

work in connection with plumbing and mechanical

engineering installations

item 200,000.00

L Allow for testing the plumbing installations to the

satisfaction of the Architect and local authority

including all labour and apparaatus for same

item 100,000.00

TO COLLECTION 1,304,500.00

BILL NR. 02 LABORATORY BUILDING Page 2/27

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

COLLECTION

Collection from page 2/22 694,750.00

Collection from page 2/23 1,449,500.00

Collection from page 2/24 868,550.00

Collection from page 2/25 1,153,000.00

Collection from page 2/26 1,304,500.00

TO SUMMARY N 5,470,300.00

BILL NR. 02 LABORATORY BUILDING Page 2/28

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 14 ELECTRICAL

INSTALLATIONS

L.V. Distribution Equipment

Distribution boards; metal clad; mixed capacity

(MCB) type; complete with intergral breaker; flush

mounted cover with switchgear casing concealed

in wall; All Distribution boards, ELCBS and

MCBS shall be of made in England for effective

automatic breaking of circuits in the event of

circuit failures and/or faults.

Main distribution panel, surface mounted; as

specified

A 400A 11 ways Main MV panel complete with

1no 400A TP&N MCCB incomer, 400A TP&N

bus-bar complete with 1no 160A TP&N

MCCB, 4nos 100A TP&N MCCB, 1no 63A

TP&N MCCB 2nos 32A TP&N MCCB

incomer and 2nos 32A TP&N MCCB Spare

ways, complete with metering and all necessary

accessories (ABB)

1 1 550,000.00 550,000.00

B 160A 14 ways Sub-MV panel complete with

1no 160A TP&N MCCB incomer, 160A TP&N

bus-bar complete with 11nos 32A TP&N

MCCB 1no 63A TP&N MCCB, and 2nos 32A

TP&N MCCB Spare ways, complete with

metering and all necessary accessories (ABB)

1 1 300,000.00 300,000.00

Distribution Board

C 100A, 12-Ways MCCB TP&N Distribution

Board (AC) Complete with 100A MCCB as

integral incoming breaker and MCB outgoings:

(ABB)

2 nr 110,000.00 220,000.00

D 100A, 8-Ways MCCB TP&N Distribution

Board (AC) Complete with 100A MCCB as

integral incoming breaker and MCB outgoings:

(ABB)

2 nr 100,000.00 200,000.00

TO COLLECTION 1,270,000.00

BILL NR. 02 LABORATORY BUILDING Page 2/29

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELECTRICAL INSTALLATION (CONT'D)

A 63A, 4-Ways MCCB TP&N Distribution

Board (AC) Complete with 100A MCCB as

integral incoming breaker and MCB outgoings:

(ABB)

2 nr 80,000.00 160,000.00

B Fuse Switch 32A (ABB) 10 nr 20,000.00 200,000.00

ELCB

C 100A TP&N ELCBs complete with metal

enclosure (ABB)

4 nr 65,000.00 260,000.00

D 63A TP&N ELCBs complete with metal

enclosure (ABB) 2 nr 50,000.00 100,000.00

Conduit; straight; 20 mm pvc; as specified;

concealed in walls, floors screed and concrete;

rate to include for all necessary fitting, accessories

and ancillaries deemed necessary for a complete

installationE 100mm diameter (Provisional) 50 m 600.00 30,000.00

F 50mm diameter (Provisional) 400 m 400.00 160,000.00

G 25mm diameter (Provisional) 400 m 350.00 140,000.00

Cables

H 4 x 185mm2 PVC/SWA/PVC cable (Provisional) 50 m 39,000.00 1,950,000.00

J 4 x 35mm2 PVC/SWA/PVC cable (Provisional) 35 m 9,100.00 318,500.00

K 4 x 25mm2 PVC/PVC cable (Provisional) 150 m 6,000.00 900,000.00

L 4 x 16mm2 PVC/PVC cable (Provisional) 50 m 4,000.00 200,000.00

M 4 x 10mm2 PVC/PVC cable (Provisional) 25 m 2,500.00 62,500.00

N 5 x 4mm2 PVC single core from MV panel to fuse

switches (Provisional)

400 m 1,200.00 480,000.00

P 4 x 4mm2 PVC/SWA/PVC cable (Provisional) 280 m 900.00 252,000.00

Q 3 x 2.5mm2 PVC/SWA/PVC cable (Provisional) 40 m 750.00 30,000.00

R 1 x 10mm2 PVC/PVC cable (Provisional) 300 m 550.00 165,000.00

S 1 x 50mm2 PVC/PVC cable (Provisional) 25 m 2,400.00 60,000.00

T 600 x600 Cable route inspection chambers 4 m 20,000.00 80,000.00

TO COLLECTION 5,548,000.00

BILL NR. 02 LABORATORY BUILDING Page 2/30

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELECTRICAL INSTALLATION (CONT'D)

Lighting Installations

Cables and conduits in final circuit; radial lighting

sub-circuit; 2nr 1.5mm2, 1-core copper pvc

insulated and colour coded cable drawninto 20mm

galvanized mild steel concealed conduit; all as

specified; rate to include for all cable and conduit

fittings, accessories and ancillaries deemed

necessary for a complete installation; comprising;

It is of paramount importance that substandard

cables are not used in any electrical installation, to

avoid fire outbreak. Cables made in Nigeria are

strictly recommended. There shall be IES, NIS and

BS coded.

A Lighting points 365 nr 3,500.00 1,277,500.00

B 10A, 1 gang 1 way switch points 67 nr 3,500.00 234,500.00

C 10A, 1 gang 2 way switch points 22 nr 3,500.00 77,000.00

D 10A, 2 gang 1 way switch points 3 nr 3,500.00 10,500.00

E 10A, 3 gang 1 way switch points 4 nr 3,500.00 14,000.00

F Ceiling fan points 88 nr 3,500.00 308,000.00

G Extractor fan points 18 nr 3,500.00 63,000.00

H Smoke detector points 55 nr 3,500.00 192,500.00

J Heat sensor points 1 nr 3,500.00 3,500.00

K Fire alarm bell points 1 nr 3,500.00 3,500.00

L Fire Alarm panel points 1 nr 3,500.00 3,500.00

Luminaires and Lambs

Luminaries and lamps; as specified; rate to include

for supply and installation of approved rated M 1X60W LED High Bay energy saving Ceiling

Reccessed light fitting 600 x 600 (Totek or equal

approved)

32 nr 17,500.00 560,000.00

TO COLLECTION 2,747,500.00

BILL NR. 02 LABORATORY BUILDING Page 2/31

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELECTRICAL INSTALLATION (CONT'D)

A 2 x 36W Compact energy saving Ceiling Reccessed

light fitting with specular reflector ( CASTIN)

150 nr 4,000.00 600,000.00

B 1 x 36W Compact fluorescent recessed/ceiling

mount light fitting with water /dust proof (

CASTIN)

2 nr 2,500.00 5,000.00

C 1 x 24W Downlight energy fluorecent energy

saving ceiling reccessed light fitting with specular

reflector (CASTIN)

62 nr 3,200.00 198,400.00

D 1x 18W wall mounted ,mirror light fitting with

specular reflector water/dust proof (CASTIN)

30 nr 2,000.00 60,000.00

E 1x 18W Compact fluorescent recessed/ceiling

mount light fitting with water/dust proof diffuser

(CASTIN)

36 nr 2,000.00 72,000.00

F 1x 18W fluorecent 3Hrs exit light fitting 8 nr 15,000.00 120,000.00

G SAP-E27 light out door luminair comprising casted

aluminium non-corroding cover mounted on 1.2m

pole (CASTIN)

4 nr 15,000.00 60,000.00

H 1 x 70W Wall Mount Vandal Resistant Bulk

head ligth fitting.

41 nr 5,000.00 205,000.00

J New clime 1500mm Ceiling Fans with

regulator

88 nr 9,000.00 792,000.00

Accessories

Accessories; lighting switches; as specified; rate to

include galvanized steel knock-out box set in

mortises in walls; (flush mounted)

K 10A 1 gang 2 way switch (ABB) 22 nr 950.00 20,900.00

L 10A 1 gang 1 way switch (ABB)67 nr 900.00 60,300.00

M 10A 2 gang 1 way switch (ABB)3 nr 950.00 2,850.00

N 10A 3 gang 1 way switch (ABB) 4 nr 1,200.00 4,800.00

TO COLLECTION 2,201,250.00

BILL NR. 02 LABORATORY BUILDING Page 2/32

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELECTRICAL INSTALLATION (CONT'D)

Power Installation

Cables and conduits in final circuit; ring power

socket sub-circuit; 3nr 2.5mm2, 1-core copper pvc

insulated and colour coded cable drawninto 20mm

galvanized mild steel concealed conduit; all as

specified; rate to include for all cable and conduit

fittings, accessories and ancillaries deemed

necessary for a complete installation; comprising;

A 13A single switched socket outlet points 9 nr 4,400.00 39,600.00

B 13A double switched socket outlet points at higher

level

83 nr 4,400.00 365,200.00

C Twin compactment electrical socket/data floor box

with 1no 13A socket 1 no data outlet (MK or

Unitrunk)

54 nr 4,400.00 237,600.00

Cables and conduits in final circuit; ring power

socket sub-circuit; 3nr 4.0mm2, 1-core copper pvc

insulated and colour coded cable drawn into 20mm

PVC concealed conduit; all as specified; rate to

include for all cable and conduit fitting

D 20A single switched socket outlet points 48 nr 5,500.00 264,000.00

TO COLLECTION 906,400.00

BILL NR. 02 LABORATORY BUILDING Page 2/33

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELECTRICAL INSTALLATION (CONT'D)

Accessories

Accessories; low voltage power outlet switches; as

specified; rate to include galvanized steel knock-

out box set in mortises in walls;

Switched; flush mounted

A 13A 1 gang switched socket outlet 9 nr 1,300.00 11,700.00

B 13A 2 gang switched socket outlet 83 nr 1,500.00 124,500.00

C Twin compactment electrical socket/data floor box

with 1no 13A socket 1 no data outlet (MK or

Unitrunk)

54 nr 30,000.00 1,620,000.00

D 20A single switched socket outlet 48 nr 2,000.00 96,000.00

COMMUNICATION

Telephone and Communication System

E RJ 11 Telephone Outlets (ABB) 35 nr 1,400.00 49,000.00

F Data Sockets Outlets (ABB) 40 nr 1,400.00 56,000.00

G Television Outlets (ABB) 34 nr 1,400.00 47,600.00

H Supply and Install approprate Main

Distribution Frames complete with installation

and operational accessories.

1 nr 120,000.00 120,000.00

J Allow for Television Distribution Board 1 nr 50,000.00 50,000.00

Conduiting & Wiring to all Data Sockets

J Conduiting and Wiring in Concealed 20mm

PVC conduit pipe to all Voice and Data Outlets

using appropriate Voice and Data Cable, cable

wired in radial circuit. Complete with all

required installation and operational accessories

75 nr 2,750.00 206,250.00

TO COLLECTION 2,381,050.00

BILL NR. 02 LABORATORY BUILDING Page 2/34

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELECTRICAL INSTALLATION (CONT'D)

A Allow for Conduiting and Wiring in Concealed

20mm PVC conduit pipe to all Television

Outlets using appropriate Television Cable ,

cable wired in radial circuit. Complete with all

required installation and operational accessories

34 nr 2,750.00 93,500.00

B Allow for Conduiting and Wiring in Concealed

20mm PVC conduit pipe to all projector

Outlets using appropriate Data and Power

Cable , cable wired in radial circuit. Complete

with all required installation and operational

accessories

6 nr 3,250.00 19,500.00

C Allow for complete earthing of the

Telecommunication System

sum 50,000.00

FIRE DETECTION/ALARM SYSTEM

E Fire detection and alarm panel, 8-Zone

Conventional type complete with backup

batteries, installation and operational

accessories (Zircon or Zeta)

1 nr 180,000.00 180,000.00

F Fire Alarm Electronic Sounder (Zircon or Zeta) 11 nr 20,000.00 220,000.00

G Manual Break Glass (Zircon or Zeta) 11 nr 7,000.00 77,000.00

H Smoke Detectors (Zircon or Zeta) 55 nr 10,000.00 550,000.00

J Xenon Flasher (Zircon or Zeta) 1 nr 10,000.00 10,000.00

K Fire Alarm Syrene with Strobe Light (Zircon or

Zeta)1 nr 19,000.00 19,000.00

L Allow for cable connecting accessories,

programming, testing and commissioning

Item 150,000.00

TO COLLECTION 1,369,000.00

BILL NR. 02 LABORATORY BUILDING Page 2/35

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELECTRICAL INSTALLATION (CONT'D)

EQUIPOTENTIAL EARTHING AND

BONDING

(ALL PROVISIONAL)

Electrical Equipotential earthing and bonding of

the building shall be made in accordance with IEE

Regulation 413-2, complying with section 547.

A S6 indelec prevectron lighting preventor system

(copper type) complete with contact pickup rod,

electrodes, triggering device etc

1 nr 350,000.00 350,000.00

B Lattice type copper matt. 2 nr 3,200.00 6,400.00

C 25 x 3mm flat bare copper earth 25 m 2,000.00 50,000.00

D Copper strip down conductor 4 nr 2,000.00 8,000.00

E Copper screw down test clamp 1 nr 3,200.00 3,200.00

F 1.22mm copper earth rod 1 m 15,000.00 15,000.00

G Allow for earthing materials Sum 100,000.00

Builder's work in connection with electrical

installation

H Allow a provisional sum of 250,000.00 for

builder’s work in connection with electrical

installations

item 250,000.00

TO COLLECTION 782,600.00

BILL NR. 02 LABORATORY BUILDING Page 2/36

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

COLLECTION

Collection from page 2/28 1,270,000.00

Collection from page 2/29 5,548,000.00

Collection from page 2/30 2,747,500.00

Collection from page 2/31 2,201,250.00

Collection from page 2/32 906,400.00

Collection from page 2/33 2,381,050.00

Collection from page 2/34 1,369,000.00

Collection from page 2/35 782,600.00

TO SUMMARY N 17,205,800.00

BILL NR. 02 LABORATORY BUILDING Page 2/37

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR.15 FITTINGS

Concrete Work

In situ concrete

Reinforced; grade 20;

A Planter Trough slab 3 m3 28,500.00 85,500.00

B Planter Trough wall 2 m3 28,500.00 57,000.00

C Coping on the planter trough; suspended; thickness not

exceeding 100mm

1 m3 28,500.00 28,500.00

Reinforcement for in situ concrete; Reinforcement to

BS 4449 (Provisional)

Bars; high yield steel

D 10-12mm diameter; straight and bent 493 kg 272.00 134,096.00

Formwork; Sawn;

E Edges of suspended slab; depth not exceeding 250mm 54 m 275.00 14,850.00

F Sides of planter trough 30 m2 1,350.00 40,500.00

G Soffit of slab 22 m2 1,350.00 29,700.00

Blockwork

Blockwork; hollow sandcrete 450x230mm high

nominal; laid stretcher bond with cement and sand

(1:3) mortar;

H 150mm thick (Balustrade) 97 m2 2,950.00 286,150.00

In situ finishings

Render; cement and sand (1:6); 15mm thick; as

specified; finished fair and smooth;

Walls; over 300mm wide

J Balustrade (Isolated Balustrade) 194 m2 650.00 126,100.00

Walls; screeded backing; 12mm thick; over 300mm

wide

K To receive brick facing tiles 23 m2 600.00 13,800.00

TO COLLECTION 816,196.00

BILL NR. 02 LABORATORY BUILDING Page 2/38

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

FITTINGS CONT'D)

Tile, slab and block finishings

Brick facing tiles; size 150x60x15mm thick; jointing

and pointing; as specified; on screeded backing

(measured separately);

A Wall (Planter Trough) 23 m2 3,250.00 74,750.00

Metalwork

Balcony Steel balustrades;

B Balcony balustrades; 900mm high; 50mm diameter;

baluster at 150mm centres welded to 50mm diameter

steel handrail; one end fixed to metal plate embedded

in concrete 100mm deep and other end fixed to

35x3mm thick flat metal rail; primed with red oxide

and finished with two coats of gloss paint

34 m 7,850.00 266,900.00

C 50mm diameter welded to 300mm high baluster at

300mm centres other end casted into concretework;

primed with red oxide and finished with two coats of

gloss paint

108 m 3,350.00 361,800.00

Aluminium duct cover

D Aluminium duct cover; 200mm wide; both end fixed

to 70x70x6mm thick angle; in accordance with

manufacturer's instruction

170 m 3,260.00 554,200.00

TO COLLECTION 1,257,650.00

COLLECTION

Collection from page 2/37 816,196.00

Collection from page 2/38 1,257,650.00

TO SUMMARY N 2,073,846.00

BILL NR. 02 LABORATORY BUILDING Page 2/39

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

ELEMENT NR. 16 DRAINAGE BELOW

GROUND

Manholes

A Manhole; size 600x600x600mm deep (average)

internally constructed of 150mm plain in-situ

concrete grade 15 base, 150mm plain hollow

sandcrete blockwork side filled solid with plain

concrete and capped with 75mm thick precast

concrete grade 20 cover slab reinforced with

single layer B.R.C. Nr. 65 mesh and with 255mm

(average ) concrete grade 15 benching and

forming 150mm diameter half round diameter in

and same rendering insides in waterproof cement

mortar (1:3) with including all necessary

excavations, earthworks and formwork

28 nr 7,500.00 210,000.00

Septic tank

B Septic tank; size 3000x2400x2400mm deep

internally of 225mm blockwork sides and 150mm

concrete (1:3:6) base capped with 150mm

concrete (1:2:4) slab reinforced with and

including single layer BRC Nr. 65 mesh and fitted

with 3Nr coated cast iron manhole cover and

frame set in grease and sand. The attached

manhole with 225mm (average) concrete (1:3:6)

benching with 100mm half round channel and

fitted with 50mm deep cover slab reinforced with

single layer BRC Nr. 65 mesh and housed to sides

of septic tank, including 2Nr 100mm diameter

asbestos cement tee piece built into sides all to

include all necessary excavations, earthworks and

disposal. The septic tank having 75mm (average)

screeded (1:4) bed finished to falls and rendered

internally all round

2 nr 225,000.00 450,000.00

TO COLLECTION 660,000.00

BILL NR. 02 LABORATORY BUILDING Page 2/40

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

DRAINAGE BELOW GROUND (CONT'D)

Soakaway pit

A Soakaway pit; size 2400x2400x2000mm deep

internally of 150mm solid blockwork sides built

honey-comb on 450x50mm concrete (1:3:6)

foundations and covered slab in four sections each

reinforced with and including BRC Nr 65 mesh

supported on 225x225mm reinforced concrete

(1:2:4) beam reinforced with 4Nr 12mm diameter

mild steel bars, and 600mm wide loose rock or

rubble (minimum) size 150 gauge and covered

with galvanized iron sheets including length of

150mm diameter asbestos cement pipe with saw

cuts at 150mm centres, with and including all

necessary excavations, earthworks and formwork

2 nr 180,000.00 360,000.00

Pipework

SOIL AND WASTE PIPEWORK

Supply, deliver and install in trench the following

soil and waste uPVC pipes complete with jointing

materials and socket to BS4515 (PANAR OR

SIMILAR APPROVED).

B 150mm diameter (provisional) 86 m 600.00 51,600.00

TO COLLECTION 411,600.00

COLLECTION

Collection from page 2/39 660,000.00

Collection from page 2/40 411,600.00

TO SUMMARY N 1,071,600.00

BILL NR. 02 LABORATORY BUILDING Page 2/41

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

SUMMARY

ELEMENT PAGE NR. TOTAL

ELEMENT NR. 1 SUBSTRUCTURE PAGE 2/3 32,022,197.00

ELEMENT NR. 2 FRAME PAGE 2/4 12,507,840.00

ELEMENT NR. 3 UPPER FLOOR PAGE 2/5 12,938,334.00

ELEMENT NR. 4 STAIRCASES PAGE 2/8 1,860,938.00

ELEMENT NR. 5 ROOF PAGE 2/12 29,470,316.80

ELEMENT NR. 6 EXTERNAL AND INTERNAL

WALLSPAGE 2/13 9,308,538.00

ELEMENT NR. 7 DOORS PAGE 2/14 3,563,400.00

ELEMENT NR. 8 WINDOWS PAGE 2/16 15,788,370.00

ELEMENT NR. 9 WALL FINISHES PAGE 2/17 5,245,050.00

ELEMENT NR. 10 FLOOR FINISHES PAGE 2/19 7,027,700.63

ELEMENT NR. 11 CEILING FINISHES PAGE 2/20 4,347,050.00

ELEMENT NR. 12 PAINTING AND DECORATING PAGE 2/21 3,122,070.00

ELEMENT NR 13 PLUMBING AND MECHANICAL

INSTALLATIONSPAGE 2/27 5,470,300.00

ELEMENT NR. 14 ELECTRICAL INSTALLATIONS PAGE 2/36 17,205,800.00

ELEMENT NR.15 FITTINGS PAGE 2/38 2,073,846.00

ELEMENT NR. 16 DRAINAGE BELOW GROUND PAGE 2/40 1,071,600.00

TO GENERAL SUMMARY N 163,023,350.43

BILL NR. 02 LABORATORY BUILDING Page 2/42

PROPOSED CONSTRUCTION OF POSTGRADUATE ICT RESEARCH LABORATORIES BUILDING FOR AFRICAN CENTRE OF EXCELLENCE AT OBAFEMI

AWOLOWO UNIVERSITY, ILE-IFE, OSUN STATE

GENERAL SUMMARY BILL

NR.

ITEM PAGE NR. TOTAL (=N=)

1 PRELIMINARIES AND GENERAL CLAUSES 6,768,934.02

2 POSTGRADUATE I.C.T. RESEARCH LABORATORIES

BUILDING

PAGE 2/41 163,023,350.43

CONTINGENCIES:

3 ALLOW A PROVISIONAL SUM OF N 6,200,000.00 FOR THE

CONTINGENCIES TO BE EXPENDED AS DIRECTED

6,200,000.00

SUB-TOTAL 175,992,284.44

4 VALUE ADDED TAX (VAT) 5% 8,799,614.22

TOTAL CONTRACT SUM 184,791,898.66

COMPLETION PERIOD:

Signed for and on behalf of:

----------------------------------------------------------------------------------

----------------------------------------------------------------------------------

-----------------------------------------------------------

Dated this --------------day of --------------------- 2016

Within Weeks of officially taking possession of Site.

BILL NR. 02 LABORATORY BUILDING Page 2/43