BIDDERS’ CONFERENCE IT-3981. Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity. Technical Annexes 1 and 4. Technical Annexes 1 and 4. Annex 1: General Requirements for Electrical Overhead and Gantry Cranes - PowerPoint PPT Presentation

Transcript of BIDDERS’ CONFERENCE IT-3981

Page 1: BIDDERS’ CONFERENCE IT-3981
Page 2: BIDDERS’ CONFERENCE IT-3981

2

BIDDERS’ CONFERENCE IT-3981Dismantling, Refurbishment, Replacement and Supply of Electrical

Overhead Travelling Cranes Over 10 Tons Capacity

January 14th-15th 2014 Handling Engineering Group

Technical Annexes 1 and 4

Page 3: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 3

Technical Annexes 1 and 4

• Annex 1: General Requirements for Electrical Overhead and Gantry Cranes

• Annex 4: PLC Programming and Documentation Requirements

January 14th-15th 2014

Page 4: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 4

Annex 1• General requirements applicable both to

new cranes and to new components for refurbishment works on existing cranes

• Some of the requirements are mandatory while others are applicable only when stated in the technical questionnaire

• Machine Directive 2006/42/EC and technical questionnaire have priority with respect to this document

January 14th-15th 2014

Page 5: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 5

Annex 1

January 14th-15th 2014

Page 6: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 6

Annex 1

January 14th-15th 2014

Page 7: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 7

Annex 1

January 14th-15th 2014

Page 8: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 8

Annex 1

January 14th-15th 2014

Page 9: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 9

Annex 1

January 14th-15th 2014

Page 10: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 10

Annex 1

January 14th-15th 2014

Page 11: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 11

Annex 1

January 14th-15th 2014

Page 12: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 12

Annex 1

January 14th-15th 2014

Page 13: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 13

Annex 1

January 14th-15th 2014

Page 14: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 14

Annex 1

January 14th-15th 2014

Page 15: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 15

Annex 1

January 14th-15th 2014

Page 16: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 16

Annex 1

January 14th-15th 2014

Page 17: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 17

Annex 1

January 14th-15th 2014

Page 18: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 18

Annex 4

Covers the following aspects of PLC programming:• Design requirements• Interface with users• Software protection• Documentation

January 14th-15th 2014

Page 19: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 19

Annex 4

January 14th-15th 2014

Page 20: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 20

Annex 4

January 14th-15th 2014

Page 21: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 21

Annex 4

January 14th-15th 2014

Page 22: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 22

Annex 4

January 14th-15th 2014

Page 23: BIDDERS’ CONFERENCE IT-3981

Handling Engineering Group 23

Annex 4

January 14th-15th 2014

Page 24: BIDDERS’ CONFERENCE IT-3981