Transcript of BEWAG / UIP Workshop Brussels – 28/04/2014 Practical example of migration from the SNCB historical...
Robert Bauwens 1
BEWAG / UIPWorkshop Brussels – 28/04/2014
Practical example of migration from the SNCB historical regulations guide
to the VPI maintenance guide
Robert Bauwens
28/04/2014
Robert Bauwens 2
Contents
• Situation TRW • ECM certificates of TRW• Wagons of ECM TRW• Maintenance Reference Files MRF• Why switching from SNCB tot VPI• When switching from SNCB TO VPI• How applying VPI• ECM certification of workshops
28/04/2014
Robert Bauwens 3
Situation TRW
Subsidiary of BLogistics with one activity: ECM
BLogistics
Founded in February 2011 as independent company
Before: B-Cargo as department of SNCB
Organization of BLogistics
1 RU BLogistics
2 keepers Xpedys and IFB
1 ECM TRW
1 last mile / mobile repair OSR
28/04/2014
Robert Bauwens 4
ECM certificates of TRW
Self-declared as ECM on 29/11/2010 – valid until 31/05/2012
Certified as ECM – certificate FR 34 2012 0001 – 23/05/2012 Bureau Veritas• Based on the protocol agreement MoU• Valid until 31/05/2015
Objective: convert the certificate to EU 445/2011 in May 2014
28/04/2014
Robert Bauwens 5
Wagons of ECM TRW
TRW became ECM:• Before 02/11/2012: the wagons of IFB overhauled according VPI - around
600 wagons• As from 02/11/2012: all the wagons of the keepers Xpedys and IFB
Wagon fleet (situation December 2013): 7363 wagons
IFB 2394 wagons (intermodal)
Xpedys 4969 wagons (conventional)
Evolution of the total fleet:
January 2013 8857 wagons
December 2013 7363 wagons
Decrease of - 1494 wagons
28/04/2014
Robert Bauwens 6
Maintenance Reference Files MRF (I)
MRF = the complete set of maintenance rules and specifications to apply on the wagons (and on the wheel sets) during each maintenance intervention
Maintenance interventions:
• Preventive maintenance Major Overhaul MOSimplified Overhaul SO
• Corrective maintenanceIncidental Repair IROthers: VSP – PMB – etc.
28/04/2014
Robert Bauwens 7
Maintenance Reference Files MRF (II)
MRF applied by ECM TRW:
• Starting with three references
SNCB regulations
VPI guidelines
SNCF regulations: 80 wagons with disc brakes• Objective: to keep only VPI
28/04/2014
Robert Bauwens 8
Why switching from the SNCB to VPI
1. Workshop capacity for MO and SO
2. Flexibility for IR beyond the GCU repairs
3. Prices
4. VPI as future European Maintenance Standard ?
28/04/2014
Robert Bauwens 9
When switching from SNCB to VPI (I)
1. Wagons
Progressive during preventive maintenance MO and SO
SNCB 90 % 71 % 58 % 7 %
VPI 10 % 29 % 42 % 93 %
SNCF = 0 %
#MO +SO 2011 2012 2013 2014
SNCB 1494 1092 729 ± 100
VPI 167 443 526 ± 1300
SNCF 0 7 0 0
TOTAL 1661 1542 1255 ± 1400
28/04/2014
Robert Bauwens 10
When switching from SNCB to VPI (II)
IR beyond the GCU repairs: two regimes at the same time according the MRF of the last overhaul of the wagon (IR in the scope of GCU according the MRF applied by the RU which approved the workshop as its auxiliary)
As from 01/01/2014• IR beyond the GCU repairs: according VPI
28/04/2014
Robert Bauwens 11
When switching from SNCB to VPI (III)
2. Wheel sets
During overhaul IS2 / IS3 Wheel sets according SNCB and wheel sets according
VPI Both authorized under the same wagon (but to avoid)
3. Other components (pneumatic components, buffers, …) No switch from SNCB to VPI Overhaul according instructions approved by the
component suppliers Overhaul in specialized workshops approved by the
component suppliers
28/04/2014
Robert Bauwens 12
How applying VPI (I)
VPI• Are guidelines• Is not always suited for Belgian wagons
SNCB • Is a regulation• Is tailor made for Belgian wagons
ECM TRW regulations• The basis is VPI• A layer added with proper TRW regulations• Layer can be in plus or minus• New situation with VPI and ECM TRW regulations must be at least as
safe as the former situation with SNCB regulations Risk Analysis
28/04/2014
Robert Bauwens 13
How applying VPI (II)
Exemples
1. VPI not so strict as SNCB regulation
a. Overhaul of particular pneumatic components
SNCB10 yearsReplace if 10 years exceeded during next OH of wagon
VPI15 yearsReplace if 15 years exceeded during OH of wagon
2. VPI is more severe than SNCB
a. Corrosion on wheel set axles and monobloc wheels
b. Play between wheel set axle and brake connector
c. Uerdinger buffers
28/04/2014
Robert Bauwens 14
How applying VPI (III)
3. TRW regulation not so strict as VPI but equal to SNCB regulations
a. No UT after reprofiling with underfloorlathe b. No brake test after brake block replacement in the field
4. Nothing in VPI proper TRW instructions
a. Autocontinu AC3Db. VTA weighing valves
28/04/2014
Robert Bauwens 15
ECM certification of workshops (I)
• SNCB workshops• SNCB workshops know the wagons• ECM knows the workshops• Computerized data exchange• Until 31/12/2013: according SNCB regulations,
since than VPI
• Other workshops• Workshops do not always know the wagons• ECM TRW doesn’t know the workshops• Not yet a standard for data exchange, not yet
computerized• Mostly according VPI
28/04/2014
Robert Bauwens 16
ECM certification of workshops (II)
• Situation end 2013
Wagon workshops: 17 workshopsVPI: 9SNCB: 1VPI / SNCB: 5Auxiliary workshops: 2
Wheels set workshops: 8 for IS2 (2 for IS2 + IS3)VPI: 6VPI / SNCB: 2
Pneumatic component workshops: 2
28/04/2014
Robert Bauwens 17
Thank you for your attention
Questions?