Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.
-
Upload
logan-boone -
Category
Documents
-
view
214 -
download
0
Transcript of Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.
![Page 1: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/1.jpg)
Bethesda Triangle
Brian GroarkConstruction Management Faculty Consultant:
Dr. Messner
![Page 2: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/2.jpg)
Bethesda Triangle 14 story apartment building Additional 4 stories below grade for
parking 580,000 SF Cast in place concrete structure Offices and retail on plaza level High end apartments on floors 12-14
![Page 3: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/3.jpg)
Bethesda Triangle Owner: Bethesda Triangle, LLC CM: Encore Development Construction began on February 14,
2002 Phased occupancy Little site space
![Page 4: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/4.jpg)
Bethesda Triangle
![Page 5: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/5.jpg)
Thesis Overview SIPS Schedule Change emergency generator Change formwork Guidelines for mold prevention
![Page 6: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/6.jpg)
CM Depth
Short Interval Production Schedule (SIPS)
![Page 7: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/7.jpg)
Reasons for Using SIPS Lack of solid schedule for the project Project will finish extremely late Needs solid, detailed schedule for all
aspects of the project Repetitive floors work well for SIPS
![Page 8: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/8.jpg)
SIPS Create a detailed SIPS schedule for
the concrete structure Compare it to the original duration
for the structure
![Page 9: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/9.jpg)
SIPS Each floor is broken up into 4
sections Crews follow in progression through
all the sections and floors Each section has the same duration
![Page 10: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/10.jpg)
Section Layout
![Page 11: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/11.jpg)
SIPS Floors G4 – plaza level are the same Floors 2 – 14 are the same Each section takes 2 weeks to
complete
![Page 12: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/12.jpg)
SIPS
![Page 13: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/13.jpg)
Results Original duration was 44 weeks SIPS duration is 31 weeks Time saved is 13 weeks
![Page 14: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/14.jpg)
Electrical Breadth
Change Emergency Generator
![Page 15: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/15.jpg)
Original Generator 2 mega-watt generator Power entire building in the event of
a black out Sell extra power back to the grid at
times when the costs of running the generator are less than electricity costs
![Page 16: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/16.jpg)
New Generator 350 kilo-watt generator Power only emergency systems
Emergency lighting and alarms Fire pump Stairwell pressurization Smoke exhaust Elevator
![Page 17: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/17.jpg)
Initial Costs
2 mega-watt – $540,000 350 KW - $40,000
![Page 18: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/18.jpg)
Cost Analysis
Hour Watts/SF Total SF Total KWHr Weekday Weekend0 1 380000 380 1900 7601 0.75 380000 285 1425 5702 0.65 380000 247 1235 4943 0.6 380000 228 1140 4564 0.5 380000 190 950 380
APARTMENT
![Page 19: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/19.jpg)
Cost Analysis
Totals KWH Dist Tran Generation Total cost (week)Off peak 47563 0.289 0.266 1.99 $1,210.48On peak 26715 0.289 0.266 4.121 $1,249.19
Inter 27285 0.289 0.266 3.485 $1,102.31
$3,561.99
![Page 20: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/20.jpg)
Cost Analysis Costs of running the generator to
power the building were compared to purchasing electricity on an hourly basis
Plus Garage Cost per KWH total cost Total cost to run gen Extra Power (KWH) profit from selling power Net Cost Profit from running gen580 2.545 $14.76 $117.13 1220 $31.05 $86.08 -$71.32485 2.545 $12.34 $117.13 1315 $33.47 $83.66 -$71.32447 2.545 $11.38 $117.13 1353 $34.43 $82.70 -$71.32
![Page 21: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/21.jpg)
Results No profit is shown from running the
generator Price of diesel fuel has increased
![Page 22: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/22.jpg)
Recommendation Use proposed generator Initial cost savings of approximately
$500,000
![Page 23: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/23.jpg)
Structural Breadth
Change Formwork System
![Page 24: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/24.jpg)
Original Formwork Traditional formwork
Built in place with shoring Stripped and re-shored
![Page 25: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/25.jpg)
New Formwork System Symons flying truss system
Large aluminum forming tables are flown into position with a crane
Much higher productivity
![Page 26: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/26.jpg)
Slab Original slab was a flat slab with
drop panels Flying truss system can only be used
with flat plate slabs Slab was redesigned to a 10” flat
plate to accommodate the new forming system
![Page 27: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/27.jpg)
Productivity With a crew of six workers:
Hand set system – 544 sq ft per day Flying truss system – 7500 sq ft per day
System Sq Ft Sq ft /day DurationLabor Costs /
DayTotal Labor
CostsHand Set - Flat Slab w/ Drop Panels 380,000 544 699 $1,544 $1,078,529Flying Truss - Flat Plate 380,000 7500 51 $1,544 $78,229
![Page 28: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/28.jpg)
Comparison
System Sq Ft Form Costs / SFTotal Mat.
CostsHand Set - Flat Slab w/ Drop Panels 380,000 $0.92 $349,600Flying Truss - Flat Plate 380,000 $0.40 $152,000
System Sq Ft Slab Costs / SFTotal Slab
CostsHand Set - Flat Slab w/ Drop Panels 380,000 $5.15 $1,957,000Flying Truss - Flat Plate 380,000 $5.82 $2,211,600
Form costs
Slab Costs
![Page 29: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/29.jpg)
Results Total cost savings of approximately
$950,000
![Page 30: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/30.jpg)
Research
Mold Prevention Guidelines
![Page 31: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/31.jpg)
Effects of Mold in Buildings Less serious symptoms of toxic mold
poisoning Skin rashes Fatigue Coughing Headaches
![Page 32: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/32.jpg)
Effects of Mold in Buildings More serious symptoms of toxic
mold poisoning Impaired breathing Memory loss Hearing, speech, and eyesight
degradation Loss of balance
![Page 33: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/33.jpg)
Causes of Mold Moisture
Leaks Condensation
![Page 34: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/34.jpg)
Guidelines for Prevention
1. Clear details of all exterior penetrations
2. Design must provide for adequate roof drainage
3. No changes to design of enclosure without architects approval
4. Proper slope of grading
![Page 35: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/35.jpg)
Guidelines for Prevention
5. Drywall must remain dry 6. Complete enclosure of building
prior to drywall installation7. Use drywall designed to reduce
mold growth8. Proper inspection9. Proper operation of equipment
![Page 36: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/36.jpg)
Conclusions SIPS can reduce schedule duration Larger generator is not profitable at
current fuel prices Flying truss formwork greatly
increases productivity Early mold prevention can save
costly repairs in the future
![Page 37: Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.](https://reader036.fdocuments.us/reader036/viewer/2022081516/56649e385503460f94b28232/html5/thumbnails/37.jpg)
Questions