Benoît Esnault Commission de Régulation de l’Energie (CRE) - ERGEG 19th Madrid Forum, 21-22...
-
Upload
gabriel-young -
Category
Documents
-
view
212 -
download
0
Transcript of Benoît Esnault Commission de Régulation de l’Energie (CRE) - ERGEG 19th Madrid Forum, 21-22...
Benoît EsnaultCommission de Régulation de l’Energie (CRE) - ERGEG19th Madrid Forum, 21-22 March 2011
Preparatory work for
Framework Guideline Tariffs
219th Madrid Forum, 21-22 March 2011
Agenda
• Background• Identification of problems• Identification of objectives• Scope• Process
319th Madrid Forum, 21-22 March 2011
Background
• Legal requirements on transmission tariffs• De-coupled entry-exit systems;• No distinction between domestic transport and “transit”;• Qualitative requirements (Commission Staff Working Document).
• KEMA study 2009• Evaluation of existing differences in the methodologies for gas
transmission network tariffs in Europe; and• If these lead to barriers to cross-border trade.
• 17th Madrid Forum invited ERGEG to start preparatory work on framework guideline on tariffs
• ACER to launch official FG development process
419th Madrid Forum, 21-22 March 2011
Main legal requirements
• Article 41 Gas Directive (2009/73/EC) • The NRA shall ensure that TSOs are granted appropriate
incentive, over both the short and long-term, to increase efficiencies, foster market integration and security of supply and support the related research activities.
• Article 13 Gas Regulation (EC) 715/2009: Transmission tariffs or methodologies
• Shall facilitate efficient gas trade and competition, while at the same time avoiding cross-subsidies between network users and providing incentives for investment;
• Reflect the actual costs incurred;• Tariffs may also be determined through market-based
arrangements, such as auctions, provided that such arrangements and the revenues arising from them are approved by the NRA.
519th Madrid Forum, 21-22 March 2011
Identification of problems
• Tariffs can act as barriers to efficient gas trade and competition• Premium on short term capacity products allocated with a short lead
time may frustrate arbitrage flows and price alignment;
• But: need to assess the relation between prices for short term and long-term capacity products and the risks associated to optimisation strategies by shippers;
• Pricing of interruptible and non-physical backhaul capacity.
• Need to find a proper balance between facilitating short term gas trading and providing long-term signals for covering costs and promoting efficient investments
• Cross subsidies between cross-border and domestic network usage• Cross subsidies within a market; and
• Cross subsidies between two adjacent markets.
Cost-reflectivity as a main principle
619th Madrid Forum, 21-22 March 2011
Identification of problems: Further issues
• Issues resulting from FG on CAM and Balancing:• Cost recovery and revenue sharing among TSOs:
under- and over-recovery of allowed revenues, risk of sunk costs, articulation between capacity and commodity, definition of the appropriate reserve price;
• Split of auction revenues between TSOs for bundled capacity products.
• Infrastructure development: to ensure a proper remuneration and investment incentivisation• Relation with the work on the Energy Infrastructure
Package.
719th Madrid Forum, 21-22 March 2011
Analysis of national charging systems
• Ongoing complementary analysis to the KEMA study (10 Member States until now);
• Picture of current situation – changes are foreseen with the implementation of the 3rd Package;
• Entry and Exit capacity separately bookable in some cases – for others distinction between tariffs on cross-border and domestic network
No common rule for the breakdown of costs
• Between entry and exit on the IPs;
• Between domestic exits and exits on the border.
• Different role for distance in tariffs calculation;
• Short term vs. long-term prices: Higher prices for daily and monthly products, with seasonality factor in some cases;
• Discount for interruptible products based on the probability of interruption;
• Few TSOs offer non-physical backhaul products.
819th Madrid Forum, 21-22 March 2011
Identification of objectives
• Objective 1: Harmonised transmission tariff structures shall facilitate efficient gas trade and competition;
• Objective 2: Harmonised transmission tariff structures shall avoid undue discrimination between cross-border and domestic network usage;
• Objective 3: Harmonised transmission tariff structures shall provide incentives for new and efficient investments
• Objective 4: Harmonised transmission tariff structures shall guarantee recovery of allowed revenues associated to cross-border interconnection points.
The work on the Gas Target Model to be taken into account in the Tariff FG development process.
919th Madrid Forum, 21-22 March 2011
Proposed scope
• Cross-border interconnection points• IPs between two or more Member States as well as IPs
between adjacent entry-exit-systems within the same Member State;
• IPs to LNG and storage facilities may be included, if relevant for market integration and the contribution to non-discrimination, effective competition and the efficient functioning of the market.
• Contribute to recovering the allowed revenues (associated to interconnection points);
• However, detailed rules for the determination of costs (or allowed revenues) are not within the scope.
1019th Madrid Forum, 21-22 March 2011
Process
• Process so far• Preparatory work by ERGEG;• 5 bilateral meetings with ENTSOG;• Initial scoping discussion with the Commission.
• Next steps (according to 3-year plan)• Q1/2011: Finalisation of scoping discussion;• April-October 2011: Official FG development process
by ACER.
1119th Madrid Forum, 21-22 March 2011
Thank you for your attention!
www.energy-regulators.eu