Route 659 (Belmont Ridge Road) Reconstruct to 4-Lanes Project
Pardon Our Dust MeetingBelmont Station Elementary School
October 27, 2016
2
Northern Virginia Transportation Authority Loudoun County Virginia Department of Transportation Dewberry Consultants, LLC Shirley Contracting Company
The Project Team
3
Objectives
Project Location Project Purpose and Need Provide an Overview of Design FeaturesDescribe Construction Sequence Discuss the Project ScheduleAnswer Your Questions
4
Project LocationNorth
South
West East
• Improve traffic safetythrough improvements toroadway geometry, operations, and grade
separation of W&OD
• Improve capacity &reduce congestion
• Enhance Connectivity ofRegional MultimodalTransportation Network
• Complete 4 lane roadway section from Route 7 to
the Dulles Greenway 5
Project Purpose and Need
6
Major Design Features Typical Section
Four lane divided roadway 26’ Wide Grass Median 10’ Wide Shared Use Path on Both Sides
of the Road
7
Construction SequenceStages 1, 2 & 3
8
Bridge Construction SequenceStages 1 & 2
9
Major Design FeaturesGrade Separated Interchange Over
W&OD Trail
10
Major Design FeaturesW&OD Trail Parking Facility
11
• Wall 1: Hay Rd. to 876’ North, Aprox.13’ Tall Scheduled to complete by end of 2017.
Major Design FeaturesNoise Barriers
12
• Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF, Approx. 13’ Tall, and Scheduled to complete by end of 2017.
Major Design FeaturesNoise Barriers
13
• Wall 2: Churchill Downs Dr. to Chesterton St. is 1,963 LF, Approx. 13’ Tall, and Scheduled to complete by end of 2017.
Major Design FeaturesNoise Barriers
14
• Wall 3: Chesterton St. to 384’ North, Aprox.13’ Tall
Scheduled to be complete by end of 2017.
Major Design FeaturesNoise Barriers
15
Architectural Finish• Concrete Posts and Concrete Panels• Panels: Ashlar Stone Pattern with a 12 Inch Tall Coping on the Top Stained Color Hopsac
Major Design FeaturesNoise Barriers
16
Project Metrics
Total Project Budget: $61 MillionConstruction Contract Value: $45.5 MillionProject Length: 1.9 MilesRight-of-Way Acquisition: 26 ParcelsAdjustments to 5 UtilitiesProject Duration: 39 months
17
Construction Metrics Communications 13,000 LF
Line Relocations Overhead Power 9,000 LF Gas Line 7,000 LF Relocations 36” Water Main: 10,000 LF Earth Moving: 125,000 CY
(15,500 Truck Loads) Storm Drainage: 14,200 LF Pipe
155 Drainage Structures Pavement Stone: 45,000 Tons Asphalt Pavement: 80,000 Tons Noise Barrier: 47,000 SF Pavement Markings: 130,000 LF
18
September 2015 Notice To Proceed
October 2015 - July 2016 Complete Design / Permitting
Summer 2016 - Winter 2016 Right of Way Acquisition
Fall 2016 - Winter 2017 Utility Relocations
October 31, 2017 Grade Separation Complete
Fall 2016 - Winter 2017 Stage 1 Construction
Winter 2017 - Fall 2018 Stage 2 Construction
Winter 2018 Stage 3 / Complete Project
Project Schedule
Addressing Your Concerns… Regarding Construction
19
A majority of the construction operations will be on weekdays during normal daytime hours, generally 6:00 am to 6:00 pm.
Weekends will be utilized as make-up day due to weather. Flagging operations to a single lane will be performed to
place safety measures and equipment access. Nighttime operations will result in noise impacts. Notices will be distributed to email distribution list and
directly to fire, rescue, and school personnel. VDOT to send press releases for major traffic shifts. Speed limit will be reduced from 45 mph to 40 mph during
construction.
20
http://www.virginiadot.org/projects/northernvirginia/belmont_ridge_road_widening.asp
(this webpage will be updated throughout the project development)
Or Google: “Belmont Ridge Road Widening”
Questions and Answers
For More Information About Route 659 Widening Project: