BELLEVUE COLLEGE GYMNASIUM REMODEL SCHEMATIC DESIGN...
Transcript of BELLEVUE COLLEGE GYMNASIUM REMODEL SCHEMATIC DESIGN...
BELLEVUE COLLEGE
GYMNASIUM REMODEL
SCHEMATIC DESIGN COST ESTIMATE
SUMMARY
Option A Phase 1 Phase 2
Architectural 1,565,372.00$ 488,477.00$
Mechanical 680,351.00$ 234,775.00$
Electrical 414,129.00$ 107,036.00$
SUBTOTAL 2,659,852.00$ 830,288.00$
COMBINED TOTAL 3,490,140.00$
40% PROJECT COST 1,396,056.00$
PROJECT TOTAL OPTION A 4,886,196.00$
Option B
Architectural 1,179,293.00$ 710,979.00$
Mechanical 587,427.00$ 303,431.00$
Electrical 347,972.00$ 161,702.00$
SUBTOTAL 2,114,692.00$ 1,176,112.00$
COMBINED TOTAL 3,290,804.00$
40% PROJECT COST 1,316,321.60$
PROJECT TOTAL OPTION B 4,607,125.60$
Estimate Issue Date: June 15, 2017
Estimate Revision: 0
For: Karee Loghry, AIA, LEED AP
Bellevue College
Gymnasium Remodel
Schematic Design Estimate
June 15, 2017
Bellevue College
Gymnasium Remodel
Schematic Design Estimate
Bellevue, WA
INTRODUCTION
Escalation & Market Conditions
Escalation has been estimated at 5% per annum to Construction Start Date
Estimating Contingency
We have included a 10% Estimating Contingency
Exclusions from Construction Cost:
Design fees
Owners administration costs
Building and land acquisition fees
Legal and accounting fees
Removal of unforeseen underground obstructions
Owner’s furniture, furnishings and equipment
Owners supplied materials
Work outside the construction site boundary.
Moving owners equipment and furniture
Any hazardous waste removal other an allowance in soft costs
Compression of schedule, premium or shift work, and restrictions on the contractor's working hours
Assessments, taxes, finance, legal and development charges
Cost escalation beyond the start dates stated in this report
Builder's risk, project wrap-up and other owner provided insurance program
Grain silos
Pre-construction services
Assumption used in establishing the estimate:
Open and competitive bidding among all proportions of the work
Construction Start Date December 2017
Items that may affect the cost estimate:
Modifications to the scope of work included in this estimate.
Special phasing requirements other than mentioned above.
Restrictive technical specifications or excessive contract conditions.
Any non-competitive bid situations.
Bids delayed beyond the projected schedule.
Page 1
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Date:
Bellevue, WA Prepared By: AC
OVERALL SUMMARY CONSTRUCTION COST
Gross Area $/SF $
Option A - Phase 1 9,795 SF 271.55 2,659,852
Option A - Phase 2 5,177 SF 160.38 830,288
TOTAL CONSTRUCTION COST (OPTION A) 3,490,140
Option B - Phase 1 7,059 SF 299.57 2,114,692
Option B - Phase 2 7,913 SF 148.63 1,176,112
TOTAL CONSTRUCTION COST (OPTION B) 3,290,804
June 15, 2017
Page 2
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 9,795 SF
Bellevue, WA Date:
Option A - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
B 10 Superstructure
Headers 1 LS 3,750.00 3,750
B2011 Exterior wall construction
CMU Infill walls, 8" 308 SF 35.00 10,780
Patch and repair to walls 1 LS 4,000.00 4,000
B2021 Windows
Exterior windows at classrooms 80 SF 82.50 6,600
B 2030 Exterior Doors
Exterior door including frame and hardware, double 1 EA 4,500.00 4,500
Exterior door including frame and hardware, single 1 EA 2,350.00 2,350
B 3010 Roof Coverings
Roofing, no work anticipated N/A
C1011 Fixed partitions
Metal studs, batt insualtion, GWB/Impact GWB/Cement backer board -
Finish both sides 11,662 SF 12.20 142,276
Metal studs at chase walls, batt insulaltion, GWB/Impact GWB/Cement
backer board - Finish both sides 1,064 SF 16.40 17,450
Metal studs, batt insualtion, GWB/Impact GWB/Cement backer board -
Finish one side 966 SF 9.00 8,694
CMU infill walls, 6" 378 SF 30.00 11,340
C1013 Retractable partitions
Operable partition at classroom 31 LF 720.00 22,320
C1017 Interior windows and storefronts
Interior glazing at wellness center 40 SF 70.00 2,800
C1021 Interior doors
Interior doors, frames and hardware, single 17 EA 2,100.00 35,700
Interior doors, frames and hardware, double 1 EA 4,040.00 4,040
C1025 Interior door sidelights and transoms
Sidelights and transoms, not required N/A
C1031 Fabricated toilet partitions
ADA toilet partition 5 EA 1,550.00 7,750
STD toilet partition 22 EA 1,340.00 29,480
Urinal screen 2 EA 560.00 1,120
C1032 Fabricated compartments and cubicles
ADA shower partition 2 EA 1,720.00 3,440
STD shower partition 6 EA 1,450.00 8,700
C1033 Storage shelving and lockers
Janitors mop rack and shelf 1 EA 455.00 455
Lockers, double stacked, 6'-0" high at male locker room 94 EA 365.00 34,310
Lockers, double stacked, 6'-0" high at female locker room 94 EA 365.00 34,310
June 15, 2017
Page 3
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 9,795 SF
Bellevue, WA Date:
Option A - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
B 10 Superstructure
June 15, 2017
Lockers, single stacked, 6'-0" high at team locker rooms 80 EA 310.00 24,800
Lockers, single stacked, 6'-0" high at unisex toilets 9 EA 310.00 2,790
Lockers, single stacked, 6'-0" high at faculty locker room 15 EA 310.00 4,650
Lockers, single stacked, 2'-0" x 2'-0" x 7'-0" high at team lockers 30 EA 420.00 12,600
C1035 Identifying devices
Code signage 9,795 SF 0.15 1,469
Room identification and wayfinding signage 9,795 SF 0.55 5,387
C1037 General fittings and misc. metals
Miscellaneous metals, allow 0.4#/SF 3,918 LB 3.50 13,713
Fire extinguisher cabinets 2 EA 290.00 580
Grab bars at restrooms 7 EA 210.00 1,470
Mirrors at restrooms 20 EA 175.00 3,500
Shower curtain and track 12 EA 150.00 1,800
Restroom accessories 1 LS 18,000.00 18,000
Shower accessories 1 LS 2,400.00 2,400
Locker benches, 8'-0", wood 12 EA 544.00 6,528
Locker benches, 5'-0" , wood 2 EA 297.50 595
Locker benches, 4'-0" , wood 2 EA 272.00 544
C3012 Wall finishes
Paint to walls 1 LS 18,120.75 18,121
Ceramic tile at wet walls 2,191 SF 17.00 37,247
C3024 Flooring including base
Carpet at classsrooms 1,183 SF 5.00 5,915Ceramic tile at team lockers 2,063 SF 17.00 35,071Ceramic tile at restrooms 2,105 SF 17.00 35,785Allowance for floor finishes at other areas 4,444 SF 6.50 28,886Base 1 LS 8,815.50 8,816
C3031 Ceiling finishes
ACT at classrooms 1,183 SF 6.35 7,512
ACT at team lockers 2,063 SF 6.35 13,100
Gypsum board, painted at restrooms / shower 2,105 SF 12.85 27,049
Paint to exposed structure, not required 4,444 SF N/A
D2010 Plumbing Fixtures
Plumbing systems, complete 1 LS 344,138.00 344,138
D3010 HVAC
HVAC systems, complete 1 LS 336,213.00 336,213
D 4010 Sprinklers
Sprinkler system, complete, assumed not required N/A
D5000 Electrical
Electrical systems, complete 1 LS 414,129.00 414,129
E1094 Residential equipment
Page 4
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 9,795 SF
Bellevue, WA Date:
Option A - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
B 10 Superstructure
June 15, 2017
Residential appliances, not required N/A
E2012 Fixed casework
No work anticipated N/A
E2013 Blinds and other window treatments
Window treatments at new windows 1 LS 880.00 880
F 2010 Building Elements Demolition
Interior walls, CMU, 6" 752 LF 30.80 23,162
Doors, per leaf 24 EA 74.50 1,788
Toilet partitions 20 EA 85.00 1,700
Urinal screens 7 EA 36.00 252
Shower partitions 5 EA 85.00 425
Restroom accessories 1 LS 460.00 460
Shower accessories 1 LS 92.50 93
Locker bench, 20'-0" 12 EA 80.00 960
Locker bench, 7'-0" 1 EA 40.00 40
Locker bench, 5'-0" 1 EA 30.00 30
Lockers 489 EA 37.50 18,338
Floor finishes 9,795 SF 1.40 13,713
Ceiling finishes 9,795 SF 1.15 11,264
Exterior walls 50 LF 190.00 9,500
Miscellaneous demolition 9,795 SF 0.80 7,836
F 2020 Hazardous Components Abatement
HAZMAT Abatement, excluded N/A
Sub-Total 1,899,413
General Conditions 15.00% 1,899,412.95 284,912
Sub-Total 2,184,325
Estimating / Design Contingency 10.00% 2,184,324.89 218,432
Sub-Total 2,402,757
Escalation - December 2017 2.50% 2,402,757.38 60,069
Sub-Total 2,462,826
GC Fee 8.00% 2,462,826.32 197,026
TOTAL CONSTRUCTION COST 2,659,852
Page 5
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 5,177 SF
Bellevue, WA Date:
Option A - Phase 2 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
B 10 Superstructure
Headers 1 LS 7,650.00 7,650
B2011 Exterior wall construction
CMU Infill walls, 8" 98 SF 35.00 3,430
Patch and repair to walls 1 LS 6,500.00 6,500
B2021 Windows
Exterior windows 225 SF 82.50 18,563
B 2030 Exterior Doors
Exterior door including frame and hardware, double 1 EA 4,500.00 4,500
B 3010 Roof Coverings
Roofing, no work anticipated N/A
C1011 Fixed partitions
Metal studs, batt insualtion, GWB/Impact GWB/Cement backer board -
Finish both sides 2,548 SF 12.20 31,086
Metal studs, batt insualtion, GWB/Impact GWB/Cement backer board -
Finish one side 1,288 SF 9.00 11,592
CMU infill walls, 6" 42 SF 30.00 1,260
C1017 Interior windows and storefronts
Interior glazing at fitness 15 SF 70.00 1,050
C1021 Interior doors
Interior doors, frames and hardware, single 6 EA 2,100.00 12,600
Interior doors, frames and hardware, double 1 EA 4,040.00 4,040
C1025 Interior door sidelights and transoms
Sidelights 2 EA 1,650.00 3,300
C1031 Fabricated toilet partitions
ADA toilet partition 1 EA 1,550.00 1,550
C1033 Storage shelving and lockers
Lockers, single stacked, 6'-0" high at faculty locker room 15 EA 310.00 4,650
C1035 Identifying devices
Code signage 5,177 SF 0.15 777
Room identification and wayfinding signage 5,177 SF 0.55 2,847
C1037 General fittings and misc. metals
Miscellaneous metals, allow 0.4#/SF 2,071 LB 3.50 7,248
Fire extinguisher cabinets 1 EA 290.00 290
Grab bars at restrooms 1 EA 210.00 210
Mirrors at restrooms 2 EA 175.00 350
Restroom accessories 1 LS 900.00 900
Shower accessories 1 LS 200.00 200
Locker benches, 4'-0" , wood 2 EA 272.00 544
June 15, 2017
Page 6
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 5,177 SF
Bellevue, WA Date:
Option A - Phase 2 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
June 15, 2017
C3012 Wall finishes
Paint to walls 1 LS 9,577.45 9,577
Ceramic tile at wet walls 203 SF 17.00 3,451
C3024 Flooring including base
Sheet goods at wellness center, laundry, storage and athletic treatment 1,152 SF 5.00 5,760
Ceramic tile at at shower / faculty lockers 267 SF 17.00 4,539Allowance for floor finishes at other areas 3,758 SF 6.50 24,427Base 1 LS 4,659.30 4,659
C3031 Ceiling finishes
ACT at wellness center, laundry, storage and athletic treatment 1,152 SF 6.35 7,315
Gypsum board, painted at shower / faculty lockers 267 SF 12.85 3,431
Allowance for ceiling finishes at remaining areas 3,758 SF 5.00 18,790
D2010 Plumbing Fixtures
Plumbing systems, complete 1 LS 24,290.00 24,290
D3010 HVAC
HVAC systems, complete 1 LS 210,485.00 210,485
D 4010 Sprinklers
Sprinkler system, complete, assumed not required N/A
D5000 Electrical
Electrical systems, complete 1 LS 107,036.00 107,036
E1094 Residential equipment
Residential appliances, not required N/A
E2012 Fixed casework
Athletic treatment room
Base cabinetry, plastic laminate 10 LF 230.00 2,300
Countertop, plastic laminate 10 LF 85.00 850
E2013 Blinds and other window treatments
Window treatments at new windows 1 LS 2,475.00 2,475
F 2010 Building Elements Demolition
Interior walls, CMU, 6" 446 LF 30.80 13,737
Doors, per leaf 21 EA 74.50 1,565
Toilet partitions 1 EA 85.00 85
Shower partitions 1 EA 85.00 85
Restroom accessories 1 LS 23.00 23
Shower accessories 1 LS 18.50 19
Locker bench, 5'-0" 1 EA 30.00 30
Lockers 10 EA 37.50 375
Floor finishes 5,177 SF 1.40 7,248
Ceiling finishes 5,177 SF 1.15 5,954
Page 7
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 5,177 SF
Bellevue, WA Date:
Option A - Phase 2 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
June 15, 2017
Exterior walls 27 LF 190.00 5,130
Miscellaneous demolition 5,177 SF 0.80 4,142
F 2020 Hazardous Components Abatement
HAZMAT Abatement, excluded N/A
Sub-Total 592,912
General Conditions 15.00% 592,912.45 88,937
Sub-Total 681,849
Estimating / Design Contingency 10.00% 681,849.32 68,185
Sub-Total 750,034
Escalation - December 2017 2.50% 750,034.25 18,751
Sub-Total 768,785
GC Fee 8.00% 768,785.11 61,503
TOTAL CONSTRUCTION COST 830,288
Page 8
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 7,059 SF
Bellevue, WA Date:
Option B - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
B 10 Superstructure
Headers 1 LS 3,300.00 3,300
B2021 Windows
Exterior windows at classrooms 80 SF 82.50 6,600
B 2030 Exterior Doors
Exterior door including frame and hardware, double 1 EA 4,500.00 4,500
B 3010 Roof Coverings
Roofing, no work anticipated N/A
C1011 Fixed partitions
Metal studs, batt insualtion, GWB/Impact GWB/Cement backer board -
Finish both sides 6,636 SF 12.20 80,959
Metal studs at chase walls, batt insulaltion, GWB/Impact GWB/Cement
backer board - Finish both sides 1,288 SF 16.40 21,123
Metal studs, batt insualtion, GWB/Impact GWB/Cement backer board -
Finish one side 588 SF 9.00 5,292
CMU infill walls, 6" 378 SF 30.00 11,340
C1013 Retractable partitions
Operable partition at classroom 31 LF 720.00 22,320
C1021 Interior doors
Interior doors, frames and hardware, single 14 EA 2,100.00 29,400
Interior doors, frames and hardware, double 1 EA 4,040.00 4,040
C1025 Interior door sidelights and transoms
Sidelights and transoms, not required N/A
C1031 Fabricated toilet partitions
ADA toilet partition 5 EA 1,550.00 7,750
STD toilet partition 22 EA 1,340.00 29,480
Urinal screen 2 EA 560.00 1,120
C1032 Fabricated compartments and cubicles
ADA shower partition 2 EA 1,720.00 3,440
STD shower partition 6 EA 1,450.00 8,700
C1033 Storage shelving and lockers
Janitors mop rack and shelf 1 EA 455.00 455
Lockers, double stacked, 6'-0" high at male locker room 94 EA 365.00 34,310
Lockers, double stacked, 6'-0" high at female locker room 94 EA 365.00 34,310
Lockers, single stacked, 6'-0" high at unisex toilets 9 EA 310.00 2,790
Lockers, single stacked, 6'-0" high at faculty locker room 15 EA 310.00 4,650
C1035 Identifying devices
Code signage 7,059 SF 0.15 1,059
Room identification and wayfinding signage 7,059 SF 0.55 3,882
June 15, 2017
Page 9
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 7,059 SF
Bellevue, WA Date:
Option B - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
June 15, 2017
C1037 General fittings and misc. metals
Miscellaneous metals, allow 0.4#/SF 2,824 LB 3.50 9,883
Fire extinguisher cabinets 1 EA 290.00 290
Grab bars at restrooms 7 EA 210.00 1,470
Mirrors at restrooms 20 EA 175.00 3,500
Shower curtain and track 12 EA 150.00 1,800
Restroom accessories 1 LS 16,200.00 16,200
Shower accessories 1 LS 2,400.00 2,400
Locker benches, 8'-0", wood 12 EA 544.00 6,528
Locker benches, 6'-0" , wood 2 EA 408.00 816
Locker benches, 4'-0" , wood 2 EA 272.00 544
C3012 Wall finishes
Paint to walls 1 LS 13,059.15 13,059
Ceramic tile at wet walls 2,149 SF 17.00 36,533
C3024 Flooring including base
Carpet at classsrooms 1,183 SF 5.00 5,915Ceramic tile at restrooms 1,897 SF 17.00 32,249Allowance for floor finishes at other areas 3,979 SF 6.50 25,864Base 1 LS 6,353.10 6,353
C3031 Ceiling finishes
ACT at classrooms 1,183 SF 6.35 7,512
Gypsum board, painted at restrooms / shower 1,897 SF 12.85 24,376
Paint to exposed structure, not required 3,979 SF N/A
D2010 Plumbing Fixtures
Plumbing systems, complete 1 LS 338,717.00 338,717
D3010 HVAC
HVAC systems, complete 1 LS 248,710.00 248,710
D 4010 Sprinklers
Sprinkler system, complete, assumed not required N/A
D5000 Electrical
Electrical systems, complete 1 LS 347,972.00 347,972
E1094 Residential equipment
Residential appliances, not required N/A
E2012 Fixed casework
No work anticipated N/A
E2013 Blinds and other window treatments
Window treatments at new windows 1 LS 880.00 880
F 2010 Building Elements Demolition
Interior walls, CMU, 6" 570 LF 30.80 17,556
Doors, per leaf 22 EA 74.50 1,639
Page 10
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 7,059 SF
Bellevue, WA Date:
Option B - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
June 15, 2017
Toilet partitions 20 EA 85.00 1,700
Urinal screens 7 EA 36.00 252
Shower partitions 5 EA 85.00 425
Restroom accessories 1 LS 460.00 460
Shower accessories 1 LS 92.50 93
Locker bench, 20'-0" 5 EA 80.00 400
Locker bench, 7'-0" 1 EA 40.00 40
Locker bench, 5'-0" 1 EA 30.00 30
Lockers 225 EA 37.50 8,438
Floor finishes 7,059 SF 1.40 9,883
Ceiling finishes 7,059 SF 1.15 8,118
Exterior walls 16 LF 190.00 3,040
Miscellaneous demolition 7,059 SF 0.80 5,647
F 2020 Hazardous Components Abatement
HAZMAT Abatement, excluded N/A
Sub-Total 1,510,111
General Conditions 15.00% 1,510,111.20 226,517
Sub-Total 1,736,628
Estimating / Design Contingency 10.00% 1,736,627.88 173,663
Sub-Total 1,910,291
Escalation - December 2017 2.50% 1,910,290.67 47,757
Sub-Total 1,958,048
GC Fee 8.00% 1,958,047.93 156,644
TOTAL CONSTRUCTION COST 2,114,692
Page 11
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 7,913 SF
Bellevue, WA Date:
Option B - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
B 10 Superstructure
Headers 1 LS 7,650.00 7,650
B2011 Exterior wall construction
CMU Infill walls, 8" 154 SF 35.00 5,390
Patch and repair to walls 1 LS 6,500.00 6,500
B2021 Windows
Exterior windows 225 SF 82.50 18,563
B 2030 Exterior Doors
Exterior door including frame and hardware, double 1 EA 4,500.00 4,500
B 3010 Roof Coverings
Roofing, no work anticipated N/A
C1011 Fixed partitions
Metal studs, batt insualtion, GWB/Impact GWB/Cement backer board -
Finish both sides 4,060 SF 12.20 49,532
Metal studs, batt insualtion, GWB/Impact GWB/Cement backer board -
Finish one side 966 SF 9.00 8,694
CMU infill walls, 6" 84 SF 30.00 2,520
C1017 Interior windows and storefronts
Interior glazing at wellness center 88 SF 70.00 6,125
C1021 Interior doors
Interior doors, frames and hardware, single 8 EA 2,100.00 16,800
Interior doors, frames and hardware, double 1 EA 4,040.00 4,040
C1025 Interior door sidelights and transoms
Sidelights 2 EA 1,650.00 3,300
C1031 Fabricated toilet partitions
ADA toilet partition 1 EA 1,550.00 1,550
C1033 Storage shelving and lockers
Lockers, single stacked, 6'-0" high at team locker rooms 60 EA 310.00 18,600
Lockers, single stacked, 6'-0" high at faculty locker room 15 EA 310.00 4,650
Lockers, single stacked, 2'-0" x 2'-0" x 7'-0" high at team lockers 30 EA 420.00 12,600
C1035 Identifying devices
Code signage 7,913 SF 0.15 1,187
Room identification and wayfinding signage 7,913 SF 0.55 4,352
C1037 General fittings and misc. metals
Miscellaneous metals, allow 0.4#/SF 3,165 LB 3.50 11,078
Fire extinguisher cabinets 2 EA 290.00 580
Grab bars at restrooms 1 EA 210.00 210
Mirrors at restrooms 1 EA 175.00 175
Shower curtain and track 1 EA 150.00 150
June 15, 2017
Page 12
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 7,913 SF
Bellevue, WA Date:
Option B - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
June 15, 2017
Restroom accessories 1 LS 900.00 900
Shower accessories 1 LS 200.00 200
Locker benches, 4'-0" , wood 2 EA 272.00 544
C3012 Wall finishes
Paint to walls 1 LS 14,639.05 14,639
Ceramic tile at wet walls 203 SF 17.00 3,451
C3024 Flooring including base
Sheet goods at wellness center, laundry, storage and athletic treatment 1,675 SF 5.00 8,375
Ceramic tile at at shower / faculty lockers 267 SF 17.00 4,539Allowance for floor finishes at other areas 5,971 SF 6.50 38,812Base 1 LS 7,121.70 7,122
C3031 Ceiling finishes
ACT at wellness center, laundry, storage and athletic treatment 1,675 SF 6.35 10,636
Gypsum board, painted at shower / faculty lockers 267 SF 12.85 3,431
Allowance for ceiling finishes at remaining areas 5,971 SF 5.00 29,855
D2010 Plumbing Fixtures
Plumbing systems, complete 1 LS 29,051.00 29,051
D3010 HVAC
HVAC systems, complete 1 LS 274,380.00 274,380
D 4010 Sprinklers
Sprinkler system, complete, assumed not required N/A
D5000 Electrical
Electrical systems, complete 1 LS 161,702.00 161,702
E1094 Residential equipment
Residential appliances, not required N/A
E2012 Fixed casework
Athletic treatment room
Base cabinetry, plastic laminate 8 LF 230.00 1,840
Countertop, plastic laminate 8 LF 85.00 680
E2013 Blinds and other window treatments
Window treatments at new windows 1 LS 2,475.00 2,475
F 2010 Building Elements Demolition
Interior walls, CMU, 6" 501 LF 30.80 15,431
Doors, per leaf 17 EA 74.50 1,267
Toilet partitions 1 EA 85.00 85
Shower partitions 1 EA 85.00 85
Restroom accessories 1 LS 23.00 23
Shower accessories 1 LS 18.50 19
Locker bench, 20'-0" 7 EA 80.00 560
Page 13
Bellevue College
Gymnasium Remodel
Schematic Design Estimate Gross Floor Area: 7,913 SF
Bellevue, WA Date:
Option B - Phase 1 Prepared By: AC
Item Description Quantity Unit Unit Cost Totals
June 15, 2017
Locker benches, 5'-0" , wood 1 EA 297.50 298
Lockers 274 EA 37.50 10,275
Floor finishes 7,913 SF 1.40 11,078
Ceiling finishes 7,913 SF 1.15 9,100
Exterior walls 61 LF 190.00 11,590
Miscellaneous demolition 7,913 SF 0.80 6,330
F 2020 Hazardous Components Abatement
HAZMAT Abatement, excluded N/A
Sub-Total 839,867
General Conditions 15.00% 839,867.10 125,980
Sub-Total 965,847
Estimating / Design Contingency 10.00% 965,847.17 96,585
Sub-Total 1,062,432
Escalation - December 2017 2.50% 1,062,431.88 26,561
Sub-Total 1,088,993
GC Fee 8.00% 1,088,992.68 87,119
TOTAL CONSTRUCTION COST 1,176,112
Page 14
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Jared Robillard DATE
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
mechanical summary SF $/SF
Option A Phase 1 and 2
Phase 1
Plumbing (Division 22) 9,795 $35.13
Mechanical (Division 23) 9,795 $34.32
Option A - Phase 1 subtotal 9,795 $69.46 $566,959 $113,392 $680,351
Phase 2
Plumbing (Division 22) 5,177 $4.69
Mechanical (Division 23) 5,177 $40.66
Option A - Phase 2 subtotal 5,177 $45.35 $195,646 $39,129 $234,775
TOTAL MECHANICAL - Option A 14,972 $50.94
$336,213
$762,605 $152,521 $915,126
24,290
210,485
June 9, 2017
subtotal OH&P total
$280,177 $56,035
$286,782 $57,356 $344,138
35,081
20,242 4,048
175,404
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Jared Robillard DATE
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
mechanical summary SF $/SF
June 9, 2017
subtotal OH&P total
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 1
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
DIVISION 22
SECTION 220000 PLUMBING WORK SPECIFIED IN DIVISION 23General Provisions
Permit, Mobilization, Submittals, Bond 9,795 SF .10 980 980 196 1,175
SECTION 221116 DOMESTIC WATER SYSTEMDomestic Water SystemsCopper Tubing
Type L, Soldered (Sweat) or brazed joints and fittingsOverhead, hangers 10' O.C.
1/2" 200 LF 4.24 848 5.50 1,100 1,948 390 2,338 3/4" 80 LF 6.50 520 5.85 468 988 198 1,186 1" 20 LF 9.60 192 6.55 131 323 65 388 1-1/4" 40 LF 13.70 548 7.70 308 856 171 1,027 1-1/2" 80 LF 17.55 1,404 8.60 688 2,092 418 2,510 2" 80 LF 27.50 2,200 10.65 852 3,052 610 3,662 2-1/2" 50 LF 42.50 2,125 12.95 648 2,773 555 3,327 3" 50 LF 58.00 2,900 14.35 718 3,618 724 4,341 4" 20 LF 100.00 2,000 20.50 410 2,410 482 2,892
Elbows, Tees, and Joints1/2" (1 per 10 LF) 67 /LF 5.65 377 23.00 1,533 1,910 382 2,292 3/4" (1 per 10 LF) 27 /LF 12.70 339 38.50 1,027 1,365 273 1,638 1" (1 per 10 LF) 2 /LF 39.50 79 46.00 92 171 34 205 1-1/4" (1 per 10 LF) 4 /LF 53.50 214 51.00 204 418 84 502 1-1/2" (1 per 10 LF) 8 /LF 82.50 660 57.50 460 1,120 224 1,344 2" (1 per 10 LF) 8 /LF 129.00 1,032 66.00 528 1,560 312 1,872 2-1/2" (1 per 10 LF) 5 /LF 129.00 645 66.00 330 975 195 1,170 3" (1 per 10 LF) 5 /LF 200.00 1,000 75.00 375 1,375 275 1,650 4" (1 per 10 LF) 2 /LF 750.00 1,500 150.00 300 1,800 360 2,160
June 9, 2017
quantity material cost labor cost engineering opiniondescription
3 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 1
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
Backflow Preventers, Reduced Pressure PrincipleFlanged with gate valves
4" 1 EA 3,750.00 3,750 276.00 276 4,026 805 4,831 6" EA 5,275.00 430.00
Water Meters 02" (160gpm) 2 EA 430.00 860 74.50 149 1,009 202 1,211
Trap Primers EAElectronic Manifold Type 4 EA 800.00 3,200 400.00 1,600 4,800 960 5,760
Water hammer arresters1" 8 EA 45.50 364 56.00 448 812 162 974
SECTION 222120 PLUMBING VALVESPlumbing Valves 9,795 SF .10 980 .05 490 1,469 294 1,763
SECTION 222123 PLUMBING PUMPSPlumbing Pumps 9,795 SF .05 490 .03 294 784 157 940
SECTION 221300 SOIL, WASTE, VENT AND STORM DRAINAGE PIPINGSoil, Waste, Vent and Storm Drainage Piping 9,795 SF 1.75 17,141 .80 7,836 24,977 4,995 29,973
4 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 1
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 223000 PLUMBING EQUIPMENTPlumbing EquipmentWater heaters, Electric
50 gal, 37 GPH 1 EA 5,075.00 5,075 1,175.00 1,175 6,250 1,250 7,500 120 gal, 147GPH 1 EA 9,875.00 9,875 1,675.00 1,675 11,550 2,310 13,860
Domestic Water Heat Pump 1 EA 36,000.00 36,000 500.00 500 36,500 7,300 43,800 Storage Tank - 125#, ASME Sec IV, Glass Lined, Jacketed, & Insulated
750 Gallon Niles Steel Tank JS-30-111 1 EA 15,000.00 15,000 300.00 300 15,300 3,060 18,360 Expansion Tank
14 Gallon, Diaphram Type, B&G PTA-30V ASME 1 EA 1,450.00 1,450 450.00 450 1,900 380 2,280 20 Gallon, Diaphram Type, B&G PTA-42V ASME 1 EA 1,575.00 1,575 450.00 450 2,025 405 2,430
Drain pans 2 EA 132.00 264 18.90 38 302 60 362
SECTION 224000 PLUMBING FIXTURESPlumbing FixturesFixtures (Includes faucet,fittings,piping & insulation to clg)
Water Closets, wall mounted 31 EA 1,550.00 48,050 700.00 21,700 69,750 13,950 83,700 Urinals 3 EA 1,375.00 4,125 700.00 2,100 6,225 1,245 7,470 Lavs 22 EA 985.00 21,670 600.00 13,200 34,870 6,974 41,844 Eyewash Stations 1 EA 600.00 600 600.00 600 1,200 240 1,440 Mop Sinks 1 EA 700.00 700 600.00 600 1,300 260 1,560 Shower, Enclosed HC 12 EA 1,600.00 19,200 600.00 7,200 26,400 5,280 31,680 Electric Water Cooler 1 EA 1,500.00 1,500 600.00 600 2,100 420 2,520 Hose bibb, Interior and Exterior 2 EA 350.00 700 250.00 500 1,200 240 1,440
Thermostatic mixing valves 1 EA 2,100.00 2,100 200.00 200 2,300 460 2,760
Subtotal Division 22 213,251 73,531 286,782 57,356 344,138
5 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 1
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
DIVISION 23
SECTION 230500 GENERAL PROVISIONSGeneral Provisions
Permit, Mobilization, Submittals, Bond 9,795 SF 1.30 12,734 12,734 2,547 15,280
SECTION 230505 PROJECT CLOSEOUT AND SYSTEM START UPProject Closeout and System Start Up 9,795 SF .15 1,469 1,469 294 1,763
SECTION 230510 BASIC MATERIALS AND METHODSBasic Materials and Methods 9,795 SF .02 196 .01 98 294 59 353
SECTION 230520 MECHANICAL DEMOLITIONMechanical Demolition 9,795 SF 1.50 14,693 14,693 2,939 17,631
SECTION 230548 VIBRATION ISOLATIONVibration Isolation 9,795 SF .02 196 .01 98 294 59 353
SECTION 230550 SEISMIC CONTROLSeismic Control 9,795 SF .02 196 .01 98 294 59 353
SECTION 230593 TESTING, ADJUSTING AND BALANCINGTesting, Adjusting and Balancing, Complex Project 9,795 SF .50 4,898 4,898 980 5,877
SECTION 230700 MECHANICAL INSULATIONMechanical Insulation 9,795 SF .30 2,939 1.30 12,734 15,672 3,134 18,806
SECTION 230800 COMMISSIONING SUPPORTCommissioning Support 9,795 SF .10 980 980 196 1,175
6 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 1
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 230810 SYSTEMS TRAININGSystems Training 9,795 SF .03 294 .02 196 490 98 588
SECTION 230820 SYSTEM O&M MANUALSSystem O&M Manuals 9,795 SF .03 294 .02 196 490 98 588
SECTION 230900 AUTOMATIC TEMPERATURE CONTROLSAutomatic Temperature Controls 9,795 SF 4.00 39,180 3.00 29,385 68,565 13,713 82,278
SECTION 231123 NATURAL GAS PIPINGNatural Gas Piping 9,795 SF .10 980 .05 490 1,469 294 1,763
SECTION 232116 PIPING SPECIALTIESPiping Specialties 9,795 SF .10 980 .10 980 1,959 392 2,351
7 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 1
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 233100 AIR DISTRIBUTIONAir DistributionGalvanized Steel Ductwork, 22 gauge
Over 5000lbs 12000 LBS .70 8,395 4.50 54,000 62,395 12,479 74,874 Flexible Ductwork in 5'-0" lengths, 12"dia ave. 50 EA 4.20 210 7.70 385 595 119 714
SECTION 233300 AIR DISTRIBUTION ACCESSORIESAir Distribution Accessories 9,795 SF .40 3,918 .20 1,959 5,877 1,175 7,052
SECTION 233400 AIR DISTRIBUTION EQUIPMENTAir Distribution Equipment 12,000 CFM 5.50 66,000 1.00 12,000 78,000 15,600 93,600
SECTION 233700 AIR DEVICESAir Devices 9,795 SF .50 4,898 .20 1,959 6,857 1,371 8,228
SECTION 234100 FILTERSFilters 9,795 SF .05 490 .02 196 686 137 823
SECTION 238200 TERMINAL HEAT TRANSFER EQUIPMENTTerminal Heat Transfer Equipment 9,795 SF .10 980 .05 490 1,469 294 1,763
Subtotal Division 23 130,143 150,034 280,177 56,035 336,213
Total Mechanical (Division 21, 22, 23) 343,394 223,565 566,959 113,392 680,351
8 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
DIVISION 22
SECTION 220000 PLUMBING WORK SPECIFIED IN DIVISION 23General Provisions
Permit, Mobilization, Submittals, Bond 5,177 SF .10 518 518 104 621
SECTION 221116 DOMESTIC WATER SYSTEMDomestic Water SystemsCopper Tubing
Type L, Soldered (Sweat) or brazed joints and fittingsOverhead, hangers 10' O.C.
1/2" 50 LF 4.24 212 5.50 275 487 97 584 3/4" 50 LF 6.50 325 5.85 293 618 124 741 1" 50 LF 9.60 480 6.55 328 808 162 969
Elbows, Tees, and Joints1/2" (1 per 10 LF) 17 /LF 5.65 94 23.00 383 478 96 573 3/4" (1 per 10 LF) 17 /LF 12.70 212 38.50 642 853 171 1,024 1" (1 per 10 LF) 5 /LF 39.50 198 46.00 230 428 86 513
Trap Primers EAElectronic Manifold Type 1 EA 800.00 800 400.00 400 1,200 240 1,440
Water hammer arresters3/4" 2 EA 28.00 56 37.00 74 130 26 156
SECTION 222120 PLUMBING VALVESPlumbing Valves 5,177 SF .10 518 .05 259 777 155 932
SECTION 221300 SOIL, WASTE, VENT AND STORM DRAINAGE PIPINGSoil, Waste, Vent and Storm Drainage Piping 5,177 SF .80 4,142 .40 2,071 6,212 1,242 7,455
June 9, 2017
quantity material cost labor cost engineering opiniondescription
9 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 224000 PLUMBING FIXTURESPlumbing FixturesFixtures (Includes faucet,fittings,piping & insulation to clg)
Water Closets, wall mounted 1 EA 1,550.00 1,550 700.00 700 2,250 450 2,700 Lavs 1 EA 985.00 985 600.00 600 1,585 317 1,902 Misc Fixtures, whirlpool, service boxes 1 EA 1,100.00 1,100 600.00 600 1,700 340 2,040 Shower, Enclosed HC 1 EA 1,600.00 1,600 600.00 600 2,200 440 2,640
Subtotal Division 22 12,271 7,971 20,242 4,048 24,290
DIVISION 23
SECTION 230500 GENERAL PROVISIONSGeneral Provisions
Permit, Mobilization, Submittals, Bond 5,177 SF 1.30 6,730 6,730 1,346 8,076
SECTION 230505 PROJECT CLOSEOUT AND SYSTEM START UPProject Closeout and System Start Up 5,177 SF .15 777 777 155 932
SECTION 230510 BASIC MATERIALS AND METHODSBasic Materials and Methods 5,177 SF .02 104 .01 52 155 31 186
SECTION 230520 MECHANICAL DEMOLITIONMechanical Demolition 5,177 SF 1.50 7,766 7,766 1,553 9,319
SECTION 230548 VIBRATION ISOLATIONVibration Isolation 5,177 SF .02 104 .01 52 155 31 186
SECTION 230550 SEISMIC CONTROLSeismic Control 5,177 SF .02 104 .01 52 155 31 186
10 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 230593 TESTING, ADJUSTING AND BALANCINGTesting, Adjusting and Balancing, Complex Project 5,177 SF .50 2,589 2,589 518 3,106
SECTION 230700 MECHANICAL INSULATIONMechanical Insulation 5,177 SF .30 1,553 1.30 6,730 8,283 1,657 9,940
SECTION 230800 COMMISSIONING SUPPORTCommissioning Support 5,177 SF .10 518 518 104 621
SECTION 230810 SYSTEMS TRAININGSystems Training 5,177 SF .03 155 .02 104 259 52 311
SECTION 230820 SYSTEM O&M MANUALSSystem O&M Manuals 5,177 SF .03 155 .02 104 259 52 311
SECTION 230900 AUTOMATIC TEMPERATURE CONTROLSAutomatic Temperature Controls 5,177 SF 4.00 20,708 3.00 15,531 36,239 7,248 43,487
SECTION 231123 NATURAL GAS PIPINGNatural Gas Piping 5,177 SF .10 518 .05 259 777 155 932
SECTION 232116 PIPING SPECIALTIESPiping Specialties 5,177 SF .10 518 .10 518 1,035 207 1,242
11 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption A - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 233100 AIR DISTRIBUTIONAir DistributionGalvanized Steel Ductwork, 22 gauge
Installed at 10' to 15'Over 5000lbs 7000 LBS .70 4,897 4.50 31,500 36,397 7,279 43,677
Flexible Ductwork in 5'-0" lengths, 12"dia ave. 40 EA 4.20 168 7.70 308 476 95 571
SECTION 233300 AIR DISTRIBUTION ACCESSORIESAir Distribution Accessories 5,177 SF .40 2,071 .20 1,035 3,106 621 3,727
SECTION 233400 AIR DISTRIBUTION EQUIPMENTAir Distribution Equipment 7,000 CFM 5.50 38,500 1.00 7,000 45,500 9,100 54,600
SECTION 233700 AIR DEVICESAir Devices 5,177 SF .50 2,589 .20 1,035 3,624 725 4,349
SECTION 234100 FILTERSFilters 5,177 SF .05 259 .02 104 362 72 435
Subtotal Division 23 72,401 82,761 155,162 31,032 186,194
Total Mechanical (Division 21, 22, 23) 84,672 90,732 175,404 35,081 210,485
12 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
DIVISION 22
SECTION 220000 PLUMBING WORK SPECIFIED IN DIVISION 23General Provisions
Permit, Mobilization, Submittals, Bond 7,059 SF .10 706 706 141 847
SECTION 221116 DOMESTIC WATER SYSTEMDomestic Water Systems SF 1.45 .85 Copper Tubing
Type L, Soldered (Sweat) or brazed joints and fittingsOverhead, hangers 10' O.C.
1/2" 200 LF 4.24 848 5.50 1,100 1,948 390 2,338 3/4" 80 LF 6.50 520 5.85 468 988 198 1,186 1" 20 LF 9.60 192 6.55 131 323 65 388 1-1/4" 40 LF 13.70 548 7.70 308 856 171 1,027 1-1/2" 80 LF 17.55 1,404 8.60 688 2,092 418 2,510 2" 80 LF 27.50 2,200 10.65 852 3,052 610 3,662 2-1/2" 50 LF 42.50 2,125 12.95 648 2,773 555 3,327 3" 50 LF 58.00 2,900 14.35 718 3,618 724 4,341 4" 20 LF 100.00 2,000 20.50 410 2,410 482 2,892
Elbows, Tees, and Joints1/2" (1 per 10 LF) 67 /LF 5.65 377 23.00 1,533 1,910 382 2,292 3/4" (1 per 10 LF) 27 /LF 12.70 339 38.50 1,027 1,365 273 1,638 1" (1 per 10 LF) 2 /LF 39.50 79 46.00 92 171 34 205 1-1/4" (1 per 10 LF) 4 /LF 53.50 214 51.00 204 418 84 502 1-1/2" (1 per 10 LF) 8 /LF 82.50 660 57.50 460 1,120 224 1,344 2" (1 per 10 LF) 8 /LF 129.00 1,032 66.00 528 1,560 312 1,872 2-1/2" (1 per 10 LF) 5 /LF 129.00 645 66.00 330 975 195 1,170 3" (1 per 10 LF) 5 /LF 200.00 1,000 75.00 375 1,375 275 1,650 4" (1 per 10 LF) 2 /LF 750.00 1,500 150.00 300 1,800 360 2,160
June 9, 2017
quantity material cost labor cost engineering opiniondescription
13 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
Backflow Preventers, Reduced Pressure PrincipleFlanged with gate valves
4" 1 EA 3,750.00 3,750 276.00 276 4,026 805 4,831 Water Meters 0
2" (160gpm) 2 EA 430.00 860 74.50 149 1,009 202 1,211 Trap Primers EA
Electronic Manifold Type 4 EA 800.00 3,200 400.00 1,600 4,800 960 5,760 Water hammer arresters
3/4" EA 28.00 37.00 1" 8 EA 45.50 364 56.00 448 812 162 974
SECTION 222120 PLUMBING VALVESPlumbing Valves 7,059 SF .10 706 .05 353 1,059 212 1,271
SECTION 222123 PLUMBING PUMPSPlumbing Pumps 7,059 SF .07 494 .04 282 776 155 932
SECTION 221300 SOIL, WASTE, VENT AND STORM DRAINAGE PIPINGSoil, Waste, Vent and Storm Drainage Piping 7,059 SF 1.75 12,353 .80 5,647 18,000 3,600 21,601
14 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 223000 PLUMBING EQUIPMENTPlumbing EquipmentWater heaters, Electric
50 gal, 37 GPH 1 EA 5,075.00 5,075 1,175.00 1,175 6,250 1,250 7,500 120 gal, 147GPH 1 EA 9,875.00 9,875 1,675.00 1,675 11,550 2,310 13,860
Domestic Water Heat Pump 1 EA 36,000.00 36,000 500.00 500 36,500 7,300 43,800 Storage Tank - 125#, ASME Sec IV, Glass Lined, Jacketed, & Insulated EA
750 Gallon Niles Steel Tank JS-30-111 1 EA 15,000.00 15,000 300.00 300 15,300 3,060 18,360 Expansion Tank EA
14 Gallon, Diaphram Type, B&G PTA-30V ASME 1 EA 1,450.00 1,450 450.00 450 1,900 380 2,280 20 Gallon, Diaphram Type, B&G PTA-42V ASME 1 EA 1,575.00 1,575 450.00 450 2,025 405 2,430
Drain pans 2 EA 132.00 264 18.90 38 302 60 362
SECTION 224000 PLUMBING FIXTURESPlumbing FixturesFixtures (Includes faucet,fittings,piping & insulation to clg)
Water Closets, wall mounted 29 EA 1,550.00 44,950 700.00 20,300 65,250 13,050 78,300 Urinals 5 EA 1,375.00 6,875 700.00 3,500 10,375 2,075 12,450 Lavs 22 EA 985.00 21,670 600.00 13,200 34,870 6,974 41,844 Misc Fixtures 1 EA 1,100.00 1,100 600.00 600 1,700 340 2,040 Eyewash Stations 1 EA 600.00 600 600.00 600 1,200 240 1,440 Mop Sinks 1 EA 700.00 700 600.00 600 1,300 260 1,560 Shower, Enclosed HC 12 EA 1,600.00 19,200 600.00 7,200 26,400 5,280 31,680 Electric Water Cooler 1 EA 1,500.00 1,500 600.00 600 2,100 420 2,520 Hose bibb, Interior and Exterior 5 EA 350.00 1,750 250.00 1,250 3,000 600 3,600
Thermostatic mixing valves 1 EA 2,100.00 2,100 200.00 200 2,300 460 2,760
Subtotal Division 22 209,994 72,270 282,264 56,453 338,717
15 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
DIVISION 23
SECTION 230500 GENERAL PROVISIONSGeneral Provisions
Permit, Mobilization, Submittals, Bond 7,059 SF 1.30 9,177 9,177 1,835 11,012
SECTION 230505 PROJECT CLOSEOUT AND SYSTEM START UPProject Closeout and System Start Up 7,059 SF .15 1,059 1,059 212 1,271
SECTION 230510 BASIC MATERIALS AND METHODSBasic Materials and Methods 7,059 SF .02 141 .01 71 212 42 254
SECTION 230520 MECHANICAL DEMOLITIONMechanical Demolition 7,059 SF 1.50 10,589 10,589 2,118 12,706
SECTION 230548 VIBRATION ISOLATIONVibration Isolation 7,059 SF .02 141 .01 71 212 42 254
SECTION 230550 SEISMIC CONTROLSeismic Control 7,059 SF .02 141 .01 71 212 42 254
SECTION 230593 TESTING, ADJUSTING AND BALANCINGTesting, Adjusting and Balancing, Complex Project 7,059 SF .50 3,530 3,530 706 4,235
SECTION 230700 MECHANICAL INSULATIONMechanical Insulation 7,059 SF .30 2,118 1.30 9,177 11,294 2,259 13,553
SECTION 230800 COMMISSIONING SUPPORTCommissioning Support 7,059 SF .10 706 706 141 847
16 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 230810 SYSTEMS TRAININGSystems Training 7,059 SF .03 212 .02 141 353 71 424
SECTION 230820 SYSTEM O&M MANUALSSystem O&M Manuals 7,059 SF .03 212 .02 141 353 71 424
SECTION 230900 AUTOMATIC TEMPERATURE CONTROLSAutomatic Temperature Controls 7,059 SF 4.00 28,236 3.00 21,177 49,413 9,883 59,296
SECTION 231123 NATURAL GAS PIPINGNatural Gas Piping 7,059 SF .10 706 .05 353 1,059 212 1,271
SECTION 232116 PIPING SPECIALTIESPiping Specialties 7,059 SF .10 706 .10 706 1,412 282 1,694
17 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 233100 AIR DISTRIBUTIONAir DistributionGalvanized Steel Ductwork, 22 gauge
Installed at 10' to 15'Over 5000lbs 9000 LBS .70 6,296 4.50 40,500 46,796 9,359 56,156
Flexible Ductwork in 5'-0" lengths, 12"dia ave. 50 EA 4.20 210 7.70 385 595 119 714
SECTION 233300 AIR DISTRIBUTION ACCESSORIESAir Distribution Accessories 7,059 SF .40 2,824 .20 1,412 4,235 847 5,082
SECTION 233400 AIR DISTRIBUTION EQUIPMENTAir Distribution Equipment 9,000 CFM 5.50 49,500 1.00 9,000 58,500 11,700 70,200
SECTION 233700 AIR DEVICESAir Devices 7,059 SF .50 3,530 .20 1,412 4,941 988 5,930
SECTION 234100 FILTERSFilters 7,059 SF .05 353 .02 141 494 99 593
SECTION 238200 TERMINAL HEAT TRANSFER EQUIPMENTTerminal Heat Transfer Equipment 7,059 SF .20 1,412 .10 706 2,118 424 2,541
Subtotal Division 23 96,737 110,522 207,259 41,452 248,710
Total Mechanical (Division 21, 22, 23) 306,730 182,792 489,522 97,904 587,427
18 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
DIVISION 22
SECTION 220000 PLUMBING WORK SPECIFIED IN DIVISION 23General Provisions
Permit, Mobilization, Submittals, Bond 7,913 SF .10 791 791 158 950
SECTION 221116 DOMESTIC WATER SYSTEMDomestic Water SystemsCopper Tubing
Type L, Soldered (Sweat) or brazed joints and fittingsOverhead, hangers 10' O.C.
1/2" 50 LF 4.24 212 5.50 275 487 97 584 3/4" 50 LF 6.50 325 5.85 293 618 124 741 1" 50 LF 9.60 480 6.55 328 808 162 969
Elbows, Tees, and Joints1/2" (1 per 10 LF) 17 /LF 5.65 94 23.00 383 478 96 573 3/4" (1 per 10 LF) 17 /LF 12.70 212 38.50 642 853 171 1,024 1" (1 per 10 LF) 5 /LF 39.50 198 46.00 230 428 86 513
Trap Primers EAElectronic Manifold Type 1 EA 800.00 800 400.00 400 1,200 240 1,440
Water hammer arresters3/4" 2 EA 28.00 56 37.00 74 130 26 156
SECTION 222120 PLUMBING VALVESPlumbing Valves 7,913 SF .10 791 .05 396 1,187 237 1,424
SECTION 221300 SOIL, WASTE, VENT AND STORM DRAINAGE PIPINGSoil, Waste, Vent and Storm Drainage Piping 7,913 SF .80 6,330 .40 3,165 9,496 1,899 11,395
June 9, 2017
quantity material cost labor cost engineering opiniondescription
19 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 224000 PLUMBING FIXTURESPlumbing FixturesFixtures (Includes faucet,fittings,piping & insulation to clg)
Water Closets, wall mounted 1 EA 1,550.00 1,550 700.00 700 2,250 450 2,700 Lavs 1 EA 985.00 985 600.00 600 1,585 317 1,902 Misc Fixtures, whirlpool, service boxes 1 EA 1,100.00 1,100 600.00 600 1,700 340 2,040 Shower, Enclosed HC 1 EA 1,600.00 1,600 600.00 600 2,200 440 2,640
Subtotal Division 22 14,733 9,476 24,209 4,842 29,051
DIVISION 23
SECTION 230500 GENERAL PROVISIONSGeneral Provisions
Permit, Mobilization, Submittals, Bond 7,913 SF 1.30 10,287 10,287 2,057 12,344
SECTION 230505 PROJECT CLOSEOUT AND SYSTEM START UPProject Closeout and System Start Up 7,913 SF .15 1,187 1,187 237 1,424
SECTION 230510 BASIC MATERIALS AND METHODSBasic Materials and Methods 7,913 SF .02 158 .01 79 237 47 285
SECTION 230512 INDOOR AIR QUALITY - HVACIndoor Air Quality - HVAC 7,913 SF .02 158 158 32 190
SECTION 230520 MECHANICAL DEMOLITIONMechanical Demolition 7,913 SF 1.50 11,870 11,870 2,374 14,243
SECTION 230548 VIBRATION ISOLATIONVibration Isolation 7,913 SF .02 158 .01 79 237 47 285
20 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 230550 SEISMIC CONTROLSeismic Control 7,913 SF .02 158 .01 79 237 47 285
SECTION 230593 TESTING, ADJUSTING AND BALANCINGTesting, Adjusting and Balancing, Complex Project 7,913 SF .50 3,957 3,957 791 4,748
SECTION 230700 MECHANICAL INSULATIONMechanical Insulation 7,913 SF .30 2,374 1.30 10,287 12,661 2,532 15,193
SECTION 230800 COMMISSIONING SUPPORTCommissioning Support 7,913 SF .07 554 554 111 665
SECTION 230810 SYSTEMS TRAININGSystems Training 7,913 SF .03 237 .02 158 396 79 475
SECTION 230820 SYSTEM O&M MANUALSSystem O&M Manuals 7,913 SF .03 237 .02 158 396 79 475
SECTION 230900 AUTOMATIC TEMPERATURE CONTROLSAutomatic Temperature Controls 7,913 SF 4.00 31,652 3.00 23,739 55,391 11,078 66,469
SECTION 231123 NATURAL GAS PIPINGNatural Gas Piping 7,913 SF .10 791 .05 396 1,187 237 1,424
SECTION 232116 PIPING SPECIALTIESPiping Specialties 7,913 SF .10 791 .10 791 1,583 317 1,899
21 of 22
mechanical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Linda Coppa DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Jared Robillard OVERHEAD & PROFIT 20%
number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opiniondescription
SECTION 233100 AIR DISTRIBUTIONAir DistributionGalvanized Steel Ductwork, 22 gauge
Installed at 10' to 15'Over 5000lbs 10000 LBS .70 6,996 4.50 45,000 51,996 10,399 62,395
Flexible Ductwork in 5'-0" lengths, 12"dia ave. 40 EA 4.20 168 7.70 308 476 95 571
SECTION 233300 AIR DISTRIBUTION ACCESSORIESAir Distribution Accessories 7,913 SF .40 3,165 .20 1,583 4,748 950 5,697
SECTION 233400 AIR DISTRIBUTION EQUIPMENTAir Distribution Equipment 10,000 CFM 5.50 55,000 1.00 10,000 65,000 13,000 78,000
SECTION 233700 AIR DEVICESAir Devices 7,913 SF .50 3,957 .20 1,583 5,539 1,108 6,647
SECTION 234100 FILTERSFilters 7,913 SF .05 396 .02 158 554 111 665
Subtotal Division 23 106,239 122,410 228,650 45,730 274,380
Total Mechanical (Division 21, 22, 23) 120,972 131,886 252,859 50,572 303,431
22 of 22
electrical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Anthony Hernandez DATEOption A
JOB NUMBER 17079 CHECKED BY Doug Svee OVERHEAD & PROFIT 20%
electrical summary
Option A Phase 1 and 2Phase 1
Electrical (Division 26)Life Safety (Division 28)
Option A - Phase 1 Subtotal
Electrical (Division 26)Life Safety (Division 28)
Option A - Phase 2 Subtotal
TOTAL ELECTRICAL - Option A
EXCLUSIONS1 - Design contingency 4 - Electrical & Telecom Utility Services est.2 - Sales tax 5 - General Contractor Overhead & Profit3 - Escalation
June 9, 2017
totalOH&Psubtotal
89,197 17,839 107,036
$434,304 $86,861 $521,165
19,414 3,883 23,297 $89,197 17,839 $107,036
$414,129
30,225
69,021
151,125
$345,107
193,982 38,796 232,779 181,350
1 of 1
electrical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Anthony Hernandez DATEOption B
JOB NUMBER 17079 CHECKED BY Doug Svee OVERHEAD & PROFIT 20%
electrical summary
Option B Phase 1 and 2Phase 1
Electrical (Division 26)Life Safety (Division 28)
Option B - Phase 1 Subtotal
Electrical (Division 26)Life Safety (Division 28)
Option B - Phase 2 Subtotal
TOTAL ELECTRICAL - Option B
EXCLUSIONS1 - Design contingency 4 - Electrical & Telecom Utility Services est.2 - Sales tax 5 - General Contractor Overhead & Profit3 - Escalation
June 9, 2017
totalOH&Psubtotal
134,751 26,950 161,702
$424,728 $84,946 $509,674
29,674 5,935 35,609 $134,751 26,950 $161,702
$347,972
28,310
57,995
141,549
$289,977
148,428 29,686 178,114 169,859
1 of 7
electrical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Anthony Hernandez DATEOption B - Phase 1
JOB NUMBER 17079 CHECKED BY Doug Svee OVERHEAD & PROFIT 20%
description number unit unit cost total unit cost total subtotal OH&P total
DIVISION 26
SECTION 260500 GENERAL ELECTRICAL PROVISIONSGeneral Provisions (Submittals, Mobilization, Permits) 1 LS 1,250.00 1,250 500.00 500 1,750 350.00 2,100 General Provisions (Cx, Training, O&M, PL & Closeout) 1 LS 1,250.00 1,250 1,250 250.00 1,500
SECTION 260510 BASIC ELECTRICAL MATERIALS AND METHODSBasic Materials and Methods 7,059 SF .15 1,059 1,059 211.77 1,271
(Consumables, Small Tools, Equip Rental, Grounding, Identification, etc.)
SECTION 260511 ELECTRICAL CONNECTIONS FOR EQUIPMENTElectrical Connections For Equipment 7,059 SF .80 5,647 .75 5,294 10,941 2,188.29 13,130 200 Amp Fused Disconnect Switch 1 EA 755.00 755 330.00 330 1,085 217.00 1,302
SECTION 260512 ELECTRICAL DEMOLITIONDemolition 7,059 SF .25 1,765 1.00 7,059 8,824 1,764.75 10,589
SECTION 260519 WIRES AND CABLES - COPPER, 3P, N , G400A Feeder Wiring 10 LF 26.92 269 16.04 160 430 85.92 516
SECTION 260923 LIGHTING CONTROLSLighting Controls 7,059 SF 1.75 12,353 .50 3,530 15,883 3,176.55 19,059
engineering opinionlabor costmaterial costquantity
June 9, 2017
2 of 7
electrical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Anthony Hernandez DATEOption B - Phase 1
JOB NUMBER 17079 CHECKED BY Doug Svee OVERHEAD & PROFIT 20%
description number unit unit cost total unit cost total subtotal OH&P total
engineering opinionlabor costmaterial costquantity
June 9, 2017
SECTION 262200 TRANSFORMERSTransformers
112 1/2 kVA 1 EA 2,981.00 2,981 1,175.00 1,175 4,156 831.20 4,987
SECTION 262416 PANELBOARDSPanelboards
400A MCB including 42 branch breakers 3.00 EA 3,175.00 9,525 1,825.00 5,475 15,000 3,000.00 18,000 Surge Protection - Branch Panels 1 EA 1,000.00 1,000 225.00 225 1,225 245.00 1,470 Fault Calc and Protective Coordination Study - Small 1 LS 6,000.00 6,000 6,000 1,200.00 7,200
SECTION 262726 WIRING DEVICESRaceway, Outlet Box and Support Provisions 7,059 SF .30 2,118 .40 2,824 4,941 988.26 5,930 Branch Wiring Provisions 7,059 SF .30 2,118 .50 3,530 5,647 1,129.44 6,777
SECTION 265100 LIGHTINGRaceway, Outlet Box and Support Provisions 7,059 SF .75 5,294 .75 5,294 10,589 2,117.70 12,706 Lighting 7,059 SF 6.50 45,884 1.50 10,589 56,472 11,294.40 67,766
Subtotal Electrical (Division 26) 148,428 29,686 178,114
3 of 7
electrical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Anthony Hernandez DATEOption B - Phase 1
JOB NUMBER 17079 CHECKED BY Doug Svee OVERHEAD & PROFIT 20%
description number unit unit cost total unit cost total subtotal OH&P total
SECTION 283111 FIRE ALARM SYSTEMFull coverage System in remodel area 7,059 SF 3.00 21,177 3.00 21,177 42,354 8,471 50,825
Notification throughout the building 39,678 SF 1.25 49,598 1.25 49,598 99,195 19,839 119,034 Subtotal Life Safety and Security Systems (Divisions 28) 141,549 28,310 169,859
engineering opinionlabor costmaterial costquantity
June 9, 2017
4 of 7
electrical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Anthony Hernandez DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Doug Svee OVERHEAD & PROFIT 20%
description number unit unit cost total unit cost total subtotal OH&P total
DIVISION 26
SECTION 260500 GENERAL ELECTRICAL PROVISIONSGeneral Provisions (Submittals, Mobilization, Permits) 1 LS 1,250.00 1,250 500.00 500 1,750 350.00 2,100 General Provisions (Cx, Training, O&M, PL & Closeout) 1 LS 1,250.00 1,250 1,250 250.00 1,500
SECTION 260510 BASIC ELECTRICAL MATERIALS AND METHODSBasic Materials and Methods 7,913 SF .15 1,187 1,187 237.39 1,424
(Consumables, Small Tools, Equip Rental, Grounding, Identification, etc.)
SECTION 260511 ELECTRICAL CONNECTIONS FOR EQUIPMENTElectrical Connections For Equipment 7,913 SF .80 6,330 .75 5,935 12,265 2,453.03 14,718
SECTION 260512 ELECTRICAL DEMOLITIONDemolition 7,913 SF .25 1,978 1.00 7,913 9,891 1,978.25 11,870
SECTION 260923 LIGHTING CONTROLSLighting Controls 7,913 SF 1.75 13,848 .50 3,957 17,804 3,560.85 21,365
SECTION 262726 WIRING DEVICESRaceway, Outlet Box and Support Provisions 7,913 SF .30 2,374 .40 3,165 5,539 1,107.82 6,647 Branch Wiring Provisions 7,913 SF .30 2,374 .50 3,957 6,330 1,266.08 7,596
SECTION 265100 LIGHTING
June 9, 2017
quantity material cost labor cost engineering opinion
5 of 7
electrical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Anthony Hernandez DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Doug Svee OVERHEAD & PROFIT 20%
description number unit unit cost total unit cost total subtotal OH&P total
June 9, 2017
quantity material cost labor cost engineering opinion
Raceway, Outlet Box and Support Provisions 7,913 SF .75 5,935 .75 5,935 11,870 2,373.90 14,243 Lighting 7,913 SF 6.50 51,435 1.50 11,870 63,304 12,660.80 75,965
Subtotal Electrical (Division 26) 134,751 26,950 161,702
6 of 7
electrical cost opinion
Bellevue College Gymnasium RemodelBuilding G
BASIS OF OPINION Schematic Design PREPARED BY Anthony Hernandez DATEOption B - Phase 2
JOB NUMBER 17079 CHECKED BY Doug Svee OVERHEAD & PROFIT 20%
description number unit unit cost total unit cost total subtotal OH&P total
SECTION 283111 FIRE ALARM SYSTEMFull coverage System in remodel area 7,913 SF 1.75 13,848 2.00 15,826 29,674 5,935 35,609
Subtotal Life Safety and Security Systems (Divisions 28) 29,674 5,935 35,609
June 9, 2017
quantity material cost labor cost engineering opinion
7 of 7