Webinar Presentation TIR Amendments Part1 April 11 2011 Part1
Beginners Manual for Product Costing in Sap Part1
-
Upload
adil-mustafa -
Category
Documents
-
view
181 -
download
21
description
Transcript of Beginners Manual for Product Costing in Sap Part1
Goals
2
• To understand the SAP functionality of product costing along
with the corresponding configuration settings.
(This is part 1 of a series of multiple sessions planned)
• To discuss real issues reported in production system, analyze
the root cause of the issue and identify potential solution
approaches
• To identify potential areas of improvement to the design
currently in place at ConAgra
Agenda for this Session
3
SAP functionality overview on Product Cost Planning:
Controlling Area and Version settings
Cost Component Structure overview
Master data for product costing (materials, BoM, Recipe etc.)
Costing variants / Valuation variant /Transfer Control concepts
Costing type, Costing version, Marking allowance
Costing sheets for overheads
Cost center planning and activity rates
Joint production, co-products, by-products
Costing of materials sourced from other plants
CAG Production issues on the above topic if any brought up
Product Cost Controlling Components
4
Product
Cost
Planning
Cost
Object
Controlling
Actual
Costing /
Material
Ledger
Information
System
5
In Cost Object Controlling,
the costs incurred in the
production of a product or
service are collected on a
cost object (such as a
production order). Which
cost object is used
depends on your
controlling requirements. It
may be a sales order, a
production order, a
process order or a
production cost collector.
Cost Object Controlling is
used to calculate work in
process, scrap costs and
variances at period close.
Product Cost Planning
refers to the creation of
cost estimates for the
production of goods or
services.
There is no reference to
a production order i.e.
the cost estimate
is independent of
any given
production order
Product Cost Planning Cost Object Controlling
Actual Costing is used to
calculate actual product
costs at period close.
The result may be
transferred to the
material master as a
weighted average price
for the closed period.
The quantity structure is
derived dynamically
using the materials
movements in the R/3
system. The values
connected with these
movements are collected
in the Material Ledger.
Actual Costing
Product Cost Controlling Components
Cost Component Structure
7
• The buckets in which the product Costs will be stored in SAP.
• This is an uniform structure throughout the ConAgra enterprise
across all Plants / Company Codes.
• Each component can have a variable and a fixed component
• Consumption cost elements are mapped to a cost component
Example:
510000 Material
920001 Direct Labor
• Some buckets may not be relevant for some products or plants.
E.g. Labor cost is not relevant for purchased parts
CAG Cost Component Structure (T-Code OKTZ)
8
1 Raw materials.
2 Packaging.
3 Labor - Direct.
4 Direct Overhead.
5 Indirect Overhead.
6 External Processing.
7 Warehousing.
8 Inbound Frt - NFG
9 Outbound Frt -STO FG
Material Master fields relevant for Product Costing
9
General:• Material Type: Valuated or not
• Base Unit of Measure. Cannot be changed without a lot of
effort once there are transactions.
Accounting view:• Valuation Class (relevant to and account determination)
The valuation class controls the account determination. Here, the
consumption account is determined, which also appears as the
primary cost element in the itemization.
G.L A/c
Inventory Consumption
3000 Raw Materials 116003 511230
7900 CAG Finished 116009 511210
7920 Semi Finisheds 116013 511220
A particular material will be of the same material type and valuation
class across all CAG plants and company codes
10
Material Master fields relevant for Product Costing
• Costing lot size (identify BoM, Recipe for Std Cost/Set-up cost)
• Price unit (to accommodate more than 2 decimals)
• Price Control (Standard/moving average)
• ML Active and Price determination Control
Costing view:
• To be able to cost a material, the Costing view must be maintained
• Cost relevancy, Bulk material
• With/without quantity structure
• Valuation category (split valuation)
• Origin Group: helps analysis by grouping materials into categories;
cost estimates and production order costs can be sub-totalled by
origin group. Examples: Meat, Pulp, Packing Materials, etc.
• Co-Product, Fixed Price, Apportionment Structure
11
• Overhead group: Key that groups the materials for the same type of
overhead application. Comapnies use it for warehousing burden
and freight overheads.
• Profit Center: used for product line analysis
• Planned Price, Commercial price, Tax price fields (how used)
• Quantity Structure data (BoM, Routing, Production Version)
MRP view:
• Material status (readiness for costing, inventory movements)
• Procurement type: F (purchased) or E (produced)
- Materials with indicator “F” can be produced but for standard cost
purposes, only the purchase price is considered.
- Materials with indicator “E” can be purchased but for standard cost
purposes, only the BOM/Routing based rolled price is considered.
• Selection Method (MRP 4 view)
Material Master fields relevant for Product Costing
12
• Special procurement
- to identify a material as a “subcontracted” material (value 30)
- to identify a material as a “phantom” material (value 50) that will
have only a BOM and not a routing
- to identify a material being procured from another CAG plant
Example: parts in a distribution center will always carry a special
procurement key pointing to the manufacturing plant
(Costing view value overrides for the purpose of costing)
• Planned Scrap related fields
Material Master fields relevant for Product Costing
Costing Variant / Valuation Variants
13
BOM Routing
Prices for Materials
Prices for Activities
Overhead
Product Cost Planning
Value Structure
Quantity Structure:
PP Master Data
Costing
Variant
Valuation
Variant
Costing
Sheet
Labor $
Machine $
Overhead $
Raw Material $
Total $
Z001
Z01
Z1
Standard
Cost
Z002
Z02
Z2
Current
CostCost estimate:
Standard costs
Prod Cost Estimates – Standard Cost, Current and various simulations
By Plant
Costing Variant / Valuation Variants
14
Variant
Attributes
Frozen
Standard
Current
Structure
Current
CostsSimulate2
Material
Price
Frozen
Standard
Frozen
Standard
Current
PriceFuture Price
BOM/
Routing
Structure at
year
beginning
Current
Structure
Current
Structure
Structure as
on next
month
Activity
Price
Frozen
Standard
Frozen
Standard
Revised
prices
Planned
price for
next year
Examples:
< ---------------------- Costing Variants --------------------------- >
Quantity Structure Selection
15
Quantity Structure Control Through
Customizing
- BOM Usage
- Priority for Alternative
- Status
- Lot size
- Validity Period
Quantity Structure Control Through
the Material Master Record
- Higher priority over the above
- Sequence: Special procurement,
Production Version, Specific
BoM/routing
Quantity Structure Control Through
the Initial Screen of the Cost
Estimate
Transfer Control - Flexible Options
16
Complete transfer: While costing a material with multi-level BOM
structure, system takes the existing “released cost” of the BOM components,
without re-calculating the cost of components. Only if component does not
already have a released cost, system calculates the cost of the component.
This is very useful when you want to cost a new finished part which uses
the already existing components
Leaving it blank: System ignores the already existing released cost of
components and recalculates the component’s cost using one of the
strategies like planned price1 or purchase info record. This is useful when
once a year you want to re-cost all materials right from the bottom upwards at
all levels.
Cross Plant Transfer: This is used in “Costing run” when you have
selected the materials with special procurement types that points to other
plants for copying the cost from
Zxxx( customized): Take the cost stored in a different costing variant
Transfer Control - Flexible Options
17
Part A (FIN)
Part B1
(SEM)Part B2
(SEM)
Part C2
(SEM)
Part C1
(SEM)Part C3 (purchased
semi fin ZSEM)
Part D (Purchased
Fin Part)
Complete Transfer:
If a released cost
exists for B2, then
stop exploding. Take
the existing released
cost
Blank:
Explode B2 and
consider its
current cost for
cost roll of part A
Costing levels are determined automatically by the system when you create
a cost estimate. Assigning the materials to costing levels ensures that
costing is performed in the proper order: first raw materials and purchased
parts, then semi-finished products, and finally the finished products.
1
2
3
4
Material Cost
18
Total Standard Cost of
purchased material
Freight
Core Material
Price payable
to material
vendorBurden
Duty
Others
Surcharges
Material Cost Options
19
Valuation Variant provides the strategy sequence of costing the
purchased material. Examples:
Sequence Strategy
1 Price specified in one of the 3 free fields in material master
(planned price 1 to 3)- Typically used to override the price
obtained in the next strategy for “exception” cases
2 Price from Purchasing Module: Sub-strategies are:
a. Price from latest P.O issued (NOT last invoice paid)
b.Purchase Info Record
3 Current standard price
System searches in the sequence defined in the valuation variant
and stops as soon as a price is found at any level
Determination of Purchase Info record
20
When there is more than one vendor for the same material, the system by
default takes the lowest price.
You can choose to mark one of the vendors as “regular vendor” so that only
that vendor’s price is considered for standard cost
Options for Surcharges
21
1. Overhead Group along with Costing Sheet (CAG Option)
2. Additive Costs
3. Statistical Purchase Conditions
Costing Sheet based Surcharges
22
Material Master
Overhead Group
Valuation Variant
Costing Sheet
Costing sheet will define the calculation base and the overhead rate.
Flexible definition of calculation Base is possible. Examples:
• Cost element + overhead group + Overhead Rate Key
• Cost center + Cost Element +Activity type + Overhead Rate Key
Surcharge Calculated
Overhead Rate Key
From To Percentage
1/1/11 12/31/11 2%
Overhead percentages can be defined for Overhead rate key by date ranges
BoM Header
24
• BOM usage: Examples for BOM usage: BOMs used exclusively for
engineering or costing purposes.
• BOM status: If complex changes are made to a BOM, you can use the
BOM status to control when the BOM is used, such as for a cost
estimate.
• Area of validity: A BOM can be defined as valid for only a limited range
of lot sizes, such as 1 to 1,000 units. You can then create a different
BOM for lot sizes exceeding 1,000 units. Therefore, only one BOM can
be used for the defined costing lot size.
• Alternative BOM: Alternative BOMs can describe different product
structures that create a product with the same properties. For example,
one alternative uses sheet metal A, while the other alternative uses
sheet metal B.
BOM Line Items
25
• Item category:
L = stock item, N = non-stock item; R = variable-size item
• Fixed quantity indicator: This indicates whether the quantity
entered is dependent on the lot size. It applies mainly to unavoidable
material loss at the start of the production process.
• Planned scrap: This topic is covered in detail separately
• Relevancy to costing indicator: If this indicator is not selected, the
system ignores the BOM item in the material cost estimate. This
enables you to devaluate BOM items (such as packaging materials)
on a flat-rate basis for inventory or commercial purposes.
• Bulk material: Bulk material is usually posted as consumption at
production cost centers as soon as it is procured, so it is not included
in the cost estimate.
Work Center
26
• Cost center
• The standard value key enables you to define the six standard values
in the operation. The system assigns a parameter key to the standard
values of the operation and of the work in the network activity. This
parameter key specifies the following:
• Formula: You can use formula parameters to which you have
assigned values. You can then link these parameters with
mathematical operations such as addition, subtraction, multiplication,
or division.
Example: Formula 2 = Standard value * Operation quantity / Base
quantity
Routing
27
Header
• Status
• Lot size range
• Task list group
• Usage
• Validity Period
• Base quantity
Operation Line
• Work Center
• Control key
• Costing Relevancy indicator
• Material to Operation assignment
Routing
28
Routing is “production-oriented bill of activities“that lists the operations required to
manufacture a product. Each operation can contain up to six activity types and a
standard value for the calculation of the activity usage.
Each operation is carried out at a work center. The work center contains formulas for
the calculation of activity usage. These formulas take account of the cost estimate lot
size and the base quantity for the routing.
Each work center is linked to a cost center. Activity prices are planned for the
combination Cost Center/Activity Type.
Operation Qty Activity Type
0010 PC-1 Preparation 2 min. 1421
0020 PC-2 Assembly 3 min. 1422
0030
Work Center
PC-3 Quality Check 5 min.
Standard
Values
Activity
Usage
Cost Center – Activity Type - Work Center – Routing Link
29
Work Center PC-1
Activity Type Efficiency
Formula
Set Up
Machine
Labor
Cost Center 4711
100 %
75 %
50 %
Formula 1
Formula 2
Formula 3
Lot Size : Pieces
Routing
Op. 10 / Work Center PC-1
Base Qty: Pieces
Set Up
Machine
Labor
Acty Type / Standard Value
a Min
b Min
c Min
n
m
Cost Center 4711
Activity Type / Price
Set Up
Machine
Labor
X $ / Min
Y $ / Min
Z $ / Min
Formula 1 =
Formula 2 = x /
Formula 3 = x /
a Min
b Min
c Min
n
n
m
m
Control Key in Recipe
30
Cost relevancy
Milestone operation?
External Processing?
Automatic goods
movement?
Co-Product
32
Co-Products have
significant revenue
and are planned
for production
Leading Co-
Product (primary)
appears on the
production order
header and as a
line item as well in
the materials list
Co-products
appear with
negative quantity
in BoM
By-Product
33
Incidental output, not
planned
Co-Product indicator
is NOT checked
By-products appear
with negative quantity
in BoM
May or may not have
its own cost. If cost
relevant then it
reduces the cost of
finished product
Quantity Structure Selection for Co-Products
34
Material Master Parameters:
- Production version with BOM and routing entries
- Production version that refers to a leading co-product
If no entries were made in the material master of the co-product, the system
attempts to determine the quantity structure through the quantity structure
determination of the costing variant. It first attempts to determine the
quantity structure via valid production versions.
Costing of Co-Products and By-Products
35
Costs for co-products are calculated using the apportionment method
Costs for by-products are calculated using the net realizable-value method. Co-
products designated as fixed-price co-products are costed in accordance with the
net realizable-value method similar to by-product.
The costs for fixed-price co-products and by-products are subtracted from the
total costs. If a fixed-price co-product or by-product has its own cost estimate, the
cost component split of the cost estimate is taken into account when the costs are
deducted from the total costs. In the process, the costs in a cost component are
deducted from the total costs in the cost component to which it belongs.
After the costs for by-products and fixed-price co-products have been taken into
account, the total costs of the production process are apportioned for all cost
components to the co-products. Equivalence numbers are used for the
apportionment process using apportionment structure. Each production version can
have its own apportionment structure
Cost Apportionment with Source Structure
36
Source
Assignment
Equivalence Number
Primary Product Co-Product 1 Co-Product 2
Material costs 3 2 1
Production costs 3 2 2
Overhead 1 1 1
Using a source structure, it is possible to specify how the costs for each cost element
group are apportioned.
This allows to account for the fact that the material usage for the first co-product, for
example, is significantly higher than that for the second co-product even though the
production costs for both products are the same
When a process order is created the system generates a settlement rule on the basis
of the apportionment structure. The equivalences specified in the apportionment
structure are transferred into the settlement rule.
Cost Center planning and Activity Type Pricing
37
Plan Externally and
enter prices by cost
center + activity type
Plan using the SAP
planning
functionality
Planned Costs in dollars by cost center
___________________________________
Planned Activity by cost center and activity type
• Can copy scheduled activity from Logistics planning
• Can plan activity-independent and activity-dependent costs
separately so as to split the activity price into “fixed” and
“variable” components
Activity Type Pricing
39
Plan Output Quantities
• Number of labor hours, quality hours etc
Plan Costs
• Dollars to be spent to provide this service
• Distinguish fixed and variable costs
Plan Input Quantities
• Number of quality hours required by Production
• Reconcile Supply and Demand
• Adjust quality hours to be supplied to meet demand from production
Calculate Activity Prices
• Costs per labor hour, per quality hour etc.
• Cost component split for planned prices
Subcontracting Options
40
• The subcontractor
receives material parts
and manufactures the
complete material
• Can keep track of
components lying with
vendor
• The subcontractor is
paid an agreed price for
the whole activity
Subcontracting External Processing
• The external processor
performs a process step
only.
• The material is processed
externally and completed in-
house.
• A price is agreed for the
external processing.
Planned Scrap
43
• Planned scrap is regarded as unavoidable scrap that is expected
to occur when a material is produced. It is also included in
inventory valuation.
• Consists of component scrap and operation scrap
• When a routing is scheduled, the scrap factor is determined from
all operations and written to the material master as assembly
scrap.
• Shown in the itemization screen of cost estimate
Component Scrap
44
Component scrap indicates the amount of scrap expected to occur
before or during the assembly of the material.
Component scrap can be defined in the material master of the
component as well as in the BOM line of the finished part. If it has
been entered in the BOM, the value specified therein applies.
Otherwise, the value in the material master record applies.
Component scrap is used in MRP to determine the input quantities of
the components. When the BOM is exploded, the system increases
the input quantities of the components by the scrap quantity
calculated.
Example:
Input quantity 200 units
Component scrap 10 %
Scrap quantity 20 units
Quantity used 220 units
Operation Scrap
45
Operation scrap is defined in the routing step. It is percentage of
scrap occurring for the operation concerned.
This scrap results in a drop in the quantity of the next operation,
since the quantity to be processed is reduced by the scrap. The
reduction in quantity is taken into account in the scheduling and in
the cost estimate.
Assembly Scrap
46
When a routing is scheduled, the scrap factor is determined from
all operations and written to the material master as assembly scrap.
Example:
Suppose the quantity to be produced is 200 units.
If you specify assembly scrap of 10%, the scrap quantity is 20 units.
The actual quantity produced is then 220 units. The system
increases the lot size and the quantity of input materials.
Mark and Release of Standard Cost Estimate
48
Marking:
The future planned
price is set in the
material master and
a link to the "new"
standard cost
estimate established.
No revaluation takes
place.
Release: Release converts the future standard price to the current standard
price. Inventory revaluation takes place. The previous standard price is
moved the field “previous” and is linked to the "old" standard cost estimate.
Cost Estimate View
50
Or “F6” gives itemized details
Or “F5” gives cost component wise totals
gives plants/company codes for the cost source
Item Categories:
M : Material
A: Co-Product
E: Activity (Labor/Burden)
G: Costing sheet based surcharge
Costing Run
51
• Costing of several
materials in a single run
• Background processing
feature
• Parallel Processing
feature
• Detailed logs
Updating Price fields in material master with costs
53
Useful for analysis
with other costs like
current costs,
simulated costs etc.
Plan Price, Tax
Price, Commercial
Price (any of these 9
fields) can be
updated
Useful Transaction Codes
54
CS01, 2, 3 : Bill of Material
C201, 2, 3 : Recipe
CR01, 2, 3 : Work Center
KL01, 2, 3 : Activity Type
OKEQ: Version
OKTZ : Cost Comp Structure
OKKN: Costing Variant
OKK4: Valuation Variant
OKEU: Source Structure
KZS2 : Costing Sheet
KP06, 7: Cost Center Planning
KP26, 7: Activity Prices
CK11N, 13N: Cost Estimate
CK40N: Costing Run
CK22: Allow Marking
CK24: Mark and Release
CKR1: Delete Cost Estimate
CKAPP01: Materials to be costed
S_P99_41000111 - Analyze/Compare Cost Estimates
Demo in the system
55
• Configuration Settings
- Costing variant, valuation variant, costing type, transfer
control, quantity control
- Costing sheet
- Allocation Structure for Co-Products
• Cost Roll Up of purchased and produced materials
• Cost Center Planning
• Activity type Pricing