Applications Lodged Listing - Combined Development Applic ...
BEFORETHEEN~RONMENTCOURT - justice.govt.nz · (x) on 26 April 2017 RPL lodged an appeal to the High...
Transcript of BEFORETHEEN~RONMENTCOURT - justice.govt.nz · (x) on 26 April 2017 RPL lodged an appeal to the High...
BEFORETHEEN~RONMENTCOURT
I MUA I TE KOOTI TAIAO 0 AOTEAROA
IN THE MATTER
AND
BETWEEN
Deci!i.ion No. [2018] NZEnvC 248
of the Resource Management Act 1991
of an application pursuant to s 149T of the Act
QUEENSTOWN AIRPORT CORPORATION LIMITED
(ENV-2011-WLG-41 )
Applicant
Court: Environment Judge J E Borthwick Environment Commissioner R M Dunlop Environment Commissioner D J Bunting
Hearing: at Christchurch on 6 November 2018
Appearances: R J Somerville QC and R S Ward for Remarkables Park Limited M Casey QC and R Tompkins for Queenstown Airport
Corporation Limited
Date of Decision: 20 December 2018
Date of Issue: 20 December 2018
DECISION OF THE ENVIRONMENT COURT ON PRELIMINARY LEGAL ISSUE AS TO COSTS
A: Application declined.
B: Costs reserved.
REASONS
Introduction
[1] Remarkables Park Ltd has filed an application for costs seeking $1,754,648.58,
which amounts to a contribution of 60% of its total costs incurred in relation to a notice of
requirement filed by Queenstown Airport Corporation Ltd.
RPL - PRELIM LEGAL ISSUE AS TO COSTS
2
[2] The application is filed some 16 months after the final determination of
proceedings. At the time of filing its application, Remarkables Park Ltd did not seek to
extend or waive the court's directions in relation to the filing of a costs application.
[3] The application for costs is opposed and this decision concerns the determination
of a single preliminary legal issue: whether RPL's application for an extension of time in
which to file an application for costs should be granted.
Notice of motion to extend time
[4] On 31 March 2017, the Environment Court released its final decision on the notice
of requirement to alter Designation 2 in the Queenstown Lakes District Plan. In that
decision, the court confirmed the requirement subject to conditions. 1
[5] While the court reserved costs, it indicated costs were not encouraged. The court
directed any applications for costs were to be filed by 21 April 2017, with replies by 5 May
2017. As intimated, no application was filed by either party within the time directed.
[6] RPL filed an application for costs on 3 September 2018 and then on
28 September 2018 filed a notice of motion seeking an extension of time to file an
application for costs using either rule 1.23 District Court Rules 2014 or s 281 of the RMA.
During the hearing RPL decided not to pursue the s 281 application. This decision
proceeds on the now agreed basis that RPL does require an order from the court to
extend time for filing, a position which it had earlier disputed.2
[7] Rule 1.23 of the District Court Rules provides as follows:
1.23 Extending and shortening time
(1) The court may, in its discretion, extend or shorten the time appointed by
these rules, or fixed by any order, for doing any act or taking any proceeding
or any step in a proceeding, on such terms (if any) as the court thinks just.
(2) The court may order an extension of time although the application for the
1 Re: Queens/own Airport Corporation Ltd [2017] NZEnvC 46.
2 Somerville, opening submissions at [8] and [11}.
3
extension is not made until after the expiration of the time appointed or fixed.
(3) The court or a Registrar may order an extension of time on application made
by written notice instead of by interlocutory application, if the parties consent.
Principles to be considered
[8] Counsel for RPL and QAC agree that the principles articulated by the Supreme
Court in Almond v Read [2017] NZSC 80 guide the exercise of the discretion when
considering an application to extend time. 3 While the Supreme Court was engaged with
the question of an extension of time for filing an appeal, we accept the factors listed are
of general application in any situation where a court is asked to extend time. The factors
inform the ultimate question whether the exercise of discretion to grant the extension
serves the interests of justice in the particular circumstances of the case 4
[9] In summary, those factors include:
(i) the length of the delay;
(ii) the reasons for the delay;
(iii) the conduct of the parties;
(iv) the prejudice to the other party; and
(v) the significance of the issues raised, both to the parties and more generally.
[10] The factors were elaborated upon in the Supreme Court decision and, as the
discussion is very helpful, we set out the relevant section in full below:
(a) The length of the delay. Clearly, the time period between the expiry of the
appeal date and the filing of the application to extend time is relevant. But in
a case where there has been a slip-up and the appeal date has been
inadvertently missed, how quickly the applicant sought to rectify the mistake
after learning of it will also be relevant. Obviously, the longer the delay, the
more the applicant will be seeking an "indulgence" from the court and the
stronger the case for an extension will need to be.
(b) The reasons for the delay. It will be particularly relevant to know whether
the delay resulted from a deliberate decision not to proceed followed by a
3 RPL, closing submissions dated 26 October 2018; Transcript (Somerville) at 137; QAC, submissions at [12). 4 Almond v Read [2017) NZSC 80 at [38).
4
change of mind, from indecision, or from error or inadvertence. If from a
change of mind or from indecision, there is less justification for an extension
than where the delay results from error or inadvertence, particularly if
understandable.
(c) The conduct of the parties, particularly of the applicant. For example, a
history of non-cooperation and/or delay by an applicant may be relevant.
(d) Any prejudice or hardship to the respondent or to others with a legitimate
interest in the outcome. Again, the greater the prejudice, the stronger the
case will have to be to justify the grant of an extension of time. Where there
is significant delay coupled with significant prejudice, then it may well be
appropriate to refuse leave even though the appeal appears to be strongly
arguable.
(e) The significance of the issues raised by the proposed appeal, both to the
parties and more generally. If there is a public interest in the issues, the
case for an extension is likely to be stronger than if there is no such interest.
[Footnotes omitted]
[11] The Supreme Court also found the merits of an appeal (in that case) will generally
not be relevant where the delay is insignificant. On the other hand, there may be cases
where the merits are overwhelmed by other factors - such as the length of delay and the
extent of prejudice to the respondent. In either event, any consideration of merits in the
context of an application to extend time will necessarily be superficial : per Almond v Read
at [39].
Timeline
[12] RPL is seeking a contribution towards its costs in relation to litigation extending
over a period of seven years.
[13] For the purpose of this decision the following events are important:
(i) Environment Court released its first Interim Decision on the NoR dated
25 September 2012;
(ii) on or about 16 October 2012 RPL and QAC appealed to the High Court
against the Interim Decision;
(iii) the Environment Court released its 'First' Final Decision on the NoR on
8 May 2013;
5
(iv) on or about 29 May 2013 RPL and OAC appealed to the High Court against
the 'First' Final Decision ;
(v) by Minute dated 17 June 2013 the Environment Court reserved costs on
the proceeding directing costs be dealt with after the final disposition of the
appeals by the senior courts;
(vi) the High Court (Whata J) released its decision on 12 September 2013
sending back the NoR to the Environment Court for reconsideration ;
(vii) the Environment Court released its 'Legitimate Expectation' Decision - also
addressing industrial land supply, on 26 November 2014;
(viii) the Environment Court released its 'Separation Distance' Decision on
22 December 2015;
(ix) the Environment Court released its 'Second' Final Decision of the
Environment Court dated 31 March 2017. The court reserves costs,
making timetable directions for any application for costs to be filed by
21 April 2017;
(x) on 26 April 2017 RPL lodged an appeal to the High Court on the Second
and Third Interim Decisions together with the 'Second' Final Decision;
(xi) RPL applied to the Environment Court for a rehearing on 22 November
2017;
(xii) the High Court (Nation J) released its decision on 1 March 2018 dismissing
RPL's appeal;
(xiii) on 20 April 2018 Environment Court released its decision refusing RPL's
application for a rehearing, reserving costs;
(xiv) on 5 May 2018 OAC and OLDC apply for costs against RPL on the
application for rehearing;
(xv) on 18 May 2018 RPL filed a memorandum opposing costs on the rehearing
saying:
Counsel foreshadow that RPL will shortly be filing an application for costs
against QAC for the entire designation proceedings, including interim
decisions, since 2010. Counsel submit that it would be more appropriate and
efficient for both applications to be dealt with together.
(xvi) on 3 September 2018 RPL applied for costs against OAC;
(xvii) on 28 September 2018 RPL filed a notice of motion for extension of time;
(xviii) on 6 November 2018 hearing held on notice of motion for extension of time.
6
[14] We set out next RPL's grounds for extension of time for filing an application for
costs.
RPL's grounds for extension of timeS
[15] RPL argues the delay in making the application for costs must be seen in the
context of RPL's appeal against the Environment Court's second Final Decision, its later
application for rehearing and the parties ongoing negotiations towards the full and final
settlement of the NOR.
[16] Acknowledging the application for costs was filed four months after the
Environment Court released its decision on the application for rehearing, RPL explained
that it did not file the application earlier because it needed time to collate the invoices
over the preceding years and to deduct from them fees incurred which cannot be claimed
as part of a costs application.6
[17] RPL contends QAC has not suffered any prejudice as a consequence of the
delay. The proceedings have only recently been concluded and "are sufficiently within
the recent memory of the Court and QAC for the costs application to be considered".7
Moreover, had RPL applied for costs within the timeframe directed, or sought an
extension of the timetable direction, it says the Environment Court would have granted
the application and put costs on hold pending the High Court's determination of its appeal
in which case QAC would then be in the same position as it is today, facing a costs
application in the second half of 2018.8 In support of this submission , RPL points to the
Environment Court having directed following the first appeal to the High Court, that costs
applications would be dealt with following the final disposition of the proceedings.9
[18] RPL submits there is a public interest in ensuring that a requiring authority, when
dealing with private land, make out the statutory criteria under s 171 RMA. When doing
so, the requiring authority should act fairly and reasonably and not act in such a way so
as to place an unnecessary burden on the landowner. A landowner should not have to
S Somerville, opening submissions dated 28 September 2018 and closing submissions dated 26 October 2018 . 6 Transcript at 142. 7 Somerville , opening submissions at [40] .
D Somerville , opening submissions at [39]-[43]. n1 z . \~1. r;;$ Minute dated 17 June 2013.
<'"1\1,. c :--;\~ O~ " / l:.'~..;-..... ~
7
incur significant cost in raising issues of public law, such as RPL's legitimate expectation
in relation to the land to be designated or the wider issues involving safety and
environmental effects, RPL is particularly critical of the fact that QAC is not willing to
make any contribution towards its costs, It says QAC is wrong to oppose costs on the
basis that it 'won' the proceeding when the court confirmed the requirement
[19] Addressing whether the exercise of discretion to grant the extension would serve
the interests of justice, RPL submits that it is simply seeking the opportunity to be able to
argue its costs application, Given the history of these proceedings and the scale of the
costs sought, RPL argues that it would be disproportionate to refuse to consider RPL's
application on its merits on account of delay,
QAC reply'O
[20] QAC, addressing the factors set out in Almond, opposes the application for
extension, QAC acknowledges that the NoR was referred to the court as involving a
matter of national importance, However, it dismisses there is public interest in the
acquisition of private land by a public body, or in RPL's legitimate expectation in relation
to the use of its land,
[21] QAC makes the point that RPL's application for costs was filed 16% months after
the expiry of the timetable directions, Even if the intervening court events excuse the
delay, RPL has not provided a reason for the further delay of some 5% months after the
release of the High Court decision or for the delay of nearly four months following the
release of the Environment Court's decision on the application for rehearing,
[22] QAC highlights the fact that the first indication that RPL might seek costs was
given in response to QAC's application for costs on the rehearing proceeding , In
opposing costs, RPL "foreshadowed" that it would "shortly be filing an application for
costs", Even then, the application was not filed for a further 3% months,
[23] QAC submits RPL has not explained its delay in filing the costs application or its
failure to apply for costs to be deferred pending the High Court appeal or indeed pending
its application for rehearing , It disputes RPL's assertion that the delay can, in part, be , <- ~\l Ab 0",
~/\~ '~~ -'0--------------------
,~ Casey, reply dated 19 October 2018 ,
% ~." i!
"'1-,. '- ", -- rc~ CO'lfll' 01' ';~ , .--.~ ..
8
explained by the fact that the parties were involved in continuing negotiations in relation
to costs. Counsel advised that on 20 November 2017, QAC made a conditional offer to
purchase Lot 6, with the proposal that each party bear its own costs. Mr Casey advised
that the offer was withdrawn on 16 May 2018 when RPL did not respond.
[24] QAC does not accept RPL's contention that had it sought an extension on the
time for filing the application for costs pending the High Court's decision, that it was
"inevitable"" the Environment Court would have granted the same. If RPL intended
seeking costs, the proper course was to file the application and then apply to suspend
the timetable pending the outcome of the High Court appeal. That way QAC could
consider its position and have had the opportunity to respond to the proposal to suspend
the timetable.
[25) QAC submits RPL's conduct of the litigation strongly militates against an
extension being granted. It contends RPL has consistently sought to lengthen the time
taken to conclude the litigation. It says RPL has been obstructive in the manner that it
has conducted this proceeding even to the point of filing an application in 2017 to rehear
the NoR proceedings. Having decided the application on a different ground, QAC points
out that the Environment Court indicated that it would have struck out the application for
rehearing on the basis that it was an abuse of process.
[26) QAC submits it will be prejudiced by the delay. In order to respond to RPL's
application for costs, QAC will need to reconstruct events going back over a seven-year
period. This will entail QAC incurring significant costs, given the effort involved due to
the volume of material that will need to be traversed .
[27) Finally, taking into account the above matters, QAC submits that RPL having
conducted unsuccessfully the litigation in a manner that caused QAC to incur significant
costs, there is no injustice in RPL being denied the significant further indulgence it now
seeks."
Discussion
[28) The parties are neighbours who each have different interests in the development
11 Transcript (Somervi lle) at 115.
~ 12 Casey, reply dated 19 October 2018 al [63].
o " \~ . ~ ~.,\'\; / 'Vl' - '- r.;.'" /
COURT of ~/.
9
of Frankton Flats.
[29] On occasion, during the course of these proceedings we have heard from counsel
that the parties were negotiating for the sale and purchase of Lot 6. The court, however,
has had to put the fact of those negotiations out of its mind when determining the matters
of law and the substantive merits of the requirement.
[30] While the court reserved costs, we also stated costs were not encouraged. As
explained to counsel during this hearing , the reason for that was that the court has been
very concerned with how both parties have conducted these proceedings. Being
conscious not to undermine their relationship any more than what the parties have
achieved themselves, we addressed some of those concerns in the court's decisions.
[31] While costs were not encouraged , this did not preclude RPL from seeking costs
and endeavouring to persuade the court that it is just and fair in the circumstances for
QAC to contribute to its costs. What the court did was to make timetable directions in
order that this be done in a timely way.
Merits of the application
[32] The merits of the proposed application for costs are relevant in circumstances
where there has been significant delay. Following Almond v Read, a decision to refuse
an extension of time based substantially on the lack of merits should only be made in a
"clearly hopeless" case.13
[33] The fact that RPL is the owner of land that is required by the Queenstown Airport
and could, subject to what we have said in earlier decisions, legitimately expect QAC
would use its own land for airport purposes may be a factor given weight on a costs
application. That said , we would not go as far as what Mr Somerville may have been
suggesting, that in such circumstances costs should follow the event.
[34] Throughout the entire proceeding this court has sought clear justification for the
NoR. RPL contributed positively to the proceeding by vigorously testing QAC's case.
However, following the release of the first High Court decision in 2013 both parties, from
10
time to time, have conducted the proceedings in a way that would have incurred the other
in unnecessary costs. In our decisions we have remarked at various points on negative
aspects of the parties' conduct, and this is summarised below.
Legitimate Expectation Decision (including industrial land supply) [2014J NZEnvC 244
[35] On appeal by RPL, the High Court referred for reconsideration the Environment
Court's findings on an alternative site north of the main runway as being "suppositious"
in view of the scarcity of industrial land. In response, RPL:
(a) did not seriously challenge the court 's findings that industrial land was in
scarce supply;
(b) took an overly simplistic approach to the issue sent back for
reconsideration. The issue was not whether QAC owns land (inside or
outside of its existing designation) , but whether it can use the land it owns
to achieve the objective of the NoR. The reason for requiring Lot 6 is that
QAC says it could not establish general aviation and helicopter facilities
north of the main runway for safety and operational reasons.'4
Separation Distance Decision [2015J NZEnvC 222
[36] On appeal by both RPL and QAC, the High Court sent back for reconsideration
the separation distance requirements for a Code C taxiway and the process for
confirming those requirements .' s QAC subsequently clarified that the works included a
dual parallel taxiway south of the main runway, a matter which the Environment Court
found had been given "scant" attention in the 2012 hearing. The court was critical of
QAC, as we thought it "self-evident a dual taxiway cannot be accommodated within 93 m
of the main runway".'6 The separation distance between the main runway and taxiway
was one of two issues referred to the Environment Court for reconsideration. Advancing
its case without sufficient regard to all the works enabled by the NOR, QAC would have
caused RPL to incur unnecessary cost.
[37] During the same hearing RPL sought:
14 [2014] NZEnvC 244 at [71]-[89] and [94]-[101].
5 [2015] NZEnvC 222 at [258].
0 ' [2015] NZEnvC 222 at [9] and [28] . z: a ...
"h . ~ , ;~ -{f ~l' ._ ~",\ ~OUflT 01' "' ... / .. _------.. -
11
(a) a determination of the legal (interpretational) issue and the substantive
merits of a Code C taxiway located 93 m from the main runway. The
determination was sought notwithstanding QAC's clarification that the NOR
included the dual taxiway, and despite RPL's acknowledgement that both
parties felt "uncomfortable" with a separation distance of 93 m;
(b) to produce extensive evidence concerning a 2014 Master Plan which, RPL
submitted, was relevant to the court's determination if QAC's long-term
planning was occurring now on a different basis. The court accepted QAC's
evidence that the 2014 Master Plan had been produced at RPL's request
and that QAC was not planning towards its implementation;17 and
(c) to relitigate the court's determination that QAC has given adequate
consideration to alternative sites 18
2017 Final Decision [201 7] NZEnvC 46
[38] Notably RPL:
(a) sought to relitigate the meaning of "reasonably necessary" in s 171 (1 )(c)
confirmed in the first High Court appeal, by advocating for a higher test in
light of its legitimate expectation ;' 9
(b) sought to relitigate the court's determination that QAC had given adequate
consideration to alternative sites and second , indirectly challenging the
adequacy of evidence which the court relied on in making its findings ;20
(c) knowing QAC had, at RPL's request, sought and obtained the Director of
CM's approval of an aeronautical study, RPL then :
(i) without having judicially reviewed the Director's decision , led
evidence extensively criticising the Director's approval of the
aeronautical study;
(ii) challenged the adequacy of the study; and
(iii) argued for additional task specific safety case(s) .21
17 [2015[ NZEnvC 222 at [35[-[37J . 18 [2015J NZEnvC 222 at [1 8J. 19 [2017J NZEnvC 46 at [21J and [25J . 20 [20 17J NZEnvC 46 at [27J.
~ 21 [201 7J NZEnvC 46 at [54J.
'" - ...., ~ '4) ~ ~"" . "111 --_. ~'(;
' .... yOIJRT 0".-~---.--
12
(d) led evidence addressing airspace capacity, when that issue had been
addressed in a prior decision;22
(e) led evidence on other matters irrelevant to the court's determination;23 and
(f) filed evidence after the decision has been reserved following the 2017
hearing without seeking the prior leave of the court.24
[39] While RPL's application for costs is not "clearly hopeless", the court would need
to consider the merits of the application for costs taking into consideration the above
findings. The merits of any costs application will necessarily involve the court making
findings on the conduct of the proceedings by the parties.
[40] We return to the other matters identified by the Supreme Court in Almond v Read
as being relevant to the discretion whether to extend the time for filing an application for
costs.
The length of the delay
[41] There has been a 16'h month delay between the expiry of the directions on costs
and the filing of the application. This delay is deliberate, in the sense that RPL was aware
of the court's directions and yet took no steps to suspend the timetable for filing
applications. RPL has assumed (asserts even) the court would have acquiesced to an
application to suspend the timetable pending the determination of its appeal by the High
Court. Indeed, until September 2018 it was RPL's position that it need take no formal
steps in relation to the timetable directions because its appeal to the High Court and
application for rehearing "interrupted" the timetable directions.25
The reasons for the delay
[42] We struggle to accept RPL's explanation for its delay pending the determination
of the High Court appeal and application for rehearing.
[43] First, we do not consider the application for rehearing relevant . RPL sought a
rehearing because it claimed there was new and important evidence that may have
22 [2017] NZEnvC 46 at [40].
23 [2017] NZEnvC 46 at [73]-[77].
~ 24 [2017] NZEnvC 46 at [19]. [78]-[79].
:5 25 RPL Apptication for costs dated 3 September 2018 at [2.7] .
13
affected or changed our decision to confirm the notice of requirement. While the
application for rehearing was finally decided on another basis, we indicated that it was
an abuse of the court's process to bring this proceeding when the High Court had already
considered (and rejected) the materiality of the evidence.26
[44] Second, the only reason given for the delay following the determination of the
High Court and the rehearing application is the time it took RPL to collate and review
copies of invoices for its costs incurred since 201027 If, as RPL claims, its decision
making on costs was informed by an error as to process28 [our term] then we would have
expected the application to be filed in accordance with the 10-working day default period
set out in the Environment Court's Practice Note 2014 2 9 Instead, it appears, RPL was
simply unprepared.
[45] Third, we do not accept RPL's explanation that the delay in filing its application
was contributed to by the parties' negotiations to settle costs. Looking at this reason for
delay in the light most favourable to RPL, the negotiations were concluded by QAC's
withdrawal of its offer in May 2018.30 Even were the parties' negotiations the controlling
reason for the delay, this did not render nugatory the court 's directions.
[46] Finally, RPL correctly points out that in 2013 we directed that any costs
applications would be dealt with following the disposition of the appeals by the higher
courtS.31 That direction was made following an application by Air New Zealand Ltd32 and
we have no record of any party responding to or opposing the application. At the time
the direction was made, both RPL and QAC had appealed the first Interim Decision.
[47] Is this sufficient basis for RPL to say this division of the court would acquiesce
were it to have sought to amend the timetable directions? We think not. RPL's
submission does not reflect the court's active case management in proceedings where
the parties have maintained trenchant positions.
26 Re: Queenstown Airport Ltd [2018] NZEnvC 52 at [51] . 27 Transcript at 142-143. 28 There have been one or more error(s) made by RPL, including that the Environment Court's timetable directions were "disrupted" by the High Court appeal; RPL did not need to seek leave to suspend the timetable or apply. for an extension of the timetable; and finally, the court will always acquiesce to a request
",<.~L OF 'itf' to suspend timetable directions.
,
l 'J:-"<- 29 Practice Note at 6.6(1) .
" r~~ 30 RPL had not responded to the offer which was made in November 2017.
\1. 4> :\ ~ 31 Minute dated 17 June 2013. m .!I • \'~~ :::s 2 Air New Zealand memorandum dated 12 June 2013. ~ • .$< ... ~ ~ i:J \~o " .. ij~t ... ~fj ~ "" \ .1;. ~«./
'\ ''7~ .... --.- ~ /
:tvr CO! 1\-\\ 0.,.-~. -.... -~----~
14
[48] Given the above, we find RPL's reasons for the delay unsatisfactory.
The conduct of the parties, particularly of the applicant
[49] The conduct of the parties has been addressed under the sub-heading "Merits of
the Application".
Any prejudice or hardship to the respondent or to others with a legitimate interest
in the outcome
[50] Not unsurprisingly, RPL and QAC take a different view on whether the delay will
occasion prejudice. We have no doubt that QAC will incur significant costs and effort in
responding to RPL's application as it will need to consider events over a seven-year
period. QAC's costs, while an important consideration, are not determinative.
[51] By RPL taking no steps in response to the 2017 costs directions, QAC was
precluded the opportunity to give its view on the suspension of the directions on costs or
some other action which would have limited any prejudice were the application not to
have been dealt with promptly. For example, RPL could have filed the application and
then, following QAC's reply, sought that costs be placed on hold pending the
determination of the High Court appeal.
[52] RPL is correct in saying that the proceedings are within the recent memory of the
court, but it does not follow that the considerations relevant to the exercise of the court's
discretion to award costs and the quantum of costs to be awarded are in the forefront of
our minds. QAC in pointing to matters that it would raise in opposition to costs, but not
recorded in the court's deciSions, is illustrative of this . 33
[53] A delay of this length occasions the risk that matters relevant to the exercise of
the discretion to award costs and the quantum of costs, may be overlooked or misjudged.
Put another way, the delay risks the matters relevant to the exercise of the discretion
having become "stale". On this occasion, this is a risk for both parties.
33 This includes QAC's contention that RPL sought to lengthen the time taken to conclude the litigation and has been obstructive in the manner that it has conducted this proceeding.
15
The significance of the issues raised by the proposed appeal, both to the parties
and more generally
[54] The NoR was referred to the court as involving a proposal of national importance.
There is considerable public interest in the reasons for QAC, being a majority
shareholding of Queenstown Lakes District Council , seeking to depart from its promise
to RPL not to require its land for airport purposes. Given the landowner's interests, QAC
should have expected that it would need to provide RPL and the court clear justification
for the requirement of its land.
[55] That said, while costs are of undoubted importance to RPL, we do not consider
there to be any public interest issue per se, in either the application for costs or even the
scale of the costs sought.
Overall interests of justice
[56] While the merits of RPL's application for costs are not "clearly hopeless",
nevertheless the overall interests of justice - informed by the factors discussed in Almond
- weigh against the opportunity RPL seeks of being able to argue its costs application.
We do not accept RPL's submission that to decline its application for an extension of time
would be a "disproportionate" response given the history of these proceedings and the
scale of the costs sought. Indeed, these considerations go to the timely and efficient
disposition of costs where costs are to be sought.
[57] The period between the expiry of the directions on costs made in the second Final
Decision in March 2017 and RPL's application for costs filed in September 2018 was
excessive. This delay was deliberate in the sense that RPL was aware of the court's
directions and yet took no steps to suspend the timetable for filing applications. In doing
so it denied QAC the opportunity to give its view on the suspension of the directions on
costs or some other action which would have limited the prejudice to QAC, including the
inherent risk to both parties of the matters relevant to determining the costs application
having become stale.
[58] Given the above, we decline to exercise our discretion to extend the time for RPL
to file an application for costs.
16
Costs
[59] Costs in relation to RPL's application, which is the subject of this decision , are
reserved . Any application for costs is to be filed by 25 January 2019 with replies by
1 February 2019. In the event no application for costs is made, the court's order will be
(without further decision of the court issuing) that there is no order as to costs.
For the court:
J Borthwick
E vironment Judge