Before Waikato Regional Council Before Waikato District ... · The proposal is for the manufacture...
Transcript of Before Waikato Regional Council Before Waikato District ... · The proposal is for the manufacture...
1
Before Waikato Regional Council Before Waikato District Council
In the Matter of the Resource Management Act 1991 (Act)
And
In the Matter of an application by Mercer Assets Limited for regional and district resource consents to establish and operate a mushroom substrate production facility at 55 Morrison Road Pukekawa
Hearing Reference LUC039919 AUTH1406570101 AUTH1406570201 and AUTH1406570301
Evidence of Dr Terry Brady on behalf of Mercer Assets
Limited Dated 18 September 2019
Jeremy Brabant
Barrister
Level 4 Vulcan Building Chambers
PO Box 1502 Shortland St
Auckland City
021 494 506
2
Qualifications and experience
1 My full name is Terence John Brady I am a Director of Terry Brady
Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of
Philosophy in Chemistry from the University of Canterbury New
Zealand I specialise in air pollution control preparation of
assessments of the effects of discharges to air and other air quality
matters and I have over 36 years direct experience in these fields
2 From 1983 to the end of 1991 I was employed by the Department of
Health as an air pollution scientist responsible for industrial emissions
for the upper half of the South Island under the Clean Air Act From
1991 to 1996 I was employed as an Air Pollution Scientist with
Woodward Clyde (NZ) Ltd (now AECOM) and from 1996 to 1999 as a
Principal I started my own consultancy in January 1999
3 My relevant experience includes assessing the actual and potential
discharges to air from a very large variety of industries throughout
New Zealand including the discharges of odour from composting I
have been involved with many industrial projects that involve the
discharge of odour and I am currently the air quality advisor in the
Audit Group for Watercare Services two wastewater plants at
Mangere and Rosedale
4 I have also designed and commissioned a considerable number of
industrial ventilation systems for air pollution control purposes
5 Some specific projects that I have been involved with that have
relevance to this application include
(a) Measurement modelling and assessment of odour
from Living Earth composting at Pikes Point in
Auckland Technical advice for monitoring programs
(b) Predictive modelling and assessment of odour from
Living Earth composting at Puketutu Island in Auckland
3
including Resource Consent application and the
successful Environment Court appeal
(c) Assessment of odour effects for composting operations
at Living EarthChristchurch City Council operation in
Christchurch
(d) Assessment of potential odour effects for New
Plymouth City Council composting operation
(e) Provided evidence in an Environment Court appeal
involving New Zealand Mushrooms Ltd Morrinsville
(f) Assessment of potential effects of odour dust and bio-
aerosols for the Living Earth Joint Venture in Careys
Gully Wellington
(g) Assessment of effects of a greenwaste composting
operation application by Whakatane District Council
(h) Measurement and assessment and remedial works for
odours from the indoor composting plant at Cresta
Mushrooms Mercer
(i) Assessment of engineering options to control odour
from Te Mata Mushrooms Havelock North (ongoing)
6 In terms of scale composting operations I have been involved with
range from a few thousand tonnes per annum to up to 75000 tonnes
per annum
7 I believe that I am well qualified to provide expert evidence on
matters that have direct relevance to the application that is before
the Independent Hearing Commissioners
8 I have read the Code of Conduct for Expert Witnesses issued as part of
the Environment Court Practice Notes I agree to comply with the
code and am satisfied the matters I address in my evidence are within
my expertise I am not aware of any material facts that I have
4
omitted that might alter or detract from the opinions I express in my
evidence
SCOPE OF EVIDENCE
9 In my evidence I will
(a) Give an overview the application and the key odour
sources as they relate to the odour control systems
proposed
(b) Discuss the basis for the design parameters selected for
odour containment
(c) The scrubber and biofilter odour control system
(d) Assess the odour impacts arising from the proposals
(e) Comment on the submissions received
(f) Comment on the Officers Report
(g) Provide context regarding alternative sites
OVERVIEW
10 The full details of the process are provided in the application technical
document1 and the following represents a short summary
11 The proposal is for the manufacture of mushroom substrate
(compost) in a fully enclosed facility that will operate with full building
air extraction on all parts of the buildings and processes that generate
odour This odour-containing air will be pre-treated in an acid
scrubber to remove ammonia followed by a water scrubber to
remove any acid mist carry over and finally the air will be treated in a
large biofilter to remove all odour
12 Manufacturing will take place in two buildings beginning with the
pre-wetting operation in the CANVACON pre-wet building followed
by transfer to the filling hall in the main composting building that
1 Terry Brady Consulting Ltd Mercer Mushrooms Application for Consent for Discharge to Air
(2) Revised Technical Report 321502R002 12 April 2019
5
contains 12 fermentation tunnels From the filling hall the tunnels are
filled using a specialised cassette filling machine Fermentation is
broadly separated into Phase 1 and Phase 2 stages that are defined by
the temperatures maintained in the fermenting mass
13 After a pasturisation stage (in Phase 2) the substrate is cooled to
ambient temperature and spawned with mushroom mycelium and
held in the tunnels for 14-21 days before removal to the growing
facility
KEY ODOUR SOURCES
14 The main odour sources in process order are
(a) The pre-wetting and turning in the Canvacon
Building
(b) Transfer of pre-wetted material to the filling hall
(c) Phase 1 Fermentation
(d) Phase 1 Turning
(e) Phase 2 Fermentation
(f) Phase 2 Turning
(g) Miscellaneous sources
15 I discuss these below
Pre-Wet
16 In the pre-wet stage straw bales are bought inside to the enclosed
Pre-Wet building with a loader which are then submerged in to a
dedicated lsquobathrsquo that is filled with nitrogen rich process water Once
the bales are fully wetted they are then stacked within the building
for one week days to allow microbial activity to build and de-wax the
straw After soaking period for 1 week the bales are formed into a
pile about 2 to 3m high together with the other raw materials in the
section of the Pre-Wet building marked as Pre-Wet Conditioning in
6
Appendix B To maintain porosity the material is mechanically turned
once in this final week
17 The pre-wet building is maintained under negative pressure at all
times to prevent odour being released to atmosphere
Transfer
18 At the end of the conditioning period the material is loaded into the
mixing line and then conveyed to the tunnel building
19 The conveyor is covered and air is extracted from it into both the
filling hall and the pre-wet building The openings in both the pre-wet
and filling hall were taken into account in the design of the total
amount of ventilation air that is required in both the pre-wet and
filling hall to maintain negative pressure
Phase 1 Fermentation
20 Each of the tunnels is provided with under-floor aeration to maintain
optimum levels of oxygen and temperature in the compost mass
Temperatures vary through the process ranging between 40-80 oC
and are largely controlled using aeration air
21 In this part of the process the aeration and extraction is a fully sealed
system that is balanced to a slight negative pressure
22 All of the air used in the phase 1 tunnels is extracted to the acidwater
scrubbers and the biofilter
Phase 1 Turning
23 Turning involves removing the substrate from one tunnel and placing
it in another via the filling hall The filing hall and the tunnels are
under negative pressure during this operation and the air is extracted
to the scrubber and biofilter
Phase 2 Fermentation
7
24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of
the fermentation but with slightly different aeration and turning
requirements and continues until a critical point called peak heat is
reached From this time on the temperature reduces to the point
when the substrate is finished and cooled At this stage it has only a
very mild potting mix smell to it
Phase 2 Turning
25 This is identical to the phase 1 turning and again the filling hall is
under negative pressure The air is extracted to the scrubber and
biofilter
Phase 3 Spawning
26 Once the substrate is cooled to ambient temperature it is removed
from the tunnels into the filling hall As there is no significant odour
from the substrate at this stage the filling hall is under slight positive
pressure using filtered air to prevent contamination The mushroom
mycelium is added and the substrate is then returned to the tunnels
and left to grow After 14 to 21 days it is removed via the load out
hall and sent to the growing rooms There is no odour from this
stage
Miscellaneous Sources
27 Because the whole composting process will be fully enclosed there
are very few sources outside that could potentially cause odour and
the only ones would include the nutrient tank (goody water tank) and
deliveries of raw materials
28 The nutrient water tank will be vented into the pre-wet building and is
therefore under negative pressure There will be no odour from this
source
29 The only raw material that has any potential for odour is the chicken
manure However this will be delivered in covered trucks and only
8
unloaded inside the pre-wet building Under normal circumstances
chicken manure has very little odour potential when it is in a covered
truck In the event that unsuitable material is bought on site Mercer
will refuse to accept it and the contract for supply will be reviewed if
there are repeat instances This is set out in the air quality
management plan
BASIS FOR THE DESIGN PARAMETERS
30 The standard hierarchy for odour control engineering is prevention
capture at source followed by treatment and finally full building
enclosure with ventilation followed by treatment
31 In the case of compost or mushroom substrate production
preventing odour generation is not possible at this time but capture
at source is used in the phase 1 and 2 operations as the tunnels are
completely sealed and ventilated to the odour control system
However capture at source is not feasible for the pre-wet phase
filling and turning the substrate and odour control for these
operations must rely on full enclosure with building ventilation to the
odour control system as there are no feasible alternatives
32 In my opinion the proposed odor control system represents the Best
Available Control Technology (BACT) that is both more advanced and
effective than the BPO requirements of the RMA It is also the same
system that I recommended to the Environment Court in the New
Zealand Mushrooms2 case when I gave evidence in support of the
residents and more recently in the Te Mata Mushrooms hearing in
Havelock North
33 The building air extraction rates used for the combined pre-wet and
compost buildings were provided by the equipment manufacturer
Christiaens and I have used them to estimate the vacuum that could
2 ENV-2006-WLG-000356 ENV-2006-WLG-000344) and ENV-2006-WLG-000347 ENV-2006-WLG-000351
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
2
Qualifications and experience
1 My full name is Terence John Brady I am a Director of Terry Brady
Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of
Philosophy in Chemistry from the University of Canterbury New
Zealand I specialise in air pollution control preparation of
assessments of the effects of discharges to air and other air quality
matters and I have over 36 years direct experience in these fields
2 From 1983 to the end of 1991 I was employed by the Department of
Health as an air pollution scientist responsible for industrial emissions
for the upper half of the South Island under the Clean Air Act From
1991 to 1996 I was employed as an Air Pollution Scientist with
Woodward Clyde (NZ) Ltd (now AECOM) and from 1996 to 1999 as a
Principal I started my own consultancy in January 1999
3 My relevant experience includes assessing the actual and potential
discharges to air from a very large variety of industries throughout
New Zealand including the discharges of odour from composting I
have been involved with many industrial projects that involve the
discharge of odour and I am currently the air quality advisor in the
Audit Group for Watercare Services two wastewater plants at
Mangere and Rosedale
4 I have also designed and commissioned a considerable number of
industrial ventilation systems for air pollution control purposes
5 Some specific projects that I have been involved with that have
relevance to this application include
(a) Measurement modelling and assessment of odour
from Living Earth composting at Pikes Point in
Auckland Technical advice for monitoring programs
(b) Predictive modelling and assessment of odour from
Living Earth composting at Puketutu Island in Auckland
3
including Resource Consent application and the
successful Environment Court appeal
(c) Assessment of odour effects for composting operations
at Living EarthChristchurch City Council operation in
Christchurch
(d) Assessment of potential odour effects for New
Plymouth City Council composting operation
(e) Provided evidence in an Environment Court appeal
involving New Zealand Mushrooms Ltd Morrinsville
(f) Assessment of potential effects of odour dust and bio-
aerosols for the Living Earth Joint Venture in Careys
Gully Wellington
(g) Assessment of effects of a greenwaste composting
operation application by Whakatane District Council
(h) Measurement and assessment and remedial works for
odours from the indoor composting plant at Cresta
Mushrooms Mercer
(i) Assessment of engineering options to control odour
from Te Mata Mushrooms Havelock North (ongoing)
6 In terms of scale composting operations I have been involved with
range from a few thousand tonnes per annum to up to 75000 tonnes
per annum
7 I believe that I am well qualified to provide expert evidence on
matters that have direct relevance to the application that is before
the Independent Hearing Commissioners
8 I have read the Code of Conduct for Expert Witnesses issued as part of
the Environment Court Practice Notes I agree to comply with the
code and am satisfied the matters I address in my evidence are within
my expertise I am not aware of any material facts that I have
4
omitted that might alter or detract from the opinions I express in my
evidence
SCOPE OF EVIDENCE
9 In my evidence I will
(a) Give an overview the application and the key odour
sources as they relate to the odour control systems
proposed
(b) Discuss the basis for the design parameters selected for
odour containment
(c) The scrubber and biofilter odour control system
(d) Assess the odour impacts arising from the proposals
(e) Comment on the submissions received
(f) Comment on the Officers Report
(g) Provide context regarding alternative sites
OVERVIEW
10 The full details of the process are provided in the application technical
document1 and the following represents a short summary
11 The proposal is for the manufacture of mushroom substrate
(compost) in a fully enclosed facility that will operate with full building
air extraction on all parts of the buildings and processes that generate
odour This odour-containing air will be pre-treated in an acid
scrubber to remove ammonia followed by a water scrubber to
remove any acid mist carry over and finally the air will be treated in a
large biofilter to remove all odour
12 Manufacturing will take place in two buildings beginning with the
pre-wetting operation in the CANVACON pre-wet building followed
by transfer to the filling hall in the main composting building that
1 Terry Brady Consulting Ltd Mercer Mushrooms Application for Consent for Discharge to Air
(2) Revised Technical Report 321502R002 12 April 2019
5
contains 12 fermentation tunnels From the filling hall the tunnels are
filled using a specialised cassette filling machine Fermentation is
broadly separated into Phase 1 and Phase 2 stages that are defined by
the temperatures maintained in the fermenting mass
13 After a pasturisation stage (in Phase 2) the substrate is cooled to
ambient temperature and spawned with mushroom mycelium and
held in the tunnels for 14-21 days before removal to the growing
facility
KEY ODOUR SOURCES
14 The main odour sources in process order are
(a) The pre-wetting and turning in the Canvacon
Building
(b) Transfer of pre-wetted material to the filling hall
(c) Phase 1 Fermentation
(d) Phase 1 Turning
(e) Phase 2 Fermentation
(f) Phase 2 Turning
(g) Miscellaneous sources
15 I discuss these below
Pre-Wet
16 In the pre-wet stage straw bales are bought inside to the enclosed
Pre-Wet building with a loader which are then submerged in to a
dedicated lsquobathrsquo that is filled with nitrogen rich process water Once
the bales are fully wetted they are then stacked within the building
for one week days to allow microbial activity to build and de-wax the
straw After soaking period for 1 week the bales are formed into a
pile about 2 to 3m high together with the other raw materials in the
section of the Pre-Wet building marked as Pre-Wet Conditioning in
6
Appendix B To maintain porosity the material is mechanically turned
once in this final week
17 The pre-wet building is maintained under negative pressure at all
times to prevent odour being released to atmosphere
Transfer
18 At the end of the conditioning period the material is loaded into the
mixing line and then conveyed to the tunnel building
19 The conveyor is covered and air is extracted from it into both the
filling hall and the pre-wet building The openings in both the pre-wet
and filling hall were taken into account in the design of the total
amount of ventilation air that is required in both the pre-wet and
filling hall to maintain negative pressure
Phase 1 Fermentation
20 Each of the tunnels is provided with under-floor aeration to maintain
optimum levels of oxygen and temperature in the compost mass
Temperatures vary through the process ranging between 40-80 oC
and are largely controlled using aeration air
21 In this part of the process the aeration and extraction is a fully sealed
system that is balanced to a slight negative pressure
22 All of the air used in the phase 1 tunnels is extracted to the acidwater
scrubbers and the biofilter
Phase 1 Turning
23 Turning involves removing the substrate from one tunnel and placing
it in another via the filling hall The filing hall and the tunnels are
under negative pressure during this operation and the air is extracted
to the scrubber and biofilter
Phase 2 Fermentation
7
24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of
the fermentation but with slightly different aeration and turning
requirements and continues until a critical point called peak heat is
reached From this time on the temperature reduces to the point
when the substrate is finished and cooled At this stage it has only a
very mild potting mix smell to it
Phase 2 Turning
25 This is identical to the phase 1 turning and again the filling hall is
under negative pressure The air is extracted to the scrubber and
biofilter
Phase 3 Spawning
26 Once the substrate is cooled to ambient temperature it is removed
from the tunnels into the filling hall As there is no significant odour
from the substrate at this stage the filling hall is under slight positive
pressure using filtered air to prevent contamination The mushroom
mycelium is added and the substrate is then returned to the tunnels
and left to grow After 14 to 21 days it is removed via the load out
hall and sent to the growing rooms There is no odour from this
stage
Miscellaneous Sources
27 Because the whole composting process will be fully enclosed there
are very few sources outside that could potentially cause odour and
the only ones would include the nutrient tank (goody water tank) and
deliveries of raw materials
28 The nutrient water tank will be vented into the pre-wet building and is
therefore under negative pressure There will be no odour from this
source
29 The only raw material that has any potential for odour is the chicken
manure However this will be delivered in covered trucks and only
8
unloaded inside the pre-wet building Under normal circumstances
chicken manure has very little odour potential when it is in a covered
truck In the event that unsuitable material is bought on site Mercer
will refuse to accept it and the contract for supply will be reviewed if
there are repeat instances This is set out in the air quality
management plan
BASIS FOR THE DESIGN PARAMETERS
30 The standard hierarchy for odour control engineering is prevention
capture at source followed by treatment and finally full building
enclosure with ventilation followed by treatment
31 In the case of compost or mushroom substrate production
preventing odour generation is not possible at this time but capture
at source is used in the phase 1 and 2 operations as the tunnels are
completely sealed and ventilated to the odour control system
However capture at source is not feasible for the pre-wet phase
filling and turning the substrate and odour control for these
operations must rely on full enclosure with building ventilation to the
odour control system as there are no feasible alternatives
32 In my opinion the proposed odor control system represents the Best
Available Control Technology (BACT) that is both more advanced and
effective than the BPO requirements of the RMA It is also the same
system that I recommended to the Environment Court in the New
Zealand Mushrooms2 case when I gave evidence in support of the
residents and more recently in the Te Mata Mushrooms hearing in
Havelock North
33 The building air extraction rates used for the combined pre-wet and
compost buildings were provided by the equipment manufacturer
Christiaens and I have used them to estimate the vacuum that could
2 ENV-2006-WLG-000356 ENV-2006-WLG-000344) and ENV-2006-WLG-000347 ENV-2006-WLG-000351
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
3
including Resource Consent application and the
successful Environment Court appeal
(c) Assessment of odour effects for composting operations
at Living EarthChristchurch City Council operation in
Christchurch
(d) Assessment of potential odour effects for New
Plymouth City Council composting operation
(e) Provided evidence in an Environment Court appeal
involving New Zealand Mushrooms Ltd Morrinsville
(f) Assessment of potential effects of odour dust and bio-
aerosols for the Living Earth Joint Venture in Careys
Gully Wellington
(g) Assessment of effects of a greenwaste composting
operation application by Whakatane District Council
(h) Measurement and assessment and remedial works for
odours from the indoor composting plant at Cresta
Mushrooms Mercer
(i) Assessment of engineering options to control odour
from Te Mata Mushrooms Havelock North (ongoing)
6 In terms of scale composting operations I have been involved with
range from a few thousand tonnes per annum to up to 75000 tonnes
per annum
7 I believe that I am well qualified to provide expert evidence on
matters that have direct relevance to the application that is before
the Independent Hearing Commissioners
8 I have read the Code of Conduct for Expert Witnesses issued as part of
the Environment Court Practice Notes I agree to comply with the
code and am satisfied the matters I address in my evidence are within
my expertise I am not aware of any material facts that I have
4
omitted that might alter or detract from the opinions I express in my
evidence
SCOPE OF EVIDENCE
9 In my evidence I will
(a) Give an overview the application and the key odour
sources as they relate to the odour control systems
proposed
(b) Discuss the basis for the design parameters selected for
odour containment
(c) The scrubber and biofilter odour control system
(d) Assess the odour impacts arising from the proposals
(e) Comment on the submissions received
(f) Comment on the Officers Report
(g) Provide context regarding alternative sites
OVERVIEW
10 The full details of the process are provided in the application technical
document1 and the following represents a short summary
11 The proposal is for the manufacture of mushroom substrate
(compost) in a fully enclosed facility that will operate with full building
air extraction on all parts of the buildings and processes that generate
odour This odour-containing air will be pre-treated in an acid
scrubber to remove ammonia followed by a water scrubber to
remove any acid mist carry over and finally the air will be treated in a
large biofilter to remove all odour
12 Manufacturing will take place in two buildings beginning with the
pre-wetting operation in the CANVACON pre-wet building followed
by transfer to the filling hall in the main composting building that
1 Terry Brady Consulting Ltd Mercer Mushrooms Application for Consent for Discharge to Air
(2) Revised Technical Report 321502R002 12 April 2019
5
contains 12 fermentation tunnels From the filling hall the tunnels are
filled using a specialised cassette filling machine Fermentation is
broadly separated into Phase 1 and Phase 2 stages that are defined by
the temperatures maintained in the fermenting mass
13 After a pasturisation stage (in Phase 2) the substrate is cooled to
ambient temperature and spawned with mushroom mycelium and
held in the tunnels for 14-21 days before removal to the growing
facility
KEY ODOUR SOURCES
14 The main odour sources in process order are
(a) The pre-wetting and turning in the Canvacon
Building
(b) Transfer of pre-wetted material to the filling hall
(c) Phase 1 Fermentation
(d) Phase 1 Turning
(e) Phase 2 Fermentation
(f) Phase 2 Turning
(g) Miscellaneous sources
15 I discuss these below
Pre-Wet
16 In the pre-wet stage straw bales are bought inside to the enclosed
Pre-Wet building with a loader which are then submerged in to a
dedicated lsquobathrsquo that is filled with nitrogen rich process water Once
the bales are fully wetted they are then stacked within the building
for one week days to allow microbial activity to build and de-wax the
straw After soaking period for 1 week the bales are formed into a
pile about 2 to 3m high together with the other raw materials in the
section of the Pre-Wet building marked as Pre-Wet Conditioning in
6
Appendix B To maintain porosity the material is mechanically turned
once in this final week
17 The pre-wet building is maintained under negative pressure at all
times to prevent odour being released to atmosphere
Transfer
18 At the end of the conditioning period the material is loaded into the
mixing line and then conveyed to the tunnel building
19 The conveyor is covered and air is extracted from it into both the
filling hall and the pre-wet building The openings in both the pre-wet
and filling hall were taken into account in the design of the total
amount of ventilation air that is required in both the pre-wet and
filling hall to maintain negative pressure
Phase 1 Fermentation
20 Each of the tunnels is provided with under-floor aeration to maintain
optimum levels of oxygen and temperature in the compost mass
Temperatures vary through the process ranging between 40-80 oC
and are largely controlled using aeration air
21 In this part of the process the aeration and extraction is a fully sealed
system that is balanced to a slight negative pressure
22 All of the air used in the phase 1 tunnels is extracted to the acidwater
scrubbers and the biofilter
Phase 1 Turning
23 Turning involves removing the substrate from one tunnel and placing
it in another via the filling hall The filing hall and the tunnels are
under negative pressure during this operation and the air is extracted
to the scrubber and biofilter
Phase 2 Fermentation
7
24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of
the fermentation but with slightly different aeration and turning
requirements and continues until a critical point called peak heat is
reached From this time on the temperature reduces to the point
when the substrate is finished and cooled At this stage it has only a
very mild potting mix smell to it
Phase 2 Turning
25 This is identical to the phase 1 turning and again the filling hall is
under negative pressure The air is extracted to the scrubber and
biofilter
Phase 3 Spawning
26 Once the substrate is cooled to ambient temperature it is removed
from the tunnels into the filling hall As there is no significant odour
from the substrate at this stage the filling hall is under slight positive
pressure using filtered air to prevent contamination The mushroom
mycelium is added and the substrate is then returned to the tunnels
and left to grow After 14 to 21 days it is removed via the load out
hall and sent to the growing rooms There is no odour from this
stage
Miscellaneous Sources
27 Because the whole composting process will be fully enclosed there
are very few sources outside that could potentially cause odour and
the only ones would include the nutrient tank (goody water tank) and
deliveries of raw materials
28 The nutrient water tank will be vented into the pre-wet building and is
therefore under negative pressure There will be no odour from this
source
29 The only raw material that has any potential for odour is the chicken
manure However this will be delivered in covered trucks and only
8
unloaded inside the pre-wet building Under normal circumstances
chicken manure has very little odour potential when it is in a covered
truck In the event that unsuitable material is bought on site Mercer
will refuse to accept it and the contract for supply will be reviewed if
there are repeat instances This is set out in the air quality
management plan
BASIS FOR THE DESIGN PARAMETERS
30 The standard hierarchy for odour control engineering is prevention
capture at source followed by treatment and finally full building
enclosure with ventilation followed by treatment
31 In the case of compost or mushroom substrate production
preventing odour generation is not possible at this time but capture
at source is used in the phase 1 and 2 operations as the tunnels are
completely sealed and ventilated to the odour control system
However capture at source is not feasible for the pre-wet phase
filling and turning the substrate and odour control for these
operations must rely on full enclosure with building ventilation to the
odour control system as there are no feasible alternatives
32 In my opinion the proposed odor control system represents the Best
Available Control Technology (BACT) that is both more advanced and
effective than the BPO requirements of the RMA It is also the same
system that I recommended to the Environment Court in the New
Zealand Mushrooms2 case when I gave evidence in support of the
residents and more recently in the Te Mata Mushrooms hearing in
Havelock North
33 The building air extraction rates used for the combined pre-wet and
compost buildings were provided by the equipment manufacturer
Christiaens and I have used them to estimate the vacuum that could
2 ENV-2006-WLG-000356 ENV-2006-WLG-000344) and ENV-2006-WLG-000347 ENV-2006-WLG-000351
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
4
omitted that might alter or detract from the opinions I express in my
evidence
SCOPE OF EVIDENCE
9 In my evidence I will
(a) Give an overview the application and the key odour
sources as they relate to the odour control systems
proposed
(b) Discuss the basis for the design parameters selected for
odour containment
(c) The scrubber and biofilter odour control system
(d) Assess the odour impacts arising from the proposals
(e) Comment on the submissions received
(f) Comment on the Officers Report
(g) Provide context regarding alternative sites
OVERVIEW
10 The full details of the process are provided in the application technical
document1 and the following represents a short summary
11 The proposal is for the manufacture of mushroom substrate
(compost) in a fully enclosed facility that will operate with full building
air extraction on all parts of the buildings and processes that generate
odour This odour-containing air will be pre-treated in an acid
scrubber to remove ammonia followed by a water scrubber to
remove any acid mist carry over and finally the air will be treated in a
large biofilter to remove all odour
12 Manufacturing will take place in two buildings beginning with the
pre-wetting operation in the CANVACON pre-wet building followed
by transfer to the filling hall in the main composting building that
1 Terry Brady Consulting Ltd Mercer Mushrooms Application for Consent for Discharge to Air
(2) Revised Technical Report 321502R002 12 April 2019
5
contains 12 fermentation tunnels From the filling hall the tunnels are
filled using a specialised cassette filling machine Fermentation is
broadly separated into Phase 1 and Phase 2 stages that are defined by
the temperatures maintained in the fermenting mass
13 After a pasturisation stage (in Phase 2) the substrate is cooled to
ambient temperature and spawned with mushroom mycelium and
held in the tunnels for 14-21 days before removal to the growing
facility
KEY ODOUR SOURCES
14 The main odour sources in process order are
(a) The pre-wetting and turning in the Canvacon
Building
(b) Transfer of pre-wetted material to the filling hall
(c) Phase 1 Fermentation
(d) Phase 1 Turning
(e) Phase 2 Fermentation
(f) Phase 2 Turning
(g) Miscellaneous sources
15 I discuss these below
Pre-Wet
16 In the pre-wet stage straw bales are bought inside to the enclosed
Pre-Wet building with a loader which are then submerged in to a
dedicated lsquobathrsquo that is filled with nitrogen rich process water Once
the bales are fully wetted they are then stacked within the building
for one week days to allow microbial activity to build and de-wax the
straw After soaking period for 1 week the bales are formed into a
pile about 2 to 3m high together with the other raw materials in the
section of the Pre-Wet building marked as Pre-Wet Conditioning in
6
Appendix B To maintain porosity the material is mechanically turned
once in this final week
17 The pre-wet building is maintained under negative pressure at all
times to prevent odour being released to atmosphere
Transfer
18 At the end of the conditioning period the material is loaded into the
mixing line and then conveyed to the tunnel building
19 The conveyor is covered and air is extracted from it into both the
filling hall and the pre-wet building The openings in both the pre-wet
and filling hall were taken into account in the design of the total
amount of ventilation air that is required in both the pre-wet and
filling hall to maintain negative pressure
Phase 1 Fermentation
20 Each of the tunnels is provided with under-floor aeration to maintain
optimum levels of oxygen and temperature in the compost mass
Temperatures vary through the process ranging between 40-80 oC
and are largely controlled using aeration air
21 In this part of the process the aeration and extraction is a fully sealed
system that is balanced to a slight negative pressure
22 All of the air used in the phase 1 tunnels is extracted to the acidwater
scrubbers and the biofilter
Phase 1 Turning
23 Turning involves removing the substrate from one tunnel and placing
it in another via the filling hall The filing hall and the tunnels are
under negative pressure during this operation and the air is extracted
to the scrubber and biofilter
Phase 2 Fermentation
7
24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of
the fermentation but with slightly different aeration and turning
requirements and continues until a critical point called peak heat is
reached From this time on the temperature reduces to the point
when the substrate is finished and cooled At this stage it has only a
very mild potting mix smell to it
Phase 2 Turning
25 This is identical to the phase 1 turning and again the filling hall is
under negative pressure The air is extracted to the scrubber and
biofilter
Phase 3 Spawning
26 Once the substrate is cooled to ambient temperature it is removed
from the tunnels into the filling hall As there is no significant odour
from the substrate at this stage the filling hall is under slight positive
pressure using filtered air to prevent contamination The mushroom
mycelium is added and the substrate is then returned to the tunnels
and left to grow After 14 to 21 days it is removed via the load out
hall and sent to the growing rooms There is no odour from this
stage
Miscellaneous Sources
27 Because the whole composting process will be fully enclosed there
are very few sources outside that could potentially cause odour and
the only ones would include the nutrient tank (goody water tank) and
deliveries of raw materials
28 The nutrient water tank will be vented into the pre-wet building and is
therefore under negative pressure There will be no odour from this
source
29 The only raw material that has any potential for odour is the chicken
manure However this will be delivered in covered trucks and only
8
unloaded inside the pre-wet building Under normal circumstances
chicken manure has very little odour potential when it is in a covered
truck In the event that unsuitable material is bought on site Mercer
will refuse to accept it and the contract for supply will be reviewed if
there are repeat instances This is set out in the air quality
management plan
BASIS FOR THE DESIGN PARAMETERS
30 The standard hierarchy for odour control engineering is prevention
capture at source followed by treatment and finally full building
enclosure with ventilation followed by treatment
31 In the case of compost or mushroom substrate production
preventing odour generation is not possible at this time but capture
at source is used in the phase 1 and 2 operations as the tunnels are
completely sealed and ventilated to the odour control system
However capture at source is not feasible for the pre-wet phase
filling and turning the substrate and odour control for these
operations must rely on full enclosure with building ventilation to the
odour control system as there are no feasible alternatives
32 In my opinion the proposed odor control system represents the Best
Available Control Technology (BACT) that is both more advanced and
effective than the BPO requirements of the RMA It is also the same
system that I recommended to the Environment Court in the New
Zealand Mushrooms2 case when I gave evidence in support of the
residents and more recently in the Te Mata Mushrooms hearing in
Havelock North
33 The building air extraction rates used for the combined pre-wet and
compost buildings were provided by the equipment manufacturer
Christiaens and I have used them to estimate the vacuum that could
2 ENV-2006-WLG-000356 ENV-2006-WLG-000344) and ENV-2006-WLG-000347 ENV-2006-WLG-000351
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
5
contains 12 fermentation tunnels From the filling hall the tunnels are
filled using a specialised cassette filling machine Fermentation is
broadly separated into Phase 1 and Phase 2 stages that are defined by
the temperatures maintained in the fermenting mass
13 After a pasturisation stage (in Phase 2) the substrate is cooled to
ambient temperature and spawned with mushroom mycelium and
held in the tunnels for 14-21 days before removal to the growing
facility
KEY ODOUR SOURCES
14 The main odour sources in process order are
(a) The pre-wetting and turning in the Canvacon
Building
(b) Transfer of pre-wetted material to the filling hall
(c) Phase 1 Fermentation
(d) Phase 1 Turning
(e) Phase 2 Fermentation
(f) Phase 2 Turning
(g) Miscellaneous sources
15 I discuss these below
Pre-Wet
16 In the pre-wet stage straw bales are bought inside to the enclosed
Pre-Wet building with a loader which are then submerged in to a
dedicated lsquobathrsquo that is filled with nitrogen rich process water Once
the bales are fully wetted they are then stacked within the building
for one week days to allow microbial activity to build and de-wax the
straw After soaking period for 1 week the bales are formed into a
pile about 2 to 3m high together with the other raw materials in the
section of the Pre-Wet building marked as Pre-Wet Conditioning in
6
Appendix B To maintain porosity the material is mechanically turned
once in this final week
17 The pre-wet building is maintained under negative pressure at all
times to prevent odour being released to atmosphere
Transfer
18 At the end of the conditioning period the material is loaded into the
mixing line and then conveyed to the tunnel building
19 The conveyor is covered and air is extracted from it into both the
filling hall and the pre-wet building The openings in both the pre-wet
and filling hall were taken into account in the design of the total
amount of ventilation air that is required in both the pre-wet and
filling hall to maintain negative pressure
Phase 1 Fermentation
20 Each of the tunnels is provided with under-floor aeration to maintain
optimum levels of oxygen and temperature in the compost mass
Temperatures vary through the process ranging between 40-80 oC
and are largely controlled using aeration air
21 In this part of the process the aeration and extraction is a fully sealed
system that is balanced to a slight negative pressure
22 All of the air used in the phase 1 tunnels is extracted to the acidwater
scrubbers and the biofilter
Phase 1 Turning
23 Turning involves removing the substrate from one tunnel and placing
it in another via the filling hall The filing hall and the tunnels are
under negative pressure during this operation and the air is extracted
to the scrubber and biofilter
Phase 2 Fermentation
7
24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of
the fermentation but with slightly different aeration and turning
requirements and continues until a critical point called peak heat is
reached From this time on the temperature reduces to the point
when the substrate is finished and cooled At this stage it has only a
very mild potting mix smell to it
Phase 2 Turning
25 This is identical to the phase 1 turning and again the filling hall is
under negative pressure The air is extracted to the scrubber and
biofilter
Phase 3 Spawning
26 Once the substrate is cooled to ambient temperature it is removed
from the tunnels into the filling hall As there is no significant odour
from the substrate at this stage the filling hall is under slight positive
pressure using filtered air to prevent contamination The mushroom
mycelium is added and the substrate is then returned to the tunnels
and left to grow After 14 to 21 days it is removed via the load out
hall and sent to the growing rooms There is no odour from this
stage
Miscellaneous Sources
27 Because the whole composting process will be fully enclosed there
are very few sources outside that could potentially cause odour and
the only ones would include the nutrient tank (goody water tank) and
deliveries of raw materials
28 The nutrient water tank will be vented into the pre-wet building and is
therefore under negative pressure There will be no odour from this
source
29 The only raw material that has any potential for odour is the chicken
manure However this will be delivered in covered trucks and only
8
unloaded inside the pre-wet building Under normal circumstances
chicken manure has very little odour potential when it is in a covered
truck In the event that unsuitable material is bought on site Mercer
will refuse to accept it and the contract for supply will be reviewed if
there are repeat instances This is set out in the air quality
management plan
BASIS FOR THE DESIGN PARAMETERS
30 The standard hierarchy for odour control engineering is prevention
capture at source followed by treatment and finally full building
enclosure with ventilation followed by treatment
31 In the case of compost or mushroom substrate production
preventing odour generation is not possible at this time but capture
at source is used in the phase 1 and 2 operations as the tunnels are
completely sealed and ventilated to the odour control system
However capture at source is not feasible for the pre-wet phase
filling and turning the substrate and odour control for these
operations must rely on full enclosure with building ventilation to the
odour control system as there are no feasible alternatives
32 In my opinion the proposed odor control system represents the Best
Available Control Technology (BACT) that is both more advanced and
effective than the BPO requirements of the RMA It is also the same
system that I recommended to the Environment Court in the New
Zealand Mushrooms2 case when I gave evidence in support of the
residents and more recently in the Te Mata Mushrooms hearing in
Havelock North
33 The building air extraction rates used for the combined pre-wet and
compost buildings were provided by the equipment manufacturer
Christiaens and I have used them to estimate the vacuum that could
2 ENV-2006-WLG-000356 ENV-2006-WLG-000344) and ENV-2006-WLG-000347 ENV-2006-WLG-000351
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
6
Appendix B To maintain porosity the material is mechanically turned
once in this final week
17 The pre-wet building is maintained under negative pressure at all
times to prevent odour being released to atmosphere
Transfer
18 At the end of the conditioning period the material is loaded into the
mixing line and then conveyed to the tunnel building
19 The conveyor is covered and air is extracted from it into both the
filling hall and the pre-wet building The openings in both the pre-wet
and filling hall were taken into account in the design of the total
amount of ventilation air that is required in both the pre-wet and
filling hall to maintain negative pressure
Phase 1 Fermentation
20 Each of the tunnels is provided with under-floor aeration to maintain
optimum levels of oxygen and temperature in the compost mass
Temperatures vary through the process ranging between 40-80 oC
and are largely controlled using aeration air
21 In this part of the process the aeration and extraction is a fully sealed
system that is balanced to a slight negative pressure
22 All of the air used in the phase 1 tunnels is extracted to the acidwater
scrubbers and the biofilter
Phase 1 Turning
23 Turning involves removing the substrate from one tunnel and placing
it in another via the filling hall The filing hall and the tunnels are
under negative pressure during this operation and the air is extracted
to the scrubber and biofilter
Phase 2 Fermentation
7
24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of
the fermentation but with slightly different aeration and turning
requirements and continues until a critical point called peak heat is
reached From this time on the temperature reduces to the point
when the substrate is finished and cooled At this stage it has only a
very mild potting mix smell to it
Phase 2 Turning
25 This is identical to the phase 1 turning and again the filling hall is
under negative pressure The air is extracted to the scrubber and
biofilter
Phase 3 Spawning
26 Once the substrate is cooled to ambient temperature it is removed
from the tunnels into the filling hall As there is no significant odour
from the substrate at this stage the filling hall is under slight positive
pressure using filtered air to prevent contamination The mushroom
mycelium is added and the substrate is then returned to the tunnels
and left to grow After 14 to 21 days it is removed via the load out
hall and sent to the growing rooms There is no odour from this
stage
Miscellaneous Sources
27 Because the whole composting process will be fully enclosed there
are very few sources outside that could potentially cause odour and
the only ones would include the nutrient tank (goody water tank) and
deliveries of raw materials
28 The nutrient water tank will be vented into the pre-wet building and is
therefore under negative pressure There will be no odour from this
source
29 The only raw material that has any potential for odour is the chicken
manure However this will be delivered in covered trucks and only
8
unloaded inside the pre-wet building Under normal circumstances
chicken manure has very little odour potential when it is in a covered
truck In the event that unsuitable material is bought on site Mercer
will refuse to accept it and the contract for supply will be reviewed if
there are repeat instances This is set out in the air quality
management plan
BASIS FOR THE DESIGN PARAMETERS
30 The standard hierarchy for odour control engineering is prevention
capture at source followed by treatment and finally full building
enclosure with ventilation followed by treatment
31 In the case of compost or mushroom substrate production
preventing odour generation is not possible at this time but capture
at source is used in the phase 1 and 2 operations as the tunnels are
completely sealed and ventilated to the odour control system
However capture at source is not feasible for the pre-wet phase
filling and turning the substrate and odour control for these
operations must rely on full enclosure with building ventilation to the
odour control system as there are no feasible alternatives
32 In my opinion the proposed odor control system represents the Best
Available Control Technology (BACT) that is both more advanced and
effective than the BPO requirements of the RMA It is also the same
system that I recommended to the Environment Court in the New
Zealand Mushrooms2 case when I gave evidence in support of the
residents and more recently in the Te Mata Mushrooms hearing in
Havelock North
33 The building air extraction rates used for the combined pre-wet and
compost buildings were provided by the equipment manufacturer
Christiaens and I have used them to estimate the vacuum that could
2 ENV-2006-WLG-000356 ENV-2006-WLG-000344) and ENV-2006-WLG-000347 ENV-2006-WLG-000351
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
7
24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of
the fermentation but with slightly different aeration and turning
requirements and continues until a critical point called peak heat is
reached From this time on the temperature reduces to the point
when the substrate is finished and cooled At this stage it has only a
very mild potting mix smell to it
Phase 2 Turning
25 This is identical to the phase 1 turning and again the filling hall is
under negative pressure The air is extracted to the scrubber and
biofilter
Phase 3 Spawning
26 Once the substrate is cooled to ambient temperature it is removed
from the tunnels into the filling hall As there is no significant odour
from the substrate at this stage the filling hall is under slight positive
pressure using filtered air to prevent contamination The mushroom
mycelium is added and the substrate is then returned to the tunnels
and left to grow After 14 to 21 days it is removed via the load out
hall and sent to the growing rooms There is no odour from this
stage
Miscellaneous Sources
27 Because the whole composting process will be fully enclosed there
are very few sources outside that could potentially cause odour and
the only ones would include the nutrient tank (goody water tank) and
deliveries of raw materials
28 The nutrient water tank will be vented into the pre-wet building and is
therefore under negative pressure There will be no odour from this
source
29 The only raw material that has any potential for odour is the chicken
manure However this will be delivered in covered trucks and only
8
unloaded inside the pre-wet building Under normal circumstances
chicken manure has very little odour potential when it is in a covered
truck In the event that unsuitable material is bought on site Mercer
will refuse to accept it and the contract for supply will be reviewed if
there are repeat instances This is set out in the air quality
management plan
BASIS FOR THE DESIGN PARAMETERS
30 The standard hierarchy for odour control engineering is prevention
capture at source followed by treatment and finally full building
enclosure with ventilation followed by treatment
31 In the case of compost or mushroom substrate production
preventing odour generation is not possible at this time but capture
at source is used in the phase 1 and 2 operations as the tunnels are
completely sealed and ventilated to the odour control system
However capture at source is not feasible for the pre-wet phase
filling and turning the substrate and odour control for these
operations must rely on full enclosure with building ventilation to the
odour control system as there are no feasible alternatives
32 In my opinion the proposed odor control system represents the Best
Available Control Technology (BACT) that is both more advanced and
effective than the BPO requirements of the RMA It is also the same
system that I recommended to the Environment Court in the New
Zealand Mushrooms2 case when I gave evidence in support of the
residents and more recently in the Te Mata Mushrooms hearing in
Havelock North
33 The building air extraction rates used for the combined pre-wet and
compost buildings were provided by the equipment manufacturer
Christiaens and I have used them to estimate the vacuum that could
2 ENV-2006-WLG-000356 ENV-2006-WLG-000344) and ENV-2006-WLG-000347 ENV-2006-WLG-000351
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
8
unloaded inside the pre-wet building Under normal circumstances
chicken manure has very little odour potential when it is in a covered
truck In the event that unsuitable material is bought on site Mercer
will refuse to accept it and the contract for supply will be reviewed if
there are repeat instances This is set out in the air quality
management plan
BASIS FOR THE DESIGN PARAMETERS
30 The standard hierarchy for odour control engineering is prevention
capture at source followed by treatment and finally full building
enclosure with ventilation followed by treatment
31 In the case of compost or mushroom substrate production
preventing odour generation is not possible at this time but capture
at source is used in the phase 1 and 2 operations as the tunnels are
completely sealed and ventilated to the odour control system
However capture at source is not feasible for the pre-wet phase
filling and turning the substrate and odour control for these
operations must rely on full enclosure with building ventilation to the
odour control system as there are no feasible alternatives
32 In my opinion the proposed odor control system represents the Best
Available Control Technology (BACT) that is both more advanced and
effective than the BPO requirements of the RMA It is also the same
system that I recommended to the Environment Court in the New
Zealand Mushrooms2 case when I gave evidence in support of the
residents and more recently in the Te Mata Mushrooms hearing in
Havelock North
33 The building air extraction rates used for the combined pre-wet and
compost buildings were provided by the equipment manufacturer
Christiaens and I have used them to estimate the vacuum that could
2 ENV-2006-WLG-000356 ENV-2006-WLG-000344) and ENV-2006-WLG-000347 ENV-2006-WLG-000351
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
9
be achieved within the buildings A maximum pressure drop
achievable for the CANVACON building is estimated to be better than
about 50 Pa3 and about 40 Pa when the filling hall also contains
odourous material Pressure drop for both buildings will be controlled
down to a useable level of about 15 Pa at all times when there is
odourous material present
34 This operating pressure drop has been based on my 15 years personal
experience with the control of odours from the PVL Proteins Ltd
rendering plant the Living Earth compost facility in Careys Gully in
Wellington and the Glencore Grain store in New Plymouth It has
been found that 5 Pa vacuum (pressure drop) is the bare minimum
that is required to keep most odours inside a building but where
there will be still significant leaks during moderate to strong winds At
a pressure drop of 7 Pa most odours are kept inside and leaks that
occur only during reasonably strong winds (10 to 15m sec-1 or more)
are relatively minor and are only noticeable in the immediate vicinity
of the building
35 At a pressure drop of 10 Pa or more experience shows that there is no
detectable leakage even during very strong winds 15 Pa is the
operating pressure drop that I recommend to give extra security but
for consent conditions purposes a value of 7 Pa represents the
minimum that must be achieved at all times and is more suitable for
compliance purposes than the expected operational value Note that
these pressure drop values are those that are made during calm
conditions and are not the same as those that prevail during
operation under normal daytime (and windy) conditions
36 I note that some submitters have the view that the CANVACON
material is permeable That is incorrect CANVACON is a multilayer
polyethylene woven material sandwiched between outer
3 This is equivalent to a 75 kg wt force on a standard 15m
2 area door
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
10
polyethylene coating layers and for practical purposes it is
impermeable
SCRUBBERS AND BIOFILTER
37 Again these are described in detail in the technical assessment The
main purpose of the acid scrubber is to remove ammonia that has the
potential to interfere with the biomass population in the biofilter
thereby reducing its ability to remove odour The water scrubber is to
remove acid mist carry over into the biofilter for the same reasons
but it will also remove additional ammonia
38 The biofilter is a very standard design using wood chips and bark that
is widely used across New Zealand and is well proven The 2 metre
depth is the standard design used by Christiaens at their other
European installations and the bulk loading ratio of air flow rate to
filter material is the same as is commonly found in New Zealand
39 The proposed consent conditions for the scrubbers and biofilter are
mostly those that I recommend that achieve a balance between being
useful and excessive monitoring for parameters that do not require
frequent measurement
SUBMISSIONS
40 Where an issue is common to most submissions I deal with it as a
single issue rather than addressing each individual submission
Odour General
41 The common theme in relation to this application is that the
submitters in opposition to the application believe that there will be
odour discharges and that they will be offensive and objectionable I
agree that the odour from mushroom substrate production is in
general terms most definitely offensive and historically residents
have been subjected to unreasonable levels of this odour However
in this application all the odour will be contained and treated to the
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
11
extent that there will be no discernible odour at or beyond the
boundary of the site
42 Mr and Mrs Taylor are concerned that the potential reduction in air
extraction from the buildings at night will result in a loss of negative
pressure and therefore cause more odour The first point to note is
that the design of the ventilation system will achieve no odour which
means that there cannot be more odour The second important
point is that any reduction in air flow from the pre-wet or building or
filling hall will still require a minimum of 7 Pa negative pressure to be
maintained that will contain the odour If for some reason this
cannot be achieved at lower air flow rates then there will be no
reduction in air flow during night time hours
43 Amira Thompson is concerned that the odour from opening the pre-
wet door will have an adverse effect on her tenants This issue was
discussed in Section 3222 of the Assessment document but I can
elaborate on why I do not expect significant odour
44 A simple schematic of the pre-wet building is shown in Attachment A
to my evidence that includes a roof-to-floor plastic curtain separating
the pre-wet pile in the annex at the upper right hand corner of the
building that will have a 300 to 500 mm gap underneath to the floor
Most importantly the air extraction point for the building is located in
this annex where most of the odour is generated An inwards velocity
into this annex will be about between 1 to 2 m sec-1 which is two to
four times the typical 05 m sec-1 usually advocated for indoor air
quality control eg for fume or fine dust4
45 This means that most of the odour in the pre-wet building will be
collected in the Annex When the door is opened for 30 to 60 seconds
or so for vehicle access there will still be an inwards air velocity of 1 to
125 m sec-1 air through the main door but more importantly the
4 Industrial Ventilation A Manual of Recommended Practice American Conference of Governmental
Industrial Hygienists 27th Edition 2010 ISBN 1-882417-22-4
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
12
odour will still be confined to the far end near the annex In my
experience in designing large spray booths with similar large openings
and large air flow rates is that very little odour will be released5
providing that the duration of the opening is short In this application
Mercer Assets have estimated that the door will only remain open for
about 30 to 60 seconds
46 K amp J Foley cite the TampT report as stating that there will be adverse
odour effects during strong wind conditions This is incorrect As I
have noted the pre-wet building and the filling hall will be operated
with a design pressure drop of 15 Pa that fully contains the odours
under all conditions TampT actually state that there may be odours if
the doors are left open or the pre-wet building fabric is damaged
That is correct but the consent conditions require that the doors be
closed and that any damage to the fabric is repaired without delay
47 Stuart Harvey is also concerned about odour during strong winds See
above
Submission of John Karena and Marise Taplin
48 John Karena and Marise Taplin have prepared a detailed submission
and I address the issues raised by reference to their paragraph
numbers These issues are also common to many other submitters
so they are commented on here rather than for individual
submissions
49 Paragraph 34 Contingencies Most of the items listed in paragraph
34 are addressed in the draft air quality management plan (AQMP)
which is the appropriate place rather than in the assessment
document since the AQMP will be modified over time (with
agreement from the Regional Council) as procedures become more
efficient and accommodate new methods or control technologies
The AQMP combines the actions to be followed to achieve full
5 As noted in the application document the large air momentum through the door prevents significant
air outwards leakage
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
13
compliance with conditions actions to minimise equipment and
systems failures and procedures to be followed in the event of failure
However fan breakdown warrants special comment
50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are
extremely rare events at all of the industrial complexes that I have
been involved with over 35 years but in the event that one fan is not
operational the remaining fan is still expected to be able to maintain
a pressure drop of 7 Pa in the pre-wet building and the filling hall
which means that there is no additional risk of odour
51 Paragraph 36 Indoor Air Quality As noted in the application
document indoor health and safety issues are controlled under the
New Zealand Health and Safety at Work Act 2015 not the Resource
Management Act and it is administered by Worksafe New Zealand
not by Regional or District Councils The suggestion that doors may
be left open to enhance the indoor working conditions would
constitute a breach of consent in relation to keeping all doors closed
and maintaining negative pressure on the buildings Leaving doors
open is not an option
52 Paragraphs 37 and 38 Fugitive Odours The submitters are
concerned that there will be a loss of containment that could occur at
night During nighttime hours the pre-wet building will remain under
negative pressure but there will be no mechanical activity that could
result in damage The minimum negative pressure of 7 Pa and the
expected pressure of about 15 Pa are equivalent to the pressure
exerted by light winds of between 35 to 5 m sec-1 respectively which
would not be sufficient to cause any tears in the CANVACON material
53 As part of my analysis of the reliability of the CANVACON material I
sought information from the manufacturer regarding its strength and
long term performance A test report is copied in Attachment B In
summary The CANVACON welded seams have a very high shear
strength of 2800 kg per metre of seam and the tensile strength of the
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
14
fabric itself is clearly greater than 2800 kg m-2 Based on this data it is
highly unlikely to spontaneously tear during the evening hours
Finally the manufacturer has provided a response regarding non-
mechanically induced catastrophic failure of the structure that is
copied in Attachment C to my evidence In short this kind of failure is
unheard of by the supplier
54 I have already commented on the fugitive odours from chicken
manure above and it will not be a significant source
55 One point that the submitter makes in paragraph 38 is that conditions
will not be sufficient to control the odour effects My only comment
in this regard is that the design that Mercer Assets has chosen is
designed to contain all the odour irrespective of the constraints
imposed by the conditions
56 A major part of my brief from Mercer Assets was to assure them that
the proposed systems will actually work as promised by the
manufacturer so that there will be no offensive odour discharges
Having analysed the proposal in detail and assessed the expected
performance against similar in-service odour control systems I am
satisfied that provided the system is built and maintained in
accordance with the technical assessment I prepared then there will
be no odour and certainly no offensive odour
57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33
of the report the take-off scrubbing liquor will be piped to a storage
tank at a rate of a few litres per hour The submitters suggest that the
ammonia that has been removed from the air stream will be released
from the scrubber liquor and cause odour That is not possible
When ammonia is removed from the air stream by dilute acid it
forms ammonium sulphate that has no odour in acidic solution There
will be no ammonia released from the scrubbing liquor
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
15
58 Paragraph 40 Odour from the Process Water I understand that
concerns regarding process water odour have been raised by air
quality advisors engaged by the submitters but the specifics of those
concerns are not presented in the submission The details of the
process water were provided in Section 2 of the application technical
report that stated that all the process liquid is contained within the
buildings and piped to the outside storage tank that is vented to the
odour control system There will be no odour from the process water
59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours
There is no unproven technology involved in this application The
substrate preparation itself is a well known technology and not very
different to what has been previously used in the existing facility The
odour control system is not unproven technology Acid scrubbing to
remove ammonia is a very common technology and biofilters are
widespread throughout New Zealand and the rest of the word In
regard to the suggestion that dispersion modeling should have been
used to assess off-site odours there is no odour to model
60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo
meteorological data presented in the application document the 2001
to 2003 data can be compared to the more recent 2018 data for
Pukekohe in Attachment D to this evidence that also includes Ruakura
for the years 2012 - 2013 These more recent roses are consistent
with the original one presented in the application and typical of all the
Waikato and Auckland regions that do not significantly change from
year to year However as noted in the application the wind rose was
only included to give an overall indication of expected winds in the
area it was not used to assess the likely odour
61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL
factors are important when assessing odours However in this
application no FIDOL assessment has been carried out as no odour is
expected to be discharged
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
16
Dust General
62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report
(Notification letter report 24 May 2019) as indicating that there are
likely to be dust problems at their property This is also a recurring
issue raised by other submitters Section 5 of the TampT report does
mention dust at 67 Morrison Rd in relation to coarse dust that could
affect drinking water but the report does not state where they
believe this dust actually comes from I am unable to clarify this any
further as I am unaware of any significant dust sources that could
cause either nuisance or effects on drinking water
63 However TampT do go on to say that the effects of dust will be
negligible and I agree with this statement
64 In relation to the raw materials bales of straw that are still bound
have negligible dust generating capacity and all the rest of the raw
material handling ie gypsum chicken manure etc including bale
break will take place indoors with no dust generation
65 Construction related dust will be controlled with a water cart andor
water sprinklers as and when required
66 Finally the majority of dust generation in the Morrison Rd area will
actually be generated by wind-blown dust and dry soil from activities
on the surrounding horticultural farms A recent satellite photo dated
3rd March 2019 showing of the extent of this in the surrounding area
is shown in Attachment E to my evidence I would expect the
deposition of dust from these sources to generate dust that would be
orders of magnitude greater than what would be expected from the
Mercer Assets site It is also worth noting that this agricultural dust
will also contain large quantities of bio-aerosols that include fungi and
bacteria
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
17
BIO-AEROSOLS
67 Bio-aerosols were addressed in the application document that
included information on bacteria and fungi including Aspergillus
fumigatus (A fumigatus) and Legionella pneumophila (L
Pneumophila) In summary the available literature indicates that
levels of bio-aerosols in the vicinity of composting plants that use
biofilters for odour control are no different to natural background
levels and no adverse effects are expected from the proposed Mercer
Assets plant I note that the Council reviewer from TampT concurs
OFFICERS REPORT
68 I have already addressed the issues contained in the officers report
that I consider relevant in the above comments relating to the
submitters concerns In regard to the proposed conditions of
consent should it be granted they have been prepared in
consultation with the Council and I have advised Mercer Assets that
they are appropriate
ALTERNATIVE SITES
69 I was asked by Mercer Assests to assess two alternative sites for the
preparation of mushroom substrate The first site was in a disused
quarry at Waikaretu that is about 47 to 50km to the south west of the
current site Two options were considered one that involved
discharging the odour via a straw filter and the other through an
elevated stack
70 Odour emission data from the existing Cresta operation projected to
the proposed production rates was used to determine the extent of
odour on neighbouring properties
71 Based on my observation of the terrain I concluded that drainage
wind flows (katabatic) would preclude the use of a simple straw filter
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
18
and a large biofilter would be required together with full enclosure
Modelling was not required to demostrate this outcome as I relied on
my own experience with similar terrain effects on odour For the
option that used at least partial enclosure odour emission rate data
from the existing Cresta operation was extrapolated to the proposed
production rates and modelled for discharge up a tall stack The
predicted odour levels are shown in Attachment F to this evidence
and are orders of magnitude greater than the accepted Ministry for
the Environment guideline of 5 OU They are indicative of significant
odour nuisance for considerable off-site distances Both options
excluded this site unless full enclosure and filtration was used
72 The second alternative site was a remote area between Island Block
(Meremere) and Maramarua Again I concluded that that operations
on that site would cause odour nuisance to residents who were
located down slope from the proposed site due to the gentle
katabatic drainage winds and that full or partial enclosure would be
required
73 The outcome was that the same level of odour control and
infrastructure (ie full enclosure and odour filtering) would be
required at these sites as at the subject site Furthermore I also
advised Mercer Assets that this level of odour control would be
required at virtually any site in the wider Auckland and Waikato
regions because of the lack of suitable sites that are sufficiently
remote to not affect neighbouring properties if a lesser level of odour
control and infrastructure were adopted
74 Having concluded that full enclosure and odour filtering is necessary
whatever location is chosen and the adoption of that method avoids
odour effects there was no basis to pursue other sites further
75 It is also useful to consider that any alternative remote site would
incur significant transportation costs with the concurrent additional
carbon dioxide (CO2) emission For either the Waikaretu or
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
19
Maramarua locations I have calculated the emission to be about 120
tonnes per year My calculations are provided in Attachment F to my
evidence
CONCLUSION
76 The proposed mushroom substrate production and odour control
system adopted by Mercer Assets represents the Best Available
Control Technology anywhere in the world My assessment is that all
odours will be controlled to a very high level such that providing the
system is maintained in accordance with the proposed consent
conditions and the guidance I have provided in the Air Quality
Management Plan there should be no odour detected at the
boundary of the site and it follows therefore that there will likewise
be no offensive or objectionable odour
Terence John Brady
18 September 2019
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
ATTACHMENT A
PRE-WET EXTRACTION DETAILS
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
Pre-Wet fermentation takes place in annex in the upper right corner of the building where the main building extraction is located above the pre-wet material Roof to floor plastic curtains shown by dashed line with 300 to 500mm gap at floor
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 05 m
Area 228 m2
Velocity 11 msec
Phase 1 PreWet Aeration Section Calc for Containment
within the building annex
D 456 m
H 03 m
Area 1368 m2
Velocity 18 msec
A
B
C
E
D
F
extraction
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
ATTACHMENT B
CANVACON STRESS TEST
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
ATTACHMENT C
CANVACON RELIABILITY
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
FromSelf ltterrytbcplnetgt Tocraig Inger ltcraigmercermushroomsconzgt SubjectCanvacon Date sentMon 02 Sep 2019 160223 +1200
Hi Again Can you get any info from the CANVACON people regarding frequency of unexpected tears or
rips that have occurred on any of their installations ie not from mechanical damage but by
wind or faulty fabric
Terry Terry Brady Consulting Ltd PO Box 96 143 Balmoral Auckland 1342 New Zealand Ph 64 9 630 8710 Mobile 64 027 2970 230 Email terrytbcplnet FromMarty McConnell ltmartymercermushroomsconzgt Toterrytbcplnet ltterrytbcplnetgt SubjectFW Canvacon Date sentSun 8 Sep 2019 220132 +0000 From Paul Whitla [mailtopaulcontainerdomescomau] Sent Wednesday 4 September 2019 1116 AM To phillokaracomaultmailtophillokaracomaugt Subject RE Canvacon Hi Phill I can tell you that in the over 300 Container Dome covers we have supplied using Canvacon I have never experienced a case of this In my personal experience I have been using Canvacon in other areas for over 20 years and have also never heard of anything like this in other businesses I have worked for In my experience if the cover has been manufactured 100 correctly there is zero of chance of this being possible In fact if you look at the test one of our suppliers carried out with an engineer earlier this year you can see the fabric is much stronger than what we require it to be from an engineering point of view Paul Whitla Managing Director - Container Domes Australia T +61 7 5445 1032 - T 1300 793 822 - E paulcontainerdomescomaultmailtosalescontainerdomescomaugt - W containerdomescomau [cidimage003png01D56312645438E0]
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
ATTACHMENT D
WIND ROSES
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 592
Pukekohe 2018 Wind Rose
NORTH
SOUTH
WEST EAST3
6
9
12
15
WIND SPEED
(ms)
gt= 100
50 - 100
30 - 50
20 - 30
10 - 20
05 - 10
Calms 399
Pukekohe 2001 -2003 Wind Rose
NORTH
SOUTH
WEST EAST26
52
78
104
13
WIND SPEED
(ms)
gt= 111
88 - 111
57 - 88
36 - 57
21 - 36
05 - 21
Calms 000
Ruakura 2012 -2013 Wind Rose
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
ATTACHMENT D
SURROUNDING LAND USE
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
ATTACHMENT E
WAIKARETU ODOUR MODEL RESULTS
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
Figure A-E-1 Predicted odour levels (OU m-3) for a single stack option 200 Tonnes per week Production Guideline = 5 OU m-3 Red triangles are dwellings and cafe (rightmost marker)
Figure A-E-2 3D version of Fig A-E-1 Guideline = 5 OU m-3 Dwellings and cafe are mauve squares
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
ATTACHMENT F
CO2 CALCULATIONS
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-
CO2 From Transport Calculation
Distance Morrison Rd to Waikeretu 47 km Similar dist for both
Round Trip 94 km Locations
Trips Per Week 17
Km Per Week 1598 km
Fuel Consumption 18 kmLitre Ref from Trucking Firm
Diesel Consumption per Week 888 Litres
Weeks Per Year 52 Weeks
Diesel Consumption per Annum 46164 Litres
Diesel CO2 emission factor 263 kg CO2Litre Fuel Ref WINFLUE Software
TOTAL CO2 Per Annum 121 Tonnes
Alternative MfE Calculation Ref MfE Table 18
km per Week 1598 km
km per Annum 83096 km
Diesel CO2 emission factor 136 kgkm gt30 Tonne 2010 to 2015 Fleet
TOTAL CO2 Per Annum 113 Tonnes
Ministry for the Environment 2019 Measuring Emissions A Guide for Organisations 2019 Summary of Emission Factors
- Qualifications and experience
- 1 My full name is Terence John Brady I am a Director of Terry Brady Consulting Ltd I hold the degrees of BSc(Hons) and Doctor of Philosophy in Chemistry from the University of Canterbury New Zealand I specialise in air pollution control prepar
- 2 From 1983 to the end of 1991 I was employed by the Department of Health as an air pollution scientist responsible for industrial emissions for the upper half of the South Island under the Clean Air Act From 1991 to 1996 I was employed as an Air
- 3 My relevant experience includes assessing the actual and potential discharges to air from a very large variety of industries throughout New Zealand including the discharges of odour from composting I have been involved with many industrial projec
- 4 I have also designed and commissioned a considerable number of industrial ventilation systems for air pollution control purposes
- 5 Some specific projects that I have been involved with that have relevance to this application include
-
- (a) Measurement modelling and assessment of odour from Living Earth composting at Pikes Point in Auckland Technical advice for monitoring programs
- (b) Predictive modelling and assessment of odour from Living Earth composting at Puketutu Island in Auckland including Resource Consent application and the successful Environment Court appeal
- (c) Assessment of odour effects for composting operations at Living EarthChristchurch City Council operation in Christchurch
- (d) Assessment of potential odour effects for New Plymouth City Council composting operation
- (e) Provided evidence in an Environment Court appeal involving New Zealand Mushrooms Ltd Morrinsville
- (f) Assessment of potential effects of odour dust and bio-aerosols for the Living Earth Joint Venture in Careys Gully Wellington
- (g) Assessment of effects of a greenwaste composting operation application by Whakatane District Council
- (h) Measurement and assessment and remedial works for odours from the indoor composting plant at Cresta Mushrooms Mercer
- (i) Assessment of engineering options to control odour from Te Mata Mushrooms Havelock North (ongoing)
-
- 6 In terms of scale composting operations I have been involved with range from a few thousand tonnes per annum to up to 75000 tonnes per annum
- 7 I believe that I am well qualified to provide expert evidence on matters that have direct relevance to the application that is before the Independent Hearing Commissioners
- 8 I have read the Code of Conduct for Expert Witnesses issued as part of the Environment Court Practice Notes I agree to comply with the code and am satisfied the matters I address in my evidence are within my expertise I am not aware of any mate
- 9 In my evidence I will
-
- (a) Give an overview the application and the key odour sources as they relate to the odour control systems proposed
- (b) Discuss the basis for the design parameters selected for odour containment
- (c) The scrubber and biofilter odour control system
- (d) Assess the odour impacts arising from the proposals
- (e) Comment on the submissions received
- (f) Comment on the Officers Report
- (g) Provide context regarding alternative sites
-
- 10 The full details of the process are provided in the application technical document and the following represents a short summary
- 11 The proposal is for the manufacture of mushroom substrate (compost) in a fully enclosed facility that will operate with full building air extraction on all parts of the buildings and processes that generate odour This odour-containing air will b
- 12 Manufacturing will take place in two buildings beginning with the pre-wetting operation in the CANVACON pre-wet building followed by transfer to the filling hall in the main composting building that contains 12 fermentation tunnels From the fi
- 13 After a pasturisation stage (in Phase 2) the substrate is cooled to ambient temperature and spawned with mushroom mycelium and held in the tunnels for 14-21 days before removal to the growing facility
- KEY ODOUR SOURCES
- 14 The main odour sources in process order are
-
- (a) The pre-wetting and turning in the Canvacon Building
- (b) Transfer of pre-wetted material to the filling hall
- (c) Phase 1 Fermentation
- (d) Phase 1 Turning
- (e) Phase 2 Fermentation
- (f) Phase 2 Turning
- (g) Miscellaneous sources
-
- 15 I discuss these below
- Pre-Wet
- 16 In the pre-wet stage straw bales are bought inside to the enclosed Pre-Wet building with a loader which are then submerged in to a dedicated lsquobathrsquo that is filled with nitrogen rich process water Once the bales are fully wetted they are then s
- 17 The pre-wet building is maintained under negative pressure at all times to prevent odour being released to atmosphere
- Transfer
- 18 At the end of the conditioning period the material is loaded into the mixing line and then conveyed to the tunnel building
- 19 The conveyor is covered and air is extracted from it into both the filling hall and the pre-wet building The openings in both the pre-wet and filling hall were taken into account in the design of the total amount of ventilation air that is requi
- Phase 1 Fermentation
- 20 Each of the tunnels is provided with under-floor aeration to maintain optimum levels of oxygen and temperature in the compost mass Temperatures vary through the process ranging between 40-80 oC and are largely controlled using aeration air
- 21 In this part of the process the aeration and extraction is a fully sealed system that is balanced to a slight negative pressure
- 22 All of the air used in the phase 1 tunnels is extracted to the acidwater scrubbers and the biofilter
- Phase 1 Turning
- 23 Turning involves removing the substrate from one tunnel and placing it in another via the filling hall The filing hall and the tunnels are under negative pressure during this operation and the air is extracted to the scrubber and biofilter
- Phase 2 Fermentation
- 24 The Phase 2 fermentation is similar to the Phase 1 stage in terms of the fermentation but with slightly different aeration and turning requirements and continues until a critical point called peak heat is reached From this time on the tempera
- Phase 2 Turning
- 25 This is identical to the phase 1 turning and again the filling hall is under negative pressure The air is extracted to the scrubber and biofilter
- Phase 3 Spawning
- 26 Once the substrate is cooled to ambient temperature it is removed from the tunnels into the filling hall As there is no significant odour from the substrate at this stage the filling hall is under slight positive pressure using filtered air to
- Miscellaneous Sources
- 27 Because the whole composting process will be fully enclosed there are very few sources outside that could potentially cause odour and the only ones would include the nutrient tank (goody water tank) and deliveries of raw materials
- 28 The nutrient water tank will be vented into the pre-wet building and is therefore under negative pressure There will be no odour from this source
- 29 The only raw material that has any potential for odour is the chicken manure However this will be delivered in covered trucks and only unloaded inside the pre-wet building Under normal circumstances chicken manure has very little odour poten
- 30 The standard hierarchy for odour control engineering is prevention capture at source followed by treatment and finally full building enclosure with ventilation followed by treatment
- 31 In the case of compost or mushroom substrate production preventing odour generation is not possible at this time but capture at source is used in the phase 1 and 2 operations as the tunnels are completely sealed and ventilated to the odour contr
- 32 In my opinion the proposed odor control system represents the Best Available Control Technology (BACT) that is both more advanced and effective than the BPO requirements of the RMA It is also the same system that I recommended to the Environment
- 33 The building air extraction rates used for the combined pre-wet and compost buildings were provided by the equipment manufacturer Christiaens and I have used them to estimate the vacuum that could be achieved within the buildings A maximum press
- 34 This operating pressure drop has been based on my 15 years personal experience with the control of odours from the PVL Proteins Ltd rendering plant the Living Earth compost facility in Careys Gully in Wellington and the Glencore Grain store in
- 35 At a pressure drop of 10 Pa or more experience shows that there is no detectable leakage even during very strong winds 15 Pa is the operating pressure drop that I recommend to give extra security but for consent conditions purposes a value of
- 36 I note that some submitters have the view that the CANVACON material is permeable That is incorrect CANVACON is a multilayer polyethylene woven material sandwiched between outer polyethylene coating layers and for practical purposes it is imp
- 37 Again these are described in detail in the technical assessment The main purpose of the acid scrubber is to remove ammonia that has the potential to interfere with the biomass population in the biofilter thereby reducing its ability to remove
- 38 The biofilter is a very standard design using wood chips and bark that is widely used across New Zealand and is well proven The 2 metre depth is the standard design used by Christiaens at their other European installations and the bulk loading
- 39 The proposed consent conditions for the scrubbers and biofilter are mostly those that I recommend that achieve a balance between being useful and excessive monitoring for parameters that do not require frequent measurement
- 40 Where an issue is common to most submissions I deal with it as a single issue rather than addressing each individual submission
- 41 The common theme in relation to this application is that the submitters in opposition to the application believe that there will be odour discharges and that they will be offensive and objectionable I agree that the odour from mushroom substrate
- 42 Mr and Mrs Taylor are concerned that the potential reduction in air extraction from the buildings at night will result in a loss of negative pressure and therefore cause more odour The first point to note is that the design of the ventilation
- 43 Amira Thompson is concerned that the odour from opening the pre-wet door will have an adverse effect on her tenants This issue was discussed in Section 3222 of the Assessment document but I can elaborate on why I do not expect significant od
- 44 A simple schematic of the pre-wet building is shown in Attachment A to my evidence that includes a roof-to-floor plastic curtain separating the pre-wet pile in the annex at the upper right hand corner of the building that will have a 300 to 500 mm
- 45 This means that most of the odour in the pre-wet building will be collected in the Annex When the door is opened for 30 to 60 seconds or so for vehicle access there will still be an inwards air velocity of 1 to 125 m sec-1 air through the main
- 46 K amp J Foley cite the TampT report as stating that there will be adverse odour effects during strong wind conditions This is incorrect As I have noted the pre-wet building and the filling hall will be operated with a design pressure drop of 15 P
- 47 Stuart Harvey is also concerned about odour during strong winds See above
- Submission of John Karena and Marise Taplin
- 48 John Karena and Marise Taplin have prepared a detailed submission and I address the issues raised by reference to their paragraph numbers These issues are also common to many other submitters so they are commented on here rather than for indivi
- 49 Paragraph 34 Contingencies Most of the items listed in paragraph 34 are addressed in the draft air quality management plan (AQMP) which is the appropriate place rather than in the assessment document since the AQMP will be modified over time (
- 50 Paragraph 34 (c) Fan Breakdown In my experience fan failures are extremely rare events at all of the industrial complexes that I have been involved with over 35 years but in the event that one fan is not operational the remaining fan is still
- 51 Paragraph 36 Indoor Air Quality As noted in the application document indoor health and safety issues are controlled under the New Zealand Health and Safety at Work Act 2015 not the Resource Management Act and it is administered by Worksafe
- 52 Paragraphs 37 and 38 Fugitive Odours The submitters are concerned that there will be a loss of containment that could occur at night During nighttime hours the pre-wet building will remain under negative pressure but there will be no mechan
- 53 As part of my analysis of the reliability of the CANVACON material I sought information from the manufacturer regarding its strength and long term performance A test report is copied in Attachment B In summary The CANVACON welded seams have a
- 54 I have already commented on the fugitive odours from chicken manure above and it will not be a significant source
- 55 One point that the submitter makes in paragraph 38 is that conditions will not be sufficient to control the odour effects My only comment in this regard is that the design that Mercer Assets has chosen is designed to contain all the odour irresp
- 56 A major part of my brief from Mercer Assets was to assure them that the proposed systems will actually work as promised by the manufacturer so that there will be no offensive odour discharges Having analysed the proposal in detail and assessed t
- 57 Paragraph 39 Odour from Scrubbing Liquor As stated in Section 33 of the report the take-off scrubbing liquor will be piped to a storage tank at a rate of a few litres per hour The submitters suggest that the ammonia that has been removed f
- 58 Paragraph 40 Odour from the Process Water I understand that concerns regarding process water odour have been raised by air quality advisors engaged by the submitters but the specifics of those concerns are not presented in the submission Th
- 59 Paragraph 41 to 44 Unproven New Technology and Off-site Odours There is no unproven technology involved in this application The substrate preparation itself is a well known technology and not very different to what has been previously used
- 60 Paragraph 45 Meteorological Data In relation to the ldquoout of daterdquo meteorological data presented in the application document the 2001 to 2003 data can be compared to the more recent 2018 data for Pukekohe in Attachment D to this evidence that
- 61 Paragraph 46 FIDOL factors It is correctly noted that the FIDOL factors are important when assessing odours However in this application no FIDOL assessment has been carried out as no odour is expected to be discharged
- Dust General
- 62 Mr and Mrs Taylor cite the Tonkin and Taylor (TampT) report (Notification letter report 24 May 2019) as indicating that there are likely to be dust problems at their property This is also a recurring issue raised by other submitters Section 5
- 63 However TampT do go on to say that the effects of dust will be negligible and I agree with this statement
- 64 In relation to the raw materials bales of straw that are still bound have negligible dust generating capacity and all the rest of the raw material handling ie gypsum chicken manure etc including bale break will take place indoors with no dus
- 65 Construction related dust will be controlled with a water cart andor water sprinklers as and when required
- 66 Finally the majority of dust generation in the Morrison Rd area will actually be generated by wind-blown dust and dry soil from activities on the surrounding horticultural farms A recent satellite photo dated 3rd March 2019 showing of the exten
- 67 Bio-aerosols were addressed in the application document that included information on bacteria and fungi including Aspergillus fumigatus (A fumigatus) and Legionella pneumophila (L Pneumophila) In summary the available literature indicates tha
- 68 I have already addressed the issues contained in the officers report that I consider relevant in the above comments relating to the submitters concerns In regard to the proposed conditions of consent should it be granted they have been prepar
- 69 I was asked by Mercer Assests to assess two alternative sites for the preparation of mushroom substrate The first site was in a disused quarry at Waikaretu that is about 47 to 50km to the south west of the current site Two options were conside
- 70 Odour emission data from the existing Cresta operation projected to the proposed production rates was used to determine the extent of odour on neighbouring properties
- 71 Based on my observation of the terrain I concluded that drainage wind flows (katabatic) would preclude the use of a simple straw filter and a large biofilter would be required together with full enclosure Modelling was not required to demostrat
- 72 The second alternative site was a remote area between Island Block (Meremere) and Maramarua Again I concluded that that operations on that site would cause odour nuisance to residents who were located down slope from the proposed site due to th
- 73 The outcome was that the same level of odour control and infrastructure (ie full enclosure and odour filtering) would be required at these sites as at the subject site Furthermore I also advised Mercer Assets that this level of odour control
- 74 Having concluded that full enclosure and odour filtering is necessary whatever location is chosen and the adoption of that method avoids odour effects there was no basis to pursue other sites further
- 75 It is also useful to consider that any alternative remote site would incur significant transportation costs with the concurrent additional carbon dioxide (CO2) emission For either the Waikaretu or Maramarua locations I have calculated the emissi
- CONCLUSION
- 76 The proposed mushroom substrate production and odour control system adopted by Mercer Assets represents the Best Available Control Technology anywhere in the world My assessment is that all odours will be controlled to a very high level such tha
-