BEFORE THE NATIONAL GREEN TRIBUNAL (WESTERN ZONE)...
Transcript of BEFORE THE NATIONAL GREEN TRIBUNAL (WESTERN ZONE)...
(J)MA No.17/2015 Page 1 of 15 In Appln. No.61/2014.(WZ)
BEFORE THE NATIONAL GREEN TRIBUNAL
(WESTERN ZONE) BENCH, PUNE
MISC. APPLICATION NO.17 OF 2015
APPLICATION NO.61 OF 2014 (WZ)
CORAM :
HON’BLE SHRI JUSTICE V.R. KINGAONKAR (JUDICIAL MEMBER) HON’BLE DR. AJAY A.DESHPANDE (EXPERT MEMBER)
In The Matter of:
CAVELOSSIM VILLAGERS FORUM
A Society registered under the Societies Act, 1860,
Bearing Registration No.196/Goa/2013,
H.No.314/L IBR-Plaza,
Patecantem, Cavelossim,
Salcete- Goa- 403731.
Through its President,
Mr. Iris Passanha, r/o H.No.314/L,
Patremcantem, Cavelossim, Salcete, Goa.
APPLICANT
VERSUS
1. VILLAGE PANCHAYAT OF CAVELOSSIM,
Cavelossim, Salcete, Goa.
2. SENIOR TOWN PLANNER,
Town and Country Planning Department,
South Goa District office,
(J)MA No.17/2015 Page 2 of 15 In Appln. No.61/2014.(WZ)
Margao, Goa.
3. THE COLLECTOR,
South Goa District,
Margao Goa.
4. ASSISTANT ENGINEER,
SUB DIVISION, Sub-Division-I,
Works Div-II,
Water Resource Department,
Gogol, Margao, Goa.
5. GOA COASTAL ZONE MANAGEMENT AUTHORITY,
C/o Department of Science, Technology &
Environment, Government of Goa,
3rd Floor, Dempo Towers,
Patto, Panaji-Goa.
6. CHAIRMAN,
Goa State Pollution Control Board,
1st Floor, Dempo Towers, Patto,
Panaji Goa.
7. CHAIRPERSON,
Goa State Biodiversity Board,
C/o Department of Science, Technology &
Environment, Opp. Saligao Seminary, Saligao
Bardez, Goa-403511.
8. M/S SHREE BALAJI CONCEPTS,
A Partnership Firm,
having its Registered office at Kadar Manzil,
1st Floor, Margao Goa-403601.
………RESPONDENTS
AND:
M/S SHREE BALAJI CONEPTS A Partner Firm, Having its registered office at Kadar Manzil, 1st Floor, Margao, Goa-403601.
(In MISC. APPLICATION No.17/2015)
APPLICANT
(J)MA No.17/2015 Page 3 of 15 In Appln. No.61/2014.(WZ)
Counsel for Applicant(s):
Mr. Nigel De Casta Frisis Advocate a/w Mr. Iris Passanha for
Jidith A.B.Almeida.
Counsel for Respondent(s):
Mr. Amit Phadte Advocate for Respondent No.1.
Mr. Dattaprasad Lawande a/w F.M.Mesquita, Mr. Nikhil Pai
Advocates for Respondent Nos.2 to 7.
Mr. Ninad Laud a/w Mr Nitin Swant, Mr. Sanjay
Malkarnekar Mr F.B.Bhaangi, Mr Rahul Garg, Mr Makarand
Rodge, Advocates for Respondent No.8.
1. This is an Application filed by the Original
Respondent No.8, (Project Proponent), raising
objection to maintainability of main Application No.61
of 2014, on the ground that the same is barred by
limitation. The bar of limitation is pleaded on the
ground of maintainability of the main application, in
view of the provisions of Sub-section (i) and (iii) of
section 14 of the National Green Tribunal Act, 2010.
2. Cavelossim Village Forum, the Original
Applicant, claims to be a registered society.
Date : April 8th, 2015
JUDGMENT
(J)MA No.17/2015 Page 4 of 15 In Appln. No.61/2014.(WZ)
Undisputedly, the Respondent No. 8 M/s Shree Balaji
Concepts, has proposed development /construction in
lands Survey Nos.9/11,91/5,91/6 and 91/8, of village
Cavelossim, Tal. Salcete State of Goa. According to the
Original Applicant, the project of Respondent No.8,
would knock cause to water bodies, fishing ponds,
channels and Nullahs and therefore, a complaint was
made to the authorities. An inspection was carried out
on 11.2.2014, which clearly revealed such illegalities.
Though the authorities gave directions to the
Respondent No.8, to stop work, yet there was no
compliance by the Respondent No.8. Therefore,
continuation of project activity by the Respondent
No.8, is causing diversion of natural channels of water
in total violation of legal provisions of the Goa
Irrigation Act, 1993, as well as Ses.24 and 25 of the
Water (Prevention & Control of Pollution) Act, 1974.
The site in question falls within NDZ area. The
construction activities were found to be carried out by
reclaiming the area in violation of CRZ Notifications. A
report of Coastal Zone Management Authority (CZMA),
dated 24th June, 2014, comprises this fact. So also, the
Goa Agricultural department and the Goa state
Diversity Board, noted that due to filling of soil and
reclamation of land, environment was being
(J)MA No.17/2015 Page 5 of 15 In Appln. No.61/2014.(WZ)
endangered due to loss of natural biodiversity. There
were several such illegalities committed by the
Respondent No.8, (M/s Shree Balaji Concepts), which
gave cause of action when serious environmental
degradation came to the notice by the Original
Applicant during inspection dated 18.12.2013,
conducted by the Village Panchayat of Cavelossim.
Consequently, the Original Applicant filed an
Application for restoration of damaged properties and
to settle the dispute regarding environmental issues
involved in the dispute, which arose out of
implementation of enactment specified in the
Schedule-I, of the National Green Tribunal Act, 2010.
3. In the meanwhile, the proceedings were stayed
by the Hon’ble High Court of Bombay at Goa, in the
Writ Petition No.450 of 2014. This Tribunal, however,
passed an order dated 7th January, 2015, which
restricted the Original Applicant to agitate only
environmental issues by way of amendment
Application, deleting Municipal issues, which were not
covered as indicated in the earlier order of December
10, 2014. The Hon’ble Division Bench disposed of the
Writ Petition No.450 of 2014, holding that the issues
related to those, which come within purview of
(J)MA No.17/2015 Page 6 of 15 In Appln. No.61/2014.(WZ)
Schedule-I, of the NGT Act, 2010, can be dealt with by
this Tribunal. All contentions of the Petitioners therein
on merits were kept open. The issue regarding
limitation also was kept open. The interim order was
vacated and the Writ Petition was disposed of.
4. It is in the above backdrop that instant
Application is filed by the Original Respondent No.8
M/s Shree Balaji Concepts.
5. Briefly stated, the construction licence was
issued on 18.6.2010 and the construction activity was
commenced in December, 2010. Therefore, ‘cause of
action’ arose for the first time in December, 2010. The
Original Applicant made complaint about alleged
illegalities in the construction to the Village Panchayat
along with copy of letter of Block Development Officer
(BDO) dated 2.9.2013, with a request for inspection of
site. Obviously, in any case, the Original Applicant
gained knowledge about illegal construction activity on
or before 2nd September, 2013. Upon plain reading of
Section 14(1) read with Section 14 (3), of the NGT Act,
2010, it is manifest that such Application cannot be
filed beyond period of six (6) months from the date of
cause of action for such dispute and the explain the
period under Sub-clause (3) can be granted only up to
(J)MA No.17/2015 Page 7 of 15 In Appln. No.61/2014.(WZ)
sixty (60) days, if ‘sufficient cause’ is shown by the
Applicant. According to the Original Respondent No.8
(M/s Shree Balaji Concepts), even if the limitation
period is compounded from 2.9.2013, being the date of
knowledge when the complaint was made to the Village
Panchayat, and BDO by the Original Applicant,
regarding so called illegal construction activities, yet,
in terms of Section 14(3), maximum limitation period
shall be over on or before 2nd March, 2014. The filing
of instant Application on 27th May, 2014, is totally
barred by limitation and, therefore, the Application is
liable to be dismissed.
6. By filing affidavit in reply on behalf of the
Original Applicant, for reasons that the developer (M/s
Shree Balaji Concepts), has not complied with the
order dated 20th May, 2014, passed by this Tribunal,
whereby direction was issued to furnish undertaking
that in case the Application is allowed the construction
will be dismantled by the developer within two (2)
weeks at its own cost. According to the Original
Applicant, there was no confirmed knowledge
regarding filling of water bodies unless inspection was
done by the Village Panchayat on 18.12.2013 and,
therefore, the Application could not be filed till a letter
(J)MA No.17/2015 Page 8 of 15 In Appln. No.61/2014.(WZ)
dated 26th February, 2014, was received from Village
Panchayat. The Applicant alleges that mere knowledge
of some construction activity going on at the site by
itself, does not give rise to cause of action, but
knowledge regarding violation of Environmental loss in
order to raise the dispute under Section 14(1) of the
NGT Act, is starting point which would trigger
limitation for filing of such Application, which shall be
taken into account as 24th June, 2014 or 11.2.2014,
in view of pleadings and, therefore, the Application is
within period of six months from such date. The
Original Applicant, therefore, sought dismissal of the
objection-petition i.e. M.A No.17 of 2015.
7. It may be stated that the objection petitioner
filed rejoinder and the Members of Village Panchayat
supported case of developer (M/s Shree Balaji
Concepts).
8. We have heard learned Advocates for the
contesting parties. We have considered the main
objection raised by M/s Shree Balaji Concepts
(developer) and response of Original Applicant.
9. On behalf of M/s Shree Balaji Concepts, it is
argued by learned Advocate Mr. Ninad Laud that the
Original Applicant did not reproduce facts regarding
(J)MA No.17/2015 Page 9 of 15 In Appln. No.61/2014.(WZ)
disposal of earlier Writ Petition by the Hon’ble High
Court with oblique intention. It is further argued that
when the Applicant made complaint to Village
Panchayat and BDO, on 2nd September, 2013, then the
Applicant was well aware about nature of construction
activities and could have gathered information
regarding alleged degradation of environment. It is
further argued that the inspection carried out by the
BDO on 30th September, 2013, was intimated to the
Original Applicant and assuming that it triggered
cause of action, then also the Application is barred by
limitation, inasmuch as it is not filed within six (6)
months, from the said date. It is contended that after
period of six (6) months, the Original Applicant cannot
claim extension of time by way of right unless and until
it is shown that he was prevented due to ‘sufficient
cause’ from filing of the Application, within timeframe
indicated in Sub-clause (1) of Section 14 of the NGT
Act, 2010. Consequently, looked from any angle, the
Application for so called degradation of environment,
is barred by limitation. It is further argued that in
December, 2013, construction activity had started,
which the Applicant admittedly noticed in January,
2014. Therefore, it was expected that within six (6)
months, he should have filed the Application. However,
(J)MA No.17/2015 Page 10 of 15 In Appln. No.61/2014.(WZ)
‘something was amiss’ which had caused
environmental degradation. It is pointed out that wife
of the President of Applicant-forum, is one of the
Member of Village Panchayat and, therefore, her
knowledge could be shared by the Applicant without
difficulty. Under the circumstances, the Application is
hopelessly barred by limitation and is liable to be
dismissed by this Tribunal, upholding the objections.
10. Countering above arguments, learned Counsel
for the Original Applicant submitted that knowledge of
construction activity by itself cannot give cause to the
Applicant to raise dispute under Sub-cause (1) of
Section 14, unless and until there is existence of
‘substantial environmental dispute’. He argued that
unless existence of such ‘substantial environmental
dispute’ was found in reality, there was no point in
filing the Application. Therefore, proper verification
through the authorities was essential. He contended
that the Applicant got confirmed the fact regarding
violation when the inspections were conducted by BDO
and other authorities. Perusal of the record shows that
on 18th December, 2013, the Village Panchayat
Secretary, found road was constructed by M/s Shree
Balaji Concepts, without CRZ approval and was,
(J)MA No.17/2015 Page 11 of 15 In Appln. No.61/2014.(WZ)
therefore, illegal activity. It was also found that rain
water drained had flowed and diverted without any
approval from the concerned authority. What appears
from the record is that the Applicant sought
information under the R.T.I. by filing an Application
dated 29th April, 2014. He received information dated
30th April, 2014. The information showed that there
was no Application filed by M/s Shree Balaji Concepts
to change natural course of the water channels. It is
important to note that by order dated 21st March,
2014, a report was issued by the Assistant Engineer to
show the construction work was being carried out
vicariously by changing natural course of water. The
Assistant Engineer, therefore, issued communication
dated 18.2.2014, to M/s Shree Balaji Concepts to stop
the work of construction activities within fifteen (15)
days, because original water bodies were found being
destructed. Thus, construction activity of M/s Shree
Balaji Concepts have been started in 2010, but when
it took ugly turn of changing natural course of water
flow, stagnation of water in the body fields and off
spring sites, which endangered environment, then only
the Applicant could say that there was ‘substantial
environmental dispute’ which could be raised by filing
Application under Section 14(1) of the NGT Act, 2010.
(J)MA No.17/2015 Page 12 of 15 In Appln. No.61/2014.(WZ)
11. We may pin-point here that mere violation of
Municipal Laws or some minor Laws caused like
destruction of a small pitch of about 2x2ft of grass due
to a large scale project, may not be treated as
‘substantial environmental dispute’. The principle De
Minmis Non Curat Lex would be attracted in such cases
and therefore, probably the Legislature purposely used
the expression ‘substantial environmental dispute’ in
relation to Sub-clause (i) of Section 14 of the NGT Act,
2010. If such interpretation is taken into account,
conduct of the Applicant can be well understood.
Obviously, it can be said that ‘substantial
environmental dispute’ could be raised by him after
due verification of the facts which he got verification
along with R.T.I information received at the fag-end of
February, 2014 and further confirmed in the last week
of June,2014. So, even assuming that ‘cause of action’
triggered on inspection of 11.2.2014, on basis of site
inspection conducted by the Water Resources
Department and frequent violation of the Irrigation
Laws by diverting natural course water channel was
noticed by the authorities. The Application falls within
period of six (6) months. For, first ‘cause of action’ to
raise such ‘substantial environmental dispute’ could
arose only had identified on 27.5.2014, or 11.2.2014,
(J)MA No.17/2015 Page 13 of 15 In Appln. No.61/2014.(WZ)
when the channel of natural water course (course of
stop of water) was noticed by the authority of
Applicant, as a result of construction activities of M/s
Shree Balaji Concepts. It need not be reiterated that
concerned authorities issued stop-work order to M/s
Shree Balaji Concepts, immediately after noticing that
work had caused change in the natural course of water
flow. Violation of conditions in the permission granted
to M/s Shree Balaji Concepts by the authorities may
be Village Panchayat or CRZ authority, also gave
‘cause of action’ to commence such a dispute.
12. Much reliance is placed on the case of
‘Aradhana Bhargav vs MoEF’ 2013 SCC on line, NGT,
84. A part of observations in the said Judgment is
extensively collected in the Application. So also,
reliance is placed on ‘Kehar Singh vs State of Haryana’
2013, SCC on line NGT 52, and ‘Vidhan Mishra vs
Union of India’ 2013, SCC OnLine NGT 429 and Oswal
Fabs and ICC Ltd vs Common (Admn) 2010 SCC on line
728. In Aradhana Bhargav vs MoEF, the Co-ordinate
Bench of this Tribunal, observed that “concept of
continuing cause of action is outside pale of the NGT
Act.” It is pointed out that concept of ‘continuing cause
of action’, is foreign expression to the provisions of
(J)MA No.17/2015 Page 14 of 15 In Appln. No.61/2014.(WZ)
statute of Limitation engrafted under Section 14(3) of
the NGT Act. So also, in Kehar Singh, it is held that
“Tribunal will have no jurisdiction to condon the delay
beyond period of sixty (60) days after expiry of such
period”. There cannot be any dispute about legal
opinion that the NGT Act, is a special enactment and,
therefore, general provisions of the Limitation Act,
1963, will not be applicable to the special provision of
limitation provided under the former Act. Only
question is whether as to when would first time ‘cause
of action’ can be counted? And can be regarded as have
arisen. In Application No.13 of 2014 (MA No.65/2014)
Amit Maru Vs Secretary, MoEF and Ors, this Tribunal
held that “the limitation will commence from first date
of arising of cause of action for ‘such dispute’. The
expression ‘such dispute’ relates to the dispute
pertaining to breach of conditions of permission
granted for development in the lands, stop work order
and diversion of water channels”. In our view, such a
dispute arose in the fag-end of February, 2014 and,
therefore, the Application is well within time, as it is
filed within limitation, as it is filed in on 275.2014, and
at the fag-end. Therefore, it is well within time because
it is filed within period of six (6) months there from.
(J)MA No.17/2015 Page 15 of 15 In Appln. No.61/2014.(WZ)
13. Under the above circumstances, objection
raised by the Original Respondent No.8, (M/s Shree
Balaji Concepts), is without any substance and is
dismissed. The office to verify whether undertaking is
given by M/s Shree Balaji Concepts, as per earlier
order dated 28th May, 2014, and if it is not given, then
defence of M/s Shree Balaji Concepts, shall not be
allowed in any manner. Misc. Application is,
accordingly, disposed of and the Main Application to
proceed and be scheduled on 23rd April, 2015.
..……………………………………………, JM
(Justice V. R. Kingaonkar)
….…………………………………………, EM (Dr.Ajay A. Deshpande)
Date: April 8th, 2015.
khk
(J)MA No.17/2015 Page 16 of 15 In Appln. No.61/2014.(WZ)