BEB801 - Project 1: Energy absorbing beam column connections

30
Energy Absorbing Beam- Column Connections BEB801 – Project 1 Keagan Leamy n8329559

Transcript of BEB801 - Project 1: Energy absorbing beam column connections

Page 1: BEB801 - Project 1: Energy absorbing beam column connections

Energy Absorbing Beam-Column Connections

BEB801 – Project 1

Keagan Leamy n8329559

Page 2: BEB801 - Project 1: Energy absorbing beam column connections

Presentation Overview

• Problem Overview

• Research Background• Concrete Connection Types

• Energy Dissipation Devices

• Proposed System• Model

• Loading

• Results

• Conclusion

Page 3: BEB801 - Project 1: Energy absorbing beam column connections

Problem Overview

Beam-Column connections are vulnerable locations in a structure, especially under seismic loading.

𝐹 𝑡 = 𝑀 𝑢 + 𝐶 𝑢 + 𝐾 𝑢

Dynamic Energy = Energy to Vibrate Structure + Energy absorbed + Energy to deform structure

Aim to increase energy absorbed, reducing energy to vibrate and deform structure

Page 4: BEB801 - Project 1: Energy absorbing beam column connections

Cyclic Loading

Boundary Conditions used for Seismic Loading, Cantilever

Column (Xue & Zhang, 2014)

Page 5: BEB801 - Project 1: Energy absorbing beam column connections

Concrete Connection Types

• Monolithic Cast-In-Place

• Precast

• Ductile Connection

• Moment Connection

• Composite Beams

Page 6: BEB801 - Project 1: Energy absorbing beam column connections

Monolithic Cast-In-Place

Example Reinforced Concrete Connection Geometry and

Steel Layout (Li & Pan, 2004)

Page 7: BEB801 - Project 1: Energy absorbing beam column connections

Monolithic Cast-In-Place

Typical Failure mode and Flexural Cracks of a Monolithic Connection

(Parastesh, Hajirasouliha, & Ramezani, 2014)

Flexural Cracks began to form in both column and beam at half theoretical ultimate load

Page 8: BEB801 - Project 1: Energy absorbing beam column connections

Precast - Ductile

Example Precast Ductile Connection Geometry and Steel

Layout (Khaloo & Paratesh, 2003)

Page 9: BEB801 - Project 1: Energy absorbing beam column connections

Precast - Ductile

Typical Failure mode and Flexural Cracks of a Precast

Ductile Connection (Khaloo & Paratesh, 2003)

Connection prevented

crack propagation

from beam to column

Page 10: BEB801 - Project 1: Energy absorbing beam column connections

Precast - Moment

Example Precast Moment Connection Geometry and Steel

Layout (Parastesh, Hajirasouliha, & Ramezani, 2014)

Page 11: BEB801 - Project 1: Energy absorbing beam column connections

Precast - Moment

Typical Failure mode and Flexural Cracks of a Precast Moment

Connection (Parastesh, Hajirasouliha, & Ramezani, 2014)

Cracks occurred at connection zone, preventing flexural cracks to form in beam

Page 12: BEB801 - Project 1: Energy absorbing beam column connections

Composite Beams

Example Composite Beam Column Geometry and Steel Layout

(Xue & Zhang, 2014)

Page 13: BEB801 - Project 1: Energy absorbing beam column connections

Composite Beams

Typical Failure mode

and Flexural Cracks of

a Composite Beam

Section (Xue & Zhang,

2014)

Severe Cracking due to

neutral axis being closer to

slab.

Performance very similar to

cast-in-place systems

Page 14: BEB801 - Project 1: Energy absorbing beam column connections

Energy Dissipation Devices

• Friction Damper

• Shear Links

• Viscoelastic Damper

Page 15: BEB801 - Project 1: Energy absorbing beam column connections

Energy Dissipation Devices

Idealised Hysteresis Loops of Energy Dissipation Devices (Constantinou, Soong, & Dargush, 1998)

Page 16: BEB801 - Project 1: Energy absorbing beam column connections

Friction Damper

Prototype Friction Damper (Morgen & Yahya, 2004)

Designed to aid with gap

opening behaviour of post

tensioned pre cast beams.

Increased energy dissipation of

specimen significantly.

Page 17: BEB801 - Project 1: Energy absorbing beam column connections

Friction Damper

Simplified Numerical Model for Friction Damper (Valente,

2013)

Energy Dissipated by

structure decreased as

energy dissipation was

concentrated in device.

This reduced the plastic

demand of the structure.

Page 18: BEB801 - Project 1: Energy absorbing beam column connections

Shear-Links

Schematic Diagram of an Aluminium Shear Link Included

into a Chevron-type OCBF (Rai & Wallace, 1998)

Page 19: BEB801 - Project 1: Energy absorbing beam column connections

Viscoelastic Damper

Picture of Viscoelastic-Wall Dampers (Liu, Wang, & Ren,

2015)

Page 20: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System

Page 21: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System

Page 22: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System - Control

Parameter Value

Stiffness: 𝒌 =𝟏𝟐𝑬𝑰

𝑳𝟑 = 0.527 × 106𝑁/𝑚𝑚

Mass (kg) 6932.2kg

Circular Frequency of Vibration: 𝝎 =

𝒌

𝒎(rad/sec)

= 8.72𝑟𝑎𝑑/𝑠𝑒𝑐

Period of Vibration: 𝑻 =𝟐𝝅

𝝎(sec) 0.72sec

Frequency: 𝒇 =𝟏

𝑻1.4 Hz

Page 23: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System - Control

-1.5

-1

-0.5

0

0.5

1

1.5

0 1 2 3 4 5 6 7

Forc

e (

kN

)

Time (s)

Force vs Time Graph

Page 24: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System - Control

Page 25: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System - Device

Variable Parameter Value

Breadth b (mm) 450

Thickness d (mm) 40

Length L (mm) 270

Mass (kg) 38.151

Young’s Modulus E (Mpa) 200 000

Second Moment of

Area 𝐼 =𝑏𝑑3

12(𝑚𝑚4)

2.4 × 106

Axial Stiffness=𝐴𝐸

𝐿(𝑁/𝑚𝑚)

13.333 × 106

Lateral Stiffness=12𝐸𝐼

𝐿3(𝑁/𝑚𝑚)

0.293 × 106

Page 26: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System - Device

Page 27: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System - Results

Page 28: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System - Results

-15

-10

-5

0

5

10

15

0 1 2 3 4 5 6 7

Dis

pla

cem

ent

(mm

)

Time (sec)

Comparrison in Displacement vs Time with and without Device

Control Device

Page 29: BEB801 - Project 1: Energy absorbing beam column connections

Proposed System - Results

-30

-20

-10

0

10

20

30

-0.4 -0.3 -0.2 -0.1 0 0.1 0.2 0.3 0.4

Forc

e (

kN

)

Displacement (mm)

Hysterises Loop For Device

Page 30: BEB801 - Project 1: Energy absorbing beam column connections

Conclusion