BE in SAP_Final

10
BE calculation guide SAP BE – Using controlling module For Calculation of BE in SAP, Based on future Price, we need to follow the following steps: Upload Raw materials future price. Upload Plan cost. Upload Plan Activity Calculate plan activity rates Run cost estimates (up to analysis stage) 1. Upload Future raw material prices (Via Upload program), which appears in Material Master data Planned Price 2 see fig 01, because priority is set for valuation variant in costing variant ZPC1 see fig 02 Fig. 01 Fig. 02

description

Calculating BreakEven Price Using other Costing version and Planning Versio

Transcript of BE in SAP_Final

  • BE calculation guide

    SAP BE Using controlling module

    For Calculation of BE in SAP, Based on future Price, we need to follow the following steps:

    Upload Raw materials future price.

    Upload Plan cost.

    Upload Plan Activity

    Calculate plan activity rates

    Run cost estimates (up to analysis stage)

    1. Upload Future raw material prices (Via Upload program), which appears in Material Master data Planned Price 2 see fig 01, because priority is set for valuation variant in costing variant ZPC1 see fig 02

    Fig. 01

    Fig. 02

  • BE calculation guide

    2. Upload Plan cost to all Work centers (Production Cost Centers 2020Split for Beltexco Ltd) using LSMW, and use Plan Version 08

    3. Upload Plan Activity for all Work centers (Production Cost Centers) using LSMW upload program, and use Plan Version 08.

    4. Calculate Plan Price for Activity using T Code KSPI and check the price in KSBT report

  • BE calculation guide

    KSBT Report:

    5. Create Cost Estimate using CK40N, using Costing ZPC1 and Costing Version other than 08and

  • BE calculation guide

    Select proper range of date for which BE is required, and complete the only up to Analysis stage to get

    the results.

  • BE calculation guide

    UPLOAD Procedure and programs (Material Prices, KP06 and KP26)

    Material Price Upload Future Price of Raw Material is uploaded considering following steps.

    1. Identify list of materials which need to valuated at Future price/ Market Price in coordination with procurement dept.

    2. Arrange all data in Upload template and complete the file in excel and convert to Notepad. 3. Use LSMW with upload program PSL_PLAN_PRICE1.

    01) Procurement dept. will provide list of Raw materials whose price are evaluated at future/market value for the month or quarter for which the BE is being provided.

    02) Upload template:

    Upload template contain following fields

    Material number (Use only)

    Check box (Use only)

    Plant (Use only)

    Future Planned Price 1

    Future Planned Price 2 (Use only)

    Future Planned Price 3

    Date from Which Future Planned Price 1 Is Valid

    Date from Which Future Planned Price 2 Is Valid (Use only)

    Date from Which Future Planned Price 3 Is Valid Then copy the data from excel upload template into Notepad document and remove space from bottom of the document remove space from the bottom of notepad and maintain space on the top of file

    Then upload file is ready for uploading.

  • BE calculation guide

    03) Upload Procedure

    Use T code LSMW to upload with program PSL_PLAN_PRICE1

    Write the program into all field Project, Subproject and object and then press execute button the following screen appears, go to item # 7 Specify Files and execute.

    After execution the following screen pops up and first press to bring the data into change mode

    double click on selected row to give path to upload file

  • BE calculation guide

    And the complete all steps

    Assign files, Read Data, Display Read Data, Convert Data, display converted data, Create batch input

    session

  • BE calculation guide

    And finally Run Batch input session and press

    And press

    And for verification check materials master data for planned prices.

  • BE calculation guide

    Uploading Planning Activity KP26

    Steps

    Prepare planning activity file in excel and then convert to Notepad for upload

    Use LSMW bearing Project Midas_fico, Subproject zfi_co Object KP26PRD

    Check upload results in report S_ALR_87013611.

  • BE calculation guide

    Uploading Planning cost KP06

    Steps

    Prepare planning activity file in excel and then convert to Notepad for upload

    Use LSMW bearing Project MIDAS SL 3 , Subproject FICO, Object KP061

    Check upload results in report S_ALR_87013611.