Bayan 2012 Guidance

19
0 www.bayan.com.sg 2012 Guidance

description

Bayan Resources 2012 Guidance

Transcript of Bayan 2012 Guidance

Page 1: Bayan 2012 Guidance

0www.bayan.com.sg

2012 Guidance

Page 2: Bayan 2012 Guidance

1

Executive Summary

www.bayan.com.sg

Total production is Budgeted to be in the range of 19.4-20.4 million MT

and this represents approximately a CAGR of 35%-36% since 2008

• Achieved through continued ramp up of all existing sites plus the

initial production from Mamahak (“MCM”)

Strong order book with 18.2 million MT of committed and contracted

sales volume for 2012

• 27.9% on fixed price basis

• ASP anticipated to be in the range of US$ 96-99/MT based on the

benchmark reference price being maintained at US$ 115.7/MT

Cash costs anticipated to increase in the range of US$ 78-80/MT

(include COGS, Royalties, and SGA)

Page 3: Bayan 2012 Guidance

2

Executive Summary (Continued)

www.bayan.com.sg

Capex

• 2012 and 2013 will be important years for investing in infrastructure

which will significantly expand capacity at the Tabang concession as

well as enabling MCM and GPK to be brought into production

2012 Capex is anticipated to be in the region of US$ 255 million and

major projects include:

• Completion of the PIK jetty extension and construction of ship loader

• Purchased KFT – 2 allocated for the Tabang/Pakar project

• Construction of the initial phase of the material handling infrastructure

at the Tabang/Pakar project as well as coal haul road

construction/upgrade

• Construction of initial site infrastructure at MCM and GPK

• Purchase of equipment to support coal handling at all mine sites

Page 4: Bayan 2012 Guidance

3

Coal Production

www.bayan.com.sg

2011 2012BGunungbayan Pratamacoal - Block I 0.4 0.9Gunungbayan Pratamacoal - Block II 3.4 3.3-3.5Perkasa Inakakerta 3.2 3.8-4.0Teguh Sinar Abadi 1.3 0.7Firman Ketaun Perkasa 1.3 2.4-2.5Fajar Sakti Prima 1.7 1.6-1.7Bara Tabang 0.6Wahana Baratama Mining 4.3 4.7-5.0Pakar South 0.9-1.0Mamahak 0.5Total 15.6 19.4-20.4

(in million MT) ProductionCoal Production

4.75.9

11.4 11.9

15.6

2007 2008 2009 2010 2011 2012B

(million MT) 19.4-20.4

1Q12B 2Q12B 3Q12B 4Q12B

(million MT)

4.2-4.34.8-5.1

5.2-5.6 5.2-5.4

Quarterly Coal Production

Note : B stands for Budgeted Figure

FY12 Production Volume is Budgeted to be in the range of 19.4 to 20.4 million MT

Existing operations will continue to ramp up combined with initial production from Pakar and Mamahak

Page 5: Bayan 2012 Guidance

4

Overburden Removal Volume (OB)

www.bayan.com.sg

2011 2012BGunungbayan Pratamacoal - Block I 4.2 15.0-16.5Gunungbayan Pratamacoal - Block II 69.2 72.8-80.3Perkasa Inakakerta 29.9 36.2-39.9Teguh Sinar Abadi 15.3 8.0-8.8Firman Ketaun Perkasa 18.2 34.0-37.5Fajar Sakti Prima 3.9 6.8-7.7Bara Tabang 2.7-3.0Wahana Baratama Mining 79.3 82.8-91.3Pakar South 4.2-4.6Mamahak 0.3 10.5-11.5Total 220.1 273.0-301.1

(in million BCM) OBOverburden Removal

63.0

104.0

160.0 178.0

220.1

2007 2008 2009 2010 2011 2012B

(million BCM) 273.0-301.1

1Q12B 2Q12B 3Q12B 4Q12B

(million BCM)

61.8-68.166.7-73.3

71.5-79.4 73.0-80.3

Quarterly Overburden Removal

Note : B stands for Budgeted Figure

FY12 OB is Budgeted to be in the range of 273.0 to 301.1 million BCM

Subcontractors have already placed orders for the required equipment with mobilization occurring throughout the year

Page 6: Bayan 2012 Guidance

5

Weighted Average Actual Strip Ratio (SR)

www.bayan.com.sg

2011 2012BGunungbayan Pratamacoal - Block I 10.3 16.6-18.3Gunungbayan Pratamacoal - Block II 20.6 22.2-22.9Perkasa Inakakerta 9.2 9.5-10.0Teguh Sinar Abadi 11.6 11.4-12.6Firman Ketaun Perkasa 14.4 14.2-15.0Fajar Sakti Prima 2.3 4.2-4.5Bara Tabang 4.5-5.0Wahana Baratama Mining 18.5 17.6-18.3Pakar South 4.6 Mamahak 20.1 20.9-23.0Total 14.1 14.1-14.8

Weighted Ave SRWeighted Average SR (:1)

Weighted Average Strip Ratio

13.5

17.4

14.0 15.0 14.1

2007 2008 2009 2010 2011 2012B

14.1-14.8

1Q12B 2Q12B 3Q12B 4Q12B

14.7-15.8 13.9-14.4 13.8-14.2 14.0-14.9

Quarterly Weighted Average SR

Note : B stands for Budgeted Figure

FY12 Weighted Average Strip Ratio is Budgeted to be in the range of 14.1 to 14.8 : 1

Page 7: Bayan 2012 Guidance

6

Cash Costs

www.bayan.com.sg

(US$ / MT)

42.9

67.256.4 61.5

78.3

2007 2008 2009 2010 2011 2012B

78.0-80.0

(1) Average cash costs include barging, royalty, and SGA(2) US$ is a convenience translation using the average quarterly exchange

rate for the quarter numbers(3) B stands for Budgeted Figure

*

Average Cash Costs per MT (*)

(US$ / liter)

* Published by Pertamina, including PBBKB and VAT

Pertamina Diesel Oil Price (*)

FY12 Average Cash Costs are Budgeted to be in the range of US$ 78.0-80.0 / MT due to : Longer overhaul distance at some sites Inflationary pressures

1.01

0.58

0.76

1.08 1.05

2008 2009 2010 2011 2012B

Page 8: Bayan 2012 Guidance

7

Coal Sales

www.bayan.com.sg

Coal Sales Volume

7.1 6.7

12.0 12.7 15.3

2007 2008 2009 2010 2011 2012B

20.0-20.8

Geographic Distribution2011

(million MT)

FY12 Sales Volume is Budgeted to be in the range of 20.0 to 20.8 million MT as strong market conditions prevails

India continues to be Bayan’s biggest customer in terms of volume

1Q12B 2Q12B 3Q12B 4Q12B

(million MT)

4.2-4.3

5.6-5.84.8-5.0

5.4-5.7

Quarterly Coal Sales

Note : B stands for Budgeted Figure

India

Italy

26%

19%

12%10%

10%

8%

5%

10%

China

India

Japan

Thailand

Taiwan

Malaysia

Others

Italy

Page 9: Bayan 2012 Guidance

8

Average Selling Price (ASP)

www.bayan.com.sg

(US$ / MT)

Average Selling Price(*)

53.1

74.9

62.0

75.5

98.5

2007 2008 2009 2010 2011 2012B

96.0-99.0

FY12 ASP is Budgeted to be in the range of US$ 96.0 to 99.0 / MT

FY 2011 ASP assumes an average US$ 115.7 / MT FOB for bituminous benchmark coal price @ 6,322 k/cal GAR

(1) ASP includes coal and non-coal sales(2) US$ is a convenience translation using the average annual exchange rate(3) B stands for Budgeted Figure

*

Average CV 5,928 5,799 5,778 5,713

Page 10: Bayan 2012 Guidance

9

Committed and Contracted Sales

www.bayan.com.sg

2012

Fixed Price Floating Price

18.2 million MT

27.9%

72.1%

Note : December 2011

As at 31 December 2011 committed and contracted sales were 18.2 million MT with an average CV of 5,743 GAR kcal

2012 Fixed Price element at US$ 78.07 / MT with an average CV of 5,115 GAR kcal

Additional sales contracts will be entered into during the year as visibility on actual production volumes increases

Page 11: Bayan 2012 Guidance

10

Capital Expenditure

www.bayan.com.sg

(1) US$ is a convenience translation using the average annual exchange rate

*

255.0

2012B

(US$ million)

CAPEX (*)

FY12 capital expenditure is anticipated to be in the region of US$ 255 million

Major capital projects include:

PIK Jetty Extension

KFT-2 to be delivered in late 2012

Integrated Tabang/Pakar expansion project

Initial development of the MCM and GPK projects

Stockpiling expansion at WBM

Page 12: Bayan 2012 Guidance

11

Capital Expenditure

www.bayan.com.sg

PIK The piling work for the PIK jetty has been

completed and construction of the marine dolphins has commenced

Construction of the conveyor gantries and ship loader continues and the overall project is anticipated to be completed 3Q12

Tabang

Engineering concept design for the Tabang/ Pakar material handling infrastructure, coal haul road construction/upgrade and associated geotechnical work are progressing well

External consultants have been appointed and working on the design whilst tender documents (for the haul road construction/upgrade) have been issued in the 4Q11

The construction will be in phases: the first of which is scheduled for completion by the end of 2012

Lubuk Tutung jetty extension

Page 13: Bayan 2012 Guidance

12

Capital Expenditure

www.bayan.com.sg

WBM Continued expansion of the stockpiles and

reclaiming capacity at the jetty and the intermediate crushing facility are progressing well and are anticipated to be completed in the 1Q12

Muji Line Commissioned the construction of a KFT-2 in

2Q11 with completion scheduled in 3Q12 KFT-2 constructed by Teraoka in China under

the supervision of an independent consultant, who are also supervising the KFT-1 refit

KFT-2 is a slightly larger version of the KFT-1 and is planned to cater for the future increase from the Tabang/Pakar concessions

KFT-1 is being re-certified and upgraded. Modification work is completed

Page 14: Bayan 2012 Guidance

Appendix

www.bayan.com.sg

Page 15: Bayan 2012 Guidance

14

Recent Acquisition

Bayan Resources effectively controls 56% of KRL and its subsidiaries and has appointed four non executive directors to the Board of Directors of KRL

On the 28 July 2011, the Company fully drew down the US$ 185 million Bridge Facility provided by ANZ/SCB to fund the partial completion of the IBU/KRL transaction

On the 24 August 2011, the Company paid for 100% of the equity of one IUP and 99% of the equity of 5 IUP’s along with the related assets; the remaining 3 IUP’s await final regulatory approved which will then allow the Company to pay the remaining balances

The initial purchase of a controlling stake in the 6 IUP’s has received regulatory approval and the equity has been transferred to KRL, in return for a controlling stake in KRL

PT. Bayan Resources Tbk

BayanConcessions

GPK Concession

PakarConcessions

MamahakConcessions

Reserves : 459.1 million MTResources : 991.7 million MT

Reserves : 442.0 million MTResources : 3,146.0 million MT

www.bayan.com.sg

Page 16: Bayan 2012 Guidance

15

Concession Sites

www.bayan.com.sg

Bayan Group

SABAHBRUNEI

SARAWAK

KALIMANTAN

Pontianak

BanjarmasinWahana

Balikpapan Coal Terminal

Tabang/PakarTeguh / Firman

Gunungbayan

Perkasa Inakakerta

GPKMamahak

Mines Concession Location Contractor

Gunungbayan (GBP) 2nd Gen CCOW East Kalimantan Buma / Petrosea

Wahana (WBM) 3rd Gen CCOW South Kalimantan Leighton

Teguh (TSA) 3rd Gen CCOW East Kalimantan Thiess

Firman (FKP) 3rd Gen CCOW East Kalimantan Thiess

Perkasa (PIK) 3rd Gen CCOW East Kalimantan Buma / Hareda

Tabang 3 x IUP East Kalimantan Owner Mining

Pakar 9 x IUP East Kalimantan Not in Production

Mamahak 4 x IUP East Kalimantan PPA

Graha Panca Karsa (GPK) IUP East Kalimantan Not in Production

Page 17: Bayan 2012 Guidance

16

Definitions

www.bayan.com.sg

PT Gunungbayan Pratamacoal GBP

PT Perkasa Inakakerta PIK

PT Wahana Baratama Mining WBM

PT Teguh Sinarabadi / PT Firman Ketaun Perkasa TSA / FKP

PT Fajar Sakti Prima / PT Bara Tabang / PT Brian Anjat Sentosa FTB

PT Leighton Contractors Indonesia Leighton

PT Thiess Contractor Indonesia Thiess

Average Selling Price ASP

Gross as Received GAR

Estimate E

Forecast / Budget Figure F

Bank Cubic Metre BCM

Metric Tonne MT

Kilocalorie per kilogram kcal / kg

Page 18: Bayan 2012 Guidance

17

Disclaimer

www.bayan.com.sg

This presentation contains forward-looking statements based on assumptions and forecasts made by PT. BayanResources Tbk management. Statements that are not historical facts, including statements about our beliefs and expectations, are forward-looking statements. These statements are based on current plans, estimates and projections, and speak only as of the date they are made. We undertake no obligation to update any of them in light of new information or future events.

These forward-looking statements involve inherent risks and are subject to a number of uncertainties, including trends in demand and prices for coal generally and for our products in particular, the success of our mining activities, both alone and with our partners, the changes in coal industry regulation, the availability of funds for planned expansion efforts, as well as other factors. We caution you that these and a number of other known and unknown risks, uncertainties and other factors could cause actual future results or outcomes to differ materially from those expressed in any forward-looking statement.

Page 19: Bayan 2012 Guidance

18

Thank You

For more information, please contact :

Investor Relations

Jocelle ConcioInvestor Relations [email protected]

www.bayan.com.sg