BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site...
Transcript of BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site...
![Page 1: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/1.jpg)
234 W. Florida Street, Fifth Floor
Milwaukee, Wisconsin 53204
(P) 414.837.3607
(F) 414.837.3608
BASIS OF DESIGN REPORT
FOUNTAIN LAKE RESTORATION PROJECT CONFINED DISPOSAL FACILITY
Project No. 2248
Prepared For:
SHELL ROCK RIVER WATERSHED DISTRICT 214 West Main Street
Albert Lea, Minnesota 56007
Prepared By:
Natural Resource Technology, Inc. 234 W. Florida Street, Fifth Floor
Milwaukee, Wisconsin 53204
May 6, 2016
_____________________________ ________________________________ Andrew M. Millspaugh, PE Richard H. Weber, PE Environmental Engineer Environmental Engineer
Environmental Consultants
WWW.NATURALRT.COM
![Page 2: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/2.jpg)
CDF BODR - Final 160506 i
TABLE OF CONTENTS
1 INTRODUCTION .................................................................................................................................. 1-1 1.1 Description of Project and Purpose .......................................................................................... 1-1 1.2 Roles and Responsibilities ........................................................................................................ 1-1
2 DESIGN OBJECTIVES ........................................................................................................................ 2-1 3 CDF DESIGN & CONSTRUCTION SCHEDULE ................................................................................. 3-1 4 DESIGN CONSTRAINTS ..................................................................................................................... 4-1
4.1 Land Development Limits .......................................................................................................... 4-1 4.2 Development Offsets ................................................................................................................. 4-1
5 PERMITS .............................................................................................................................................. 5-1 5.1 MDNR Dam Safety .................................................................................................................... 5-1 5.2 MPCA Construction Stormwater ............................................................................................... 5-2 5.3 USACE/MPCA Section 404/401 ............................................................................................... 5-2 5.4 Freeborn County Land Use ....................................................................................................... 5-2 5.5 Board of Water and Soil Resources .......................................................................................... 5-3 5.6 Minnesota Department of Transportation ................................................................................. 5-3
6 GEOTECHNICAL INVESTIGATION SUMMARY ................................................................................ 6-1 6.1 Berm Foundation Conditions ..................................................................................................... 6-1 6.2 Berm Borrow Source Soil .......................................................................................................... 6-2
7 CONTAINMENT BERM DESIGN ........................................................................................................ 7-1 7.1 Berm Profile ............................................................................................................................... 7-1 7.2 Slope Stability Modeling ............................................................................................................ 7-1 7.3 Seepage Analysis ..................................................................................................................... 7-2 7.4 Consolidation/Settlement Analysis ............................................................................................ 7-3
8 CDF DESIGN ....................................................................................................................................... 8-1 8.1 Existing Site Conditions ............................................................................................................ 8-1 8.2 Cell Location & Berm Alignment ............................................................................................... 8-1 8.3 Cell Grading Plan ...................................................................................................................... 8-1 8.4 General Construction Elements ................................................................................................ 8-1 8.5 Stormwater Management .......................................................................................................... 8-2 8.6 Outlet Weir Structure ................................................................................................................. 8-3 8.7 Dredge Material Settling Test .................................................................................................... 8-3 8.8 CDF Flow Pattern ...................................................................................................................... 8-4
9 WATER TREATMENT ......................................................................................................................... 9-1 10 SITE CONSTRUCTION ..................................................................................................................... 10-1
10.1 Site Preparation ...................................................................................................................... 10-1 10.2 Berm Construction .................................................................................................................. 10-1
10.2.1 Construction Documentation .................................................................................... 10-1 10.2.2 Construction Tolerances ........................................................................................... 10-2
11 SITE OPERATIONS & PHASED DEVELOPMENT .......................................................................... 11-1 12 BENEFICIAL USE & LONG TERM CARE ........................................................................................ 12-1 13 REFERENCES ................................................................................................................................... 13-1
![Page 3: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/3.jpg)
TABLE OF CONTENTS
CDF BODR - Final 160506 ii
FIGURES
Figure 1 Site Location Map
Figure 2 Site Layout
Figure 3 Soil Boring Locations
Figure 4 CDF Site Development Plan
Figure 5 CDF Berm Section Detail
TABLES
Table 1 Geotechnical Testing Plan
APPENDICES
Appendix A Preliminary Project Schedule
Appendix B Boring Logs
Appendix C Geotechnical Laboratory Reports Received as of May 6, 2016
Appendix D Jones, Haugh & Smith Plat of Survey
Appendix E FAA No Hazard Determination Letter
![Page 4: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/4.jpg)
CDF BODR - Final 160506 ACR-1
ACRONYMS AND ABBREVIATIONS
Barr Barr Engineering, Co.
BODR Basis of Design Report
BWSR Board of Water and Soil Resources
CDF confined disposal facility
CY cubic yard
CQA construction quality assurance
CUP conditional use permit
FAA Federal Aviation Administration
JHS Jones, Haugh & Smith, Inc.
MDNR Minnesota Department of Natural Resources
MNDOT Minnesota Department of Transportation
MPCA Minnesota Pollution Control Agency
NPDES National Pollutant Discharge Elimination System
NRT Natural Resource Technology, Inc.
QC quality control
SDS State Disposal System
SRRWD Shell Rock River Watershed District
SWPPP Stormwater Pollution Prevention Plan
TMDL total maximum daily load
TSS total suspended solids
USACE United States Army Corps of Engineers
USGS United States Geological Survey
WSB WSB & Associates
![Page 5: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/5.jpg)
CDF BODR - Final 160506 1-1
1 INTRODUCTION
1.1 Description of Project and Purpose
Fountain Lake, located in Albert Lea, Freeborn County, MN, (Figure 1) covers approximately 555 acres,
and is central to the City’s identity and tourism. In 2008, Fountain Lake was added to Minnesota’s list of
impaired waters due to nutrient loading and eutrophication. The Shell Rock River Watershed District
(SRRWD) continues to implement improvements to water-related resources within the district limits, which
includes Fountain Lake. SRRWD has worked in cooperation with the Minnesota Pollution Control Agency
(MPCA) to perform a Total Maximum Daily Load (TMDL) study to determine pollution reduction strategies
for Fountain Lake. As a result, several upland watershed protection initiatives have been implemented
with examples including tributary creek stabilization, septic system improvements, and rough fish
management. Investigatory work performed by Barr Engineering and summarized in technical reports
(Barr 2009, 2014) determined that a significant nutrient source to Fountain Lake is internal phosphorus
loading from lakebed sediment. Phosphorus can become resuspended in the water column when
sediment is disturbed from wind, waves, fish, and boats, causing algae to grow.
With the substantial completion of upstream management practices, SRRWD seeks to further improve
lake water quality by removing phosphorus-laden sediment through dredging. Sediment dredging will
decrease internal phosphorus loading and will provide areas of deeper water as an additional benefit. To
manage removed sediment from dredging, a confined disposal facility (CDF) will be constructed and
used. A CDF is an engineered facility for containment of dredged material in one or more areas or cells.
The constructed containment berms or structures of a CDF enclose the disposal area above any adjacent
water surface, isolating the dredged material from adjacent waters during placement. This document
serves as the Basis of Design Report (BODR) for a CDF facility to support the hydraulic dredging of
Fountain Lake. Dredging is currently targeted to commence in 2017 and span up to 5 years to achieve
the targeted volume of sediment removal.
1.2 Roles and Responsibilities
Several entities are involved in the CDF design; these entities and their roles include the following:
Shell Rock River Watershed District: SRRWD is the project owner and holds, or will hold,
contracts and permits with various entities for the design and execution of this project. SRRWD
will secure access to the site for development. SRRWD will contract directly with one or more
contractors for CDF construction.
![Page 6: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/6.jpg)
INTRODUCTION
CDF BODR - Final 160506 1-2
Natural Resource Technology, Inc. (NRT): NRT is contracted to SRRWD and is the engineer of
record for CDF design.1 NRT will perform the CDF design as described in this BODR and prepare
permit applications, construction plans, and technical specifications for inclusion in project bid
documents. NRT will maintain a project schedule for the design and permitting.
WSB & Associates (WSB): WSB is contracted to SRRWD and will provide support for site
characterization and wetland or floodplain considerations related to CDF development.
Jones, Haugh & Smith (JHS): JHS is contracted to SRRWD and will provide land surveying
support.
Barr Engineering (Barr): Barr is contracted to SRRWD and will provide technical support related
to a berm breach/inundation study hydraulic model of the CDF design.
Earthwork Contractor: An earthwork or general contractor will be selected from qualified bids
and will be contracted to SRRWD for CDF construction.
1 SRRWD and NRT entered into a professional services agreement dated March 8, 2016 based on a proposal dated February 18, 2016, and that agreement is incorporated herein in full by reference and may be referred to herein as the “Agreement.” The review and approval of this Basis of Design Report in no way alters or amends the terms of the Agreement.
![Page 7: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/7.jpg)
CDF BODR - Final 160506 2-1
2 DESIGN OBJECTIVES
Beginning in July 2015, NRT provided technical review of potential CDF sites as locations were identified by
SRRWD. The selected area is shown in Figure 2 outlining the extents available for development into one or
more CDF cells. This land was secured by SRRWD for project use in April 2016. The CDF site development
design will proceed to achieve the following objectives:
1. Maximize CDF storage of dredged sediment: This design objective seeks to maximize the storage of dredged sediment based on the shallow dredge scenario of an amount estimated to be between 1 and 1.5 million cubic yards (CY).
2. Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with the CDF configuration to balance earthwork grading activities, such as cut and fill quantities, and to minimize project cost.
3. Use Passive Water Treatment: This design objective seeks to design the CDF facility such that influent dredge slurry is managed through gravity separation of the sediment from lake water used to convey the sediment without the need for additional active water treatment of CDF effluent. Separated water will be returned to Fountain Lake through an adjacent drainage ditch and Bancroft Creek.
![Page 8: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/8.jpg)
CDF BODR - Final 160506 3-1
3 CDF DESIGN & CONSTRUCTION SCHEDULE
The CDF schedule is driven by the overall project goal to begin hydraulic dredging in 2017. To achieve
this goal, at least one containment cell of the CDF site will be designed and constructed during 2016. The
CDF design will proceed expeditiously to support preparation of permit applications and project bid
documents. A detailed project schedule is shown in Appendix A. The schedule for CDF development
includes the following critical elements:
CDF Design: This task includes the technical site design consisting of the following elements:
o CDF cell configuration and containment berm alignment. Available land will be used as efficiently as possible considering existing topography, physical and administrative constraints, and soil properties. CDF design may include one or more CDF cells.
o BODR review with SRRWD and concurrence on design approach. Following concurrence on the BODR approach, further review and input by SRRWD will occur during weekly progress conference calls.
o Berm geotechnical stability analysis to evaluate the designed berm configuration following review of geotechnical investigation boring logs and laboratory data.
o CDF cell inundation study to assess projects risks for MDNR dam safety permit. A preliminary inundation study was performed by Barr Engineering (Barr, March 2016) and reviewed by MDNR (MDNR, March 2016). This study determined the siting of the CDF presents a low risk hazard to life and property.
o CDF operational components including slurry influent locations, outlet structure location, and type of outlet structure.
o Site stormwater management features to accommodate surface runoff.
o Technical plans and specifications to support construction bid documents. The plan set is anticipated to include the following sheets:
1. Title Sheet
2. Existing Site Conditions
3. Confined Disposal Facility Base Grades
4. CDF Cell 1 Base Grades
5. CDF Cell 1 Cross Sections
6. CDF Cell 2 Base Grades
7. CDF Cell 2 Cross Sections
8. CDF Cell 3 Base Grades
![Page 9: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/9.jpg)
CDF DESIGN & CONSTRUCTION SCHEDULE
CDF BODR - Final 160506 3-2
9. CDF Cell 3 Cross Sections
10. Stormwater Management Plan
11. Details (e.g., Berms, Roads, Ditches, BMPs)
12. Water Control Structure Details
CDF Permitting: This task requires elements from the CDF design task to complete permit applications for submittal. Permit applications (See Section 5) will be submitted at the direction of SRRWD as soon as required design information is completed and reviewed. Permitting agency personnel will be contacted prior to submittal to facilitate permit application preparation to potentially streamline agency review. Permit review is anticipated to take at least 45 days for most permits. This duration could be extended if a longer review period is needed or if revisions and resubmittal is required. CDF permitting will proceed concurrent with lake dredging permitting process.
Bidding & Contracting: This task requires completion of the CDF design task to prepare bid documents, but will be performed concurrent with CDF permitting. NRT will work in coordination with SRRWD to prepare a unified bid package, which may include multiple bid options, for bid solicitation. NRT will prepare general conditions, construction plans, and technical specifications. SRRWD will prepare supplementary conditions and other contract documents that they require (e.g., insurance, bonding). The bid solicitation will be released by SRRWD as required by Minnesota law, and the bid period (anticipated to be 3 weeks) will be administered by NRT. Thereafter, NRT will deliver to SRRWD a bid tabulation summary and engineers recommendation for awarding the bid to the lowest qualified bidder. SRRWD shall have 3 to 6 weeks to review bids and award a contract or contracts.
Site Access: This task requires SRRWD to identify development boundaries and to acquire physical site access (through ownership or easements).
CDF Construction: This task includes the physical site development and construction of the CDF cells. Construction in 2016 may be limited to one cell and general site development features (e.g., access roads and stormwater controls). The design is based on construction and operation of the CDF in above freezing conditions, generally anticipated to be between the months of April and October. The construction duration in the project schedule will be revised following receipt of contractor bids.
![Page 10: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/10.jpg)
CDF BODR - Final 160506 4-1
4 DESIGN CONSTRAINTS
Design of the CDF facility will incorporate the following constraints:
Available land for development
Required offsets from physical and administrative features
Permit limitations
Siting restrictions
Operational use of the CDF for 1 to 5 years
4.1 Land Development Limits
SRRWD has purchased land for CDF construction as shown on Figure 2. The available land covers an
estimated 101 acres, as reported on a plat of survey performed by JHS (Appendix D). Additional land is
under consideration by SRRWD that may be added to the current land extents. Changes will be
documented in an updated plat of survey.
Known development restrictions through easements or other site constraints are described in this BODR.
The land to be developed is former agricultural farm ground with no observed environmental impacts. The
land is void of buildings and no subsurface foundations are known to be present. Agricultural drain tile
may be encountered during site development and will be removed as necessary to accommodate CDF
cell construction. There are apparent unpaved access roads, presumably for agricultural equipment that
traverse areas of the site and will be affected by CDF construction.
4.2 Development Offsets
Within the available land purchased by SRRWD there will be several offsets from physical and
administrative features that will limit construction extents. Anticipated offsets are from parcel boundaries,
utilities, surface water features, wetlands, and floodplains.
Siting Requirements: CDF design will adhere to siting restrictions outlined in MPCA’s guidance
document “Managing Dredge Materials” (MPCA, 2014) related to proximity to groundwater, proximity to
parcel boundaries, and construction within wetlands. Siting requirements for regulated disposal facilities,
such as municipal or industrial landfills, are not considered in this design.
Groundwater: Final CDF surface elevations will be above the observed groundwater table. Observations
of the groundwater depths will occur through temporary piezometers installed around the site as shown in
![Page 11: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/11.jpg)
DESIGN CONSTRAINTS
CDF BODR - Final 160506 4-2
Figure 3. Depths to groundwater are periodically be recorded by SRRWD personnel. Piezometers will be
abandoned in accordance with Minnesota regulations prior to CDF construction.
Parcel Boundaries: Construction of containment berms will be located at least 50 feet from site property
lines shown on Figure 2. The 50-foot offset will apply to the outside toe of CDF cell containment berms.
Ancillary features, such as stormwater conveyance swales or temporary access roads, may be
constructed within 50 feet of property lines.
Wetlands and Floodplains: Development of the south portion of the site may include areas containing
identified wetlands and floodplains as shown on Figure 2. Site development will be designed using the full
extents of available land; however, construction within these areas will not occur without necessary
federal, state, and local approvals. SRRWD and their wetland consultant WSB will coordinate obtaining
necessary approvals and delineations.
Utilities: Adjacent known utilities are shown on Figure 2 based on a survey of marked utilities from a
Minnesota one-call utility locate. Identified utilities include overhead electric, buried gas, and buried fiber
optic. Access easements associated with the identified utilities will be reviewed on plat of survey
documents prepared by JHS to determine use restrictions. Construction that may limit access, such as
containment berms, will not be constructed within utility easements. Features that do not limit access,
such as temporary site roads, may be constructed if allowed.
Surface Water Features: An unnamed drainage ditch is located adjacent to the development area.
Freeborn County’s ditch system program requires a minimum of 16.5 feet of grass along the ditch bank
that serves a filter for influent water runoff. Site construction will minimize disturbance of existing grass
filter strips. CDF effluent pipes or ditches may cross the grass strip to access the drainage ditch for return
of effluent water to Fountain Lake. Disturbances will be stabilized with appropriate measures to maintain
the integrity of the grass buffer. If existing drainage ditches or swales are identified within the CDF
development footprint, water flow will be rerouted through stormwater conveyance features.
Federal Aviation Administration (FAA): The site is located within 5 miles of an FAA regulated airport,
which restricts land development within and adjacent to aircraft approach zones. The FAA provided a
“Determination of No Hazard to Air Navigation” (Appendix E) provided site development and equipment
does not exceed a maximum elevation of 1270 feet at specified coordinates that correspond to the
easternmost extent of the development area. The design will comply with the identified elevation
restriction.
![Page 12: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/12.jpg)
CDF BODR - Final 160506 5-1
5 PERMITS
Several permits from various regulatory agencies are required prior to construction and operation of the
proposed CDF cells. Permit coordination and acquisition will be conducted by NRT on behalf of SRRWD
as set forth in the Agreement. Any permit fees will be provided by SRRWD to accompany prepared
applications.
5.1 MDNR Dam Safety
Based on planned CDF containment berm heights and the containment volume of CDF cells, a Dam
Safety Permit will be required from the Minnesota Department of Natural Resources (MDNR) pursuant to
Minnesota Administrative Rule 6115.0400. The CDF design will include components necessary to
complete a Dam Safety Permit application for review by MDNR. Design elements for the permit
application include the following:
Site location map: This will show the CDF site location with ground surface elevation contours in relation to nearby infrastructure such as buildings and roadways.
Site geotechnical investigation summary: This will include a map of soil boring locations, boring logs summarizing subsurface geological conditions, groundwater elevations, and geotechnical properties of site soil.
CDF berm alignment: This will include a site map showing the planned construction alignment of CDF berms.
CDF berm typical cross section: This will include profile cut-through cross section(s) of containment berms for the designed CDF cell(s).
CDF berm slope stability analysis: This will include modeling software output files of slip surfaces and associated safety factors for various berm profiles and failure conditions. Stability analyses will be performed on the maximum planned berm height. Additional analyses will be performed if differing foundation material or berm borrow source materials are identified from the geotechnical investigation. Stability analysis will include end of construction, long-term operation at full storage capacity, rapid drawdown, and seismic. Both interior and exterior slopes will be evaluated.
CDF berm seepage analysis: This will include a graphical flow path analysis of water seepage through the CDF berm and an estimation of the hydraulic gradient at the berm outside toe at full storage capacity.
Consolidation/Settlement analysis: This will include consolidation and settlement calculation of both the CDF berm and foundation material based on information obtained from the geotechnical evaluation.
Dam Breach Inundation Study: This will include a hydraulic model using HEC-RAS software to evaluate the effects of a sudden breach of a CDF berm based on volumes and berm geometries of planned CDF cells. SRRWD’s consultant Barr Engineering will prepare this study. A
![Page 13: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/13.jpg)
PERMITS
CDF BODR - Final 160506 5-2
preliminary study was prepared in January 2016 using conceptual CDF volumes and berm geometries to initiate discussions with MDNR. Following discussions and comments from MDNR, the model assumptions and input parameters were modified and a revised study was completed in March 2016 and summarized in a technical memorandum. MDNR responded by email on March 14, 2016 stating the model approach is suitable for use in the permit application for the CDF design.
5.2 MPCA Construction Stormwater
MPCA requires a National Pollutant Discharge Elimination System (NPDES)/State Disposal System
(SDS) Construction Stormwater General Permit for any construction activity that will disturb one or more
acre of land. Application for this permit requires preparation of a Stormwater Pollution Prevention Plan
(SWPPP) outlining site management methods for controlling stormwater and preventing off-site
transportation of sediment during construction. NRT will prepare the SWPPP for inclusion in the permit
application.
5.3 USACE/MPCA Section 404/401
Operation of the constructed CDF will discharge lake water separated from the dredge slurry to the
adjacent unnamed ditch and ultimately back to Fountain Lake. The US Army Corps of Engineers
(USACE) classifies CDF effluent as the discharge of dredged material, which is regulated under Section
404 of the Clean Water Act. MPCA determines discharge parameters for the discharge of dredged
material under Section 401 of the Clean Water Act. This permit is obtained through submittal of a joint
application form to USACE and MPCA. NRT will prepare this permit application on behalf of SRRWD.
Available laboratory data for sediment and lake water samples are assumed adequate for
characterization and permitting purposes. Additional sampling is not included in the design.
5.4 Freeborn County Land Use
SRRWD, with assistance from NRT, will request a conditional use permit (CUP) from Freeborn County.
This conditional use permit will address elevations in a shoreland district, excavations within 100 feet of a
property line, extraction and storage of sand, gravel and other materials, water control structures,
mosquito control, pest control, odor control, and placement of fill. NRT, on behalf of the Shell Rock
Watershed District, will prepare all documents needed to present to the Freeborn County Planning
commission and County Commissions for the approval of the CUP. Possible attendance of NRT
engineers can be arranged for the planning commissioners meeting and/or County Commissioner’s
meeting.
![Page 14: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/14.jpg)
PERMITS
CDF BODR - Final 160506 5-3
5.5 Board of Water and Soil Resources
SRRWD is required to submit a copy of a CDF design report (the “Project Plan”) to the Board of Water
and Soil Resources (BWSR) and the director of the MDNR Division of Waters (“Director”), as required by
Minn. Stat. section 103D.605. NRT, in coordination with SRRWD, will prepare a final document to be
designated as the Project Plan. The BWSR and Director are required to review and report on the Project
Plan back to the SRRWD. After receiving these reports, the SRRWD is required to hold a public hearing
on the Project Plan and thereafter Establish the Project pursuant to Minnesota Law, Chapter 103D.
5.6 Minnesota Department of Transportation
MNDOT requires a permit for the installation of temporary dredge slurry pipe under the I-90 highway
bridge/culvert crossing. NRT will prepare this permit application on behalf of SRRWD.
![Page 15: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/15.jpg)
CDF BODR - Final 160506 6-1
6 GEOTECHNICAL INVESTIGATION SUMMARY
A geotechnical investigation and laboratory testing program was performed by WSB during March and
April 2016 to characterize site soils. Site soils are assumed satisfactory to support and construct CDF
containment berms; an objective of this geotechnical investigation is to inform that assumption. Standard
penetration tests and split spoon samples were collected from 35 borings using a hollow-stem auger drill
rig. Temporary piezometers were installed in 11 borings to evaluate groundwater conditions. Soil boring
locations are shown on Figure 3 and consisted of the following types:
Berm Foundation Borings: These borings were located along anticipated alignments of CDF berms to evaluate foundation soil conditions to support slope stability and consolidation analyses.
Berm Borrow Source Borings: These borings were located in anticipated excavation areas for obtaining material to construct CDF berms. Borings evaluated soil types for use in berm design and slope stability analyses.
General Investigation Borings: These borings were located throughout the anticipated CDF construction areas to evaluate soil conditions and identify subsurface stratigraphy.
Piezometers: Following completion of 11 borings around the site perimeter, the borings were converted to temporary piezometers (i.e., water table wells) to evaluate the depth of groundwater below ground surface. Groundwater depths will periodically be recorded by SRRWD personnel beginning in April and continuing until final bid documents are prepared. Groundwater conditions from April monitoring are shown on Figure 3.
Samples were collected and tested according to the geotechnical testing plan in Table 1 to obtain site soil
properties from discrete samples of observed soil types. Results of laboratory testing are summarized in
Table 2. Boring logs and completed laboratory testing reports are included in Appendix B and C. More
subsurface investigation is planned for potential additional land under consideration for purchase by
SRRWD, to provide additional information for identified soft deposits in the southern areas of Cells 2 and
3. Geotechnical data will be used to inform the final berm design and construction process.
6.1 Berm Foundation Conditions
Eighteen (18) soil borings were performed along anticipated berm alignments. On Figure 3, berm
alignment borings included borings 1, 2, 3, 6, 9, 12, 22, 23, 24, 25, 26, 33, 39, 41, 44, 45, 48, and 49.
Boring logs are included in Appendix B. Samples were collected from berm foundation borings and tested
for physical and strength properties indicated in Table 1. Laboratory data received as May 6, 2016 of this
report are included in Appendix C. Remaining laboratory tests are still in process by WSB and will be
reviewed upon receipt. All laboratory data will be reviewed and considered in the CDF design.
![Page 16: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/16.jpg)
GEOTECHNICAL INVESTIGATION SUMMARY
CDF BODR - Final 160506 6-2
The generalized subsurface profile beneath perimeter berms is primarily sandy lean clay (i.e., glacial till)
overlain by varying thicknesses of organic clay (i.e., topsoil). Layers of sand were encountered in a few
borings with no apparent consistent pattern of thickness or depth/elevation.
Along the anticipated south berm alignments of Cells 2 and 3, soft organic deposits were encountered,
described by WSB as “peat”, “muck”, and “swamp deposits.” These soft deposits were encountered in
borings 41, 48, and 49. Soft deposits are generally unsuitable for foundation material and require
consideration in the CDF design. As a result, a secondary investigation will be implemented to target this
area of identified soft deposits, to obtain physical and strength properties to evaluate potential
construction methods or removal and replacement during CDF construction.
6.2 Berm Borrow Source Soil
Eleven (11) borings were performed from areas of higher elevation around Cells 1, 2, and 3 that will be
targeted as borrow source areas for berm construction material. On Figure 3, borings from berm borrow
source areas include borings 10, 16, 17, 18, 20, 27, 30, 31, 35, 37, and 42. Boring logs are included in
Appendix B. Samples were collected from berm borrow source borings and tested for physical and
strength properties indicated in Table 1. Laboratory data received as of the date of this report are
included in Appendix C. Remaining laboratory tests continue to be performed and will be reviewed upon
completion. All laboratory data will be reviewed and considered in the CDF design. Berm borrow source
material is generally described by WSB as lean clay to sandy lean clay (i.e., glacial till) overlain by varying
thicknesses of organic clay (i.e., topsoil). Like the borings under the berm alignments, layers of sand were
encountered in a few borings with no apparent consistent pattern of thickness or depth/elevation.
![Page 17: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/17.jpg)
CDF BODR - Final 160506 7-1
7 CONTAINMENT BERM DESIGN
CDF containment berms will be designed as earthen dikes following recommended practices in USACE
design manuals EM110-2-5025 (Dredging and Dredged Material Management) and EM110-2-1913
(Design and Construction of Levees). The containment berm design will include the following
components:
Berm profile development (i.e., side slope, height, crest width).
Slope stability modeling of the containment berm.
Seepage analysis of water from CDF through the containment berm.
Consolidation/settlement analysis of berm and foundation soil.
7.1 Berm Profile
The containment berm will be constructed with a general trapezoidal geometry consisting of a maximum
side slope, a maximum crest height, and a minimum crest width. The maximum crest height will be
measured from the lowest ground surface elevation of the planned berm alignment. Berm sections along
the alignment at higher ground surface elevations will have a lower height than the maximum section. A
representative berm cross section detail is shown in Figure 5 and includes the following components:
Side Slopes: MPCA’s guidance document “Managing Dredge Materials” (MPCA, 2014) states that the exterior slopes of all dikes or berms must be no steeper than 3:1 horizontal:vertical. Steeper side slopes up to 2.5:1 will be considered for the interior side slope based on stability analyses to maximize storage capacity and minimize earthwork.
Crest Width: The width of the berm crest will be wide enough to accommodate inspection vehicles (e.g., pickup truck) and potential construction equipment (e.g., excavator). The design minimum crest width will be 12 feet, which is the US Interstate Highway System standard traffic lane width.
Crest Height: The crest height will be a factor for determining the CDF storage capacity and will be based balancing earthwork costs with storage capacity gains. The maximum crest height will be set at the lowest existing ground elevation along the planned berm alignment. The selected maximum height will be converted into a maximum crest elevation for use along the remaining berm alignment where ground surface elevations are higher. Therefore, the maximum crest height will only be constructed at the point of lowest ground surface elevation. The maximum design crest height is estimated to be 25 feet.
7.2 Slope Stability Modeling
The containment berm design cross section at the maximum crest height will be modeled for slope
stability using limit equilibrium computer software (Geostudio’s Slope/W). The slope stability analysis will
![Page 18: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/18.jpg)
CONTAINMENT BERM DESIGN
CDF BODR - Final 160506 7-2
determine safety factors at failure for various modeled conditions. The following failure conditions will be
modeled:
End of Construction: The interior and exterior berm slopes will be modeled using strength parameters and drainage conditions representative of the berm and foundation material following completion of construction and prior to filling the CDF.
Long-Term Steady Seepage: The interior and exterior berm slopes will be modeled using strength parameters and drainage conditions representative of the berm and foundation material with the CDF at full storage capacity with dredged sediment and water.
Rapid Drawdown: The interior and exterior berm slopes will be modeled using strength parameters and drainage conditions representative of the berm and foundation material for the condition where elevated exterior water conditions fall rapidly but remain elevated within the containment berm. Such conditions could occur during emergency cell dewatering of ponded water or receding of floodwaters around the exterior of the CDF.
Seismic Pseudo-static: The interior and exterior berm slopes will be modeled using strength parameters representative of the berm and foundation material with the CDF at full storage capacity and applying a representative horizontal ground acceleration of a potential earthquake. According to the United States Geological Survey (USGS) Earthquake Hazards Program, Minnesota has a low seismic activity hazard with 4 recorded earthquakes from 1973 to 2012. The 2014 seismic hazard map indicates a peak ground acceleration of 2-4% gravity (2% probability of exceedance in 50 years) for the CDF site. This model scenario will apply a horizontal seismic acceleration 0.04g (i.e., 4% gravity).
Slope stability modeling scenarios will be performed for the maximum berm height. Additional analyses
will be performed as needed to account for areas with different foundation soil types or berm construction
materials. Safety factor output from slope stability modeling will be compared to the following
recommended safety factors from the USACE Engineering and Design guidance document, “Dredging
and Dredged Material Management” (EM 110-2-5025, 2015):
Stability Analysis Condition Minimum Safety Factor
End of Construction 1.3
Steady Seepage 1.3
Rapid Drawdown 1.0
There is no minimum safety factor guidance for seismic analyses as seismic evaluations are generally
related to deformation of the design element. For the CDF seismic analysis, a minimum safety factor of
1.0 will be used.
7.3 Seepage Analysis
A seepage analysis will be performed to evaluate the profile of water seepage through the containment
berm at the maximum planned storage or dredge material and water. The seepage profile will be
graphically estimated using the Casagrande Method for earth dams (Casagrande, 1937). The seepage
![Page 19: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/19.jpg)
CONTAINMENT BERM DESIGN
CDF BODR - Final 160506 7-3
profile will be used within the limit equilibrium slope stability model for the long-term steady seepage,
rapid drawdown, and seismic scenarios.
A hydraulic gradient (pressure) calculation will be performed to estimate the seepage pressure at the
outside slope of the containment berm based on the seepage profile. Results of the seepage analysis and
hydraulic gradient estimate will be used to determine if seepage control measures are needed for the
containment berm. Examples of seepage control measures include toe drains to capture seepage flow or
toe berms to resist excessive hydraulic gradients.
7.4 Consolidation/Settlement Analysis
A consolidation/settlement analysis will be performed for the maximum height berm section and
foundation soils using soil characteristics obtained from laboratory testing. The analysis will estimate the
magnitude of vertical consolidation or settlement resulting from the increased overburden pressure of the
constructed berm. Results of the analysis will be used to specify the constructed berm height such that
the target height is achieved following post-construction consolidation.
![Page 20: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/20.jpg)
CDF BODR - Final 160506 8-1
8 CDF DESIGN
8.1 Existing Site Conditions
Existing site conditions are shown in Figure 2 with ground surface elevation contours and available land
for CDF development. Additional site features include design constraints such as utilities, buildings,
surface water, wetlands, and flood plains. The CDF construction within the available area will be designed
to achieve identified design objectives and may include multiple CDF cells. The maximum anticipated
flowrate into a CDF cell will be 6,000 gallons per minute; however, the flowrate may be adjusted by the
dredging contractor.
8.2 Cell Location & Berm Alignment
CDF cells will make use of existing ground surface topography to the greatest extent possible to minimize
earthwork. The anticipated CDF cell configuration will include up to three cells as shown in Figure 4
identified as Cells 1, 2, and 3.
8.3 Cell Grading Plan
A cut/fill grading plan will be developed for each CDF cell showing design elevation contours for
containment berms, borrow source excavation areas, and appurtenant areas (e.g., stormwater
management features). Soil quantities will be estimated based on the grading plan for use in preparing a
cost estimate and a project bid form.
8.4 General Construction Elements
General construction elements associated with site development are shown in Figure 4 and include the
following:
Site Access: A site entrance will be designed to access the west portion of the site from 740th Avenue directly north of the overhead electric utility.
Staging Area: The main site staging area for equipment, materials, and construction offices will be located east of the site access point on high elevation land that will not be part of the storage area for CDF Cell 1. A second staging area may be developed on the high ground elevation between CDF Cells 2 and 3 for closer access during construction of these cells.
Access Roads: Site access roads will extend from the site access point to the staging area. During construction, earthwork equipment will perform grading operations without the need for access roads around the site. Final site development will include access roads for inspecting and maintaining the CDF cells. Access roads will extend from the main staging area to each of the constructed CDF cells and allow for access to the top of the containment berms.
![Page 21: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/21.jpg)
CDF DESIGN
CDF BODR - Final 160506 8-2
Temporary Fencing: Site fencing may be installed around the CDF cells and staging areas with appropriate signage to identify the area as an active construction site. The type of fencing will be determined in coordination with SRRWD. Fencing options could be wire or plastic mesh attached to posts driven into the ground or permanent chain link fence.
Utilities: No connections to off-site utilities are anticipated to support CDF construction or operation. Buried discharge lines will be designed for conveyance of CDF effluent from the cell outlet structure to the unnamed ditch and Bancroft Creek for return to Fountain Lake.
Site Vegetation: Containment berm side slopes and other disturbed areas that are not access roads will be seeded for vegetation. Vegetation will protect the constructed areas from erosion and be maintained by mowing. Eroded areas, should they occur either inside or outside the CDF, will be repaired to maintain berm integrity.
Instrumentation and Control: Operation of the CDF cells will be through physical inspections and manual operation. Instruments for monitoring or logic process control are not part of the design. Electric distribution and/or lighting are not part of the design.
Redundant Systems: The site will be designed to operate passively except for pumping of dredge slurry influent into the CDF. Effluent will be controlled through a gravity flow weir structure. Should the influent or withdrawal systems malfunction (e.g., pipe failure, pipe plug, or weir problem), the dredging contractor will be required to stop dredging and repair the malfunction. Redundant systems are not in the design.
Flood Management: The CDF discharge to the drainage ditch will have a check valve to minimize backflow in the event of elevated flow conditions in the ditch. The weir structure will incorporate a manual gate valve to close the effluent pipe and shut off CDF discharge if necessary to limit additional flow to the drainage ditch.
8.5 Stormwater Management
Site development will be designed to manage stormwater during active construction and during long-term
operation of the CDF cells. Construction operations will require an NPDES construction stormwater permit
from MPCA for disturbing more than one acre of land. The permit requires preparation of a Stormwater
Pollution Prevention Plan (SWPPP) for implementing stormwater management controls during
construction. The SWPPP will outline measures for controlling stormwater on the site and for preventing
the off-site transport of sediment from disturbed land. Example control measures include diversion
ditches/berms, sediment traps, and silt fence.
The CDF site design will include a comparison of stormwater flow paths between pre-construction
conditions and the designed post-construction condition. Overland flow paths will be evaluated to
determine the need for features to convey stormwater around, under, or away from CDF containment
berms. Analysis and design of stormwater management features will be based on the 2-year recurrence
interval storm for sediment retention BMPs and the 25-year recurrence interval storm for stormwater
conveyance features.
![Page 22: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/22.jpg)
CDF DESIGN
CDF BODR - Final 160506 8-3
8.6 Outlet Weir Structure
CDF cells will incorporate an overflow weir-type outlet structure for controlling the elevation of ponded
water within the cell intended to allow adequate sediment settling to meet permit requirements for TSS
removal. The outlet is anticipated to be a pre-cast concrete or prefabricated steel structure. The overflow
weir length will be determined based on anticipated CDF influent flow rates and dredge material settling
characteristics. Adjustable weir boards will be added to the control structure to increase the weir elevation
as the CDF cell is filled. Weir boards may also be removed for dewatering the CDF and the dredged
materials at the completion of dredging into a cell. Stock models from vendors of pre-fabricated and
pre-engineered outlet control structures will be prioritized for evaluation over custom structures. Soil
conditions will be evaluated for bearing capacity and consolidation at the outlet structure location.
Nominal ground improvement (e.g., compacted aggregate base) or concrete spread footings are
anticipated to be sufficient.
The outlet structures will be designed to be within the CDF cells just beyond the interior toe of the
containment berm slope. Effluent from each outlet structure will flow through a buried pipe under the
adjacent containment berm and continue through buried pipe outside of the berms. It is anticipated that
flow from each CDF will be combined into a single pipeline to the southeast corner of the facility property
for a single permitted outfall, with discharge to the unnamed drainage ditch for return to Bancroft Creek
and Fountain Lake. The design will determine the size, alignment, and installation requirements of the
effluent pipe. Access to the outlet structure for operation and maintenance will be by an elevated
personnel catwalk from the adjacent containment berm. The elevated catwalk is anticipated to be a pre-
fabricated and pre-engineered structure based on the design span from the berm to the structure for the
anticipated load of personnel only. Operation of the adjustable weir boards is anticipated to be through
mechanical means such as pulleys and cranks such that electrical power is not needed.
8.7 Dredge Material Settling Test
Bulk sediment and water samples were collected from Fountain Lake by Barr Engineering in 2013 and a
Long Tube Column Settling Test was performed. Test results provide sediment settling characteristics for
use in evaluating CDF parameters such as settling surface area and influent flow rate in relation to
achieving a target effluent concentration for total suspended solids (TSS). The laboratory data will be
analyzed for determination of settling characteristics. Obtained information will be used with the available
land area to evaluate influent flow rates that would provide suitable reduction in TSS in CDF effluent by
gravity settling without aid of chemical conditioning or active water treatment. The required effluent TSS
concentration will be set by MPCA through the Section 404 permit program.
![Page 23: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/23.jpg)
CDF DESIGN
CDF BODR - Final 160506 8-4
8.8 CDF Flow Pattern
Available land, existing topography, sediment settling characteristics, and anticipated influent flow rate will
be evaluated to design the CDF flow pattern. This will determine the locations of the dredge material
influent pipe and the weir outlet structure for each cell. The dredging contractor will be responsible for
installing and relocating, as necessary, the slurry discharge pipe into CDF cells. Following discharge of
dredge slurry into a CDF cell, sediment settling will proceed through gravity flow and separated water will
be returned to Fountain Lake. Use of slurry or water pumping equipment is not anticipated during normal
CDF operation.
![Page 24: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/24.jpg)
CDF BODR - Final 160506 9-1
9 WATER TREATMENT
Effluent from the CDF is considered the discharge of dredged material and is regulated by USACE under
Section 404 of the Clean Water Act. In Minnesota, the MPCA certifies the discharge of dredged material
complies with state water quality standards under Section 401 of the Clean Water Act. Sediment from
Fountain Lake will be transported to the CDF as a slurry where the sediment will settle in the CDF and the
water will return to Fountain Lake. Therefore, the water quality parameter of concern is TSS to ensure
removed sediment is not being returned to the lake. Initial correspondence with MPCA in August 2015
indicated that there is not a numeric standard, but the discharge must not contain “excessive suspended
solids.” Sediment settling characteristics from the single referenced column settling test will be evaluated
to estimate effluent TSS concentrations. TSS of the effluent will be monitored during CDF operation as
required by the obtained permit conditions. Ability to meet the established effluent TSS limit is anticipated
to be possible without the need of supplementary water treatment. Additional SRRWD water discharge
limits, if any, have not been identified at this time. A designated area will be reserved for the possible
installation of a temporary water treatment system if determined necessary in the future during CDF
operation.
![Page 25: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/25.jpg)
CDF BODR - Final 160506 10-1
10 SITE CONSTRUCTION
Site construction is anticipated to proceed with preparation and grading of CDF Cell 1, which will be used
first when dredging commences. Remaining cells will be constructed in a phased manner with CDF Cell 2
and then Cell 3. Development of the CDF cell areas will begin with site preparation and progress to
containment berm construction.
10.1 Site Preparation
The CDF areas will first be prepared through survey layout and staking according to design plans.
Stormwater management controls, such as silt fence, will be installed around the areas to be disturbed.
Site preparation will continue with clearing and grubbing of trees and vegetation within the planned
construction footprint. Topsoil will be stripped from the berm alignment and borrow source excavation
areas. Stripped topsoil will be stockpiled in an accessible area on site for use on the constructed berm
side slopes. Additional topsoil may be stripped from remaining areas within the CDF footprint if needed
based on cut/fill calculations or if segregation is desired for potential use. Topsoil quantities will be
estimated based on site investigation boring log stratigraphy.
Rough grading of the CDF interior is generally anticipated to ensure a predominant ground surface slope
in the direction of the outlet structure. Site enhancements for sediment dewatering through seepage
drains or lower permeability layers is not included the design. Along centerline base of the containment
berm alignment, a continuous inspection trench will be excavated at least 6 feet deep to observe
subsurface conditions directly below the berm focusing on unsuitable soil types or near surface
agricultural drain tiles. Any unsuitable soil types or drain tiles as determined by NRT and SRRWD will be
removed. The trench will be backfilled and compacted prior to berm construction.
10.2 Berm Construction
As site preparation activities progress, containment berms will be constructed. Berm construction will be
performed in compacted lifts until the target crest elevation is achieved.
10.2.1 Construction Documentation
Construction oversight is anticipated by a competent engineering professional to ensure construction
proceeds as intended in the plans and specifications. Actual site conditions will be observed and
documented as construction progresses. Operations will be documented through daily reports by the
earthwork contractor and oversight personnel. Facility documentation will be through record (i.e., as-built)
![Page 26: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/26.jpg)
SITE CONSTRUCTION
CDF BODR - Final 160506 10-2
documentation surveys and a construction completion report. Construction Quality Assurance (CQA) and
Quality Control (QC) requirements will be included in the construction specifications and may be
incorporated into a separate CQA document.
10.2.2 Construction Tolerances
The earthwork contractor will be required to provide adequate survey control to achieve horizontal and
vertical tolerances of +/- 0.1 feet. Compaction tolerances for containment berms will be based on berm
soil properties and will be monitored through moisture-density testing at a frequency dictated in the
construction specifications.
![Page 27: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/27.jpg)
CDF BODR - Final 160506 11-1
11 SITE OPERATIONS & PHASED DEVELOPMENT
Operation of the CDF will be outlined in a separate operation and maintenance plan that will be provided
to the selected dredging contractor who will operate the CDF during dredging. Dredging into the CDF is
anticipated to occur up to 5 years after initiating dredging of Fountain Lake. Following dredging, CDF cells
will be operated to minimize water retention, and operations will proceed in accordance with a separate
CDF closure plan, which will be prepared after evaluating options with SRRWD.
Operation, inspection, and maintenance will be performed or coordinated by SRRWD when dredging
operations are not taking place. The operation and maintenance plan will include provisions for
inspections, flow rates, outlet structure operation, effluent sampling, and berm maintenance.
Site development may be performed in phases based on factors such as permitting, land acquisition,
cost, and schedule. CDF Cell 1 will be constructed first, followed by Cells 2 and 3.
![Page 28: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/28.jpg)
CDF BODR - Final 160506 12-1
12 BENEFICIAL USE & LONG TERM CARE
The design includes passive separation for depositing the sediment in the CDF and further dewatering of
the deposited materials. Over time, it is estimated that water in the sediment will be reduced through
evaporation; active dewatering following dredging is not included in the current design. Long-term care
and ultimate use of deposited dredge material will be outlined in a separate document. Following the
completion of the dredging program, site closure options may include returning the site to agricultural use
or harvesting dredge material for beneficial use. The project lifetime of the CDF cells is anticipated to be
associated only with the Fountain Lake Restoration Project as defined in this BODR. Use of the CDF cells
for future dredging projects beyond this timeframe is not part of the design.
![Page 29: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/29.jpg)
CDF BODR - Final 160506 13-1
13 REFERENCES
Barr Engineering, March 2016, “Fountain Lake Dredging Confined Disposal Facility (CDF) Dam Break Analysis,” Technical Memorandum.
Barr Engineering, May 2014, “Draft Preliminary Engineering Report,” Fountain Lake Restoration
Barr Engineering, May 2009, “Draft Fountain Lake Sediment and Dredging Assessment,”
Casagrande, Arthur, June 1937, “Seepage Through Dams,” Journal of the New England Water Works Association.
Engineering Soil Testing, Inc., April 2016, Geotechnical Laboratory Testing Data: Unconfined Compressive Strength, Grain Size, Atterberg Limits, Moisture Content, Direct Shear.
Jones, Haugh, & Smith, April 22, 2016, “Certificate of Survey in NW1/4, E1/2 SW1/4, SE1/4 & SW1/4 NE1/4 Section 29-T103-R21W.”
MDNR, March 14, 2016, “RE: Fountain Lake – Dam Safety Regs,” Email Correspondence, Jason Boyle (MDNR) to Andrew Millspaugh, Andy Henschel, Omid Mohseni, and Janna Kieffer.
MPCA, August 4, 2015, “RE: 401 Water Quality Certification Question,” Email Correspondence, Jim Brist (MPCA) to Andrew Millspaugh.
MPCA, April 2014, “Managing Dredge Materials in the State of Minnesota.”
USACE, July 31, 2015, “Dredging and Dredged Material Management,” Engineering and Design, Manual EM1110-2-5025.
USACE, January 1, 2001, “Geotechnical Investigations,” Engineering and Design, Manual EM1110-1-1804
USACE, April 30, 2000, “Design and Construction of Levees,” Engineering and Design, Manual EM1110-2-1913
USGS, Earthquake Hazards Program, Minnesota Earthquake Information, www.earthquake.usgs.gov/earthquakes/states/?region=Minnesota, Accessed April 12, 2016.
WSB & Associates, April 2016, “Log of Test Boring,” Boring Logs for Geotechnical Site Investigation.
![Page 30: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/30.jpg)
FIGURES
![Page 31: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/31.jpg)
SITE
PROJECT NO.
FIGURE NO.
2248/4.0
1
DMD 05/05/16AMM
ATURALN
TESOURCERECHNOLOGY
AMMDRAWN: CHK'D: APP'D: DATE:04/13/16DATE: 05/05/16DATE:
SITE LOCATION
FOUNTAIN LAKE RESTORATION PROJECT
CONFINED DISPOSAL FACILITY
BASIS OF DESIGN REPORT
SHELL ROCK RIVER WATERSHED DISTRICT
ALBERT LEA, MINNESOTA
Copyright:© 2013 National Geographic Society, i-cubed
0
SCALE IN FEET
10002000
N
![Page 32: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/32.jpg)
I-90 W
I-90 E
74
0T
H A
VE
NU
E
237TH STREET
0
SCALE IN FEET
200400
N
1
2
3
0
12
40
1
2
5
0
1
2
6
0
1
2
4
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
4
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
5
0
1
2
5
0
1
2
6
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
3
0
1
2
4
0
1
2
3
0
1
2
4
0
1
2
3
0
1
2
3
0
1
2
4
0
1250
1
2
3
0
1
2
4
0
1
2
5
0
1230
1240
1
2
5
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
4
0
1
2
5
0
1
2
5
0
1
2
4
0
1
2
5
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
7
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
6
0
GAS LINE
OVERHEAD ELECTRIC LINE
EXISTING GRADE CONTOUR
MAJOR
EXISTING GRADE CONTOUR
MINOR
1250
FIBER OPTIC LINE
500 YEAR FLOOD
100 YEAR FLOOD
PARCEL LINES
WETLAND
CDF PARCEL LINE
SOURCE NOTES:
1. COORDINATE SYSTEM IS NAD 83 FREEBORN COUNTY, MINNOSOTA COUNTY SYSTEM (US FEET)
2. AERIAL IMAGE SOURCE: Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS,
USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
3. CDF PARCEL LINE, UTILITY LINES FROM JONES HAUGH SMITH ENGINEERS & SURVEYORS FILE 16-038.DWG.
4. EXISTING GROUND CONTOURS AND PARCEL LINES PROVIDED BY FREEBORN COUNTY VERTICAL DATUM
NAVD 88 (US SURVEY FOOT).
5. 100 YEAR AND 500 YEAR FLOODPLAIN LINES PROVIDED BY FEMA FLOOD MAP SERVICE CENTER:
HTTP://MSC.FEMA.GOV/PORTAL/ADVANCE SEARCH
6. WETLAND BOUNDARIES FROM WSB & ASSOCIATES, INC.
DRAINAGE
DITCH
DRAINAGE DITCH
CROSSING
WETLAND
POND
PROJECT NO.
2248/4.0
FIGURE NO.
2
04/13/16
RE
FE
RE
NC
E:
DR
AW
N B
Y:
CH
EC
KE
D B
Y:
AP
PR
OV
ED
B
Y:
DR
AW
IN
G N
O:
DA
TE
:
DA
TE
:
DM
D
.
DA
TE
:
AM
M05/05/16
AM
M
05/05/16
ATURALN
TESOURCERECHNOLOGY
Fig 2_S
ite Layout
FO
UN
TA
IN
L
AK
E R
ES
TO
RA
TIO
N P
RO
JE
CT
CO
NF
IN
ED
D
IS
PO
SA
L F
AC
IL
IT
Y
BA
SIS
O
F D
ES
IG
N R
EP
OR
T
SH
EL
L R
OC
K R
IV
ER
W
AT
ER
SH
ED
D
IS
TR
IC
T
AL
BE
RT
L
EA
, M
IN
NE
SO
TA
SIT
E LA
YO
UT
![Page 33: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/33.jpg)
I-90 W
I-90 E
74
0T
H A
VE
NU
E
237TH STREET
0
SCALE IN FEET
200400
N
1
2
3
0
12
40
1
2
5
0
1
2
6
0
1
2
4
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
4
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
5
0
1
2
5
0
1
2
6
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
3
0
1
2
4
0
1
2
3
0
1
2
4
0
1
2
3
0
1
2
3
0
1240
1
2
5
0
1
2
3
0
1
2
4
0
1
2
5
0
1230
1240
1
2
5
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
4
0
1
2
5
0
1
2
5
0
1
2
4
0
1
2
5
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
7
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
6
0
GAS LINE
OVERHEAD ELECTRIC LINE
EXISTING GRADE CONTOUR
MAJOR
EXISTING GRADE CONTOUR
MINOR
1250
PIEZOMETER
BORING
FIBER OPTIC LINE
500 YEAR FLOOD
100 YEAR FLOOD
PARCEL LINES
WETLAND
CDF PARCEL LINE
1
2
4
0
1
2
4
0
1
2
3
5
1
2
3
5
1
2
3
0
1
2
3
0
1
2
2
5
PB-3
PB-7
PB-8
PB-20
PB-18
PB-24
PB-14
PB-23
PB-11
PB-22
PB-17
PB-16
PB-10
PB-26
PB-32
PB-30
PB-27
PB-31
PB-35
PB-37
PB-44
PB-42
PB-45
PB-45
PB-47
PZ-1
1228.75
PZ-2
1237.35
PZ-6
1221.60
PZ-12
1225.70
PZ-9
1241.20
PZ-25
1228.70
PZ-33
1224.30
PZ-39
PZ-41
PZ-48
PZ-48
PZ-49
1219.00
1
2
2
5
1
2
2
0
1220
NOTE: DASHED LINE ON GROUNDWATER
CONTOURS IS INFERRED.
GROUNDWATER CONTOUR,
APRIL 13, 2016
GROUNDWATER FLOW
DIRECTION
DRAINAGE
DITCH
DRAINAGE DITCH
CROSSING
WETLAND
POND
SOURCE NOTES:
1. COORDINATE SYSTEM IS NAD 83 FREEBORN COUNTY, MINNOSOTA COUNTY SYSTEM (US FEET)
2. AERIAL IMAGE SOURCE: Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS,
USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
3. CDF PARCEL LINE, UTILITY LINES FROM JONES HAUGH SMITH ENGINEERS & SURVEYORS FILE 16-038.DWG.
4. EXISTING GROUND CONTOURS AND PARCEL LINES PROVIDED BY FREEBORN COUNTY VERTICAL DATUM
NAVD 88 (US SURVEY FOOT).
5. 100 YEAR AND 500 YEAR FLOODPLAIN LINES PROVIDED BY FEMA FLOOD MAP SERVICE CENTER:
HTTP://MSC.FEMA.GOV/PORTAL/ADVANCE SEARCH
6. WETLAND BOUNDARIES FROM WSB & ASSOCIATES, INC.
PROJECT NO.
2248/4.0
FIGURE NO.
3
04/13/16
RE
FE
RE
NC
E:
DR
AW
N B
Y:
CH
EC
KE
D B
Y:
AP
PR
OV
ED
B
Y:
DR
AW
IN
G N
O:
DA
TE
:
DA
TE
:
DM
D
.
DA
TE
:
AM
M05/05/16
AM
M
05/05/16
ATURALN
TESOURCERECHNOLOGY
Fig 3_S
oil B
oring Locations
FO
UN
TA
IN
L
AK
E R
ES
TO
RA
TIO
N P
RO
JE
CT
CO
NF
IN
ED
D
IS
PO
SA
L F
AC
IL
IT
Y
BA
SIS
O
F D
ES
IG
N R
EP
OR
T
SH
EL
L R
OC
K R
IV
ER
W
AT
ER
SH
ED
D
IS
TR
IC
T
AL
BE
RT
L
EA
, M
IN
NE
SO
TA
SO
IL B
OR
IN
G LO
CA
TIO
NS
![Page 34: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/34.jpg)
I-90 W
I-90 E
74
0T
H A
VE
NU
E
237TH STREET
0
SCALE IN FEET
200400
N
1
2
3
0
12
40
1
2
5
0
1
2
6
0
1
2
4
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
4
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
5
0
1
2
5
0
1
2
6
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
3
0
1
2
4
0
1
2
3
0
1
2
4
0
1
2
3
0
1
2
3
0
1
2
4
0
1250
1
2
3
0
1
2
4
0
1
2
5
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
4
0
1
2
5
0
1
2
5
0
1
2
4
0
1
2
5
0
1
2
5
0
1
2
6
0
1
2
7
0
1
2
7
0
1
2
3
0
1
2
4
0
1
2
5
0
1
2
6
0
POTENTIAL CDF CELL
LIMITS
GAS LINE
OVERHEAD ELECTRIC LINE
EXISTING GRADE CONTOUR
MAJOR
EXISTING GRADE CONTOUR
MINOR
1250
FIBER OPTIC LINE
500 YEAR FLOOD
100 YEAR FLOOD
PARCEL LINES
WETLAND
CDF PARCEL LINE
1
2
3
0
1240
1
2
5
0
POTENTIAL STAGING/
STOCKPILE/ STORMWATER
MANAGEMENT AREA (TO BE
DETERMINED BASED ON
PROPERTY PURCHASE)
DRAINAGE
DITCH
DRAINAGE DITCH
CROSSING
WETLAND
POND
SITE
ENTRANCE
CELL 1
29.4 ACRES
TOP OF BERM ELEV. = 1,251
POOL ELEVATION = 1,248
TOP OF SEDIMENT = 1246
SITE ACCESS
ROAD
SITE STAGING/
STOCKPILE AREA
POTENTIAL WATER
TREATMENT AREA
POTENTIAL WATER
TREATMENT AREA
CELL 2
12.6 ACRES
TOP OF BERM ELEV. = 1,247
POOL ELEVATION = 1,244
TOP OF SEDIMENT = 1242
CELL 3
7.7 ACRES
TOP OF BERM ELEV. = 1,255
POOL ELEVATION = 1,252
TOP OF SEDIMENT = 1250
SOURCE NOTES:
1. COORDINATE SYSTEM IS NAD 83 FREEBORN COUNTY, MINNOSOTA COUNTY SYSTEM (US FEET)
2. AERIAL IMAGE SOURCE: Source: Esri, DigitalGlobe, GeoEye, i-cubed, Earthstar Geographics, CNES/Airbus DS,
USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
3. CDF PARCEL LINE, UTILITY LINES FROM JONES HAUGH SMITH ENGINEERS & SURVEYORS FILE 16-038.DWG.
4. EXISTING GROUND CONTOURS AND PARCEL LINES PROVIDED BY FREEBORN COUNTY VERTICAL DATUM
NAVD 88 (US SURVEY FOOT).
5. 100 YEAR AND 500 YEAR FLOODPLAIN LINES PROVIDED BY FEMA FLOOD MAP SERVICE CENTER:
HTTP://MSC.FEMA.GOV/PORTAL/ADVANCE SEARCH
6. WETLAND BOUNDARIES FROM WSB & ASSOCIATES, INC.
PROJECT NO.
2248/4.0
FIGURE NO.
4
04/13/16
RE
FE
RE
NC
E:
DR
AW
N B
Y:
CH
EC
KE
D B
Y:
AP
PR
OV
ED
B
Y:
DR
AW
IN
G N
O:
DA
TE
:
DA
TE
:
DM
D
.
DA
TE
:
AM
M05/05/16
AM
M
05/05/16
ATURALN
TESOURCERECHNOLOGY
Fig 4_C
DF
S
ite D
evelopm
ent
FO
UN
TA
IN
L
AK
E R
ES
TO
RA
TIO
N P
RO
JE
CT
CO
NF
IN
ED
D
IS
PO
SA
L F
AC
IL
IT
Y
BA
SIS
O
F D
ES
IG
N R
EP
OR
T
SH
EL
L R
OC
K R
IV
ER
W
AT
ER
SH
ED
D
IS
TR
IC
T
AL
BE
RT
L
EA
, M
IN
NE
SO
TA
CD
F S
IT
E D
EV
ELO
PM
EN
T P
LA
N
![Page 35: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/35.jpg)
EDGE OF DRAINAGE DITCH
TOE OF BERM
CENTERLINE OF DITCH AND PARCEL LINE
EDGE OF DRAINAGE DITCH
3
1
3
1
PRE-CONSTRUCTION SURFACE
PRE-CONSTRUCTION
SURFACE
TOP OF BERM
ELEVATION
TOE OF BERM
EMBANKMENT
KEYWAY
P
L
TOE OF BERM
3
1
3
1
PRE-CONSTRUCTION
SURFACE
TOP OF BERM
ELEVATION
TOE OF BERM
EMBANKMENT
KEYWAY
PRE-CONSTRUCTION
SURFACE
P
L
NOT TO SCALE
1
TYPICAL CDF BERM CROSS-SECTION ALONG A DRAINAGE DITCH AND PARCEL LINE
PARCEL
LINE OFFSET
MIN. 50.0'
DRAINAGE
FEATURE
OFFSET
MIN. 16.5'
WHICHEVER IS GREATER
12.0' TYP.
VARIES
~0'-25'
12.0' TYP.
4.0'
2.0'
PARCEL
LINE OFFSET
MIN. 50.0'
UTILITY EASEMENT
(WIDTH VARIES)
WHICHEVER CONTROLS
STORMWATER
MANAGEMENT
DITCH
2
TYPICAL CDF BERM CROSS-SECTION ALONG A UTILITY EASEMENT AND PARCEL LINE
VARIES
~0'-25'
NOT TO SCALE
PROJECT NO.
2248/4.0
FIGURE NO.
5
04/13/16
RE
FE
RE
NC
E:
DR
AW
N B
Y:
CH
EC
KE
D B
Y:
AP
PR
OV
ED
B
Y:
DR
AW
IN
G N
O:
DA
TE
:
DA
TE
:
DM
D
.
DA
TE
:
AM
M05/05/16
AM
M05/05/16
ATURALN
TESOURCERECHNOLOGY
Fig 5_B
erm
S
ection D
etail
CD
F B
ER
M S
EC
TIO
N D
ET
AIL
FO
UN
TA
IN
L
AK
E R
ES
TO
RA
TIO
N P
RO
JE
CT
CO
NF
IN
ED
D
IS
PO
SA
L F
AC
IL
IT
Y
BA
SIS
O
F D
ES
IG
N R
EP
OR
T
SH
EL
L R
OC
K R
IV
ER
W
AT
ER
SH
ED
D
IS
TR
IC
T
AL
BE
RT
L
EA
, M
IN
NE
SO
TA
![Page 36: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/36.jpg)
TABLES
![Page 37: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/37.jpg)
CDF Pre-Design Geotechnical Investigation Testing PlanShell Rock River Watershed DistrictFountain Lake Restoration ProjectAlbert Lea, MN
DRAFT
CDF# of Borings for
investigationTarget Boring
Depth (ft) Testing ParametersASTM D1586
SPTASTM D1587Shelby Tube
ASTM D2216Water Content
ASTM D421/422Gradation
ASTM D4318 Atterberg
ASTM D2435 Consolidation
ASTM D2166 Unconfined
Compressive Strength
ASTM D4767 Triaxial Shear
ASTM D2937In Situ Density
ASTM D698Compaction Piezometer
West Cell 8 25 80 8 16 4 4 1 7 1 8 - 5
SW1 Cell 5 25 50 5 10 3 3 1 4 1 5 - 3
SW2 Cell 5 25 50 5 10 3 3 1 4 1 5 - 3
TOTALS 180 18 36 10 10 3 15 3 18 - 11
CDF# of Borings for
investigationTarget Boring
Depth (ft) Testing ParametersASTM D1586
SPT Shelby TubeASTM D2216Water Content Gradation Atterberg Consolidation
Unconfined Compressive
StrengthASTM D2850 / D3080 Shear In Situ Density
ASTM D698Compaction Piezometer
West Cell 9 25 90 - 18 - - - - 2 - 3 -
SW1 Cell 8 25 80 - 16 - - - - 2 - 2 -
SW2 Cell 5 25 50 - 10 - - - - 2 - 2 -
TOTALS 220 - 44 - - - - 6 - 7
CDF# of Borings for
investigationTarget Boring
Depth (ft) Testing ParametersASTM D1586
SPT Shelby Tube water content water content Gradation Atterberg
Unconfined Compressive
Strength Consolidation Shear Compaction Piezometer
West Cell 6 15 36 - - - - - - - - - -
SW1 Cell 1 15 6 - - - - - - - - - -
SW2 Cell 2 15 12 - - - - - - - - - -
TOTALS 54 - - - - - - - - - -
Testing Summary
Testing Summary
Testing SummaryGeneral CDF Storage Area Characterization
Split Spoon Standard Penetration Test▪ SPT N-Value (ASTM D1586) - 2.5 ft intervals.▪ USCS Visual Classification (ASTM D2487)- All split spoon samples for general classification▪ Pocket Penetrometer / Torvane - All Intact samples for general strength▪ Assume that visual classification can correlate to geotechnical testing properties of materials tested in berm alignment and excavation areas.
Split Spoon Standard Penetration Test▪ SPT N-Value (ASTM D1586) - 2.5 ft intervals.▪ USCS Visual Classification (ASTM D2487)- All split spoon samples for general classification▪ Pocket Penetrometer / Torvane - All Intact samples for general strength▪ Water Content (ASTM D2216) - Assume 2 per boring (above/below water table) for general classification▪ Compaction - Standard Proctor (ASTM D698) - 5-point tests of remolded soils for berm construction.▪ Shear - Triaxial compression (ASTM D2850 Unconsolidated Undrained - fine grained soils) and/or Direct (ASTM D3080 - coarse grained soils), Assume 1 for each soil type per CDF.
Split Spoon Standard Penetration Test▪ SPT N-Value (ASTM D1586) - 2.5 ft intervals.▪ USCS Visual Classification (ASTM D2487)- All split spoon samples for general classification▪ Pocket Penetrometer / Torvane - All Intact fine-grained samples for general strength▪ Water Content (ASTM D2216) - Assume 2 per boring (above/below water table) for general classification▪ Gradation: Sieve & Hydrometer (ASTM D421/422) - Assume 1 from 50% of borings▪ Atterberg Limits (ASTM D4318) - paired with moisture samples on fine grained material for general classification. Assume 1 test from 50% of borings.▪ Undisturbed fine-grained sample collection (ASTM D1587 - Shelby Tube) - for consolidation and shear testing if fine-grained material is present. Assume 1 per boring.▪ In situ density (ASTM D2937) on collected undisturbed samples for unit weight determination.▪ Consolidation (ASTM D2435) - fine grained material only for design of berm foundation/construction settlement. Assume 1 per CDF.▪ Shear - Triaxial compression (ASTM D4767 - fine grained) - Consolidated undrained test (3-point) with pore pressure measurements. Test 1 shelby tube per CDF.▪ Unconfined Compressive Strength (ASTM D2166) - fine grained material from remaining shelby tube samples.▪ Temporary Piezometer for groundwater level observation
Cell Berm Perimeter
Excavation / Berm Material Borrow Areas
Geotechnical Investigation Plan DRAFT 160202 Page 1 of 1
![Page 38: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/38.jpg)
APPENDIX A
PROJECT SCHEDULE
![Page 39: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/39.jpg)
ID Task Name Duration Start Finish Predecessors1 CDF Site Development / Due Diligence 26 days Fri 3/11/16 Fri 4/15/162 Board Authorization ‐ NTP 1 day Fri 3/11/16 Fri 3/11/163 Site Geotechnical Investigation & Survey 24 days Mon 3/14/16 Thu 4/14/16 24 Establish Site Property Boundaries & Easements 1 day Fri 4/15/16 Fri 4/15/16 35 Final Design of CDF / Plans & Specs 83 days Mon 4/11/16 Wed 8/3/166 CDF BODR Report 15 days Mon 4/11/16 Fri 4/29/16 4FS‐5 days7 Final Berm Configuration 10 days Mon 4/18/16 Fri 4/29/16 4,6FF8 Stability Analysis 10 days Mon 4/25/16 Fri 5/6/16 7FS‐5 days9 District Review of BODR / Final Configuration *** 5 days Mon 5/2/16 Fri 5/6/16 710 Update BARR Inundation Analysis 14 days Mon 5/2/16 Thu 5/19/16 711 Stormwater and Access Design 10 days Mon 5/9/16 Fri 5/20/16 912 Independent QA Review of CFD Plan ‐ 5 days Fri 5/20/16 Thu 5/26/16 1013 Final Design & Specifications 42 days Mon 5/9/16 Tue 7/5/1614 Complete Plans / Drawing Set 20 days Mon 5/9/16 Fri 6/3/16 915 Technical Specifications 20 days Mon 5/9/16 Fri 6/3/16 916 Contract From ‐ Bid Tables 20 days Mon 5/9/16 Fri 6/3/16 917 Update CDF cost estimates (phased construction)10 days Mon 5/16/16 Fri 5/27/16 14SS+5 days
18 Advertise for Bids / Bidding Period 22 days Mon 6/6/16 Tue 7/5/16 16,15,1419 CDF Permitting 63 days Fri 5/6/16 Wed 8/3/1620 Dam Safety Permit 54 days Fri 5/20/16 Wed 8/3/16 1021 Dredge Material Disposal Notice 30 days Fri 5/27/16 Thu 7/7/16 1222 MPCA ?Section 404 & 401 Permits 42 days Fri 5/27/16 Mon 7/25/16 1223 Construction Stormwater Permit (over 1 AC) 21 days Mon 5/23/16 Mon 6/20/16 1124 Local & Other Permits (BWSR, Cond. Use) 30 edays Fri 5/6/16 Sun 6/5/16 925 Public Hearing / Board Meeting / Establish
Project15 days Mon 6/6/16 Fri 6/24/16 24
26 2016 CDF Facility Construction 81 days Wed 7/6/16 Wed 10/26/1627 Award of CDF Construction Contract 21 days Wed 7/6/16 Wed 8/3/16 1828 Mobilization 15 days Thu 8/4/16 Wed 8/24/16 27,2029 Cell 1 CDF Earthworks 45 days Thu 8/25/16 Wed 10/26/16 2830 Cell 2 Earthworks 40 edays Sat 4/1/17 Thu 5/11/17 2931 Cell 3 Earthworks 30 edays Thu 5/11/17 Sat 6/10/17 3032 Begin Operation & Maintenance of Sediment
Facility ‐ Ongoing until Closed1 day Mon 4/3/17 Mon 4/3/17
33 Dredging Procurement & Permitting 123 days Mon 4/18/16 Wed 10/5/1634 Determine staging areas / pipeline access way
/ alignment10 days Mon 4/18/16 Fri 4/29/16 4
35 Determine dredging restrictions (if any) 5 days Fri 5/20/16 Thu 5/26/16 1036 Dredge Prism Development 20 days Mon 4/18/16 Fri 5/13/16 437 Performance Specification for Dredging,
operation of disposal site and water treatment 30 edays Thu 7/7/16 Sat 8/6/16 21
38 Issue RFP / Bidding Period 30 edays Sat 8/6/16 Mon 9/5/16 3739 Proposal Evaluation & Award 30 edays Mon 9/5/16 Wed 10/5/16 3840 Dredge Permitting 42 days Thu 5/26/16 Mon 7/25/1641 Env. Assessment Worksheet 60 edays Thu 5/26/16 Mon 7/25/16 1242 MDNR Public Waters Work Permit 60 edays Thu 5/26/16 Mon 7/25/16 1243 Water Appropriation Permit 60 edays Thu 5/26/16 Mon 7/25/16 1244 Lake Dredging Season 1 7 mons Thu 4/13/17 Wed 10/25/17 29FS+6 mons
CDF Site Development / Due Diligence
3/11
Site Geotechnical Investigation & Survey
4/15
CDF BODR Report
Final Berm Configuration
Stability Analysis
District Review of BODR / Final Configuration ***
Update BARR Inundation Analysis
Stormwater and Access Design
Independent QA Review of CFD Plan ‐
Complete Plans / Drawing Set
Technical Specifications
Contract From ‐ Bid Tables
Update CDF cost estimates (phased construction)
Advertise for Bids / Bidding Period
CDF Permitting
Dam Safety Permit
Dredge Material Disposal Notice
MPCA ?Section 404 & 401 Permits
Construction Stormwater Permit (over 1 AC)
Local & Other Permits (BWSR, Cond. Use)
Public Hearing / Board Meeting / Establish Project
2016 CDF Facility Construction
Award of CDF Construction Contract
Mobilization
Cell 1 CDF Earthworks
Cell 2 Earthworks
Cell 3 Earthworks
Begin Operation & Maintenance of Sediment Facility ‐ Ongoing until Closed
Dredging Procurement & Permitting
Determine staging areas / pipeline access way / alignment
Determine dredging restrictions (if any)
Dredge Prism Development
Performance Specification for Dredging, operation of disposal site and water treatment
Issue RFP / Bidding Period
Proposal Evaluation & Award
Dredge Permitting
Env. Assessment Worksheet
MDNR Public Waters Work Permit
Water Appropriation Permit
LaLake Dredging Season 1
Feb '16 Mar '16 Apr '16 May '16 Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 N
Task
Split
Milestone
Summary
Project Summary
Manual Task
Duration‐only
Manual Summary
Progress
critical
Schedule Estimate ‐ Through Dredging Season 1 only
Shell Rock River Watershed DistrictFountain Lake Restoration
CDF Construction and Dredging Schedule
Wed 4/13/16
Page 1 of 1
Project: Preliminary Project Schedule v09Date: Wed 4/13/16
![Page 40: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/40.jpg)
APPENDIX B
SOIL BORING LOGS
![Page 41: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/41.jpg)
34
3 1/4" HSA 0' - 22'
OH
CL
CL
CL
Topsoil
Fine Alluvium
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SH
SB
SB
SB
SB
SB
6
4
5
6
7
8
7
8
6
ORGANIC CLAY, black, moist
LEAN CLAY, grayish brown, mottled, wet,very soft
LEAN CLAY, gray to reddish brown, mottled,wet, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/21/2016 END: 3/21/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22243:00 pm3/21/2016 None
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 1PAGE 1 OF 1SURFACE ELEVATION: 1232.3 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
DESCRIPTION OF MATERIAL
![Page 42: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/42.jpg)
25
3 1/4" HSA 0' - 22'
OL
SM
SC
SP-SM
ML
CL
Topsoil
Coarse Alluvium
Mixed Alluvium
Coarse Alluvium
Fine Alluvium
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
NR
SB
SB
SH
5
4
4
7
17
11
6
6
ORGANIC SILT, black, moist, loose
SILTY SAND, dark brown, wet, very loose
CLAYEY SAND, dark brown, wet, very soft
SAND WITH SILT, fine grained, brown, wet,loose to medium dense
SILT, gray, moist, medium dense
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray, wet, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/21/2016 END: 3/21/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
222412:50 pm3/21/2016 5.9 1235.8
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 2PAGE 1 OF 1SURFACE ELEVATION: 1241.7 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
DESCRIPTION OF MATERIAL
![Page 43: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/43.jpg)
14
3 1/4" HSA 0' - 22'
OH
CL
CL
CL
Topsoil
Glacial Till
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SH
SB
SB
SB
SB
SB
SB
6
4
7
9
4
6
7
8
8
ORGANIC CLAY, black, moist, soft
LEAN CLAY WITH SAND AND GRAVEL,brown to grayish brown, mottled, wet, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to grayish brown, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, firm to very soft tosoft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/28/2016 END: 3/28/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 21241:00 pm3/28/2016 None
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 3PAGE 1 OF 1SURFACE ELEVATION: 1230.1 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
DESCRIPTION OF MATERIAL
![Page 44: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/44.jpg)
22
3 1/4" HSA 0' - 22'
OH
CL
SP
CL
SP
CL
Topsoil
Glacial Till
Coarse Alluvium
Glacial Till
Coarse Alluvium
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SB
SB
SB
SH
4
4
4
4
1
1
3
4
3
ORGANIC CLAY, black, moist, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, grayish brown, mottled, wet, verysoft
SAND WITH A LITTLE GRAVEL, medium tofine grained, gray, water bearing, very loose
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, wet, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, fine to medium grained, gray, waterbearing, very loose
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, wet, very soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/21/2016 END: 3/21/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22245:10 pm3/21/2016 5.1 1222.8
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 6PAGE 1 OF 1SURFACE ELEVATION: 1227.9 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
DESCRIPTION OF MATERIAL
![Page 45: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/45.jpg)
17
3 1/4" HSA 0' - 14.5'
CL
CL
CL
Glacial Till
Glacial Till
Glacial Till
1
2
3
4
5
6
7
SB
SB
SB
SB
SB
SB
SB
7
12
15
9
15
8
10
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown to reddish brown, mottled,moist, soft to firm (Sod at grade)
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown, moist, firm, a layer ofgrayish brown Lean Clay at 6-7'
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, wet, soft to firm
End of Boring 16.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/11/2016 END: 3/11/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
14.5 13.7161:50 pm3/11/2016 13.5 1221.6
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 7PAGE 1 OF 1SURFACE ELEVATION: 1235.1 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
DESCRIPTION OF MATERIAL
![Page 46: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/46.jpg)
18
3 1/4" HSA 0' - 14.5'
OH
CL
SC
CL
Topsoil
Glacial Till
Mixed Alluvium
Glacial Till
1
2
3
4
5
6
7
SB
SB
SB
SB
SB
SB
SB
5
3
3
5
3
4
6
ORGANIC CLAY, black, moist, soft to verysoft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to reddish brown, mottled, wet,very soft
CLAYEY SAND WITH A LITTLE GRAVEL,brown to reddish brown, mottled, wet, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray, mottled, wet, very soft to soft
End of Boring 16.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/14/2016 END: 3/14/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
14.5 11161:45 pm3/14/2016 8.0 1218.5
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 8PAGE 1 OF 1SURFACE ELEVATION: 1226.5 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
1203
DESCRIPTION OF MATERIAL
![Page 47: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/47.jpg)
23
3 1/4" HSA 0' - 22'
OH
CL
CL
Topsoil
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SH
SB
SB
SB
SB
SB
SB
SB
7
5
3
5
6
6
7
8
10
ORGANIC CLAY, black, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to grayish brown, mottled, wet,very soft to soft, a few lenses of Sand
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft to firm
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/17/2016 END: 3/17/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
222412:40 pm3/17/2016 7.5 1237.4
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 9PAGE 1 OF 1SURFACE ELEVATION: 1244.9 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
DESCRIPTION OF MATERIAL
![Page 48: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/48.jpg)
18
3 1/4" HSA 0' - 22'
CL
CL
CL
Fill
Glacial Till
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SB
SB
SB
SB
8
5
7
9
14
4
7
8
5
6
FILL, a mixture of Lean Clay, Organic Clay,brown, gray, black
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, grayish brown to reddish brown,mottled, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown to reddish brown, mottled,moist, firm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL,dark gray, wet, very soft to soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/11/2016 END: 3/11/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 14.3241:15 pm3/11/2016 None
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 10PAGE 1 OF 1SURFACE ELEVATION: 1243.9 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
DESCRIPTION OF MATERIAL
![Page 49: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/49.jpg)
24
3 1/4" HSA 0' - 14.5'
OH
CL
CL
Topsoil
Glacial Till
Glacial Till
1
2
3
4
5
6
7
SB
SB
SB
SB
SB
SB
SB
5
3
5
6
6
4
5
ORGANIC CLAY, black, wet, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, grayish brown to reddish brown,mottled, wet, very soft to soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft to very soft tosoft
End of Boring 16.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/14/2016 END: 3/14/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
14.5 141612:05 pm3/14/2016 None
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 11PAGE 1 OF 1SURFACE ELEVATION: 1228.9 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
DESCRIPTION OF MATERIAL
![Page 50: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/50.jpg)
24
3 1/4" HSA 0' - 22'
OH
CL
SM
CL
CL
Topsoil
Glacial Till
Coarse Alluvium
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SH
SB
SB
SB
5
6
6
5
5
6
6
8
6
ORGANIC CLAY, black, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, grayish brown, mottled, wet, soft
SILTY SAND WITH A LITTLE GRAVEL,gray, wet, loose
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, grayish brown, mottled, wet, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/22/2016 END: 3/22/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22245:25 pm3/22/2016 13.2 1216.1
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 12PAGE 1 OF 1SURFACE ELEVATION: 1229.3 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
DESCRIPTION OF MATERIAL
![Page 51: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/51.jpg)
15
3 1/4" HSA 0' - 14.5'
OL
CL
CL
CL
CL
Topsoil
Glacial Till
Glacial Till
Glacial Till
Glacial Till
1
2
3
4
5
6
7
SB
SB
SB
SB
SB
SB
SB
5
4
4
6
8
6
8
ORGANIC CLAY, black, moist
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to reddish brown, mottled, wet,very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, reddish brown, mottled, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark grayish brown, mottled, moist,soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
End of Boring 16.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/14/2016 END: 3/14/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
14.5 141612:55 pm3/14/2016 None
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 14PAGE 1 OF 1SURFACE ELEVATION: 1227.4 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
1203
DESCRIPTION OF MATERIAL
![Page 52: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/52.jpg)
17
3 1/4" HSA 0' - 22'
OL
CL
SC
CL
CL
Topsoil
Glacial Till
Mixed Alluvium
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SB
SB
SB
SB
9
8
6
5
8
10
11
6
4
4
ORGANIC CLAY, black, moist, firm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to reddish brown, mottled,moist, soft
CLAYEY SAND, brown, moist, firm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray to red, mottled, moist, firm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray, wet, soft to very soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/11/2016 END: 3/11/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
24 22.22411:55 am3/11/2016 20.8 1236.4
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 16PAGE 1 OF 1SURFACE ELEVATION: 1257.2 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1256
1255
1254
1253
1252
1251
1250
1249
1248
1247
1246
1245
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
DESCRIPTION OF MATERIAL
![Page 53: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/53.jpg)
36
3 1/4" HSA 0' - 22'
CL
SC
CL
CL
Fine Alluvium
Mixed Alluvium
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SH
SB
SB
SB
SB
5
5
8
9
9
9
7
6
5
LEAN CLAY, brown to grayish brown,mottled, moist, soft
CLAYEY SAND WITH A LITTLE GRAVEL,brown to grayish brown,mottled, moist, soft tofirm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown to grayish brown, mottled,wet, firm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, firm to soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/28/2016 END: 3/28/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 14.32411:30 am3/28/2016 7.5 1241.9
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 17PAGE 1 OF 1SURFACE ELEVATION: 1249.4 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1248
1247
1246
1245
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
DESCRIPTION OF MATERIAL
![Page 54: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/54.jpg)
14
3 1/4" HSA 0' - 22'
CL
CL
SP
Glacial Till
Glacial Till
Coarse Alluvium
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SH
SB
SB
SB
SB
SB
SB
4
5
3
7
6
9
8
8
7
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown, wet, very soft to soft to verysoft to soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft to firm to soft
SAND, fine grained, gray, water bearing, loose
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/14/2016 END: 3/14/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 19.1243:40 pm3/14/2016 15.8 1220.7
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 18PAGE 1 OF 1SURFACE ELEVATION: 1236.5 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
DESCRIPTION OF MATERIAL
![Page 55: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/55.jpg)
40
3 1/4" HSA 0' - 22'
CL
CL
CL-CH
CH
CL
SC
CL
Topsoil
Fine Alluvium
Fine Alluvium
Fine Alluvium
Fine Alluvium
Mixed Alluvium
Fine Alluvium
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SB
SB
SB
SB
6
8
7
3
4
4
3
3
6
7
LEAN CLAY, dark brown, moist, soft, a fewOrganics
LEAN CLAY, brown to grayish brown,mottled, wet, soft, a layer of Silty Sand 6-7'
LEAN CLAY, gray to grayish brown, mottled,wet, very soft
FAT CLAY, dark gray to reddish brown,mottled, wet, very soft
LEAN CLAY, dark gray, wet, very soft
CLAYEY SAND WITH A LITTLE GRAVEL,dark gray, moist, soft
LEAN CLAY, grayish brown, mottled, moist,soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/28/2016 END: 3/28/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 19.5242:10 pm3/28/2016 18.8 1229.6
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 20PAGE 1 OF 1SURFACE ELEVATION: 1248.4 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1247
1246
1245
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
DESCRIPTION OF MATERIAL
![Page 56: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/56.jpg)
14
3 1/4" HSA 0' - 22'
OL
SC
CL
CL
Topsoil
Mixed Alluvium
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SH
SB
SB
SB
SB
SB
5
6
12
9
15
9
9
7
6
ORGANIC CLAY, black, moist, soft
CLAYEY SAND A LITTLE GRAVEL, brown,mottled, moist, firm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown to reddish brown, mottled,moist, firm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray to red, moist, firm to soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/17/2016 END: 3/17/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 21.1242:40 pm3/17/2016 19.5 1223.2
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 22PAGE 1 OF 1SURFACE ELEVATION: 1242.7 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
DESCRIPTION OF MATERIAL
![Page 57: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/57.jpg)
15
3 1/4" HSA 0' - 22'
OL
CL
CL
CL
Topsoil
Glacial Till
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SH
SB
SB
SB
SB
SB
SB
SB
6
6
10
10
7
7
7
9
7
ORGANIC CLAY, black, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to reddish brown, mottled,moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown, moist, firm
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, firm to soft to firmto soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/22/2016 END: 3/22/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 21.82411:20 pm3/22/2016 None
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 23PAGE 1 OF 1SURFACE ELEVATION: 1231.5 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
DESCRIPTION OF MATERIAL
![Page 58: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/58.jpg)
12
3 1/4" HSA 0' - 22'
CL
SM
SM
SM
CL
CL-CH
SM
Topsoil
Coarse Alluvium
Coarse Alluvium
Coarse Alluvium
Fine Alluvium
Fine Alluvium
Coarse Alluvium
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SB
SB
SH
SB
5
9
11
9
9
4
6
3
5
LEAN CLAY, dark brown, moist, soft, a fewOrganics
SILTY SAND WITH GRAVEL, brown, moist,loose
SILTY SAND WITH A LITTLE GRAVEL,gray, moist, medium dense
SILTY SAND WITH GRAVEL, brown, moist,loose
LEAN CLAY, brown to reddish brown,mottled, wet, firm to very soft to soft
LEAN CLAY, dark gray, wet, very soft
SILTY SAND, gray, water bearing, loose
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/28/2016 END: 3/28/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 7.5244:05 pm3/28/2016 18.4 1231.7
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 24PAGE 1 OF 1SURFACE ELEVATION: 1250.1 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1249
1248
1247
1246
1245
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
DESCRIPTION OF MATERIAL
![Page 59: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/59.jpg)
18
3 1/4" HSA 0' - 22'
OL
CL
CL
CL-CH
Topsoil
Mixed Alluvium
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SH
SB
SB
SB
SB
SB
SB
6
3
5
7
7
7
8
9
10
ORGANIC CLAY, black, moist, soft to verysoft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, grayish brown to reddish brown,mottled, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
LEAN CLAY, gray, wet, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/17/2016 END: 3/17/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22245:05 pm3/17/2016 17.0 1212.7
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 25PAGE 1 OF 1SURFACE ELEVATION: 1229.7 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
DESCRIPTION OF MATERIAL
![Page 60: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/60.jpg)
17
3 1/4" HSA 0' - 22'
OLCL
CL
CL
Glacial TillGlacial Till
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SH
SB
SB
SB
SB
SB
SB
4
6
6
5
5
7
7
9
8
ORGANIC CLAYLEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to grayish brown, mottled,moist, very soft to soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark brown to grayish brown,mottled, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, firm to soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/29/2016 END: 3/29/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 172412:10 pm3/29/2016 12.6 1230.7
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 26PAGE 1 OF 1SURFACE ELEVATION: 1243.3 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
DESCRIPTION OF MATERIAL
![Page 61: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/61.jpg)
40
3 1/4" HSA 0' - 22'
OL
CL
CL
CL-CH
Topsoil
Fine Alluvium
Fine Alluvium
Fine Alluvium
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SH
SB
SB
SB
SB
2
7
7
5
6
5
4
3
3
ORGANIC CLAY, black, wet, very soft
LEAN CLAY, grayish brown, mottled, wet,soft
LEAN CLAY, gray to reddish brown, mottled,moist, soft
LEAN CLAY, dark gray, wet, very soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/29/2016 END: 3/29/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 21.82411:55 am3/29/2016 21.6 1233.1
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 27PAGE 1 OF 1SURFACE ELEVATION: 1254.7 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1254
1253
1252
1251
1250
1249
1248
1247
1246
1245
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
DESCRIPTION OF MATERIAL
![Page 62: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/62.jpg)
52
3 1/4" HSA 0' - 22'
OLCL
ML
CL
CL
CH
TopsoilFine Alluvium
Fine Alluvium
Fine Alluvium
Fine Alluvium
Fine Alluvium
1
2
3
4
5
6
7
8
9
10
SB
SB
SH
SB
SB
SB
SB
SB
SB
SB
4
9
10
6
3
3
3
3
2
ORGANIC CLAY, black, moist, very softLEAN CLAY, brown to reddish brown,mottled, moist, very soft to firm
SILT, brown to reddish brown, mottled, moist,loose
LEAN CLAY, reddish brown to gray, mottled,wet, soft
LEAN CLAY, gray to reddish brown, mottled,wet, very soft
FAT CLAY, dark gray, wet, very soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/29/2016 END: 3/29/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 21.32410:45 am3/29/2016 21.0 1227.9
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 30PAGE 1 OF 1SURFACE ELEVATION: 1248.9 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1248
1247
1246
1245
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
DESCRIPTION OF MATERIAL
![Page 63: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/63.jpg)
25
3 1/4" HSA 0' - 22'
OLCL
CL
SC
CL
Fine AlluviumFine Alluvium
Fine Alluvium
Mixed Alluvium
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SH
SB
SB
SB
SB
SB
4
6
5
4
7
8
7
8
11
ORGANIC CLAYLEAN CLAY, brown to grayish brown,mottled, wet, very soft to soft, a few lenses ofSand
LEAN CLAY, gray to reddish brown, mottled,wet, a few lenses of Sand, very soft to soft
CLAYEY SAND, brown, saturated, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft to firm
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/29/2016 END: 3/29/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 16.2244:45 pm3/29/2016 14.4 1230.6
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 31PAGE 1 OF 1SURFACE ELEVATION: 1245 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
DESCRIPTION OF MATERIAL
![Page 64: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/64.jpg)
19
3 1/4" HSA 0' - 14.5'
OL
CL
CL
Topsoil
Glacial Till
Glacial Till
1
2
3
4
5
6
7
SB
SB
SB
SB
SB
SB
SB
4
2
3
3
3
4
5
ORGANIC CLAY, black, moist, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to grayish brown, mottled, wet,very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, wet, very soft to soft
End of Boring 16.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/14/2016 END: 3/14/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
14.5 19.5165:00 pm3/14/2016 5.5 1222.4
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 32PAGE 1 OF 1SURFACE ELEVATION: 1227.9 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
DESCRIPTION OF MATERIAL
![Page 65: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/65.jpg)
13
3 1/4" HSA 0' - 22'
CL
CL
CL
CL
Topsoil
Glacial Till
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SH
SB
SB
SB
SB
SB
5
4
4
6
6
6
7
8
7
LEAN CLAY, dark brown, moist, soft to verysoft, a few Organics
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown to reddish brown, mottled,moist, soft
LEAN CLAY WITH SAND, brown to grayishbrown, mottled, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/25/2016 END: 3/25/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
222412:05 pm3/25/2016 15.0 1212.1
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 33PAGE 1 OF 1SURFACE ELEVATION: 1227.1 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
1203
DESCRIPTION OF MATERIAL
![Page 66: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/66.jpg)
26
3 1/4" HSA 0' - 22'
OL
CL
ML
CL
CL
Topsoil
Fine Alluvium
Fine Alluvium
Fine Alluvium
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SB
SB
SB
SB
5
4
9
8
8
8
6
3
4
2
ORGANIC CLAY, black, moist, soft to verysoft
LEAN CLAY, brown, moist, soft
SILT, brown to grayish brown, mottled, wet,loose
LEAN CLAY, brown to grayish brown,mottled, wet, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft to very soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/29/2016 END: 3/29/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 13.8242:25 pm3/29/2016 12.9 1246.2
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 35PAGE 1 OF 1SURFACE ELEVATION: 1259.1 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1258
1257
1256
1255
1254
1253
1252
1251
1250
1249
1248
1247
1246
1245
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
DESCRIPTION OF MATERIAL
![Page 67: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/67.jpg)
38
3 1/4" HSA 0' - 22'
OL
CL
CL-CH
CL
SM
CL
Topsoil
Fine Alluvium
Fine Alluvium
Fine Alluvium
Coarse Alluvium
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SH
SB
SB
SB
SB
SB
SB
3
4
7
2
4
4
2
10
6
ORGANIC CLAY, black, moist, very soft
LEAN CLAY, brown to grayish brown,mottled, moist, very soft to soft
LEAN CLAY, gray, wet, very soft
LEAN CLAY, gray, moist, very soft, a fewlenses of Sand
SILTY SAND WITH GRAVEL, gray, wet towater bearing at 19.7', very loose to loose
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/29/2016 END: 3/29/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 6.82412:00 pm3/29/2016 19.7 1221.4
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 37PAGE 1 OF 1SURFACE ELEVATION: 1241.1 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
DESCRIPTION OF MATERIAL
![Page 68: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/68.jpg)
27
3 1/4" HSA 0' - 22'
OL
CL
CL
CL
SP
Glacial Till
Glacial Till
Glacial Till
Glacial Till
Coarse Alluvium
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SH
SB
SB
SB
SB
SB
SB
1
1
2
5
3
4
8
8
7
ORGANIC CLAY, black, wet, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray, mottled, wet, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, grayish brown, moist, soft to verysoft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, very soft to soft
SAND WITH A LITTLE GRAVEL, fine tomedium grained, water bearing, loose
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/25/2016 END: 3/25/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22242:30 pm3/25/2016 1.0 1237.9
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 39PAGE 1 OF 1SURFACE ELEVATION: 1238.9 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
55 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
DESCRIPTION OF MATERIAL
![Page 69: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/69.jpg)
52
3 1/4" HSA 0' - 22'
CL
PT
PT
SM
SP-SM
CL
Topsoil
Swamp Deposits
Swamp Deposits
Coarse Alluvium
Coarse Alluvium
Glacial Till
1
2
34
5
6
7
8
9
10
11
SB
SB
SBSH
SB
SB
SB
SB
SB
SB
SB
2
2
1
1
WH
WH
WH
5
5
5
LEAN CLAY, dark brown, moist, very soft
PEAT, black, wet, very soft
MUCK, gray, wet
SILTY SAND WITH A LITTLE GRAVEL,gray, water bearing, loose
SAND WITH SILT AND WITH GRAVEL,medium to coarse grained, gray, water bearing,loose
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, wet, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/23/2016 END: 3/23/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
222410:05 am3/23/2016 3.8 1230.2
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 41PAGE 1 OF 1SURFACE ELEVATION: 1234 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
56 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
DESCRIPTION OF MATERIAL
![Page 70: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/70.jpg)
17
3 1/4" HSA 0' - 22'
CL
SM
CL
CL
Fine Alluvium
Coarse Alluvium
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SB
SB
SB
SB
4
6
7
8
11
7
6
8
12
11
LEAN CLAY, brown to reddish brown,mottled, moist, very soft to soft
SILTY SAND WITH A LITTLE GRAVEL,grayish brown, water bearing, at 10' a fewlenses of Lean Clay
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to grayish brown, mottled,moist
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, firm
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/29/2016 END: 3/29/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 6.5243:25 pm3/29/2016 6.0 1238.5
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 42PAGE 1 OF 1SURFACE ELEVATION: 1244.5 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
56 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1244
1243
1242
1241
1240
1239
1238
1237
1236
1235
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
DESCRIPTION OF MATERIAL
![Page 71: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/71.jpg)
39
3 1/4" HSA 0' - 22'
CL
CL
CL
ML
CL
SM
CL
Topsoil
Glacial Till
Fine Alluvium
Fine Alluvium
Fine Alluvium
Coarse Alluvium
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SH
SB
SB
SB
SB
SB
SB
7
5
5
5
7
9
7
3
7
LEAN CLAY, dark brown, moist, soft a fewOrganics
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark brown to reddish brown,mottled, moist, soft
LEAN CLAY, gray, mottled, wet, soft
SILT, gray, moist, loose
LEAN CLAY, gray, mottled, moist, soft
SILTY SAND WITH A LITTLE GRAVEL,dark gray, water bearing, very loose
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/28/2016 END: 3/28/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 19.5246:30 pm3/28/2016 12.4 1222.8
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 44PAGE 1 OF 1SURFACE ELEVATION: 1235.2 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
56 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1234
1233
1232
1231
1230
1229
1228
1227
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
DESCRIPTION OF MATERIAL
![Page 72: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/72.jpg)
17
3 1/4" HSA 0' - 22'
OL
CL
CL
CL
SM
Topsoil
Glacial Till
Glacial Till
Glacial Till
Coarse Alluvium
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SH
SB
SB
SB
SB
SB
4
4
4
5
7
8
13
18
23
ORGANIC CLAY, black, moist, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to reddish brown, mottled, wet,very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, brown to grayish brown, mottled,moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft to firm
SILTY SAND WITH A LITTLE GRAVEL,gray, water bearing, medium loose
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/28/2016 END: 3/28/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22 20.8245:20 pm3/28/2016 18.9 1204.3
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 45PAGE 1 OF 1SURFACE ELEVATION: 1223.2 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
56 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
1203
1202
1201
1200
1199
DESCRIPTION OF MATERIAL
![Page 73: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/73.jpg)
20
3 1/4" HSA 0' - 14.5'
OL
SC
CL
CL
Topsoil
Mixed Alluvium
Glacial Till
Glacial Till
1
2
3
4
5
6
7
SB
SB
SB
SB
SB
SB
SB
6
4
5
5
5
7
10
ORGANIC CLAY, black, moist, soft
CLAYEY SAND WITH A LITTLE GRAVEL,gray, mottled, wet, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, gray to reddish brown, mottled,moist, soft to firm
End of Boring 16.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/22/2016 END: 3/22/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
14.5166:20 pm3/22/2016 12.7 1209.9
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 47PAGE 1 OF 1SURFACE ELEVATION: 1222.6 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
56 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
1203
1202
1201
1200
1199
DESCRIPTION OF MATERIAL
![Page 74: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/74.jpg)
18
3 1/4" HSA 0' - 22'
SC
PT
PT
CL
CL
SM
Topsoil
Swamp Deposits
Swamp Deposits
Glacial Till
Glacial Till
Coarse Alluvium
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SB
SB
SB
SB
SH
SB
SB
5
2
2
3
5
6
1
CLAYEY SAND, dark brown, moist, soft, afew Organics
PEAT, black, moist, very soft
MUCK, gray, wet, very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark brown to gray, mottled, moist,very soft to soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
SILTY SAND, dark gray, wet, very loose
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/22/2016 END: 3/22/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22243:30 pm3/22/2016 None
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 48PAGE 1 OF 1SURFACE ELEVATION: 1227.2 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
56 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1226
1225
1224
1223
1222
1221
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
1203
DESCRIPTION OF MATERIAL
![Page 75: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/75.jpg)
15
3 1/4" HSA 0' - 22'
PT
CL
CL
Swamp Deposits
Glacial Till
Glacial Till
1
2
3
4
5
6
7
8
9
10
SB
SB
SB
SH
SB
SH
SB
SB
SB
SB
5
4
5
5
7
6
7
7
PEAT, black, moist, soft to very soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, grayish brown, mottled, moist, soft
LEAN CLAY WITH SAND AND A LITTLEGRAVEL, dark gray, moist, soft
End of Boring 24.0 ft.
TIME CASINGDEPTH
CAVE-INDEPTH
WATERDEPTH
WATERELEVATION
WATER LEVEL MEASUREMENTS
SAMPLEDDEPTHDATE METHOD
START: 3/22/2016 END: 3/22/2016
Logged By:
DAJR. Kurth
Notes:
Crew Chief:
LABORATORY TESTSMC(%)
DD(pcf)
LL(%)
PL(%)
22241:05 pm3/22/2016 None
PROJECT NAME: SRRWD-CPF Site
LOG OF TEST BORING
PROJECT LOCATION: Freeborn County, MN BORING NUMBER PB 49PAGE 1 OF 1SURFACE ELEVATION: 1221.4 ftCLIENT/WSB #: 02286-180
DEPTH(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
USCS GEOLOGICORIGIN
SAMPLE
No. TYPEWLN
WS
B B
OR
ING
LO
G -
WS
B.G
DT
- 4
/11
/16
15:
56 -
K:\0
228
6-1
80\G
EO
TE
CH
-CM
T\S
RR
WD
-CP
F-S
ITE
, FR
EE
BO
RN
CO
UN
TY
, MN
.GP
J
ELEV.(ft)
1220
1219
1218
1217
1216
1215
1214
1213
1212
1211
1210
1209
1208
1207
1206
1205
1204
1203
1202
1201
1200
1199
1198
1197
DESCRIPTION OF MATERIAL
![Page 76: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/76.jpg)
APPENDIX C
GEOTECHNICAL LABORATORY REPORTS RECEIVED AS OF MAY 6, 2016
![Page 77: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/77.jpg)
1
9530 James Ave South Bloomington, MN 55431
.002.005
Hydrometer Analysis
Fines
.2 .5
Sample
Type
.02 .05
Fine
TWT
#20 #40
20 50
Other Tests
*
5
2.68*
39.1
14.7
24.4
2.68*
31.4
14.8
16.6
2.68*
pH
Shrinkage Limit
Penetrometer
Qu (psf)
Dry Density (pcf)
Specific Gravity
Porosity
Organic Content
Liquid Limit
Plastic Limit
Plasticity Index
Water Content
Coarse Fine Coarse Medium
West
West
West
Sand
1
Gravel
3
6
Grain Size Distribution ASTM D422
4/21/16Report Date:
Test Date:
Reported To:
Project:
Job No. : 103084/19/16#02286-180
WSB & Associates
TWT
TWT
Sandy Lean Clay (CL)
Sandy Lean Clay (CL)
Sandy Lean Clay w/a trace of gravel (CL)
*
Boring Depth (ft)
9.5-11
7-9
22-24
3/8"
2
#4
Mass (g)
*
2"
1.5"
#200
281.2
#100 #200
#10
#20
#40
#100
1"
3/4"
63.5
52.3
Location
2 3/4 3/8 #4
321.9
#10
72.1
100.0
98.2
88.8
84.3
100.0
98.9
96.1
92.2
86.3
100.0
90.4
Percent Passing
203.5
72.3
62.3
96.4
92.0
98.1
94.8
64.7
83.9
*
Remarks:
D60
D30
D10
CU
CC
Soil Classification
(* = assumed)
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100 Grain Size (mm)
Per
cen
t P
ass
ing
![Page 78: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/78.jpg)
0.001 20.5
Hydrometer Data
0.001 8.6 0.001 10.3
0.006 31.40.003 26.00.006 22.6 0.006 20.9
13.6 0.003 15.5 0.003
0.008 34.60.012 36.60.009 28.0 0.009 25.1
0.012 29.1
0.031 47.60.020 41.90.012 37.5
0.019 45.0 0.020 34.30.030 50.8 0.032 40.2
Diameter % Passing Diameter % Passing
RemarksSpecimen 1 Specimen 2 Specimen 3
88.884.3
63.552.3
#20#40
#100#200#200
Specimen 1 Specimen 2 Specimen 3
64.762.3
Reported To: WSB & Associates
3
Diameter (mm) % Passing
#20#40
#100#200
92.2
Report Date: 4/21/16
Boring Depth (ft)
Sample
Type Soil Classification
Spec 1
#40#100
86.372.3
#20
West 1 9.5-11
Spec 3
72.1
90.483.9
Grain Size Distribution ASTM D422Job No. : 10308
Project: #02286-180Test Date: 4/19/16
TWT Sandy Lean Clay (CL)
Location
Sandy Lean Clay (CL)
Sandy Lean Clay w/a trace of gravel (CL)
Spec 2 West 7-9 TWT
West 6 22-24 TWT
Sieve Data
Specimen 1 Specimen 2 Specimen 3Sieve % Passing
2"
#4 98.9
1.5"1"
#10 96.1
Sieve % Passing2"
1.5"
3/4"1"
3/4"
#4 98.1#10 94.8
Sieve % Passing2"
1.5"1"
98.23/4" 100.0
#4 96.4
9530 James Ave South Bloomington, MN 55431
#10 92.0
3/8" 100.0 3/8" 100.0 3/8"
![Page 79: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/79.jpg)
1
9530 James Ave South Bloomington, MN 55431
.002.005
Hydrometer Analysis
Fines
.2 .5
Sample
Type
.02 .05
Fine
TWT
#20 #40
20 50
Other Tests
*
5
2.68*
37.4
22.2
15.2
2.68*
33.2
16.2
17.0
2.68*
pH
Shrinkage Limit
Penetrometer
Qu (psf)
Dry Density (pcf)
Specific Gravity
Porosity
Organic Content
Liquid Limit
Plastic Limit
Plasticity Index
Water Content
Coarse Fine Coarse Medium
West
SW1
SW1
Sand
23
Gravel
26
44
Grain Size Distribution ASTM D422
4/21/16Report Date:
Test Date:
Reported To:
Project:
Job No. : 103084/19/16#02286-180
WSB & Associates
TWT
TWT
Sandy Lean Clay w/a trace of gravel (CL)
Lean Clay w/sand (CL)
Lean Clay (CL)
*
Boring Depth (ft)
4.5-6
7-9
7-9
3/8"
2
#4
Mass (g)
*
2"
1.5"
#200
285.2
#100 #200
#10
#20
#40
#100
1"
3/4"
81.6
71.7
Location
2 3/4 3/8 #4
298.0
#10
95.2
99.8
99.5
100.0
98.3
97.2
95.3
91.3
85.3
100.0
94.6
Percent Passing
275.0
67.4
55.2
100.0
100.0
99.1
97.7
88.2
91.0
*
Remarks:
D60
D30
D10
CU
CC
Soil Classification
(* = assumed)
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100 Grain Size (mm)
Per
cen
t P
ass
ing
![Page 80: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/80.jpg)
0.001 8.3
Hydrometer Data
0.001 11.3 0.001 12.4
0.006 24.10.003 13.30.006 23.1 0.006 27.4
16.9 0.003 18.6 0.003
0.009 31.90.012 31.30.009 27.6 0.009 31.1
0.012 36.6
0.030 63.90.020 51.90.012 40.3
0.020 36.8 0.020 45.80.032 42.3 0.030 55.9
Diameter % Passing Diameter % Passing
RemarksSpecimen 1 Specimen 2 Specimen 3
99.899.5
81.671.7
#20#40
#100#200#200
Specimen 1 Specimen 2 Specimen 3
88.255.2
Reported To: WSB & Associates
26
Diameter (mm) % Passing
#20#40
#100#200
91.3
Report Date: 4/21/16
Boring Depth (ft)
Sample
Type Soil Classification
Spec 1
#40#100
85.367.4
#20
West 23 4.5-6
Spec 3
95.2
94.691.0
Grain Size Distribution ASTM D422Job No. : 10308
Project: #02286-180Test Date: 4/19/16
TWT Sandy Lean Clay w/a trace of gravel (CL)
Location
Lean Clay w/sand (CL)
Lean Clay (CL)
Spec 2 SW1 7-9 TWT
SW1 44 7-9 TWT
Sieve Data
Specimen 1 Specimen 2 Specimen 3Sieve % Passing
2"
#4 97.2
1.5"1"
#10 95.3
Sieve % Passing2"
1.5"
3/4" 100.01"
3/4"
#4 99.1#10 97.7
Sieve % Passing2"
1.5"1"
3/4"
#4 100.0
9530 James Ave South Bloomington, MN 55431
#10 100.0
3/8" 98.3 3/8" 100.0 3/8"
![Page 81: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/81.jpg)
1
(* = assumed)
Soil Classification
CU
CC
92.6
*
Remarks:
D60
D30
D10
66.7
53.0
98.2
95.1
100.0
99.5
58.0
Percent Passing
205.4
91.1
85.2
100.0
98.1
94.8
90.0
83.5
97.1
#10
68.0
100.0
71.5
52.4
Location
2 3/4 3/8 #4
311.6
#200
431.5
#100 #200
#10
#20
#40
#100
1"
3/4"
#4
Mass (g)
*
2"
1.5"
3/8"
2
Boring Depth (ft)
7-9
9.5-11
9.5-11
WSB & Associates
TWT
TWT
Sandy Lean Clay (CL)
Sandy Silty Clay (CL-ML/ML)
Sandy Lean Clay (CL)
*
Grain Size Distribution ASTM D422
4/21/16Report Date:
Test Date:
Reported To:
Project:
Job No. : 103084/19/16#02286-180
Gravel
33
45
SW1
SW2
SW2
Sand
39
Coarse Fine Coarse Medium
Liquid Limit
Plastic Limit
Plasticity Index
Water Content
Dry Density (pcf)
Specific Gravity
Porosity
Organic Content
pH
Shrinkage Limit
Penetrometer
Qu (psf)
25.4
14.8
10.6
18.3
111.8
2.68*
17.7
13.5
4.2
2.68* 2.68*
20 50
Other Tests
*
5 .2 .5
Sample
Type
.02 .05
Fine
TWT
#20 #40
.002.005
Hydrometer Analysis
Fines
9530 James Ave South Bloomington, MN 55431
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100 Grain Size (mm)
Per
cen
t P
ass
ing
![Page 82: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/82.jpg)
9530 James Ave South Bloomington, MN 55431
#10 95.1
3/8" 100.0 3/8" 3/8" 100.03/4"
#4 98.2
1.5"1"
Sieve % Passing2"
#4 100.0#10 99.5
1"3/4"
#10 94.8
Sieve % Passing2"
1.5"
3/4"
#4 98.1
1.5"1"
Sieve % Passing2"
Sieve Data
Specimen 1 Specimen 2 Specimen 3
Sandy Lean Clay (CL)
Spec 2 SW2 9.5-11 TWT
SW2 45 9.5-11 TWT
TWT Sandy Lean Clay (CL)
Location
Sandy Silty Clay (CL-ML/ML)
68.0
97.192.6
Grain Size Distribution ASTM D422Job No. : 10308
Project: #02286-180Test Date: 4/19/16
Spec 1
#40#100
83.566.7
#20
SW1 39 7-9
Spec 3
Report Date: 4/21/16
Boring Depth (ft)
Sample
Type Soil Classification
Reported To: WSB & Associates
33
Diameter (mm) % Passing
#20#40
#100#200
90.0
#200
Specimen 1 Specimen 2 Specimen 3
58.053.071.552.4
#20#40
#100#200
RemarksSpecimen 1 Specimen 2 Specimen 3
91.185.2
Diameter % Passing Diameter % Passing
0.032 40.0 0.033 35.0
0.012 33.60.020 34.4 0.021 26.7
0.031 46.70.020 40.0
0.009 29.00.012 27.50.009 23.2 0.009 16.6
0.013 20.3
20.70.006 19.0 0.006 13.0
12.3 0.003 6.7 0.0030.001 16.4
Hydrometer Data
0.001 7.1 0.001 5.4
0.006 25.20.003
![Page 83: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/83.jpg)
1
9530 James Ave South Bloomington, MN 55431
.002.005
Hydrometer Analysis
Fines
.2 .5
Sample
Type
.02 .05
Fine
TWT
#20 #40
20 50
Other Tests
*
5
114.6
2.68*
16.6
pH
Shrinkage Limit
Penetrometer
Qu (psf)
Dry Density (pcf)
Specific Gravity
Porosity
Organic Content
Liquid Limit
Plastic Limit
Plasticity Index
Water Content
Coarse Fine Coarse Medium
SW2
Sand
48
Gravel
Grain Size Distribution ASTM D422
4/21/16Report Date:
Test Date:
Reported To:
Project:
Job No. : 103084/19/16#02286-180
WSB & Associates
Sandy Lean Clay (CL)*
Boring Depth (ft)
17-19
3/8"
2
#4
Mass (g)
*
2"
1.5"
#200
203.5
#100 #200
#10
#20
#40
#100
1"
3/4"
Location
2 3/4 3/8 #4 #10
100.0
98.3
95.3
90.6
83.9
Percent Passing
69.3
52.1
*
Remarks:
D60
D30
D10
CU
CC
Soil Classification
(* = assumed)
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100 Grain Size (mm)
Per
cen
t P
ass
ing
![Page 84: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/84.jpg)
Hydrometer Data
0.001 7.00.0030.006 19.0
11.2
0.012 26.90.009 22.7
0.021 32.30.032 39.1
Diameter % Passing Diameter % Passing
RemarksSpecimen 1 Specimen 2 Specimen 3
#20#40
#100#200#200
Specimen 1 Specimen 2 Specimen 3
52.1
Reported To: WSB & Associates
Diameter (mm) % Passing
#20#40
#100#200
90.6
Report Date: 4/21/16
Boring Depth (ft)
Sample
Type Soil Classification
Spec 1
#40#100
83.969.3
#20
SW2 48 17-19
Spec 3
Grain Size Distribution ASTM D422Job No. : 10308
Project: #02286-180Test Date: 4/19/16
TWT Sandy Lean Clay (CL)
Location
Spec 2
Sieve Data
Specimen 1 Specimen 2 Specimen 3Sieve % Passing
2"
#4 98.3
1.5"1"
#10 95.3
Sieve % Passing2"
1.5"
3/4"1"
3/4"
#4#10
Sieve % Passing2"
1.5"1"
3/4"
#4
9530 James Ave South Bloomington, MN 55431
#10
3/8" 100.0 3/8" 3/8"
![Page 85: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/85.jpg)
Project: Job: 10308
Client: Date: 4/25/2016
Boring # 2 3 6 12 26 44 39 24
Location West West West West SW1 SW1 SW1 SW2
Depth (ft) 22-24 7-9 22-24 14.5-16 7-9 7-9 7-9 19.5-21
Sample Type TWT TWT TWT TWT TWT TWT TWT TWT
Liquid Limit 30.5 31.4 39.1 25.4 33.2 37.4 25.4 42.4
Plastic Limit 14.1 14.8 14.7 13.2 16.2 22.2 14.8 19.2
Plasticity Index 16.4 16.6 24.4 12.2 17.0 15.2 10.6 23.2
Boring # 33 49
Location SW2 SW2
Depth (ft) 9.5-11 12-14
Sample Type TWT TWT
Liquid Limit 17.7 27.0
Plastic Limit 13.5 13.7
Plasticity Index 4.2 13.3
Sample Information & Classification
Sample Information & Classification
Lean Clay
(CL)
Lean Clay
(CL)
Sandy Lean Clay
w/a trace of
gravel
(CL)
Lean Clay w/sand
(CL)
#02286-180
WSB & Associates
Laboratory Test Summary
MaterialClassification
Sandy Silty Clay
(CL-ML/ML)
Sandy Lean Clay
w/a little gravel
(CL)
Atterberg Limits (ASTM:D4318)
Sandy Lean Clay
(CL)
MaterialClassification
Sandy Lean Clay
w/a trace of
gravel and some
patches of silty
sand
(CL)
Sandy Lean Clay
(CL)
Sandy Lean Clay
(CL)
Atterberg Limits (ASTM:D4318)
![Page 86: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/86.jpg)
Project: Job: 10308
Client: Date: 4/26/16
Location West SW-1 SW-2
Boring 9 39 48
Depth (ft) 4.5-6.5 7-9 17-19
Type or BPF TWT TWT TWT
Water Content (%) 32.0 18.3 16.6
Dry Density (pcf) 88.9 111.8 114.6
Location
Boring
Depth (ft)
Type or BPF
Water Content (%)
Dry Density (pcf)
Location
Boring
Depth (ft)
Type or BPF
Water Content (%)
Dry Density (pcf)
Water Content, Dry Density
Sample Information & Classification
Classification
Lean Clay (CL/CH)
Water Content, Dry Density (ASTM:D7263)
Water Content, Dry Density (ASTM:D7263)
Sample Information & Classification
Classification
Laboratory Test Summary
Sandy Lean Clay(CL)
#02286-180
WSB & Associates
Sample Information & Classification
Sandy Lean Clay(CL)
Classification
![Page 87: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/87.jpg)
Project: Job:Client: Date:
Remarks:
Depth:
Ht. (in) 5.81
2.0
2.00 tsf
11.2
Depth:
Ht. (in): 5.78
2.0
1.52 tsf
6.6
LL:
PL:
PI:
9530 James Ave South Bloomington, MN 55431
Height to Diameter Ratio:
30.5
0.060Strain Rate (in/min):
Strain Rate (in/min):
Boring:
Sample #: West
Soil Type:Sandy Lean Clay (CL)
9.5-11PB-1
3T
Soil Type:
14.1
16.1
116.1
Dia. (in): 2.88
Unconfined Comp. Strength:
Strain at Failure (%):
Height to Diameter Ratio:
16.4
Boring: PB-2
Sample #: West
Sandy Lean Clay w/a trace of gravel
and some patches of silty sand (CL)
Sketch of Specimen After
Failure
Sample Type:
22-24
Unconfined Comp. Strength:
21.8
Strain at Failure (%):
W.C. (%):
104.4
Unconfined Stress/Strain Curves ASTM: D2166
WSB & Associates103084/27/16
#02286-180
Yd (pcf):
W.C. (%):
Yd (pcf):
Dia. (in) 2.88
Sketch of Specimen After
Failure
0.060
Sample Type: 3T
0
0.5
1
1.5
2
2.5
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
![Page 88: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/88.jpg)
Project: Job:Client: Date:
Remarks:
Depth:
Ht. (in) 5.80
2.0
1.80 tsf
4.8
LL:
PL:
PI:
Depth:
Ht. (in): 5.86
2.0
1.33 tsf
20.0
LL:
PL:
PI:
9530 James Ave South Bloomington, MN 55431
31.4
Height to Diameter Ratio:
16.6
39.1
14.8
0.060Strain Rate (in/min):
Strain Rate (in/min):
Boring:
Sample #: West
Soil Type:Sandy Lean Clay (CL)
7-9PB-3
3T
Soil Type:
14.7
18.5
111.7
Dia. (in): 2.87
Unconfined Comp. Strength:
Strain at Failure (%):
Height to Diameter Ratio:
24.4
Boring: PB-6
Sample #: West
Sandy Lean Clay w/a trace of gravel
(CL)
Sketch of Specimen After
Failure
Sample Type:
22-24
Unconfined Comp. Strength:
18.2
Strain at Failure (%):
W.C. (%):
111.3
Unconfined Stress/Strain Curves ASTM: D2166
WSB & Associates103084/27/16
#02286-180
Yd (pcf):
W.C. (%):
Yd (pcf):
Dia. (in) 2.88
Sketch of Specimen After
Failure
0.060
Sample Type: 3T
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
![Page 89: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/89.jpg)
Project: Job:Client: Date:
Remarks:
Depth:
Ht. (in) 5.66
2.0
0.84 tsf
17.7
LL:
PL:
PI:
Depth:
Ht. (in): 5.75
2.0
1.39 tsf
7.8
9530 James Ave South Bloomington, MN 55431
25.4
Height to Diameter Ratio:
12.2
13.2
0.060Strain Rate (in/min):
Strain Rate (in/min):
Boring:
Sample #: West
Soil Type:Sandy Lean Clay w/a trace of gravel
(CL)
14-16.5PB-12
3T
Soil Type:
16.5
112.8
Dia. (in): 2.84
Unconfined Comp. Strength:
Strain at Failure (%):
Height to Diameter Ratio:
Boring: PB-22
Sample #: West
Lean Clay w/sand (CL)
Sketch of Specimen After
Failure
Sample Type:
9.5-11.5
Unconfined Comp. Strength:
16.6
Strain at Failure (%):
W.C. (%):
120.9
Unconfined Stress/Strain Curves ASTM: D2166
WSB & Associates103084/27/16
#02286-180
Yd (pcf):
W.C. (%):
Yd (pcf):
Dia. (in) 2.85
Sketch of Specimen After
Failure
0.060
Sample Type: 3T
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
![Page 90: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/90.jpg)
Project: Job:Client: Date:
Remarks:
Depth:
Ht. (in) 5.70
2.0
1.29 tsf
7.9
Depth:
Ht. (in): 5.78
2.0
0.55 tsf
19.0
LL:
PL:
PI:
9530 James Ave South Bloomington, MN 55431
Height to Diameter Ratio:
42.4
0.060Strain Rate (in/min):
Strain Rate (in/min):
Boring:
Sample #: West
Soil Type:Sandy Lean Clay w/a trace of gravel
(CL)
4.5-6.5PB-23
3T
Soil Type:
19.2
33.8
87.4
Dia. (in): 2.85
Unconfined Comp. Strength:
Strain at Failure (%):
Height to Diameter Ratio:
23.2
Boring: PB-24
Sample #: SW2
Lean Clay (CL)
Sketch of Specimen After
Failure
Sample Type:
19.5-21.5
Unconfined Comp. Strength:
26.5
Strain at Failure (%):
W.C. (%):
95.9
Unconfined Stress/Strain Curves ASTM: D2166
WSB & Associates103084/27/16
#02286-180
Yd (pcf):
W.C. (%):
Yd (pcf):
Dia. (in) 2.88
Sketch of Specimen After
Failure
0.060
Sample Type: 3T
0
0.2
0.4
0.6
0.8
1
1.2
1.4
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
0
0.1
0.2
0.3
0.4
0.5
0.6
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
![Page 91: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/91.jpg)
Project: Job:Client: Date:
Remarks:
Depth:
Ht. (in) 5.83
2.0
1.02 tsf
8.6
Depth:
Ht. (in): 5.71
2.0
0.43 tsf
1.4
LL:
PL:
PI:
Yd (pcf):
W.C. (%):
Yd (pcf):
Dia. (in) 2.88
Sketch of Specimen After
Failure
0.060
Sample Type: 3T
112.0
Unconfined Stress/Strain Curves ASTM: D2166
WSB & Associates103084/27/16
#02286-180
Unconfined Comp. Strength:
18.3
Strain at Failure (%):
W.C. (%):
17.0
Boring: PB-26
Sample #: SW1
Lean Clay w/sand and some patches of
silty sand (CL)
Sketch of Specimen After
Failure
Sample Type:
7-9
3T
Soil Type:
16.2
22.1
96.0
Dia. (in): 2.89
Unconfined Comp. Strength:
Strain at Failure (%):
Height to Diameter Ratio:
Strain Rate (in/min):
Boring:
Sample #: SW1
Soil Type:Lean Clay w/sand (CL)
7-9PB-25
9530 James Ave South Bloomington, MN 55431
Height to Diameter Ratio:
33.2
0.060Strain Rate (in/min):
0
0.2
0.4
0.6
0.8
1
1.2
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
![Page 92: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/92.jpg)
Project: Job:Client: Date:
Remarks:
Depth:
Ht. (in) 5.64
2.0
0.46 tsf
3.2
LL:
PL:
PI:
Depth:
Ht. (in): 5.67
2.0
0.49 tsf
6.7
LL:
PL:
PI:
9530 James Ave South Bloomington, MN 55431
17.7
Height to Diameter Ratio:
4.2
37.4
13.5
0.060Strain Rate (in/min):
Strain Rate (in/min):
Boring:
Sample #: SW2
Soil Type:Sandy Silty Clay (CL-ML/ML)
9.5-11PB-33
3T
Soil Type:
22.2
31.2
90.2
Dia. (in): 2.83
Unconfined Comp. Strength:
Strain at Failure (%):
Height to Diameter Ratio:
15.2
Boring: PB-44
Sample #: SW1
Lean Clay (CL)
Sketch of Specimen After
Failure
Sample Type:
7-9
Unconfined Comp. Strength:
16.4
Strain at Failure (%):
W.C. (%):
117.5
Unconfined Stress/Strain Curves ASTM: D2166
WSB & Associates103084/27/16
#02286-180
Yd (pcf):
W.C. (%):
Yd (pcf):
Dia. (in) 2.85
Sketch of Specimen After
Failure
0.060
Sample Type: 3T
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
0
0.1
0.2
0.3
0.4
0.5
0.6
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
![Page 93: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/93.jpg)
Project: Job:Client: Date:
Remarks:
Depth:
Ht. (in) 5.92
2.1
1.37 tsf
3.7
Depth:
Ht. (in): 5.85
2.0
1.45 tsf
12.0
LL:
PL:
PI:
9530 James Ave South Bloomington, MN 55431
Height to Diameter Ratio:
27.0
0.060Strain Rate (in/min):
Strain Rate (in/min):
Boring:
Sample #: SW-2
Soil Type:Sandy Lean Clay w/a patch of sand
(CL)
9.5-11.5PB-45
3T
Soil Type:
13.7
15.6
115.4
Dia. (in): 2.87
Unconfined Comp. Strength:
Strain at Failure (%):
Height to Diameter Ratio:
13.3
Boring: PB-49
Sample #: SW-2
Sandy Lean Clay w/a little gravel (CL)
Sketch of Specimen After
Failure
Sample Type:
12-14
Unconfined Comp. Strength:
16.1
Strain at Failure (%):
W.C. (%):
114.2
Unconfined Stress/Strain Curves ASTM: D2166
WSB & Associates103084/27/16
#02286-180
Yd (pcf):
W.C. (%):
Yd (pcf):
Dia. (in) 2.87
Sketch of Specimen After
Failure
0.060
Sample Type: 3T
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0 2 4 6 8 10 12 14 16 18 20
Axial Strain (%)
Deviator Stress (tsf)
![Page 94: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/94.jpg)
ASTM: D3080
Project/Client:
Boring No.: Sample No. Depth:
Location: Sample Type:
Soil Type:
0.2
φ=φ=φ=φ= 29.1 deg. φ=φ=φ=φ= 29.1 deg.
3.60
Direct Shear Test
Test Date:
Job No.:
#02286-180 / WSB Associates, Inc.
PB-18 West 7-9 Top 4/20/2016
0.55 1.48
0.72 1.80
Dry Density (pcf)
2.21
111.8 114.3 117.5
Normal Stress
Shear Stress
Dry Density (pcf)
Before Shear
Thickness (In.)
Water Content (%) 17.1 15.7
0.93 0.92 0.91
18.4
111.7
14.4 13.7
A B C D
(*) = Assumed Specific Gravity
Remarks: Specimens trimmed to given sizes; Inundated after applying normal load. Consolidated and
sheared to given displacements at constant rate of 0.003 inches/minute.
Plastic Limit:
Plasticity Index:
Specific Gravity (*):
Liquid Limit:
2.67
4/25/2016
Max Stress
Failure Criterion:
Mixture of Silty Sand, Sand, Sand with Silt and Clayey Sand
TWT Date Reported:
Shear Rate
0.003 (in/min)
Initial
2.50 2.50Diameter (In.)
"These tests are for informational purposes only and must be reviewed by a
qualified professional engineer to verify that the test parameters shown are
appropriate for any particular design."
0.96Thickness (In.)
Water Content (%)
0.96
15.9
108.7 109.3
10308
CohesionTSF0.259
Apparent
X
0.96
2.50
Peak Conditions
Friction Angle: Friction Angle:
At Given Shear Disp. Of:
Apparent
Cohesion0.278 TSF
-0.025
-0.02
-0.015
-0.01
-0.005
0
0 0.05 0.1 0.15 0.2
Ch
an
ge i
n T
hic
kn
ess (
inch
)
0
0.5
1
1.5
2
2.5
0 0.05 0.1 0.15 0.2Shear Displacement (inch)
Sh
ear
Str
ess (
TS
F)
0
0.5
1
1.5
2
2.5
3
3.5
4
0 0.5 1 1.5 2 2.5 3 3.5 4
Normal Stress (TSF)
Sh
ear
Str
ess (
TS
F)
![Page 95: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/95.jpg)
APPENDIX D
JONES, HAUGH & SMITH PLAT OF SURVEY
![Page 96: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/96.jpg)
![Page 97: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/97.jpg)
![Page 98: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/98.jpg)
![Page 99: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/99.jpg)
![Page 100: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/100.jpg)
![Page 101: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/101.jpg)
![Page 102: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/102.jpg)
APPENDIX E
FAA NO HAZARD DETERMINATION LETTER
![Page 103: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/103.jpg)
![Page 104: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/104.jpg)
![Page 105: BASIS OF DESIGN REPORT FOUNTAIN LAKE RESTORATION …9804AD9D... · Balance earthwork with site terrain: This design objective seeks to effectively use existing site conditions with](https://reader034.fdocuments.us/reader034/viewer/2022042109/5e8a19ff59ded02471293f4c/html5/thumbnails/105.jpg)