BASE DE P.U.
-
Upload
max-alvarez -
Category
Documents
-
view
216 -
download
0
Transcript of BASE DE P.U.
-
8/19/2019 BASE DE P.U.
1/2
______________________________________, S.A. DE C.V.
ANALISIS DE PRECIOS UNITARIOS
CLIENTE
OBRA
UBICACION
UNIDAD
CONCEPTO UNIDAD CANTIDAD COSTO IMPORTE
KG -
-
-
-
-
-
-
-
-
-
IMPORTE DE MATERIALES -
-
CABO TNO 0.0010 344.13 0.34
OFICIAL TNO 0.0060 289.89 1.74
AYUDANTE TNO 0.0060 158.60 0.95
-
-
-
-
RENDIMIENTO 1.00 SUBTOTAL 3.04IMPORTE DE MANO DE OBRA 3.04
% 3.00 3.04 0.09
-
-
-
-
-
-
RENDIMIENTO 1.00 SUBTOTAL -
IMPORTE DE EQUIPO -
COSTO DIRECTO 3.13
INDIRECTOS 17.00% 0.53
PRECIO UNITARIO 3.66
M A T E R I A L E S
HERRAMIENTA
M A N O D E O B R A
E Q U I P O
OBSERVACIONES:
-
8/19/2019 BASE DE P.U.
2/2