BAR0065_A_EN

13
Quality requirements applicable to Suppliers/Partners on SaM146 nacelle Program BAR0065 A Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisation Seule la base documentaire garantit la dernière version applicable. Les éditions papier doivent être contrôlées avant utilisation This document is the property of Aircelle and shall not be used, duplicated or distributed without their approval Only the documentation data base can guarantee the applicable issue. Printed copies must be checked before use Page 1/2 Processus/Sous processus Purchase Objet/Object The aim of this document is to define the requirements applicable to the Suppliers and Partners within the framework of the SaM146 program. Domaine d’application/Scope This document is applicable to suppliers of modules of the nacelle, of main parts and assemblies, of equipments and systems composing the SaM146 nacelle to all services and jobs : - of Aircelle’s Suppliers / Partners / Sub-contractors - for complete contract duration, - for each time, that it is referenced in a contractual document between Aircelle and the supplier (for example : into the contract, into the purchase order, into the Statement Of Work, in the Aircelle’s product Technical Specification, …) - in all program phases, from development to product support, - for all operations and supplies associated with the SaM146 Nacelle program. Principe/Principe Identification within purchase process of document BQR0234 Acteurs concernés/ Actors concerned N/A Approbation – application – diffusion & signatures / Approval – application- distribution & signatures Applicable par Applicable by Aircelle SA Aircelle Ltd Aircelle Maroc Secteur spécifique Specific sector Classification Public /Public Aircelle / Reserved Aircelle Restreint / Limited Diffusion externe External distribution Autorisée sans accord préalable du coordinateur Authorised without any preliminary agreement from the co-ordinator Nécessite l’accord préalable du coordinateur Requires the preliminary agreement from the co-ordinator Non diffusable Distribution forbidden Rédaction / writing N/A Vérification/ Check P. Labedan Approbation / approval N/A Pour application Aircelle / For application by Aircelle N/A Pour application Aircelle Ltd /For application by Aircelle Ltd N/A

Transcript of BAR0065_A_EN

Quality requirements applicable to Suppliers/Partners on SaM146 nacelle

Program

BAR0065 A

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisation Seule la base documentaire garantit la dernière version applicable. Les éditions papier doivent être contrôlées avant utilisation

This document is the property of Aircelle and shall not be used, duplicated or distributed without their approval Only the documentation data base can guarantee the applicable issue. Printed copies must be checked before use

Page 1/2

Processus/Sous processus Purchase

Objet/ Object The aim of this document is to define the requirements applicable to the Suppliers and Partners within the framework of the SaM146 program. Domaine d’application/ Scope This document is applicable to suppliers of modules of the nacelle, of main parts and assemblies, of equipments and systems composing the SaM146 nacelle to all services and jobs : - of Aircelle’s Suppliers / Partners / Sub-contractors - for complete contract duration, - for each time, that it is referenced in a contractual document between Aircelle and the supplier (for example : into the contract, into the purchase order, into the Statement Of Work, in the Aircelle’s product Technical Specification, …) - in all program phases, from development to product support, - for all operations and supplies associated with the SaM146 Nacelle program. Principe/ Principe Identification within purchase process of document BQR0234 Acteurs concernés/ Actors concerned N/A

Approbation – application – diffusion & signatures / Approval – application- distribution & signatures Applicable par Applicable by

Aircelle SA

Aircelle Ltd

Aircelle Maroc Secteur spécifique Specific sector

Classification Public / Public Aircelle / Reserved Aircelle Restreint / Limited Diffusion externe External distribution

Autorisée sans accord préalable du coordinateur

Authorised without any preliminary agreement from the co-ordinator

Nécessite l’accord préalable du coordinateur

Requires the preliminary agreement from the co-ordinator

Non diffusable Distribution forbidden

Rédaction / writing N/A

Vérification/ Check P. Labedan

Approbation / a pproval N/A

Pour application Aircelle / For application by Aircelle N/A

Pour application Aircelle Ltd / For application by Aircelle Ltd N/A

Quality requirements applicable to Suppliers/Partners on SaM146 nacelle

Program

BAR0065 A

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisation Seule la base documentaire garantit la dernière version applicable. Les éditions papier doivent être contrôlées avant utilisation

This document is the property of Aircelle and shall not be used, duplicated or distributed without their approval Only the documentation data base can guarantee the applicable issue. Printed copies must be checked before use

Page 2/2

REPERTOIRE DES EVOLUTIONS / RECORD OF REVISIONS

EVOLUTIONS / CHANGES Edition /

Issue Date § modifiés / modified §

Synthèse de la modification / Synthesis of change

Modifié par / Modified by

A 08/03/2010 Identification dans le processus acheter du

document BQR0234 P. Labedan

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 2/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

EVOLUTIONS / CHANGESEdition /

Issue Date § modifiés /modified §

Synthèse de la modification /Synthesis of change

Modifié par /Modified by

A 23/06/06 Tous / All

Création en fonction des exigencesPowerJet spécifiées dans le MPS réf.SaM146.PWJ.PGM.PLA.00001 indice 01du 16/09/2005 / Creation according to thePowerJet’s requirements specified in theMPS ref. SaM146.PWJ.PGM.PLA.00001issue 01 of 16/09/2005

Jean FrançoisBLAGONJA

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 3/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

DIFFUSION / DISTRIBUTIONInterne /Internal

Document complet /Full document

Information de parution uniquement /Advice notification

LE HAVRE

R. GUYADER LH420 (original) Arnaud HAUGEL, Pierre LABEDAN, PhilippeROUDAUT, Vincent LAFOND, NicolasDEZEUSTRE, B. BYTTEBIER, V. BLANDIN, C. DELA FOUCHARDIERE, JL LEVAVASSEUR, E.REMOUE, JF. REYNAUD, JL. CHOBY, JL.CAMPAGNE, T. DI GIANNANTONIO, B.PENNEQUIN, Mathieu SADOULET

MEUDON / PLAISIR NA

Serge DAVID, Jean Pierre BIRARD, ArmandBULTE, Thierry DEFRESNE, Jérôme POLENNE,Armand BULTE, Didier COQUELET, MarcCHAMBON, Thierry MARTIN, Julien RAPIN, DenisGUILLOIS, Gilles LANVIER, Sonia MALKI, PascalLAZERAND, Christophe AUGER, Jerome CAVEL

TOULOUSE NA NA

BURNLEY NA NA

PONT AUDEMER NA NA

SLCA NA NA

Externe autorisée /Authorized external

Destinataires (Autorités, Clients) / Recipients (authorities, Customers)PowerJet for information(Alexis KHODALITSKY)

þ Oui Yes

o Non No

Tous fournisseurs en particuliers fournisseurs majeurs et partenaires "Built ToPrint" et "Built To Spec" sur programme Nacelle SaM146All suppliers in particular major Partners / Suppliers “Built to Print” and “Built toSpec on SaM146 Nacell Program”

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 4/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

ENGLISH VERSIONSUMMARY page

1. SUBJECT AND OBJECTIVES ...............................................................................5

2. SCOPE....................................................................................................................5

3. DOCUMENT REFERENCES FOR APPLICATION.................................................5

4. TERMINOLOGY......................................................................................................64.1. ABBREVIATIONS............................................................................................................. 64.2. DEFINITIONS ................................................................................................................... 6

5. ADDITIONAL INFORMATION ................................................................................6

6. QUALITY REQUIREMENTS...................................................................................66.1. LANGUAGE...................................................................................................................... 66.2. COMPLIANCE MATRIX.................................................................................................... 66.3. DVI PROCESS IN DEVELOPMENT PHASE .................................................................... 76.4. DVI PROCESS IN PRODUCTION PHASE ....................................................................... 8

APPENDIX 1 : BQR0234-FORM1A - SAM146 NACELLE QUALITY REQUIREMENTS.9

APPENDIX 2 : BQR0234-FORM2A- ACCEPTANCE TEST REPORT FORMAT FORMODULES AND ITEMS WITH AIRCELLE TECHNICAL SPECIFICATIONS.................10

APPENDIX 3 : LIST OF DOCUMENTS REFERENCED .................................................11

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 5/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

1. SUBJECT AND OBJECTIVESThe aim of this document is to define the requirements applicable to the Suppliers and Partners within theframework of the SaM146 program.

The objective of this document is to communicate the Aircelle’s requirements to the major Suppliers andPartners in the frame of the SaM146 Program. In particular but not limited to, it represents a flow down ofPowerJet‘s requirements, PowerJet being the customer of Aircelle. Then, these Aircelle’s Qualityrequirements include PowerJet’s requirements which are not declined in the general Aircelle’s Qualityrequirements.

Then, this present Quality specification is as a supplement to the:

• SAFRAN general quality requirements ref. QA-000725 (for design and production parts),

• SAFRAN general quality requirements ref. GRP-0081 (for intellectual services)

• Aircelle Quality requirements ref. BQR0003

2. SCOPEThis document is applicable to suppliers of modules of the nacelle, of main parts and assemblies, ofequipments and systems composing the SaM146 nacelle to all services and jobs :

- of Aircelle’s Suppliers / Partners / Sub-contractors

- for complete contract duration,

- for each time, that it is referenced in a contractual document between Aircelle and the supplier (forexample : into the contract, into the purchase order, into the Statement Of Work, in the Aircelle’sproduct Technical Specification, …)

- in all program phases, from development to product support,

- for all operations and supplies associated with the SaM146 Nacelle program.

In a first plan, this document is applicable to the suppliers “BUILT TO SPEC” and “BUILT TO PRINT” forwhom the writing of a Product Quality Plan is imposed by Aircelle to describe the Quality dispositionsimplemented by the supplier to answer to all of the quality requirements which are applicable on thisprogram SaM146. These Quality requirements are identified in appendix 1 in a specific column applicablefor “BUILT TO SPEC” or “BUILT TO PRINT”” suppliers.

In a second plan, this document is applicable to all of other suppliers (“simple” suppliers who manufacturepurchased articles with an Aircelle’s industrial and manufacturing specification, but only for Qualityrequirements identified in the “compliance matrix” specified in appendix 1 in the column “Applicable for allsuppliers”. It’s not necessary that such suppliers establish a compliance matrix, except if formally requiredby Aircelle.

The compliance with Aircelle’s Quality requirements shall be reviewed by the all suppliers in thedevelopment phase and before the beginning of production phase. In particular, for “BUILT TO SPEC”and “BUILT TO PRINT” suppliers, this review shall be done in the same time of the Aircelle’s approval ofthe supplier’s Product Quality Plan.

3. DOCUMENT REFERENCES FOR APPLICATION

See appendix 3

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 6/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

4. TERMINOLOGY

4.1. ABBREVIATIONSRefer to QA-000725 §1.1

ATP: Acceptance Test Procedure

ATR: Acceptance Test Report

BTP: BUILT TO PRINT supplier

BTS: “BUILT TO SPEC” supplier

4.2. DEFINITIONSRefer to QA-000725 §1.1.

In this document, it will be called “Suppliers” all the Suppliers and the Partners ofAircelle.A "BUILT TO SPEC" supplier is in charge and responsible of its definition. He shall ensure and replythat its definition, its industrialization and its manufacturing of all items are in accordance with Aircelle’sTechnical Specification.

A "BUILT TO PRINT" is supplier in charge to industrialize and produce a consequent assembly or sub-assembly of several primary items and/or systems (as a main module of the nacelle), but the "Built ToPrint" supplier is not in charge of the technical conception.

“Other supplier” is a supplier in charge to industrialize and produce a primary item or an equipped itemfrom the Aircelle definition. Such supplier is not in charge of the technical conception.

5. ADDITIONAL INFORMATIONThis present Aircelle Quality specification is established in accordance with PowerJet’s Qualityrequirements specified in the Program Management Specification ref. SaM146.PWJ.PGM.PLA.00001dated 16/09/2005.

6. QUALITY REQUIREMENTS

6.1. LANGUAGEAll documents shall be written in English.

6.2. COMPLIANCE MATRIX

6.2.1.1. MatrixAircelle carried out a sorting of the applicable and non applicable requirements to the "BTS", "BTP" andother Suppliers and declined them in a compliance matrix.

Completing the matrix (see guidelines §6.1.1.2.), Suppliers have to make their answers concerning eachpoint, available at any Aircelle request. They have moreover to make sure that these requirements aredeclined, respected in their own Suppliers and to give the evidence of it to Aircelle.

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 7/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

The focal point for the communication about the matrix is the Aircelle Supplier Quality Assurancerepresentative in charge of the supplier’s product.

The matrix format to be used is the one provided by Aircelle .The matrix format is an attached Excel tableattached in appendix 1. All answers have to be completed on this form.

6.2.1.2. Guidelines for the completion of the matrixA “BTP” completes the matrix for the requirements he is concerned with: if the box "Aircelle's Qualityrequirements applicable to “BTP” is Y (Yes).A "BTS" completes the matrix for the requirements he is concerned with : if the box "Aircelle's Qualityrequirements applicable to “BTS" is Y (Yes).Other Suppliers completes the matrix for the requirements he is concerned with : if the box "Aircelle'sQuality requirements applicable to “all Suppliers” is Y (Yes).

For each requirement, the box "Supplier's answer" shall contain the answer of the supplier according towhich he fullfills the requirement through its Quality System (what can be the case for requirementsalready transmitted through the QA-000725 or the BQR0003). The supplier shall referenced itsprocedures which is compliant with the Aircelle’s Quality requirement.

In the case where the requirement is not taken in account in his quality system, the box must contain themeans specifically implemented within the entity to be in compliance.

The answer has to be accurate and answer to following questions: what, who, when, how, how much andwhy.

The supplier of course has the possibility of exposing the method or the existing alternative solution in hissystem and this solution will be studied internally in Aircelle.

The box "Status" allows the supplier during the implementation of the requirement filling WIP when thesolution is in the way to be implemented but it’s only an intermediate status.The matrix is thus in permanent evolution until all the requirements are taken into account by thesuppliers.

The status of each Quality requirement shall be closed (status =”OK”) and shall be treated by the supplierat the DVI review of its product or in the same time of Aircelle’s approval of supplier’s ProductQuality Plan.

The compliance matrix shall be attached in appendix of the supplier’s Product Quality Plan (if requiredby Aircelle) or presented at the DVI review before the first product delivery.

6.2.1.3. Communication of the matrix evolutions between Aircelle and SuppliersThe matrix must always be up to date and can be required by Aircelle at anytime. It can also betransmitted to our Customer PowerJet at request.If necessary, the supplier can refer to the Aircelle Quality correspondent for any question or difficulty.Following the answers from the Supplier, Aircelle can require some information or refuse Supplier’sanswers and shall require other dispositions or solutions from the Supplier.Aircelle can also send evolutions of the matrix in case of some requirements changes or evolutions due tothe supplier. These evolutions will be identified by a letter as A, B, C, D … in this document or in thecolumn “requirement issue” in the compliance matrix.

6.3. DVI PROCESS IN DEVELOPMENT PHASETo Produce and attest the conformity of items to an Aircelle’s frozen definition or specification :

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 8/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

In development phase, Suppliers can establish its industrial file with an advance and preliminary definitionidentified by a definition change number :• DCAD number (Aircelle’s definition is complete in development phase )• or ACAD number (Aircelle’s definition or Aircelle’s specification is not complete) . In this case,

the Supplier cannot launch the production and shall contact the Aircelle correspondent to obtain afrozen and complete definition with DCAD number.

• CAD number (definition is complete in production phase)But, before the FIRST LAUNCHING OF PRODUCTION file of all Supplier‘s items, Supplier shall obtain toAircelle the number of Aircelle’s DCAD or CAD corresponding to the Aircelle’s frozen and completedefinition or specification for each Supplier’s items (Supplier shall contact Aircelle’s Purchaser if it don’thave received this DCAD or CAD number) . This DCAD’s or CAD’s number shall be noticed on theSupplier’s manufacturing file and will be reported on its statement of conformity for the delivery at Aircellefacilities.

DVI Aircelle’s acceptance :

In addition of chapter 2.3 of DVI Aircelle’s procedure and for the development phase, a DVI is required byAircelle for all parts which concerns :• certification tests phases (in case of doubt, please contact Aircelle’s certification responsible)• a justification of the definition design in series.The DVI of such parts shall be delivered in the same time of the first delivery of these parts andthe DVI shall be at least in status “accepted and to be completed” by Aircelle. The actions whichmust be completed shall not be suspensive and shall be approved by Aircelle.A “refused” DVI inhibits the delivery of the item taken into consideration. An article subject to DVIprocess cannot be delivered without its file or with an incomplete file without previous writtenauthorization from Aircelle’s Quality correspondent.All Supplier’s DVIs shall be in a closed status and accepted by Aircelle for the nacelle’s certificationrank and corresponding to Supplier’s items production rank. Consequently, Aircelle recommends toits Suppliers to foresee a definitive acceptance of the DVI by Aircelle as soon as possible (withoutany deviation).

6.4. DVI PROCESS IN PRODUCTION PHASEAny product will be accepted at Aircelle’s reception if DVI is not in a closed status (definitivelyaccepted) at the certification phase and at the production phase.

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 9/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

APPENDIX 1 : BQR0234-FORM1A - SAM146 NACELLE QUALITY REQUIREMENTS

Name of file: BQR0234-Form1A Quality Requirements of 23-06-06.xls

\\fichier-pl\plaisir\Small Nacelles\SaM146 Nacelle\Espace de Travail\05.Qualité\Plan Qualité Produit SaM146\Exigences Qualité SaM146 applicables aux fournisseurs\BQR0234-Form1A Quality Requirements du 23-06-06.xls

Otherwise the supplier has to justify in the DVI why certain not functional dimensions were not record.(example = manufacturing CN without change of tool and without change of reférentiel of manufacturing,

the conformance of certains records guarantee the conformity of the other dimensions)

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 10/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

APPENDIX 2 : BQR0234-FORM2A- ACCEPTANCE TEST REPORT FORMAT FORMODULES AND ITEMS WITH AIRCELLE TECHNICAL SPECIFICATIONS

Name of file: BQR0234-Form2A ATR model du 16-03-2006.xls

I:\CPB coordinateur\BQR0234-Form2A ATR model du 16-03-2006.xls

The Suppliers for modules and items with Aircelle technical specifications are required to deliver theproducts with an Acceptance Test Report in this Aircelle format. In addition the supplier shall establish anAcceptance Test Procedure which describes all tests requested on the material. The ATR shall beattached in appendix of the ATP.

The content of the document (columns designation, type and criteria) must be filled by the Supplier andfinally approved by Aircelle Quality. The focal point is the Aircelle’s Quality correspondent in charge of theSupplier’s product.

In header of the document, suppliers must fill the designation of the controlled part or module, followed byits part number, its serial number and its issue.

On the principal table, suppliers must complete:ü The designation of the control (example: profile, step, exit area…)ü The type of the control (section, measurement, visual…)ü The criteria and defined thresholdsü The result : failed / passed or the valueü The stamp of the inspectorü The concession number if applicable or any comments

On the second table, suppliers must complete the reference of the drawings, their designation and theirissue. The document has finally to be signed, stamped and dated by the supplier’s inspector.

BQR0234 AQuality requirements applicable toSuppliers/Partners on SaM146 nacelle

Program

Page : 11/11

Ce document est la propriété de Aircelle et ne doit pas être utilisé, communiqué ou reproduit sans son autorisationThis document is the property of Aircelle and shall not be used, duplicated or distributed without their approval

APPENDIX 3 : LIST OF DOCUMENTS REFERENCED

General quality requirements :Quality requirements applicable to Aircelle's suppliers BQR0003Quality requirements applicable to SAFRAN's suppliers QA-000725Quality requirements for intellectual services applicable to SAFRANs supplier GRP-0081

General Aircelle’s Procedures :Processing and exploitations of non-conformities AQG0027DVI process BQG0005Guidelines for writing a PRID Nacelle (only for major nacelle assemblies) BQG0078Traceability of items BQG0135Special process qualification BQM0009Management and follow-up of specific tooling (for reference of tools if Aircelle is theowner of these tools) BQM0031Supplier’s non-conformance BQR0042Supplier shipping / Toulouse site (only for major nacelle assemblies = modules) BQR0098Article classification ATG0008General technical specification ATG0024Aeronautical product qualification and certification ATV0022Article Functional category BTG0007Article – Material – Process classification BTG0009Determining key design characteristics BTG0010Guideline of non-conformance classification BTG0003Marking of items BTG0027Constitution of definition file BTG0029List of validated couples suppliers and materials / ingredients BQL0059(see this list on http://www.aircelle.com/suppliers_qa_docs.html )

Specific documents of SaM146 Nacelle program :Configuration Management Plan for the SaM146 program BPG0103List of material and product authorized on SaM146 Nacelle program HMLP0006General Protection plan for corrosion of SaM146 program BTG0072List of processes on SaM146 Nacelle Program SPM0001Aircelle internal Note on industrial ACAD management (ACAD “light”) SM-P-NI06-0109

PowerJet Procedures :Assembly quality Assurance SaM146.PWJ.QUA.PRO.00022Test Quality Assurance SaM146.PWJ.QUA.PRO.00023Test facilities validation SaM146.PWJ.QUA.PRO.00091

General standard procedures :Metrology requirements ISO10012Control of non-conforming product AS9131Retention rules AS/EN9130Part numbering and Marking ATA 200/2000Product preservation ATA3002D Marking prEN9132