- 1 -
BANGLADESH: Urban Resilience Project
Implementation Support Review Mission
June 16-20, 2019
Aide Memoire
INTRODUCTION
1. A World Bank Team1 carried out an Implementation Support Review (ISR) mission for the Urban Resilience Project (URP) from June 16 to 20, 2019. The objective of the mission was to: (i) review
implementation progress; (ii) review project targets and assess results indicators; and (iii) assess
implementation challenges and recommend remedial measures. This Aide Memoire (AM) summarizes the
mission’s findings, recommendations, and agreements reached with the relevant agencies to expedite
implementation. The AM was discussed at the wrap-up meeting on June 20, 2019 with the Secretary,
Planning Division, Ministry of Planning as Chair. As agreed, this AM will be classified as “Public” under
the World Bank’s Access to Information policy.
PROJECT DATA AND OVERALL STATUS
2. URP is a multi-ministerial project, executed by four implementing agencies; (i) Department of Disaster Management (DDM); (ii) Rajdhani Unnayan Kartripakkha (RAJUK); (iii) Project Coordinating
Monitoring Unit (PCMU); and (iv) Dhaka North City Corporation (DNCC) on behalf of DNCC, Dhaka
South City Corporation (DSCC), Fire Service and Civil Defense (FSCD) and Sylhet City Corporation
(SCC). Project activities are highly technical, inter-related across agencies which require phased planning
and implementation and are integral to the overall complex reform agenda for urban resilience. After a
slow start, the project is now making significant progress towards achieving the Project Development
Objective (PDO). IDA disbursement is at 29%.
3. Out of the four Implementing Agencies (IAs), DNCC is most advanced and implementation progress is
satisfactory. All consultancy services of RAJUK, DDM, and PCMU are under implementation after
significant initial delays related to procurement. DDM is expected to start the Training, Exercises and
Drills (TED) program from July 15, 2019, which brings together all emergency services supported under
the project. RAJUK has improved implementation and construction planning of the Urban Resilience Unit
(URU), being established under the Project, is expected to commence in October 2019. Based on the
mission, it was agreed that to achieve the PDO a restructuring was required to reallocate funds, adjust
results indicators and targets, and extend the closing date.
4. Many important activities such as completion of additional decentralized emergency services warehouses,
delivery of emergency management equipment, completion of Emergency Operation Centers (EOCs), etc.
are planned in the next few months. The mission advised the PIUs to take the opportunity to disseminate
these important milestones and raise awareness of the work the Government is doing to improve urban
resiliency and what has already been achieved, particularly in light of the recent fire events.
Table 1: Project Data as of June 30, 2019
Board Approval : March 24, 2015
Effectiveness Date : August 3, 2015
Closing Date : June 30, 2020
Mid-Term Review : December 8-13, 2018
Original IDA Credit XDR 122.80 million
(US$ 173 million equivalent)
GoB Contribution: US$ 6.5 million
IDA Amount Disbursed XDR 35.63 million
(US$ 49.34 million equivalent) (29%)
1 Swarna Kazi (Sr. Disaster Risk Management Specialist and Task Team Leader), Ignacio Urrutia (Sr. Disaster Risk Management
Specialist and Co-Task Team Leader), Haris Khan (Sr. Disaster Risk Management Specialist and Co-Task Team Leader), A.N.M.
Mustafizur Rahman (Sr. Procurement Specialist), Aisha De Guzman (Sr. Financial Management Specialist), Nadia Sharmin (Sr.
Environment Specialist), Md. Akhtar Zaman (Sr. Social Development Specialist), Debashish Paul Shuvra (Disaster Risk Management
Analyst), Mohammad Rafiqul Islam (Disaster Risk Management Analyst), S M Mehedi Hasan (Technical Consultant), Dewan Rakibul
Islam (Technical Consultant), Partha Protim Nath (Research Assistant), Mohammad Abdul Basit (Research Assistant), Md. Towshikur
Rahman (Research Assistant), Olivia Moutushi Sarker (Team Associate) and Amani Haque (Program Associate).
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
-
- 2 -
5. Reallocation: There are savings in the DDM and PCMU activities mostly due to lower prices in services from original estimates. There is approximately US$7 million financing gap in the RAJUK component
due to; (i) increased cost of Value Added Tax (VAT) & Income Tax (new legislation); (ii) higher than
estimated cost of consultancy services; (iii) price escalation; and (iv) increased construction cost for the
proposed Urban Resilience Unit (URU) building. This gap can be covered with savings from the DDM
and PCMU components. As agreed during the mission, RAJUK, DDM, and PCMU have agreed on a
proposed re-allocation among components. PCMU as the coordinating PIU, will lead the reallocation
process.
6. Revised Result Framework (RF): A revised RF has been developed based on the scope, timeline and
targets of the project. Activities remain the same, the proposed changes are intended to reflect the results
expected under the project more appropriately. Proposed revised results framework is in Annex IV.
7. Closing Date Extension: To properly complete ongoing activities, including construction of the URU
building and complete the sector reform activities, a 22-month extension until April 30, 2022 is required.
Initial delays were mostly related to the procurement of goods and services which are new to the country.
The extension will allow for: (i) reprogramming the implementation schedule of the Training, Exercises,
and Drills (TED) program under DDM which is now under an accelerated work program that may
compromise quality and the capacity of institutions to internalize the content; (ii) completion of the
consultancy services under RAJUK and adoption of the outcomes of these services in manner such that
these are embedded and integrated into RAJUK’s newly formed Urban Resilience Unit (URU); and (iii)
completion of the construction of the URU building which will require time until the end of the dry season
in 2022.
8. Next Steps for Restructuring: Formal request for restructuring to be sent to the Bank by July 15, 2019.
Restructuring to be completed by October 2019.
IMPLEMENTATION PROGRESS AND KEY FINDINGS
Component A: Reinforcing the Country’s Emergency Management Response Capacity (US$ 110
million)
9. The goal of Component A is to operationalize an integrated emergency management system that will enable to plan and respond to both everyday emergencies as well as major disasters in an organized and
effective manner. The component will finance: (i) construction and/or refurbishment of decentralized
facilities for emergency management and response; (ii) establishment of a communications network for
these facilities to operate during emergencies; (iii) provide specialized search and rescue equipment; and
(iv) train for emergency operations and response. The increased capacity to be evaluated through exercises
and drills.
10. At the time the project was designed, DNCC did not have any suitable premises, it was discussed, when
there was space, an EOC would be included for DNCC. Over the course of the project, DNCC now has a
well-established office space. As agreed with the Hon’ble Mayor DNCC, an EOC will now be established
for DNCC. Suitable, space has been allocated, a design and supervision firm and technical consultant are
already onboard, technical specifications are available, and there are savings within the component to
include this activity.
11. Out of the fifty-seven (57) planned decentralized facilities: Fifty-one2 (51) have been constructed or
renovated, and six (6) are in progress. Construction activities are on track for completion.
12. Construction of FSCD Command and Control Room (CCR) in Dhaka is 95% complete. Construction of
FSCD CCR including warehouses in Sylhet is 75% complete. Finishing work is ongoing in both CCR.
These two facilities are expected to be completed by July 15, 2019.
2 2 Fixed Control Rooms (CoC Mirpur and Sylhet), 13 Emergency Management Warehouses associated with 13 Auxiliary Control Rooms (11 Dhaka, 2 Sylhet) along with 8 Emergency Management Warehouses (DNCC-5, DSCC-3), 1 Emergency Operation Center
associated with 1 Urban Resilience Unit (Sylhet), 3 Disaster Risk Management Offices (DNCC, DSCC & SCC), 10 Zonal Control
Rooms (1 control at each zonal office)
-
- 3 -
13. The main delay under Component A works is with DSCC. The construction of the Emergency Operating
Centre (EOC) at DSCC, has progressed only 30%, due to site handover issues. As agreed during the
mission with the Hon’ble Mayor DSCC, the activity will be expedited immediately. This activity is
planned to be completed by September 30, 2019.
14. Supply and installation of emergency management and communication technology is ongoing. Equipment includes radio sets, terminals, communication towers, antennas, and mobile communication vehicle. The
sets of specialized equipment are being procured and delivered to the respective facilities. Contracts have
already been signed for most of the Information and Communication Technology (ICT) equipment
packages. Only remaining are- G-1-6/ICT Equipment for CCR at FSCD, Sylhet, G-1-7/ICT Equipment
for CCR at FSCD, Dhaka, G-1-8/ Specialized ICT Equipment (DMR(Digital Mobile Radio) Network and
Related Installations-VHF (Very High Frequency)) for FSCD, and G-1-12/ ICT Equipment for EOC at
DSCC. A list of equipment for FSCD that has already been supplied or under tender in attached in Annex
V.
15. Procurement of ICT Equipment for CCR at FSCD, Sylhet and Dhaka, and ICT Equipment for EOC DSCC
are in tender evaluation stage and will be signed by August 30, 2019. Tender is floated for Specialized
ICT Equipment (DMR Network and Related Installations-VHF) for FSCD and is expected to be signed
by October 30, 2019.
16. Application for frequency allocation from the Bangladesh Telecommunication Regulatory Commission
(BTRC) has been submitted by DNCC and DSCC. BTRC has granted frequency allocation for Ultra-high
Frequency (UHF) devices for DNCC. It was agreed that both DNCC and DSCC will follow-up urgently
for the pending frequency allocation of the High Frequency (HF) and UHF devices respectively.
Frequency allocation for all FSCD devices have already been granted.
17. Specialized Search and Rescue (SAR) equipment are being procured to increase capacity for timely
response in the event of an emergency. Most equipment has already been procured and delivery is ongoing.
The only SAR equipment that remains is the rescue boat, which is scheduled to be delivered by March 31,
2020.
18. The Training, Exercises, and Drills (TED) is being led by DDM, they have submitted all five deliverables (1.1: Final Curriculum, 1.2: Comprehensive Course Materials, 1.3: Tracking Tool Report, and 1.4:
Emergency Operations Plan (EOP) Planning Process report and 1.5: Final Training Plan) of first phase
under the contract. DDM must follow up closely to ensure that the trainings commence as soon as possible.
It was agreed that the trainings will start from July 15, 2019 and are scheduled to continue for two years
from commencement, depending on an extension of the project’s closing date.
Component B: Vulnerability Assessment of Critical and Essential Facilities (US$ 12 million)
19. The objective of this component is to develop a consensus-driven analytical foundation required for
longer-term investments to reduce risk in the built environment. This is being carried out through two sub-
components led by RAJUK, B1 (Consultancy Service S-4): Vulnerability assessment of critical and
essential facilities; and B2 (Consultancy Service S-5): Development of a Risk-Sensitive Land Use
Planning (RSLUP) practice, including a Strategic Environmental Assessment (SEA). Both contracts were
signed in October 2018. There was a substantial increase in the contract price from the estimated value.
Based on the mission findings, the extension of the project is required to achieve the required outcomes
and internalize the services rendered. Close monitoring by RAJUK is essential.
20. S-4: Consultancy Services for Vulnerability Assessment and Prioritized Investment Plan for Critical Assets
in Dhaka for URU. The Inception Report was approved on March 27, 2019. Prioritization parameters,
methodology and framework for survey and studies have been completed. Situation Analysis Report, data
collection, documentation, digitization, characterization of exposure data, preparation of GIS database has
been submitted. Rapid Visual Assessment (RVA) is ongoing, which encompasses 5 million sqm (about
4,000 structures) in greater Dhaka.
-
- 4 -
21. S-5: Consultancy Services for Development of Risk-sensitive Land Use Planning Practice for URU. The
Inception Report for this package was approved on March 27, 2019. The final Draft SEA Interim Report
will be submitted addressing Bank’s observation by July 15, 2019. As part of the geological survey and
investigation, 500 microtremor tests have been conducted in greater Dhaka, based on which the borehole
layout plan for the Standard Penetration Tests (SPTs) and Cone Penetration Tests (CPTs) will be prepared.
Comprehensive Situation Analysis and Diagnosis Report and Final Consultation Report has been
submitted. Preliminary data collection, report including comprehensive study to assess implications of
hazards, vulnerabilities and risks, are under preparation.
Component C: Improved Construction, Urban Planning and Development (US$ 41 million)
22. The objective of this component is to put in place the institutional infrastructure and competency to reduce
long-term disaster vulnerability, addressing both the existing built environment as well as future
development. The Minister of Housing and Public Works (MoHPW) approved the establishment of URU,
in principle, on April 29, 2019. Formal minutes will be circulated. After assessing the requirements during
the Mid Term Review (MTR), it was agreed that the one remaining consultancy package (with regard to
accreditation process) may be merged with an appropriate ongoing contract. Most importantly approval of
BNBC 2017 from respective authority within the project period is also crucial for utilizing the outcome in
full for this component.
23. S-6: Consultancy Services consultancy Services for Operationalizing the URU. Inception Report and
Situation Analysis were approved on March 27, 2019. Revised Institutional Design and Operational Study
(IDOS) was submitted on June 14, 2019. In addition to the services associated with the operationalization
of the URU, it will also be equipped with field and laboratory equipment.
24. S-7: Consultancy Services for Electronic Construction Permitting (ECP) System. The Inception Report
covering Construction Permitting, Assessment and Situation Analysis is complete. Baseline and Business
Operation Design (BOD) has been developed and is expected that the 1st prototype of software and ECP
strategy and action plan with relevant engagement and documentation will be submitted by July 20, 2019.
25. S-9: Consultancy Services for Building Code Implementation and Enforcement Strategy. Inception reports
that cover the initial assessment on code enforcement violations, status on violation cases, and resolutions
has been submitted and approved. Situation Analysis and Consultations Report is being reviewed.
Education campaign and outreach program of current findings to be initiated and will be integrated with
the next deliverables. Outcomes from this component will be integrated with ECP system.
26. S-11: Consultancy Services Regarding the Design and Supervision of URU Construction. The Design &
Supervision firm submitted the draft architectural drawing of the URU on June 16, 2019. All final design
and Bill of Quantities (BoQ) will be submitted by July 25, 2019. Works contract is expected to be signed
by November 15, 2019 and completion of construction will take approximately 2 years from
commencement, depending on closing date extension. Close monitoring and supervision by RAJUK will
be needed to ensure timely completion.
Component D: Project Coordination, Monitoring and Evaluation
27. PCMU is responsible for the overall coordination and monitoring of this multi-agency project. A key
activity is Monitoring and Evaluation (M&E) of all components through a specialized M&E Firm. The
M&E firm is now in place, a system is established, and the indicators are being tracked. The M&E Firm
has submitted four (4) Quarterly Progress Reports, M&E Framework Report and Baseline Survey Report.
28. PCMU signed a contract for the Internal Audit and the Draft Final report was submitted on May 15, 2019.
The PMIS dashboard (https://urp.gov.bd/) has been prepared. It was launched on June 13, 2019 at the
Project Steering Committee (PSC) meeting.
https://urp.gov.bd/
-
- 5 -
Operation & Maintenance (O&M) and Sustainability
29. While state of the art equipment is being procured, EOCs and an URU established, the project is also
looking at the sustainability of operations. This is being achieved through appropriate training of key staff,
a retention and absorption plan to mainstream these human resources in the government system and
allocation of appropriate recurring budget for new systems and infrastructure. All IAs should share a
sustainability plan, which would include budget, human resources and O&M, by September 30, 2019.
30. Through this project, RAJUK has begun the establishment of the URU. As of now, 54 personnel including
35 engineers, architects and planners, have been recruited. They are closely involved with the technical
interventions and are being trained through this process to improve their technical capacity. Once URU is
full established, the manpower will be integrated within URU to provide capacity building support,
operationalizing laboratory and field-testing activities and technical activities.
FIDUCIARY COMPLIANCE
31. Procurement
DNCC: Out of four implementing agencies DNCC has more complex procurement packages of
Goods/ICT equipment. Procurement process of all planned packages are in various stages of procurement.
As per STEP data and mission findings out of seven Specialized ICT Equipment (VHF and HF Radio
Terminals/DMR network and Related Installations) packages, three contracts are signed. Mission has
agreed on the time line for remaining four packages which is in the procurement process. Final delivery is
dependent on frequency issues. The high value package of DMR network (URP-DNCC/G-1-8/Specialized
ICT Equipment (DMR Network and Related Installations-VHF) for FSCD) are in bidding stage which
requires due diligence for successful outcome. Moreover, five procurement packages of ICT Equipment
for CCR/EOC/warehouses of city corporations are in bidding stages. Mission has agreed on a time line
in finalizing the contracts. DNCC will develop an inventory tool or procure off-the shelf software with
unique identification numbers for key ICT/rescue/heavy equipment for monitoring these sensitive and
valuable goods.
RAJUK is implementing key service packages; (i) Design and Supervision of URU Building; (ii)
Operationalizing the URU; (iii) Assessing the Current State and Deploying a Web-based Integrated
Information Management System for the Construction Permit System; (iv) Building Code Implementation
and Enforcement Strategy for URU; (v) Vulnerability Assessment and Prioritized Investment Plan for
Critical Assets in Dhaka; (vi) Development of Risk Sensitive Land Use Planning Practice. As all contracts
are lump-sum based complex contracts, RAJUK will start reporting deliverables from July 2019 through
an excel based platform. For all the above contracts the replaced key staff requires substantial monitoring
to cover-up the missing time-input.
DDM has one key consultancy contract of US$10 million which was signed on November 2018 and as
agreed in this mission the appropriate concurrence will be required for training budget allocation from
provisional-sum. DDM post-review contracts will have to be handled more professional way based on the
findings of the last review.
Those contracts are not generated through STEP may not be counted as completed contract.
32. Financial Management
Key FM actions such as the conduct of internal audit and installation of IBAS++ has been completed. It
was noted that the implementing agencies need to establish more stringent controls in ensuring that records
are updated, transactions are properly reviewed, and all expenditures are supported with the necessary
documents. The project experienced initial implementation delays and expenses are expected to increase
significantly in the coming months. This will mean more expenditures need to be appropriately processed
and supported with relevant documentation. As such, it is recommended that the PIUs strengthen the
bookkeeping process; establish and implement internal controls over transactions; and ensure that all
transactions are sufficiently reviewed by the qualified personnel. The following actions are recommended:
-
- 6 -
a. Ensure that all payment vouchers on file are completely supported with relevant documentation
and duly signed by the required personnel and officers of the government - It was noted during the
review of transactions that certain payment vouchers had missing signatories and/or have incomplete
supporting documents. IAs should ensure that all signatories sign the Payment Voucher as evidence
of review and are completely supported being the official document that supports all transactions.
Failure to present adequate documentation may result to ineligible expenses.
b. Ensure complete and updated books of account such as cash book, advance register, monthly bank
reconciliation statement and assets register. In addition, while the IAs are transitioning to the use
of IBAS++ and taking into consideration that the system is not yet able to produce real-time data
and customizable financial reports, it is recommended that the account officers continue with the
use of MS Excel sheets to monitor financial transactions and implement database back-up policies
and procedures to ensure the integrity of accounting records and avoid loss of information. As per
discussion with FMS, they have started regularly saving digital records at least monthly in back-up
drives.
c. Submit Internal Audit Report and monitor resolution of audit issues. M.I. Chowdury Firm was hired
by the PCMU to conduct the internal audit covering all the 4 IAs. As per PCMU, final discussions
of the audit findings were held on the second week of June 2019 and the final report is expected to
be submitted by the third week of June 2019. Prior to the finalization of the internal audit report,
PCMU has been assisting the various IAs in improving FM capacity by providing trainings on
different FM areas such as IBAS++, IFR and voucher preparation, cashbook maintenance and proper
record keeping. The mission commends the proactivity of PCMU in strengthening FM system of
the project.
d. Ensure maintenance of an Asset Registry and conduct annual physical count of inventory and
project assets – the project involves procurement of a number of goods. IAs should ensure an annual
physical count of all assets purchased for the project. PCMU will share a template of Asset register
that can be used by the IAs.
e. Ensure accuracy of tax deductions – it was noted that a difference was noted in the re-computation
of VAT in consultancy services for a certain contract with PCMU. It is recommended that the
correction be reviewed, and adjustments be made on the succeeding payments.
Compliance with the financial covenants
a. Audited project financial statements – External audit will continue to be carried out annually by the
Foreign Aided Project Audit Directorate (FAPAD) of C&AG. All IAs have submitted the audited
financial statements (AFS) for the period July 1, 2017 to June 30, 2018. During the mission, the
FMS of the different IAs provided updates on the status of the audit findings noted by FAPAD.
b. Interim Unaudited Financial Reports (IFRs) – IFRs are due for submission 45 days after the end of
each calendar quarter. The consolidated IUFR prepared by the PCMU for the quarter ended March
31, 2019 was submitted timely, on May 8, 2019. During the consolidated financial review, issues
were noted in the IFR of DNCC and it was agreed that the IFRs will be reviewed and revised to
include the corrections.
Disbursement Performance
Details of disbursement by category of expenditure is shown in the table 2. The disbursement under the
project is SOE based and as of June 18, 2019 is SDR 34.64 million which is 28% of the credit. About
SDR 935 thousand worth of withdrawal applications are targeted to be processed by June 30, 2019. A
large number of high valued procurement packages are still ongoing.
-
- 7 -
Table 02: Status of Fund Utilization/Disbursement Against Allocation as of 18 June 2019
(IDA 5590: Amounts in SDR)
Particulars
Financing
allocation
(a)
Withdrawn
from Bank
(b)
WAs in
process
(c)
Amount
undisbursed
from the
Bank
(a-b-c)
Disbursement
Rate3
Utilization
Rate 4
Goods, Works, CS, Non-CS,
Training and IOC 122,800,000 25,926,119 934,635 95,939,245 21% 22%
Emergency Expenses - - - - 0% 0%
Designated Account-A DNCC - 4,403,214 - (4,403,214)
Designated Account-B RAJUK - 2,610,361 - (2,610,361)
Designated Account-C DDM 898,297 (898,297)
Designated Account-D PCMU - 797,142 - (797,142)
Total 122,800,000 34,635,134 934,635 87,230,231 28% 22%
Withdrawal Applications (WA) of amount of SDR 563,353.17 have been submitted and under the processing
by the Bank as of June 19, 2019. With the latest data, total of USD 49.22 million (SDR 35.57 million) will be
disbursed from the beginning of project life should all WAs be processed by June 30, 2019. It is recommended
that the overall disbursement projection be reviewed for the remaining life of the project to have more realistic
projections and assess if there are funds to be unused. At this point in the life of the project, the overall
projection should be assessed to determine if there is a need to restructure and/or reallocate funds to other
expenses and/or components.
SAFEGUARD MANAGEMENT
33. Environmental Safeguards
i. City Corporation and FSCD: The overall performance of environmental safeguard compliance is on
track. The second monitoring report includes environmental safeguard status of the activities performed by
DNCC, DSCC, SCC and FSCD has been shared with the Bank. It was agreed that the implementing agency
would share the 3rd environmental monitoring report by December 1, 2019. The monitoring report should
also include the next six months training plan.
ii. DDM: DDM needs to share field status of environmental safeguard compliance of the refurbishment
work of three floors including setting up an office. The status can be incorporated in the environmental
monitoring report shared by city corporation. The contractor and field workers require training on the ESMF
before commencing the task.
iii. RAJUK: RAJUK has shared the revised Inception Report on Strategic Environmental Assessment
(SEA). RAJUK agreed to share the draft interim report of SEA by June 30, 2019. The mission has been
informed that the independent consultant for conducting the Environmental Impact Assessment (EIA) of the
RAJUK multi-storied building is on board. RAJUK agreed to share the draft EIA with the Bank by August 15,
2019 along with RAJUK’s review comment.
34. Social Safeguards
All subprojects of the constituent PIUs of the project were screened at the design stage and identified free from
incumbrances triggering any social safeguards compliance issues. Grievance redress mechanisms (GRM) and
a system for labor influx monitoring have been established as applicable with the respective PIUs. The PCMU
has also been carrying out oversight of the grievance management and labor influx issues including risks of
GBV at works site. The mission learnt that at least two complaints under the DNCC component were
successfully attended, one related to structure design and other related to labor safety. All PIUs having civil
3 Disbursement rate is the rate of the amount of withdrawal applications paid by the Bank divided by the IDA financing. 4 Utilization rate is the rate of the amount of withdrawal applications paid by the Bank (net of the Designated Accounts) and those in process, divided
by the IDA financing.
-
- 8 -
works component are reporting on labor influx and GRM activities but with inadequate representation like
disclosure and formal registration of complaints as per GRM. Monitoring and evaluation by PCMU has
consultant resources to attend social development and safeguards issues. All PIUs are requested to combine
social development, safeguards, labor influx and grievance management in their regular reports shared with
the PCMU and the World Bank.
NEXT STEPS AND AGREED ACTIONS
❖ Dhaka North City Corporation (DNCC):
▪ DNCC and DSCC to urgently follow up with Bangladesh Telecommunication Regulatory
Commission (BTRC) for frequency allocation permission.
▪ Complete construction of Emergency Operations Centers (EOC) in DSCC (with necessary assistance
from DSCC and approval from DSCC authority) by September 30, 2019
▪ Sign contracts of all remaining ICT equipment by October 30, 2019
❖ Department of Disaster Management (DDM):
▪ Start training of Training, Exercises, Drills (TED) program by July 15, 2019
❖ Rajdhani Unnayan Kartripakkha (RAJUK - Capital Development Authority):
▪ Sign works contract of URU building by November 15, 2019
❖ Project Coordination and Monitoring Unit (PCMU):
▪ Coordinate with Implementing Agencies for restructuring of the project
NEXT REVIEW: The next mission is proposed to take place on November 2019.
-
- 9 -
Annexes
Annex I: Key Agreed Actions ............................................................................................. - 10 -
Annex II: List of People Met .............................................................................................. - 25 -
Annex III: Updated Results Framework ............................................................................. - 26 -
Annex IV: Proposed Results Framework for Restructuring ............................................... - 32 -
Annex V: List of Equipment for FSCD from DNCC-URP Part ......................................... - 41 -
Annex VI: Proposed Institutional Design of Urban Resilience Unit .................................. - 43 -
Annex VII: Number of Staffs Engaged with URU and URU Technical Staffs.................. - 44 -
Annex VIII: Training Provided to URU Staffs under URP-RAJUK part .......................... - 45 -
Annex IX: Illustration ......................................................................................................... - 46 -
-
- 10 -
Annex I: Key Agreed Actions
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
All PIUs
1.
Upgradation of Financial
Management System to Multi-User
system
On-going All IA’s are uploading financial data into
IBAS++
2. Submission of Sustainability Plan On-going DNCC organized a workshop on Sustainability
plan on March 14, 2019
3. Uploading all post review package
documents in STEP On-going
4. Adaptation of labor influx monitoring
system and report quarterly On-going DNCC prepared the report
5.
Ensure that all payment vouchers on
file are supported with relevant
documentation and duly signed by the
required personnel and officers of the
government
On-going
6.
Prepare Asset Registry and conduct
annual physical count of inventory
and project assets
On-going
7.
Ensure complete and updated books
of account such as cash book,
advance register, monthly bank
reconciliation statement
On-going
-
- 11 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
DDM
8.
BD-DDM-29946 CS-QBS /
Consultancy Services for Training
Exercises and Drills (TED) Program
Contract Signing Done: November 19, 2018
Final Curriculum approved by Ministry on
May 16. 2019. Tentative Training July 15,
2019.
Reviewing ongoing of budget for
Comprehensive Budget Plan. Approval
procedure needs to be confirmed.
Prior concurrence from Bank to clear line item.
Confirmation of the availability
of the key personnel Done: November 26, 2018
Contract Effectiveness Done: December 11, 2018
Submission of Inception Report Done: January 21, 2019
Submission of Draft Done: May 16, 2019
Commencement of Training July 15, 2019
9.
BD-DDM-28928 CS-QBS
/Consultancy Services for "Design
and Supervision Consultancy" to
outfit NDMRTI & ERCC Facilities in
Dhaka
Preparation of Tender
Documents for NDMRTI and
ERCC renovation works
Done: January 7, 2019
Approval from DG (DDM) Done: January 27, 2019
10.
BD-DDM-44875 CW-RFB
/Renovation of the facility that would
house ERCC (BD-DDM-44875-GO-
RFB)
Tender Floating Done: January 31, 2019
Completion of Tender
Evaluation NoA (Notification of Award) pending
approval. Sent to MoDMR
Contract Signing July 15, 2019
Commencement of works July 30, 2019
Completion of works December 1, 2019
-
- 12 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
11.
BD-DDM-44877-CW-RFB
/Renovation of the facility that would
house NDMRTI (BD-DDM-44877-
GO-RFB)
Tender Floating Done: January 31, 2019
Completion of Evaluation NoA pending approval. Sent to MoDMR
Contract Signing July 15, 2019
Commencement of works July 30, 2019
Completion of works December 1, 2019
12. Recruitment of Contract Management
Specialist Done: April 1, 2019
13.
Draft Bid Documents including
Clauses for Labor Management and
Occupational Health and Safety
Share with Task Team and
Environment Safeguard Team Done: January 7, 2019
14. Submission of Safeguard Screening
Report
Environmental Screening
Report & Social Screening
Report
Done: December 9, 2018
DNCC
15.
URP-DNCC/G-1-1 / Procurement of
Specialized ICT Equipment (VHF
and HF Radio Terminals and Related
Installations) for FSCD (Lot-1: VHF,
Lot-2: HF)
Contract Signing Done: Lot 1: May 21, 2018
Done: Lot 2: May 30, 2018
Delivery of Equipment Done: Lot 1: January 6, 2019
Done: Lot 2: April 11, 2019
16.
URP-DNCC/G-1-2 / Procurement of
Specialized ICT Equipment (VHF
and HF Radio Terminals and Related
Installations) for City Corporations
(Lot-1: VHF, Lot-2: HF)
Contract Signing
Done: Lot 1: October 17, 2018 For VHF, Frequency Allocation permit is
obtained. But for HF the issue is still pending.
After frequency allocation permit, delivery will
commence.
Done: Lot 2: October 22, 2018
Delivery of Equipment
-
- 13 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
17.
URP-DNCC/G-1-3 / Procurement of
Specialized ICT Equipment (UHF
Radio Terminals and Related
Installations) for DSCC
Contract Signing Done: August 19, 2018 Mission team visited DSCC to discuss need to
expedite the Frequency Allocation permit as
well as Import Permission and Release of
Equipment permit. Delivery of Equipment
18.
URP-DNCC/G-1-4 / Procurement of
Specialized ICT Equipment (Lot-01:
DMR Network, UHF Radio
Terminals and Related Installations,
Lot-02: HF Radio Terminals and
Related Installations) for SCC
Tender Floating Done: November 7, 2018
Lot 1: Contract Signed
Lot 2: Frequency Allocation issue needs to be
resolved first. PIU to push for permission.
Completion of Tender
Evaluation- Lot 1
Completion of Tender
Evaluation- Lot 2
Contract Signing- Lot 01 Done: June 25, 2019
Contract Signing- Lot 02
Delivery- Lot 01
Delivery- Lot 02
19.
URP-DNCC/G-1-5 / Procurement of
ICT Equipment for Emergency
Operation Center (EOC) at SCC
Tender Floating Done: December 20, 2018
Completion of Tender
Evaluation July 30, 2019 NoA to be issued by July 30, 2019
Contract Signing August 30, 2019
Delivery of Equipment December 1, 2019
Installation of Equipment February 15, 2020
-
- 14 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
20.
URP-DNCC/G-1-6 / Procurement of
ICT Equipment for Command and
Control Room (CCR) at FSCD,
Sylhet
Tender Floating Done: December 20, 2018
Completion of Tender
Evaluation July 15, 2019 NoA to be issued by July 15, 2019
Contract Signing August 30, 2019
Delivery of Equipment December 31, 2019
Installation of Equipment March 15, 2020
21.
URP-DNCC/G-1-7 / Procurement of
ICT Equipment for Command and
Control Room (CCR) at FSCD,
Dhaka
Tender Floating Done: December 20, 2018
Completion of Tender
Evaluation July 30, 2019
Pending with consultant for technical
evaluation
Contract Signing August 30, 2019
Delivery of Equipment December 31, 2019
Installation of Equipment March 15, 2020
22.
URP-DNCC/G-1-8 / Procurement of
Specialized ICT Equipment (DMR
Network and Related Installations-
VHF) for FSCD
Tender Floating Done: May 14, 2019 Tender floated. Bid Closing date July 26, 2019
Tender Evaluation Report Sent
to the Bank August 15, 2019
Contract Signing October 30, 2019
Delivery and Installation of
Equipment October 15, 2020
-
- 15 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
23.
URP-DNCC/G-1-9 / Procurement of
Specialized ICT Equipment (DMR
Network and Related Installations-
VHF/HF/UHF) for DNCC
Tender Floating Done: November 8, 2018
Completion of Tender
Evaluation Done: May 25, 2019
Contract Signing Done: June 25, 2019
Delivery of Equipment January 1, 2020
24.
URP-DNCC/G-1-10 / Procurement of
Specialized ICT Equipment (DMR
Network and Related Installations-
UHF) for DSCC
Tender Floating
Completion of Tender
Evaluation Done: May 30, 2019
Contract Signing Done: June 23, 2019
Delivery of Equipment
25.
URP-DNCC/G-1-11 / Procurement of
ICT Equipment for Warehouses for
DNCC and DSCC
Tender Floating
Completion of Tender
Evaluation June 30, 2019 NoA to be issued by July 15, 2019
Contract Signing July 30, 2019
Delivery of Equipment October 30, 2019
26.
URP-DNCC/G-1-12 / Procurement of
ICT Equipment for Emergency
Operation Center (EOC) at DSCC
Tender Floating Done: December 27, 2018
Completion of Tender
Evaluation July 30, 2019
Pending with consultant for technical
evaluation
Contract Signing August 30, 2019
Delivery of Equipment February 1, 2020
-
- 16 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
27.
URP-DNCC/G-2-1 / Procurement of
Specialized Search and Rescue
Equipment (Emergency Tenders) for
FSCD
Shipment/Delivery: Phase 1 Done: August 30, 2018
Shipment/Delivery: Phase 2 Done: November 6, 2018
28.
URP-DNCC/G-2-3 / Procurement of
Specialized Search and Rescue
Equipment (Breathing Apparatus
Tenders)
Contract Signing Done: July 5, 2018
Shipment/Delivery Date Done: March 27, 2019
29.
URP-DNCC/G-2-4 / Procurement of
Specialized Search and Rescue
Equipment (Personal Protective
Equipment)
Contract Signing Done: June 4, 2018
Shipment/Delivery Date Done: March 20, 2019
30.
URP-DNCC/G-2-5 / Procurement of
Specialized Search and Rescue
Equipment (Rescuer Tools- Drone)
Contract Signing Done: August 6, 2018
Shipment/Delivery Date Done: November 20, 2018
31.
URP-DNCC/G-2-6 / Procurement of
Specialized Search and Rescue
Equipment (Lot-1: Ambulance, Lot-
2: Mortuary Van)
Contract Signing
Done: Lot-1: January 31, 2018
Done: Lot-2: January 31, 2018
Delivery of Equipment:
Lot-1: July 30, 2019 Shipping started on June 30, 2019.
Done: Lot-2: Dec 15, 2018
32.
URP-DNCC/G-2-9 / Procurement of
Turn Table Ladders Tender (60m) for
FSCD
Contract Signing Done: September 16, 2018
Delivery of Equipment August 30, 2019 Shipment started from July 01, 2019.
-
- 17 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
33. URP-DNCC/G-2-10 / Procurement of
HazMat Tender for FSCD
Contract Signing Done: March 31, 2019
Delivery of Equipment December 20, 2019 Awaiting FSCD approval on drawings. Will be
shipped in September 2019
34.
URP-DNCC/G-2-11 / Procurement of
Search and Rescue Equipment
(Rescue Boat)
Contract Signing July 30, 2019 NoA will be issued by July 15, 2019
Delivery of Equipment March 1, 2020
35. Procurement of MCCV
Technical Specification and
detailed estimate July 15, 2019
Preparation of technical specification will be
completed by July 15, 2019
Include in Procurement Plan July 30, 2019
Tender Floating August 15, 2019
Contract Signing September 30, 2019
36.
URP-DNCC/S-7 / GIS- Phase 1:
Need Assessment for Implementation
of GIS Infrastructure in the Urban
Resilience Project
Contract Signing Done: March 11, 2019
Completion September 1, 2019 Trainings started in DNCC office.
37.
URP-DNCC/S-8 / Enhancement the
effectiveness of DRR Emergency
Warehouses at DNCC
Contract Signing Done: June 13, 2019
Completion January 13, 2020
-
- 18 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
38.
URP-DNCC/ S-9 / Preparation of
GIS Based Maps (Ward level) at
DNCC, DSCC & SCC
RFP Issuance July 15, 2019 Proposals will be received by August 15, 2019
Completion of evaluation September 15, 2019 Evaluation will be completed by September 15,
2019
Contract Signing October 30, 2019
Completion October 30, 2020
39.
URP-DNCC/ W-1-1 / Construction of
FSCD Command and Control Room,
Dhaka (Vertical extension of 1st &
2nd floor of newly constructed
warehouse at FSCD Compound,
Mirpur-10, Dhaka)
Contract Signing Done: May 28, 2018
Completion July 15, 2019 95% work completed (Finishing work ongoing)
40.
URP-DNCC/ W-1-2 / Construction of
FSCD Command & Control Center
including Warehouses at South
Surma, Sylhet
Contract Signing Done: March 31, 2018
Completion July 30, 2019 75% work completed (Finishing work started)
41.
URP-DNCC/ W-2-1 / Construction of
Emergency Operation Center (EOC),
DRM Office and Urban Resilience
Unit at SCC Sylhet (Vertical
extension of 5th floor of SCC Nagar
Bhaban, Sylhet)
Contract Signing Done: May 28, 2018
Construction Completion Done: April 30, 2018 Civil construction completed
42.
URP-DNCC/ W-2-2 / Construction of
Emergency Operating Centre (EOC)
at DRM Office and Urban Resilience
Unit at DSCC, Dhaka
Contract Signing Done: November 18, 2018 Mission team met with Hon. Mayor DSCC to
discuss site handover issue. This will be
expedited. Construction Completion September 30, 2019
-
- 19 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
43. Submission of Bi-Annual
Environmental Monitoring Report Second EMR Submission Done: June 13, 2019
44. Approval of Frequency Allocation for
ICT equipment
Approval for FSCD Done: May 14, 2018
Approval for DNCC Status as of No. 13 and 14
Approval for DSCC Status as of No. 13 and 14
Approval for SCC Status as of No. 13 and 14
45. Inclusion of all proposed procurement
packages in STEP Done
46. Discussion with NBR on the issue of
CD & VAT for ICT Equipment Meeting with NBR July 20, 2019 PCMU to support DNCC
47.
Assign a deputy or technical staff in
DNCC to sign vouchers and review
work of FMS
48. Submit revised IFR and review bank
reconciliations statements
PCMU
49.
URP/PCMU/S-1 / Monitoring and
Evaluation Consultancy through a
Firm
Submission of PMIS Dashboard
Development Report Done: December 31, 2018
Establishment of PMIS
Dashboard Done: June 13, 2019
Submission of draft 3rd QPR Done: June 13, 2019
50. URP/PCMU/S-2 / Internal Audit
through a Firm
Submission of Internal Audit
Report June 30, 2019 Draft Final Report submitted on May 15, 2019.
-
- 20 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
51. Initiation of Restructuring Request June 20, 2019
52. 10th Project Steering Committee
(PSC) Meeting September 2019
9th PSC chaired by Hon. Secretary on June 13,
2019. Next PSC in September 2019
53. Review VAT computation June 30, 2019
RAJUK
54.
URP/RAJUK/S-4 / Consultancy
Services for Vulnerability
Assessment and Prioritized
Investment Plan for Critical Assets in
Dhaka for URU
Confirmation of the availability
of the key personnel
Approval of Inception Report Done: March 27, 2019
Submission of Situation
Analysis Report Done: June 12, 2019
Completion of RVA October 30, 2019
Fist deliverable is of 2 million sqm of
Vulnerability Assessment and Prioritized
Investment Plan for Critical Assets in Dhaka
55.
URP/RAJUK/S-5 / Consultancy
Services for Development of a Risk-
sensitive Land Use Planning Practice
for URU
Confirmation of availability of
key personnel Done: May 30, 2019
PIU received replacement proposal of Team
Leader and review process is ongoing.
Approval of inception report Done: March 27, 2019
Submission of Situation
Analysis Report Done: June 14, 2019
Submission of SEA Revised
Inception Report Done: June 12, 2019
-
- 21 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
Submission of SEA Revised
Interim Report July 15, 2019
Final SEA Report Submission August 30, 2019
Geotechnical and geological
tests and reports January 2020
Microtremor testing completed.
Borehole plan for SPT (Standard Penetration
Test) and CPT (Cone Penetration Test)
submitted on June 13, 2019
55.
URP/RAJUK/S-6 / Consultancy
Services for Operationalizing the
URU in RAJUK
Confirmation of availability of
key personnel Done: February 25, 2019 Confirmed by PIU
Approval of inception report Done: March 27, 2019
Inception report and Situation Analysis report
approved on March 26, 2019. Revised IDOS is
submitted on May 22, 2019.
Approval of Situation Analysis
and feasibility study report Done: March 27, 2019
IDOS (Intuitional Design and
Organizational Study) Done: June 30, 2019
Revised version of IDOS was received on June
14, 2019.
56.
URP/RAJUK/S-7 / Consultancy
Services for Assessing the Current
State and Deploying a Web-based
Integrated Information Management
System for the Construction Permit
System of RAJUK
Approval of inception report Done: March 27, 2019
Construction Permitting
Assessment System report Sent to Bank on May 23, 2019
Strategic Planning report July 31, 2019
Will be considered after the approval of
Construction Permitting Assessment System
report
57.
URP/RAJUK/S-8 / Consultancy
Services for Professional
Accreditation Program in RAJUK
Re-access requirement
RAJUK shared ToR with the Bank on May 28,
2019. On June 18, 2019 a meeting held with
different stakeholders like IEB, IAB etc.
-
- 22 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
58.
URP/RAJUK/S-9 / Consultancy
Services for Building Code
Enforcement
Confirmation of availability of
key personnel Confirmation verification pending by RAJUK
Approval of inception report Done: March 27, 2019
Submission of Situation
Analysis Report Done: May 2, 2019
59.
URP/RAJUK/S-11 / Consultancy
Services for Design and Supervision
of Urban Resilience Unit (URU)
Building including Research,
Training, and Testing Laboratory
facilities under RAJUK in Dhaka,
Bangladesh
Approval of Inception Report Done: March 27, 2019
Survey Report, Preliminary
Architectural Report and Draft
feasibility report
Done: May 15, 2019
Approval of Final Architectural
Design of URU Building July 25, 2019
Remaining design and drawings July 30, 2019
Preparation of Tender
Documents August 10, 2019
60. URP/RAJUK/W-2/ Establishment of
URU Building
Tender Floating August 30, 2019
Contract Signing November 15, 2019
Mobilization November 30, 2019
Complete Construction November 30, 2021
-
- 23 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
61.
URP/RAJUK/G-12 / Procurement of
Field and Laboratory Equipment for
URU
Approval of procurement plan Done: December 17, 2018
Tender Floating Done: January 3, 2019
Completion of Evaluation Done: April 2, 2019
Contract Signing Done: May 16, 2019
Supply and Delivery December 1, 2019
62.
URP/RAJUK/G-13 / Procurement of
Field and Laboratory Equipment for
URU
Approval of procurement plan Done: December 17, 2018
Tender Floating Done: January 15, 2019
Completion of Evaluation Board Approved. Minutes to be signed by
Chairman of RAJUK
Contract Signing July 20, 2019
Supply and Delivery December 1, 2019
63.
URP/RAJUK/G-15 / Procurement of
Field Equipment for Vulnerability
Assessment Aspect of Structures &
Geo physics (post review)
Approval of procurement plan Done: December 17, 2018
Tender Floating Done: January 3, 2019
Completion of Evaluation Done: March 31, 2019
Contract Signing Done: May 6, 2019
Supply and Delivery December 1, 2019
-
- 24 -
No. Activity Description Actions/ Sub-Activities Due Date as per ISR
(June 16-20, 2019) Remarks
64.
URP/RAJUK/G-16 /Procurement of
Equipment for Exploration of RSLUP
Profile: 200 kN Truck Mounted CPT
Equipment (post review)
Approval of procurement plan Done: December 17, 2018
Tender Floating Done: January 3, 2019
Completion of Evaluation Under review by RAJUK procurement
Contract Signing
Supply and Delivery
60 Submission of Draft EIA Report of
URU Building
Contract Signing Done: May 30, 2019
Draft Final Report August 15, 2019
Completion September 30, 2019
61 Updated Detailed Work Plan Submission to Bank July 15, 2019
62 Coordination with authorities and the
consultants on BNBC 2017 Continuous
-
- 25 -
Annex II: List of People Met
Division, Ministry of Planning
• Mr. Md. Nurul Amin, Secretary, Planning Division
Economic Relation Department, Ministry of Finance
• Mr. Tahmid Hasnat Khan, Joint Secretary, Finance Division
• Mr. Najia Islam, Deputy Secretary, Economic Relation Department
Project Coordinating Monitoring Unit (PCMU), Programming Division, Ministry of Planning
• Mr. Zafar Ullah, PD-URP, DG-PCMU, Programming Division
• Md. Khayrul Hasan, Director, URP, PCMU, Programming Division
• Ms. Jahan Ara, Deputy Director, URP, PCMU, Programming Division
Ministry of Housing and Public Works (MoHPW)
• Mr. Md. Shahid Ullah Khandaker, Secretary, MoHPW
Ministry of Local Government Rural Development & Cooperatives (MoLGRD&C)
• Mr. Helal Uddin Ahmed, Secretary, LGD
Ministry of Disaster Management & Relief (MoDMR)
• Mr. Md. Shah Kamal, Secretary, MoDMR
• Mr. M. Khalid Mahmood, Joint Secretary, MoDMR
Dhaka North City Corporation (DNCC)
• Md. Atiqul Islam, Hon’ble Mayor, DNCC
• Dr. Tariq Bin Yousuf, Project Director, URP-DNCC Part
• Mohammad Abul Kashem, Deputy Project Director (Procurement & Contract Management), URP-DNCC Part
• Mr. Abdul Halim, Sr. Procurement Specialist, URP-DNCC Part
Dhaka South City Corporation (DSCC)
• Mr. Mohammad Sayeed Khokon, Hon’ble Mayor, DSCC
• Mr. Md. Sirajul Islam, DPD-URP DNCC, DSCC
• Mr. Abu Tayeb Rokon , System Analyst, Dhaka South City Corporation
Department of Disaster Management (DDM)
• Md. Abdul Mannan, PD, URP-DDM
• Md. Hasan Zahid, Procurement Specialist, URP-DDM
• Mr. Shyamal Chandra Shill, Accountant, URP-DDM
Rajdhani Unnayan Kartripakkha (RAJUK)
• Dr. Sultan Ahmed, Chairman, RAJUK
• Mr. Abdul Latif Helaly, Project Director, URP-RAJUK
• Mr. Md. Aminur Rahman, Deputy Project Director, URP-RAJUK
• Mr. Md. Shahjahan, Sr. Financial Management and Planning Specialist, URP-RAJUK
• Mr. Md. Mahboob Hassan, Sr. Procurement Specialist, URP-RAJUK
• Mr. Md. Saifur Rahman Joarder, Procurement Specialist, URP-RAJUK
Fire Service and Civil Defense (FSCD)
• Brigadier General Md Sazzad Hussain, ndc, afwc, psc, Mphil, DG, FSCD
• Mr. Zillur Rahaman, Lieutenant Colonel, Director (Operations), FSCD
Monitoring and Evaluation Firm (GOPA Consultants, and Services and Solutions Int. Ltd.)
• Mr. Richard Carlos Worden, Acting Team Leader, URP M&E. PCMU, Planning Commission
• Mr. Shaker Ahmed, Deputy Team Leader, URP M&E. PCMU, Planning Commission
• Mr. A.B.M. Shamsul Arefin, M&E Specialist, URP-PCMU, Planning Commission
• Mr. Syed Muhammad Latif, Environmental Safeguard Specialist, URP M&E. PCMU, Planning Commission
• Mr. Monzur Rahman, Social Safeguard Specialist, URP M&E. PCMU, Planning Commission
• Mr. Md. Farid Uddin, Managing Director, Services and Solutions International Limited (SSIL)
-
- 26 -
Annex III: Updated Results Framework
Project Development Objective Indicators
Indicator Name Unit of
Measure Baseline
Cumulative Target Values
Frequency Data Source/
Methodology
Responsible
for
data
collection
Comments
YR1 YR2 YR3 YR4 YR5
Share of wards with decentralized
emergency response services in
Dhaka (DNCC/DSCC jurisdiction)5
Number
PAD
Targets 0 0 0 23 45 68
Annual
DNCC, DSCC,
FSCD/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 23 45
Share of wards with decentralized
emergency response services in
Sylhet (SCC jurisdiction)6
Number
PAD
Targets 0 0 0 7 14 20
Annual
SCC, FSCD/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 20
Increased capacity of officials and
emergency management response
personnel7
Composite
Scale
PAD
Targets N/A
Base
line
Base
line
Base
line
+ 1
Basel
ine +
2
Base
line
+ 3 Annual
DDM/ Based on
the training,
exercises and
drills consultant
PCMU and
M&E
Consultants
In progress
Actual
Achieved N/A N/A N/A N/A N/A
Systems established to reduce
vulnerability of new buildings in
Dhaka and Sylhet8
Number
PAD
Targets 0 0 0 0 1 3
Annual
RAJUK, SCC/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 0
5 Number of wards where corresponding zonal offices are equipped with ECT kits and are at least partially within five kilometers radius of at least one emergency management warehouse or one equipped FSCD control room
6 Number of wards within five kilometers of at least one emergency management warehouse or equipped FSCD control room
7Annual inter-agency exercise and drills program that tests and evaluates the skills and abilities of emergency personnel on an aggregate score of 1-10. The methodology for determining the baseline will be developed by the training,
exercises and drills consultant prior to program commencement. 8 Systems include: Urban Resilience Unit, Electronic Construction Permitting, Professional Accreditation Program
-
- 27 -
Indicator Name Unit of
Measure Baseline
Cumulative Target Values
Frequency Data Source/
Methodology
Responsible
for
data
collection
Comments
YR1 YR2 YR3 YR4 YR5
Intermediate Results Indicators
Component A
DDM facilities renovated (ERCC,
NDMRTI) Number
PAD
Targets 0 0 2 2 2 2
Annual
DDM/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 0
FSCD facilites constructed and/or
renovated9
Number
PAD
Targets 0 0 10 20 29 31
Annual
FSCD/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 13 28
DNCC/DSCC/SCC facilities
constructed and/or renovated10 Number
PAD
Targets 0 0 10 15 24 26
Annual
DNCC/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 8 8 24
DDM/DNCC/DSCC/SCC/FSCD and
Satellite Control Room facilities
equipped with ECT suites and/or
kits11
Number
PAD
Targets 0 0 0 25 53 57
Annual
DNCC/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 17
9 Two fixed control rooms, 12 emergency management warehouses and 17 auxiliary control rooms 10 10 emergency management warehouses, two emergency operations centers, three disaster risk management offices, 10 zonal control rooms, one urban resilience unit 11 6 ECT suites and 51 “flyaway” communications kits
-
- 28 -
Indicator Name Unit of
Measure Baseline
Cumulative Target Values
Frequency Data Source/
Methodology
Responsible
for
data
collection
Comments
YR1 YR2 YR3 YR4 YR5
FSCD emergency management
warehouses equipped with
specialized search and rescue
equipment
Number
PAD
Targets 0 0 0 10 12 12
Annual
FSCD/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 13
Multi-agency exercises and drills
completed Number
PAD
Targets 0 0 2 4 8 12
Annual
DDM/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 0
Component B
Identification of critical and essential
facilities and lifelines for Dhaka12 Percentage
PAD
Targets 0 0 50 100 100 100
Annual
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress.
Will be revised during
upcoming
restructuring.
Database of critical and
essential facilities
developed
Actual
Achieved 0 0 0 0 100
12 Consulting firm will first identify all critical and essential facilities and lifelines for Dhaka, then prioritize a limited list to survey and assess for the following stage
-
- 29 -
Indicator Name Unit of
Measure Baseline
Cumulative Target Values
Frequency Data Source/
Methodology
Responsible
for
data
collection
Comments
YR1 YR2 YR3 YR4 YR5
Vulnerability of prioritized critical
and essential facilities and lifelines
assessed for Dhaka
Percentage
PAD
Targets 0 0 0 25 75 100
Annual
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress.
Will be revised during
upcoming
restructuring.
Inception, Stakehoilder
engagemenmt, and
Situation Analysis
completed. Survey
completed.
Methodology for
vulnerability
assessment established
(RVA, PEA & DEA)
10% RVA completed
Actual
Achieved 0 0 0 0 25
Component C
E-Permits for construction issued by
RAJUK13 Number
PAD
Targets N/A 0 0 0
Basel
ine
set
Base
line
+30
%
Annual
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress. Will be
revised during
upcoming
restructuring.
Current construction
permitting practice
studies completed.
Actual
Achieved N/A 0 0 0 0
13 Baseline will be set one year after system is publicly launched
-
- 30 -
Indicator Name Unit of
Measure Baseline
Cumulative Target Values
Frequency Data Source/
Methodology
Responsible
for
data
collection
Comments
YR1 YR2 YR3 YR4 YR5
RAJUK Urban Resilience Unit
facility constructed Percentage
PAD
Targets 0 0 20 80 100 100
Annual
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress. Will be
revised during
upcoming
restructuring.
All design and
specifications for the
URU construction is
completed
Actual
Achieved 0 0 0 0 5
RAJUK Urban Resilience Unit
facility equipped with laboratory and
field-testing equipment
Percentage
PAD
Targets 0 0 0 50 75 100
Annual
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
3 of the 4 packages for
equipment are signed
and to be delivered
shortly. Technical
evaluation of the
remaining 1 package
underway.
Actual
Achieved 0 0 0 0 0
Professional Accreditation Program
for Engineers, Architects and
Planners established
N/A PAD
Targets
N/A
Consu
ltat
ion p
roce
ss w
ith
sta
keh
old
ers
com
ple
ted
Res
earc
h a
nd a
nal
yti
cal
form
ula
tio
n
com
ple
ted
Acc
redit
atio
n b
oar
d e
stab
lish
ed
Pla
tform
for
conti
nued
ed
uca
tio
n a
nd
trai
nin
g t
o s
upp
ort
cer
tifi
cati
on
est
abli
shed
Outr
each
and E
du
cati
onal
Cam
pai
gn
com
ple
ted
Annual
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
Will be revised during
upcoming
restructuring.
-
- 31 -
Indicator Name Unit of
Measure Baseline
Cumulative Target Values
Frequency Data Source/
Methodology
Responsible
for
data
collection
Comments
YR1 YR2 YR3 YR4 YR5
Actual
Achieved N/A
N/A
N/A
N/A
N/A
Component D
Monitoring Reports produced Number
PAD
Targets 0 4 8 12 16 20
Quarterly PCMU
PCMU and
M&E
Consultants
In progress. Target will
be revised during
upcoming
restructuring. Actual
Achieved 0 0 0 1 4
-
- 32 -
Annex IV: Proposed Results Framework for Restructuring
Indicator Name
Un
it
Ba
seli
ne Cumulative Target Values
Fre
qu
ency
Da
ta S
ou
rce/
Met
ho
do
log
y
Res
po
nsi
ble
for
da
ta
coll
ecti
on
Comments
YR1 YR2 YR3 YR4 YR5 YR6 YR7
Project Development Objective Indicators
Ex
isti
ng
Share of wards with
decentralized emergency response
services in Dhaka
(DNCC/DSCC jurisdiction)14
Nu
mber
PAD
Targets 0 0 0 23 45 68 68 68
An
nu
al
DNCC,
DSCC,
FSCD/ Monitoring
Reports
PCMU
and
M&E Consult
ants
In progress
Actual
Achieved 0 0 0 23 45
Ex
isti
ng Share of wards with
decentralized
emergency response
services in Sylhet
(SCC jurisdiction)15
Nu
mber
PAD
Targets 0 0 0 7 14 20 20 20
An
nu
al
SCC, FSCD/
Monitoring
Reports
PCMU and
M&E
Consult
ants
In progress
Actual
Achieved 0 0 0 0 20
Ex
isti
ng Increased capacity of
officials and emergency
management response
personnel16
Co
mpo
site
Sca
le
PAD
Targets N/A N/A N/A
Baseline
Baseline + 1 Baseline + 2 Baseline + 2 Baseline + 3
An
nu
al
DDM/ Based on the
training,
exercises and drills
consultant
PCMU
and M&E
Consult
ants
Revised as
follows Actual
Achieved N/A N/A N/A N/A N/A
Rev
ised
Increased capacity of officials and
emergency
management response personnel17
Co
mpo
site
Sca
le
Revised
Targets N/A N/A N/A N/A N/A Baseline Baseline + 1 Baseline + 3
An
nu
al
DDM/ Based
on the
training,
exercises and
drills
consultant
PCMU and
M&E
Consultants
In progress
Actual
Achieved N/A N/A N/A N/A N/A
14 Number of wards where corresponding zonal offices are equipped with ECT kits and are at least partially within five kilometers radius of at least one emergency management warehouse or one equipped FSCD control room 15 Number of wards within five kilometers of at least one emergency management warehouse or equipped FSCD control room
16Annual inter-agency exercise and drills program that tests and evaluates the skills and abilities of emergency personnel on an aggregate score of 1-10. The methodology for determining the baseline will be developed by the training,
exercises and drills consultant prior to program commencement.
17Annual inter-agency exercise and drills program that tests and evaluates the skills and abilities of emergency personnel on an aggregate score of 1-10. The methodology for determining the baseline will be developed by the training,
exercises and drills consultant prior to program commencement.
-
- 33 -
Indicator Name
Un
it
Ba
seli
ne Cumulative Target Values
Fre
qu
ency
Da
ta S
ou
rce/
Met
ho
do
log
y
Res
po
nsi
ble
for
da
ta
coll
ecti
on
Comments
YR1 YR2 YR3 YR4 YR5 YR6 YR7
Ex
isti
ng Systems established to
reduce vulnerability of
new buildings in
Dhaka and Sylhet18
Nu
mber
PAD Targets
0 0 0 0 1 3
An
nu
al RAJUK,
SCC/
Monitoring
Reports
PCMU
and
M&E Consult
ants
Revised as
follows Actual
Achieved 0 0 0 0 0
Rev
ised
Systems developed to
increase resilience of
built environment in Dhaka19 N
um
ber
Revised
Targets 0 0 0 0 0 0 1 3
An
nu
al RAJUK,
SCC/
Monitoring Reports
PCMU
and M&E
Consult
ants
In progress
Actual
Achieved 0 0 0 0 0
Intermediate Results Indicators
Component A
Ex
isti
ng
DDM facilities (ERCC, NDMRTI)
renovated Nu
mber
PAD
Targets 0 0 2 2 2 2
An
nu
al
DDM/ Monitoring
Reports
PCMU
and M&E
Consult
ants
Revised as
follows
Actual
Achieved 0 0 0 0 0
Rev
ised
DDM facilities
(ERCC, NDMRTI) renovated and
equipped Nu
mber
Revised
Targets 0 0 0 0 0 1 2 2
An
nu
al
DDM/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 0
18 Systems include: Urban Resilience Unit, Electronic Construction Permitting, Professional Accreditation Program 19 Systems include: Urban Resilience Unit, Electronic Construction Permitting System, Risk Sensitive Land Use Planning Practice
-
- 34 -
Indicator Name
Un
it
Ba
seli
ne Cumulative Target Values
Fre
qu
ency
Da
ta S
ou
rce/
Met
ho
do
log
y
Res
po
nsi
ble
for
da
ta
coll
ecti
on
Comments
YR1 YR2 YR3 YR4 YR5 YR6 YR7
Ex
isti
ng
FSCD facilities
constructed and/or renovated N
um
ber
PAD Targets
0 0 10 20 29 31
An
nu
al
FSCD/
Monitoring Reports
PCMU
and
M&E Consult
ants
Revised as
follows Actual
Achieved 0 0 0 13 28
Rev
ised
FSCD facilities
constructed and/or renovated and
equipped20 Nu
mber
Revised
Targets 0 0 10 20 28 28 28 28
An
nu
al
FSCD/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 13 28
Ex
isti
ng
DNCC/DSCC/SCC facilities constructed
and/or renovated Nu
mber
PAD Targets
0 0 10 15 24 26
An
nu
al
DNCC/ Monitoring
Reports
PCMU
and M&E
Consult
ants
Revised as
follows Actual
Achieved 0 0 8 8 24
Rev
ised
DNCC/DSCC/SCC
facilities constructed and/or renovated and
equipped21 Nu
mber
Revised
Targets 0 0 10 15 24 30 30 30
An
nu
al
DNCC/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 8 8 24
Ex
isti
ng
DDM/DNCC/DSCC/S
CC/FSCD and
Satellite Control Room facilities equipped
with ECT suites and/or
kits
Nu
mber
PAD
Targets 0 0 0 25 53 57
An
nu
al
DNCC/
Monitoring
Reports
PCMU and
M&E
Consultants
Revised as follows
Actual
Achieved 0 0 0 0 17
20 2 fixed control rooms, 13 emergency management warehouses and 13 auxiliary control rooms 21 8 emergency management warehouses, 3 emergency operations centers, 8 disaster risk management offices, 10 zonal control rooms, one urban resilience unit in Sylhet EOC
-
- 35 -
Indicator Name
Un
it
Ba
seli
ne Cumulative Target Values
Fre
qu
ency
Da
ta S
ou
rce/
Met
ho
do
log
y
Res
po
nsi
ble
for
da
ta
coll
ecti
on
Comments
YR1 YR2 YR3 YR4 YR5 YR6 YR7
Rev
ised
DDM/DNCC/DSCC/S
CC/FSCD and Satellite Control Room
facilities equipped
with Emergency
Communication
Technology (ECT)
suites and/or kits22
Nu
mb
er
Revised
Targets 0 0 0 0 17 57 57 57
An
nu
al
DNCC/ Monitoring
Reports
PCMU
and M&E
Consult
ants
In progress
Actual
Achieved 0 0 0 0 17
Ex
isti
ng FSCD emergency
management warehouses equipped
with specialized search
and rescue equipment
Nu
mber
PAD
Targets 0 0 0 10 12 12
An
nu
al
FSCD/ Monitoring
Reports
PCMU
and M&E
Consult
ants
In progress
Actual
Achieved 0 0 0 0 13
Ex
isti
ng
Multi-agency exercises
and drills completed
Nu
mber
PAD Targets
0 0 2 4 8 12
An
nu
al
DDM/ Monitoring
Reports
PCMU
and M&E
Consult
ants
Revised as
follows Actual
Achieved 0 0 0 0 0
Rev
ised
Multi-agency training,
exercises and drills (TED) program
completed Nu
mber
Revised
Targets 0 0 0 0 0 6 9 12
Qu
arte
rly
DDM/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 0
Component B
Ex
isti
ng
Identification of
critical and essential
facilities and lifelines for Dhaka P
erce
nta
ge
PAD
Targets 0 0 50 100 100 100
An
nu
al
RAJUK/ Monitoring
Reports
PCMU
and M&E
Consult
ants
Merged with the
next
indicator and revised
as follows Actual
Achieved 0 0 0 0 0 100
22 6 ECT suites and 51 “flyaway” communications kits
-
- 36 -
Indicator Name
Un
it
Ba
seli
ne Cumulative Target Values
Fre
qu
ency
Da
ta S
ou
rce/
Met
ho
do
log
y
Res
po
nsi
ble
for
da
ta
coll
ecti
on
Comments
YR1 YR2 YR3 YR4 YR5 YR6 YR7
Ex
isti
ng
Vulnerability of
prioritized critical and essential facilities and
lifelines assessed for
Dhaka
Per
cen
tage
PAD
Targets 0 0 0 25 75 100
An
nu
al
RAJUK/ Monitoring
Reports
PCMU
and M&E
Consult
ants
Revised as
follows Actual
Achieved 0 0 0 0 25
Rev
ised
Vulnerability
assessment of critical and essential facilities
and development of
vulnerability reduction strategy and program
Per
cen
tage
Revised
Targets 0 0 0 0
20%
Database of critical
and essential
facilities developed
60%
1. Survey and Rapid Visual Assessment
(RVA) completed
2. Preliminary
Engineering Analysis
and Vulnerability
assessment conducted
80%
Detailed Engineering
Analysis and
defining the structural
performance
standards are
completed
100%
1. Detailed design and
cost estimation for retrofitting of all the
selected structures
completed
2. Design of long-term
vulnerability reduction
investment plan and
Dhaka Urban Resilience Strategy completed
An
nu
al
RAJUK/
Monitoring Reports
PCMU
and
M&E Consult
ants
In progress
Actual
Achieved 0 0 0 0 20
New
Development of a risk-
sensitive land use planning practice in
Dhaka Per
cen
tage Revised
Targets 0 0 0 0
40%
1. Assessment of
plans and planning
systems of RAJUK and stakeholders
conducted
2. Strategic
framework and
implementation plan for geotechnical and
geological
investigation prepared
70%
1. Strategic
Environment Assessment (SEA)
Report for Greater
Dhaka area developed
2. Develop
methodology and framework for Risk-
Sensitive Land Use
Planning Practice (RSLUP) particularly
suited for Dhaka
3. Seismic
Microzonation studies
conducted
90%
1. Framework for
mainstreaming Disaster Risk
Reduction
(DRR) into the greater Dhaka
planning system
developed
2. Greater Dhaka
Risk Sensitive Land Use
Strategy
developed.
100%
1. Risk Sensitive Land Use Planning practice
developed for the
greater Dhaka planning system
2. Integrating and mainstreaming Hazard
and Vulnerable Risk
Assessment (HVRA) into the current planning
practice
An
nu
al
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 40
-
- 37 -
Indicator Name
Un
it
Ba
seli
ne Cumulative Target Values
Fre
qu
ency
Da
ta S
ou
rce/
Met
ho
do
log
y
Res
po
nsi
ble
for
da
ta
coll
ecti
on
Comments
YR1 YR2 YR3 YR4 YR5 YR6 YR7
Component C
Ex
isti
ng
E-Permits for
construction issued by RAJUK N
um
ber
PAD Targets
N/A 0 0 0 Baseline set Baseline +30%
An
nu
al
RAJUK/
Monitoring Reports
PCMU
and
M&E Consult
ants
Revised as
follows Actual
Achieved N/A 0 0 0 0
Rev
ised
Electronic Construction
Permitting (ECP)
System developed by RAJUK
Per
cen
tage Revised
Targets N/A 0 0 0
30%
Assessment of
current construction
permitting practice
70%
1. System design completed
2. Prototype/s of ECP System developed
followed by end-user’s
feedback, testing and bug-fixing completed
90%
1. ECP system
implemented
2. Trainings
provided and Operational
Acceptance Test
(OAT) performed
100%
ECP integrated into RAJUK
An
nu
al
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved N/A 0 0 0 30
Ex
isti
ng
RAJUK Urban Resilience Unit facility
constructed
Per
centa
ge PAD
Targets 0 0 20 80 100 100
An
nu
al
RAJUK/ Monitoring
Reports
PCMU
and M&E
Consult
ants
Revised as
follows Actual
Achieved 0 0 0 0 5
Rev
ised
RAJUK Urban Resilience Unit
Constructed,
Established and Functional
Per
cen
tage Revised
Targets 0 0 0 0
20%
All design and specifications for the
URU construction is
completed
60%
1. Institutional design and Organizational
Study is conducted
2. A comprehensive
out-reach campaign is
designed and implemented
80%
Capacity
building and training for URU
staffs conducted
100%
1. URU building
construction completed
2. URU set-up
completed and
functional
An
nu
al
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
In progress
Actual
Achieved 0 0 0 0 20
-
- 38 -
Indicator Name
Un
it
Ba
seli
ne Cumulative Target Values
Fre
qu
ency
Da
ta S
ou
rce/
Met
ho
do
log
y
Res
po
nsi
ble
for
da
ta
coll
ecti
on
Comments
YR1 YR2 YR3 YR4 YR5 YR6 YR7
Ex
isti
ng RAJUK Urban
Resilience Unit facility
equipped with
laboratory and field-testing equipment
Per
cen
tage
PAD
Targets 0 0 0 50 75 `100
An
nu
al
RAJUK/
Monitoring
Reports
PCMU and
M&E
Consultants
Revised as
follows
Actual
Achieved 0 0 0 0 0
Rev
ised
RAJUK Urban
Resilience Unit facility equipped with
laboratory and field-
testing equipment
Per
cen
tage
Revised
Targets 0 0 0 0 0
70%
Test equipm