- 1 - BANGLADESH: Urban Resilience Project Implementation Support Review Mission June 16-20, 2019 Aide Memoire INTRODUCTION 1. A World Bank Team 1 carried out an Implementation Support Review (ISR) mission for the Urban Resilience Project (URP) from June 16 to 20, 2019. The objective of the mission was to: (i) review implementation progress; (ii) review project targets and assess results indicators; and (iii) assess implementation challenges and recommend remedial measures. This Aide Memoire (AM) summarizes the mission’s findings, recommendations, and agreements reached with the relevant agencies to expedite implementation. The AM was discussed at the wrap-up meeting on June 20, 2019 with the Secretary, Planning Division, Ministry of Planning as Chair. As agreed, this AM will be classified as “Public” under the World Bank’s Access to Information policy. PROJECT DATA AND OVERALL STATUS 2. URP is a multi-ministerial project, executed by four implementing agencies; (i) Department of Disaster Management (DDM); (ii) Rajdhani Unnayan Kartripakkha (RAJUK); (iii) Project Coordinating Monitoring Unit (PCMU); and (iv) Dhaka North City Corporation (DNCC) on behalf of DNCC, Dhaka South City Corporation (DSCC), Fire Service and Civil Defense (FSCD) and Sylhet City Corporation (SCC). Project activities are highly technical, inter-related across agencies which require phased planning and implementation and are integral to the overall complex reform agenda for urban resilience. After a slow start, the project is now making significant progress towards achieving the Project Development Objective (PDO). IDA disbursement is at 29%. 3. Out of the four Implementing Agencies (IAs), DNCC is most advanced and implementation progress is satisfactory. All consultancy services of RAJUK, DDM, and PCMU are under implementation after significant initial delays related to procurement. DDM is expected to start the Training, Exercises and Drills (TED) program from July 15, 2019, which brings together all emergency services supported under the project. RAJUK has improved implementation and construction planning of the Urban Resilience Unit (URU), being established under the Project, is expected to commence in October 2019. Based on the mission, it was agreed that to achieve the PDO a restructuring was required to reallocate funds, adjust results indicators and targets, and extend the closing date. 4. Many important activities such as completion of additional decentralized emergency services warehouses, delivery of emergency management equipment, completion of Emergency Operation Centers (EOCs), etc. are planned in the next few months. The mission advised the PIUs to take the opportunity to disseminate these important milestones and raise awareness of the work the Government is doing to improve urban resiliency and what has already been achieved, particularly in light of the recent fire events. Table 1: Project Data as of June 30, 2019 Board Approval : March 24, 2015 Effectiveness Date : August 3, 2015 Closing Date : June 30, 2020 Mid-Term Review : December 8-13, 2018 Original IDA Credit XDR 122.80 million (US$ 173 million equivalent) GoB Contribution: US$ 6.5 million IDA Amount Disbursed XDR 35.63 million (US$ 49.34 million equivalent) (29%) 1 Swarna Kazi (Sr. Disaster Risk Management Specialist and Task Team Leader), Ignacio Urrutia (Sr. Disaster Risk Management Specialist and Co-Task Team Leader), Haris Khan (Sr. Disaster Risk Management Specialist and Co-Task Team Leader), A.N.M. Mustafizur Rahman (Sr. Procurement Specialist), Aisha De Guzman (Sr. Financial Management Specialist), Nadia Sharmin (Sr. Environment Specialist), Md. Akhtar Zaman (Sr. Social Development Specialist), Debashish Paul Shuvra (Disaster Risk Management Analyst), Mohammad Rafiqul Islam (Disaster Risk Management Analyst), S M Mehedi Hasan (Technical Consultant), Dewan Rakibul Islam (Technical Consultant), Partha Protim Nath (Research Assistant), Mohammad Abdul Basit (Research Assistant), Md. Towshikur Rahman (Research Assistant), Olivia Moutushi Sarker (Team Associate) and Amani Haque (Program Associate). Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of BANGLADESH: Urban Resilience Project Implementation Support … · 2020. 6. 16. · - 1 -...

  • - 1 -

    BANGLADESH: Urban Resilience Project

    Implementation Support Review Mission

    June 16-20, 2019

    Aide Memoire

    INTRODUCTION

    1. A World Bank Team1 carried out an Implementation Support Review (ISR) mission for the Urban Resilience Project (URP) from June 16 to 20, 2019. The objective of the mission was to: (i) review

    implementation progress; (ii) review project targets and assess results indicators; and (iii) assess

    implementation challenges and recommend remedial measures. This Aide Memoire (AM) summarizes the

    mission’s findings, recommendations, and agreements reached with the relevant agencies to expedite

    implementation. The AM was discussed at the wrap-up meeting on June 20, 2019 with the Secretary,

    Planning Division, Ministry of Planning as Chair. As agreed, this AM will be classified as “Public” under

    the World Bank’s Access to Information policy.

    PROJECT DATA AND OVERALL STATUS

    2. URP is a multi-ministerial project, executed by four implementing agencies; (i) Department of Disaster Management (DDM); (ii) Rajdhani Unnayan Kartripakkha (RAJUK); (iii) Project Coordinating

    Monitoring Unit (PCMU); and (iv) Dhaka North City Corporation (DNCC) on behalf of DNCC, Dhaka

    South City Corporation (DSCC), Fire Service and Civil Defense (FSCD) and Sylhet City Corporation

    (SCC). Project activities are highly technical, inter-related across agencies which require phased planning

    and implementation and are integral to the overall complex reform agenda for urban resilience. After a

    slow start, the project is now making significant progress towards achieving the Project Development

    Objective (PDO). IDA disbursement is at 29%.

    3. Out of the four Implementing Agencies (IAs), DNCC is most advanced and implementation progress is

    satisfactory. All consultancy services of RAJUK, DDM, and PCMU are under implementation after

    significant initial delays related to procurement. DDM is expected to start the Training, Exercises and

    Drills (TED) program from July 15, 2019, which brings together all emergency services supported under

    the project. RAJUK has improved implementation and construction planning of the Urban Resilience Unit

    (URU), being established under the Project, is expected to commence in October 2019. Based on the

    mission, it was agreed that to achieve the PDO a restructuring was required to reallocate funds, adjust

    results indicators and targets, and extend the closing date.

    4. Many important activities such as completion of additional decentralized emergency services warehouses,

    delivery of emergency management equipment, completion of Emergency Operation Centers (EOCs), etc.

    are planned in the next few months. The mission advised the PIUs to take the opportunity to disseminate

    these important milestones and raise awareness of the work the Government is doing to improve urban

    resiliency and what has already been achieved, particularly in light of the recent fire events.

    Table 1: Project Data as of June 30, 2019

    Board Approval : March 24, 2015

    Effectiveness Date : August 3, 2015

    Closing Date : June 30, 2020

    Mid-Term Review : December 8-13, 2018

    Original IDA Credit XDR 122.80 million

    (US$ 173 million equivalent)

    GoB Contribution: US$ 6.5 million

    IDA Amount Disbursed XDR 35.63 million

    (US$ 49.34 million equivalent) (29%)

    1 Swarna Kazi (Sr. Disaster Risk Management Specialist and Task Team Leader), Ignacio Urrutia (Sr. Disaster Risk Management

    Specialist and Co-Task Team Leader), Haris Khan (Sr. Disaster Risk Management Specialist and Co-Task Team Leader), A.N.M.

    Mustafizur Rahman (Sr. Procurement Specialist), Aisha De Guzman (Sr. Financial Management Specialist), Nadia Sharmin (Sr.

    Environment Specialist), Md. Akhtar Zaman (Sr. Social Development Specialist), Debashish Paul Shuvra (Disaster Risk Management

    Analyst), Mohammad Rafiqul Islam (Disaster Risk Management Analyst), S M Mehedi Hasan (Technical Consultant), Dewan Rakibul

    Islam (Technical Consultant), Partha Protim Nath (Research Assistant), Mohammad Abdul Basit (Research Assistant), Md. Towshikur

    Rahman (Research Assistant), Olivia Moutushi Sarker (Team Associate) and Amani Haque (Program Associate).

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • - 2 -

    5. Reallocation: There are savings in the DDM and PCMU activities mostly due to lower prices in services from original estimates. There is approximately US$7 million financing gap in the RAJUK component

    due to; (i) increased cost of Value Added Tax (VAT) & Income Tax (new legislation); (ii) higher than

    estimated cost of consultancy services; (iii) price escalation; and (iv) increased construction cost for the

    proposed Urban Resilience Unit (URU) building. This gap can be covered with savings from the DDM

    and PCMU components. As agreed during the mission, RAJUK, DDM, and PCMU have agreed on a

    proposed re-allocation among components. PCMU as the coordinating PIU, will lead the reallocation

    process.

    6. Revised Result Framework (RF): A revised RF has been developed based on the scope, timeline and

    targets of the project. Activities remain the same, the proposed changes are intended to reflect the results

    expected under the project more appropriately. Proposed revised results framework is in Annex IV.

    7. Closing Date Extension: To properly complete ongoing activities, including construction of the URU

    building and complete the sector reform activities, a 22-month extension until April 30, 2022 is required.

    Initial delays were mostly related to the procurement of goods and services which are new to the country.

    The extension will allow for: (i) reprogramming the implementation schedule of the Training, Exercises,

    and Drills (TED) program under DDM which is now under an accelerated work program that may

    compromise quality and the capacity of institutions to internalize the content; (ii) completion of the

    consultancy services under RAJUK and adoption of the outcomes of these services in manner such that

    these are embedded and integrated into RAJUK’s newly formed Urban Resilience Unit (URU); and (iii)

    completion of the construction of the URU building which will require time until the end of the dry season

    in 2022.

    8. Next Steps for Restructuring: Formal request for restructuring to be sent to the Bank by July 15, 2019.

    Restructuring to be completed by October 2019.

    IMPLEMENTATION PROGRESS AND KEY FINDINGS

    Component A: Reinforcing the Country’s Emergency Management Response Capacity (US$ 110

    million)

    9. The goal of Component A is to operationalize an integrated emergency management system that will enable to plan and respond to both everyday emergencies as well as major disasters in an organized and

    effective manner. The component will finance: (i) construction and/or refurbishment of decentralized

    facilities for emergency management and response; (ii) establishment of a communications network for

    these facilities to operate during emergencies; (iii) provide specialized search and rescue equipment; and

    (iv) train for emergency operations and response. The increased capacity to be evaluated through exercises

    and drills.

    10. At the time the project was designed, DNCC did not have any suitable premises, it was discussed, when

    there was space, an EOC would be included for DNCC. Over the course of the project, DNCC now has a

    well-established office space. As agreed with the Hon’ble Mayor DNCC, an EOC will now be established

    for DNCC. Suitable, space has been allocated, a design and supervision firm and technical consultant are

    already onboard, technical specifications are available, and there are savings within the component to

    include this activity.

    11. Out of the fifty-seven (57) planned decentralized facilities: Fifty-one2 (51) have been constructed or

    renovated, and six (6) are in progress. Construction activities are on track for completion.

    12. Construction of FSCD Command and Control Room (CCR) in Dhaka is 95% complete. Construction of

    FSCD CCR including warehouses in Sylhet is 75% complete. Finishing work is ongoing in both CCR.

    These two facilities are expected to be completed by July 15, 2019.

    2 2 Fixed Control Rooms (CoC Mirpur and Sylhet), 13 Emergency Management Warehouses associated with 13 Auxiliary Control Rooms (11 Dhaka, 2 Sylhet) along with 8 Emergency Management Warehouses (DNCC-5, DSCC-3), 1 Emergency Operation Center

    associated with 1 Urban Resilience Unit (Sylhet), 3 Disaster Risk Management Offices (DNCC, DSCC & SCC), 10 Zonal Control

    Rooms (1 control at each zonal office)

  • - 3 -

    13. The main delay under Component A works is with DSCC. The construction of the Emergency Operating

    Centre (EOC) at DSCC, has progressed only 30%, due to site handover issues. As agreed during the

    mission with the Hon’ble Mayor DSCC, the activity will be expedited immediately. This activity is

    planned to be completed by September 30, 2019.

    14. Supply and installation of emergency management and communication technology is ongoing. Equipment includes radio sets, terminals, communication towers, antennas, and mobile communication vehicle. The

    sets of specialized equipment are being procured and delivered to the respective facilities. Contracts have

    already been signed for most of the Information and Communication Technology (ICT) equipment

    packages. Only remaining are- G-1-6/ICT Equipment for CCR at FSCD, Sylhet, G-1-7/ICT Equipment

    for CCR at FSCD, Dhaka, G-1-8/ Specialized ICT Equipment (DMR(Digital Mobile Radio) Network and

    Related Installations-VHF (Very High Frequency)) for FSCD, and G-1-12/ ICT Equipment for EOC at

    DSCC. A list of equipment for FSCD that has already been supplied or under tender in attached in Annex

    V.

    15. Procurement of ICT Equipment for CCR at FSCD, Sylhet and Dhaka, and ICT Equipment for EOC DSCC

    are in tender evaluation stage and will be signed by August 30, 2019. Tender is floated for Specialized

    ICT Equipment (DMR Network and Related Installations-VHF) for FSCD and is expected to be signed

    by October 30, 2019.

    16. Application for frequency allocation from the Bangladesh Telecommunication Regulatory Commission

    (BTRC) has been submitted by DNCC and DSCC. BTRC has granted frequency allocation for Ultra-high

    Frequency (UHF) devices for DNCC. It was agreed that both DNCC and DSCC will follow-up urgently

    for the pending frequency allocation of the High Frequency (HF) and UHF devices respectively.

    Frequency allocation for all FSCD devices have already been granted.

    17. Specialized Search and Rescue (SAR) equipment are being procured to increase capacity for timely

    response in the event of an emergency. Most equipment has already been procured and delivery is ongoing.

    The only SAR equipment that remains is the rescue boat, which is scheduled to be delivered by March 31,

    2020.

    18. The Training, Exercises, and Drills (TED) is being led by DDM, they have submitted all five deliverables (1.1: Final Curriculum, 1.2: Comprehensive Course Materials, 1.3: Tracking Tool Report, and 1.4:

    Emergency Operations Plan (EOP) Planning Process report and 1.5: Final Training Plan) of first phase

    under the contract. DDM must follow up closely to ensure that the trainings commence as soon as possible.

    It was agreed that the trainings will start from July 15, 2019 and are scheduled to continue for two years

    from commencement, depending on an extension of the project’s closing date.

    Component B: Vulnerability Assessment of Critical and Essential Facilities (US$ 12 million)

    19. The objective of this component is to develop a consensus-driven analytical foundation required for

    longer-term investments to reduce risk in the built environment. This is being carried out through two sub-

    components led by RAJUK, B1 (Consultancy Service S-4): Vulnerability assessment of critical and

    essential facilities; and B2 (Consultancy Service S-5): Development of a Risk-Sensitive Land Use

    Planning (RSLUP) practice, including a Strategic Environmental Assessment (SEA). Both contracts were

    signed in October 2018. There was a substantial increase in the contract price from the estimated value.

    Based on the mission findings, the extension of the project is required to achieve the required outcomes

    and internalize the services rendered. Close monitoring by RAJUK is essential.

    20. S-4: Consultancy Services for Vulnerability Assessment and Prioritized Investment Plan for Critical Assets

    in Dhaka for URU. The Inception Report was approved on March 27, 2019. Prioritization parameters,

    methodology and framework for survey and studies have been completed. Situation Analysis Report, data

    collection, documentation, digitization, characterization of exposure data, preparation of GIS database has

    been submitted. Rapid Visual Assessment (RVA) is ongoing, which encompasses 5 million sqm (about

    4,000 structures) in greater Dhaka.

  • - 4 -

    21. S-5: Consultancy Services for Development of Risk-sensitive Land Use Planning Practice for URU. The

    Inception Report for this package was approved on March 27, 2019. The final Draft SEA Interim Report

    will be submitted addressing Bank’s observation by July 15, 2019. As part of the geological survey and

    investigation, 500 microtremor tests have been conducted in greater Dhaka, based on which the borehole

    layout plan for the Standard Penetration Tests (SPTs) and Cone Penetration Tests (CPTs) will be prepared.

    Comprehensive Situation Analysis and Diagnosis Report and Final Consultation Report has been

    submitted. Preliminary data collection, report including comprehensive study to assess implications of

    hazards, vulnerabilities and risks, are under preparation.

    Component C: Improved Construction, Urban Planning and Development (US$ 41 million)

    22. The objective of this component is to put in place the institutional infrastructure and competency to reduce

    long-term disaster vulnerability, addressing both the existing built environment as well as future

    development. The Minister of Housing and Public Works (MoHPW) approved the establishment of URU,

    in principle, on April 29, 2019. Formal minutes will be circulated. After assessing the requirements during

    the Mid Term Review (MTR), it was agreed that the one remaining consultancy package (with regard to

    accreditation process) may be merged with an appropriate ongoing contract. Most importantly approval of

    BNBC 2017 from respective authority within the project period is also crucial for utilizing the outcome in

    full for this component.

    23. S-6: Consultancy Services consultancy Services for Operationalizing the URU. Inception Report and

    Situation Analysis were approved on March 27, 2019. Revised Institutional Design and Operational Study

    (IDOS) was submitted on June 14, 2019. In addition to the services associated with the operationalization

    of the URU, it will also be equipped with field and laboratory equipment.

    24. S-7: Consultancy Services for Electronic Construction Permitting (ECP) System. The Inception Report

    covering Construction Permitting, Assessment and Situation Analysis is complete. Baseline and Business

    Operation Design (BOD) has been developed and is expected that the 1st prototype of software and ECP

    strategy and action plan with relevant engagement and documentation will be submitted by July 20, 2019.

    25. S-9: Consultancy Services for Building Code Implementation and Enforcement Strategy. Inception reports

    that cover the initial assessment on code enforcement violations, status on violation cases, and resolutions

    has been submitted and approved. Situation Analysis and Consultations Report is being reviewed.

    Education campaign and outreach program of current findings to be initiated and will be integrated with

    the next deliverables. Outcomes from this component will be integrated with ECP system.

    26. S-11: Consultancy Services Regarding the Design and Supervision of URU Construction. The Design &

    Supervision firm submitted the draft architectural drawing of the URU on June 16, 2019. All final design

    and Bill of Quantities (BoQ) will be submitted by July 25, 2019. Works contract is expected to be signed

    by November 15, 2019 and completion of construction will take approximately 2 years from

    commencement, depending on closing date extension. Close monitoring and supervision by RAJUK will

    be needed to ensure timely completion.

    Component D: Project Coordination, Monitoring and Evaluation

    27. PCMU is responsible for the overall coordination and monitoring of this multi-agency project. A key

    activity is Monitoring and Evaluation (M&E) of all components through a specialized M&E Firm. The

    M&E firm is now in place, a system is established, and the indicators are being tracked. The M&E Firm

    has submitted four (4) Quarterly Progress Reports, M&E Framework Report and Baseline Survey Report.

    28. PCMU signed a contract for the Internal Audit and the Draft Final report was submitted on May 15, 2019.

    The PMIS dashboard (https://urp.gov.bd/) has been prepared. It was launched on June 13, 2019 at the

    Project Steering Committee (PSC) meeting.

    https://urp.gov.bd/

  • - 5 -

    Operation & Maintenance (O&M) and Sustainability

    29. While state of the art equipment is being procured, EOCs and an URU established, the project is also

    looking at the sustainability of operations. This is being achieved through appropriate training of key staff,

    a retention and absorption plan to mainstream these human resources in the government system and

    allocation of appropriate recurring budget for new systems and infrastructure. All IAs should share a

    sustainability plan, which would include budget, human resources and O&M, by September 30, 2019.

    30. Through this project, RAJUK has begun the establishment of the URU. As of now, 54 personnel including

    35 engineers, architects and planners, have been recruited. They are closely involved with the technical

    interventions and are being trained through this process to improve their technical capacity. Once URU is

    full established, the manpower will be integrated within URU to provide capacity building support,

    operationalizing laboratory and field-testing activities and technical activities.

    FIDUCIARY COMPLIANCE

    31. Procurement

    DNCC: Out of four implementing agencies DNCC has more complex procurement packages of

    Goods/ICT equipment. Procurement process of all planned packages are in various stages of procurement.

    As per STEP data and mission findings out of seven Specialized ICT Equipment (VHF and HF Radio

    Terminals/DMR network and Related Installations) packages, three contracts are signed. Mission has

    agreed on the time line for remaining four packages which is in the procurement process. Final delivery is

    dependent on frequency issues. The high value package of DMR network (URP-DNCC/G-1-8/Specialized

    ICT Equipment (DMR Network and Related Installations-VHF) for FSCD) are in bidding stage which

    requires due diligence for successful outcome. Moreover, five procurement packages of ICT Equipment

    for CCR/EOC/warehouses of city corporations are in bidding stages. Mission has agreed on a time line

    in finalizing the contracts. DNCC will develop an inventory tool or procure off-the shelf software with

    unique identification numbers for key ICT/rescue/heavy equipment for monitoring these sensitive and

    valuable goods.

    RAJUK is implementing key service packages; (i) Design and Supervision of URU Building; (ii)

    Operationalizing the URU; (iii) Assessing the Current State and Deploying a Web-based Integrated

    Information Management System for the Construction Permit System; (iv) Building Code Implementation

    and Enforcement Strategy for URU; (v) Vulnerability Assessment and Prioritized Investment Plan for

    Critical Assets in Dhaka; (vi) Development of Risk Sensitive Land Use Planning Practice. As all contracts

    are lump-sum based complex contracts, RAJUK will start reporting deliverables from July 2019 through

    an excel based platform. For all the above contracts the replaced key staff requires substantial monitoring

    to cover-up the missing time-input.

    DDM has one key consultancy contract of US$10 million which was signed on November 2018 and as

    agreed in this mission the appropriate concurrence will be required for training budget allocation from

    provisional-sum. DDM post-review contracts will have to be handled more professional way based on the

    findings of the last review.

    Those contracts are not generated through STEP may not be counted as completed contract.

    32. Financial Management

    Key FM actions such as the conduct of internal audit and installation of IBAS++ has been completed. It

    was noted that the implementing agencies need to establish more stringent controls in ensuring that records

    are updated, transactions are properly reviewed, and all expenditures are supported with the necessary

    documents. The project experienced initial implementation delays and expenses are expected to increase

    significantly in the coming months. This will mean more expenditures need to be appropriately processed

    and supported with relevant documentation. As such, it is recommended that the PIUs strengthen the

    bookkeeping process; establish and implement internal controls over transactions; and ensure that all

    transactions are sufficiently reviewed by the qualified personnel. The following actions are recommended:

  • - 6 -

    a. Ensure that all payment vouchers on file are completely supported with relevant documentation

    and duly signed by the required personnel and officers of the government - It was noted during the

    review of transactions that certain payment vouchers had missing signatories and/or have incomplete

    supporting documents. IAs should ensure that all signatories sign the Payment Voucher as evidence

    of review and are completely supported being the official document that supports all transactions.

    Failure to present adequate documentation may result to ineligible expenses.

    b. Ensure complete and updated books of account such as cash book, advance register, monthly bank

    reconciliation statement and assets register. In addition, while the IAs are transitioning to the use

    of IBAS++ and taking into consideration that the system is not yet able to produce real-time data

    and customizable financial reports, it is recommended that the account officers continue with the

    use of MS Excel sheets to monitor financial transactions and implement database back-up policies

    and procedures to ensure the integrity of accounting records and avoid loss of information. As per

    discussion with FMS, they have started regularly saving digital records at least monthly in back-up

    drives.

    c. Submit Internal Audit Report and monitor resolution of audit issues. M.I. Chowdury Firm was hired

    by the PCMU to conduct the internal audit covering all the 4 IAs. As per PCMU, final discussions

    of the audit findings were held on the second week of June 2019 and the final report is expected to

    be submitted by the third week of June 2019. Prior to the finalization of the internal audit report,

    PCMU has been assisting the various IAs in improving FM capacity by providing trainings on

    different FM areas such as IBAS++, IFR and voucher preparation, cashbook maintenance and proper

    record keeping. The mission commends the proactivity of PCMU in strengthening FM system of

    the project.

    d. Ensure maintenance of an Asset Registry and conduct annual physical count of inventory and

    project assets – the project involves procurement of a number of goods. IAs should ensure an annual

    physical count of all assets purchased for the project. PCMU will share a template of Asset register

    that can be used by the IAs.

    e. Ensure accuracy of tax deductions – it was noted that a difference was noted in the re-computation

    of VAT in consultancy services for a certain contract with PCMU. It is recommended that the

    correction be reviewed, and adjustments be made on the succeeding payments.

    Compliance with the financial covenants

    a. Audited project financial statements – External audit will continue to be carried out annually by the

    Foreign Aided Project Audit Directorate (FAPAD) of C&AG. All IAs have submitted the audited

    financial statements (AFS) for the period July 1, 2017 to June 30, 2018. During the mission, the

    FMS of the different IAs provided updates on the status of the audit findings noted by FAPAD.

    b. Interim Unaudited Financial Reports (IFRs) – IFRs are due for submission 45 days after the end of

    each calendar quarter. The consolidated IUFR prepared by the PCMU for the quarter ended March

    31, 2019 was submitted timely, on May 8, 2019. During the consolidated financial review, issues

    were noted in the IFR of DNCC and it was agreed that the IFRs will be reviewed and revised to

    include the corrections.

    Disbursement Performance

    Details of disbursement by category of expenditure is shown in the table 2. The disbursement under the

    project is SOE based and as of June 18, 2019 is SDR 34.64 million which is 28% of the credit. About

    SDR 935 thousand worth of withdrawal applications are targeted to be processed by June 30, 2019. A

    large number of high valued procurement packages are still ongoing.

  • - 7 -

    Table 02: Status of Fund Utilization/Disbursement Against Allocation as of 18 June 2019

    (IDA 5590: Amounts in SDR)

    Particulars

    Financing

    allocation

    (a)

    Withdrawn

    from Bank

    (b)

    WAs in

    process

    (c)

    Amount

    undisbursed

    from the

    Bank

    (a-b-c)

    Disbursement

    Rate3

    Utilization

    Rate 4

    Goods, Works, CS, Non-CS,

    Training and IOC 122,800,000 25,926,119 934,635 95,939,245 21% 22%

    Emergency Expenses - - - - 0% 0%

    Designated Account-A DNCC - 4,403,214 - (4,403,214)

    Designated Account-B RAJUK - 2,610,361 - (2,610,361)

    Designated Account-C DDM 898,297 (898,297)

    Designated Account-D PCMU - 797,142 - (797,142)

    Total 122,800,000 34,635,134 934,635 87,230,231 28% 22%

    Withdrawal Applications (WA) of amount of SDR 563,353.17 have been submitted and under the processing

    by the Bank as of June 19, 2019. With the latest data, total of USD 49.22 million (SDR 35.57 million) will be

    disbursed from the beginning of project life should all WAs be processed by June 30, 2019. It is recommended

    that the overall disbursement projection be reviewed for the remaining life of the project to have more realistic

    projections and assess if there are funds to be unused. At this point in the life of the project, the overall

    projection should be assessed to determine if there is a need to restructure and/or reallocate funds to other

    expenses and/or components.

    SAFEGUARD MANAGEMENT

    33. Environmental Safeguards

    i. City Corporation and FSCD: The overall performance of environmental safeguard compliance is on

    track. The second monitoring report includes environmental safeguard status of the activities performed by

    DNCC, DSCC, SCC and FSCD has been shared with the Bank. It was agreed that the implementing agency

    would share the 3rd environmental monitoring report by December 1, 2019. The monitoring report should

    also include the next six months training plan.

    ii. DDM: DDM needs to share field status of environmental safeguard compliance of the refurbishment

    work of three floors including setting up an office. The status can be incorporated in the environmental

    monitoring report shared by city corporation. The contractor and field workers require training on the ESMF

    before commencing the task.

    iii. RAJUK: RAJUK has shared the revised Inception Report on Strategic Environmental Assessment

    (SEA). RAJUK agreed to share the draft interim report of SEA by June 30, 2019. The mission has been

    informed that the independent consultant for conducting the Environmental Impact Assessment (EIA) of the

    RAJUK multi-storied building is on board. RAJUK agreed to share the draft EIA with the Bank by August 15,

    2019 along with RAJUK’s review comment.

    34. Social Safeguards

    All subprojects of the constituent PIUs of the project were screened at the design stage and identified free from

    incumbrances triggering any social safeguards compliance issues. Grievance redress mechanisms (GRM) and

    a system for labor influx monitoring have been established as applicable with the respective PIUs. The PCMU

    has also been carrying out oversight of the grievance management and labor influx issues including risks of

    GBV at works site. The mission learnt that at least two complaints under the DNCC component were

    successfully attended, one related to structure design and other related to labor safety. All PIUs having civil

    3 Disbursement rate is the rate of the amount of withdrawal applications paid by the Bank divided by the IDA financing. 4 Utilization rate is the rate of the amount of withdrawal applications paid by the Bank (net of the Designated Accounts) and those in process, divided

    by the IDA financing.

  • - 8 -

    works component are reporting on labor influx and GRM activities but with inadequate representation like

    disclosure and formal registration of complaints as per GRM. Monitoring and evaluation by PCMU has

    consultant resources to attend social development and safeguards issues. All PIUs are requested to combine

    social development, safeguards, labor influx and grievance management in their regular reports shared with

    the PCMU and the World Bank.

    NEXT STEPS AND AGREED ACTIONS

    ❖ Dhaka North City Corporation (DNCC):

    ▪ DNCC and DSCC to urgently follow up with Bangladesh Telecommunication Regulatory

    Commission (BTRC) for frequency allocation permission.

    ▪ Complete construction of Emergency Operations Centers (EOC) in DSCC (with necessary assistance

    from DSCC and approval from DSCC authority) by September 30, 2019

    ▪ Sign contracts of all remaining ICT equipment by October 30, 2019

    ❖ Department of Disaster Management (DDM):

    ▪ Start training of Training, Exercises, Drills (TED) program by July 15, 2019

    ❖ Rajdhani Unnayan Kartripakkha (RAJUK - Capital Development Authority):

    ▪ Sign works contract of URU building by November 15, 2019

    ❖ Project Coordination and Monitoring Unit (PCMU):

    ▪ Coordinate with Implementing Agencies for restructuring of the project

    NEXT REVIEW: The next mission is proposed to take place on November 2019.

  • - 9 -

    Annexes

    Annex I: Key Agreed Actions ............................................................................................. - 10 -

    Annex II: List of People Met .............................................................................................. - 25 -

    Annex III: Updated Results Framework ............................................................................. - 26 -

    Annex IV: Proposed Results Framework for Restructuring ............................................... - 32 -

    Annex V: List of Equipment for FSCD from DNCC-URP Part ......................................... - 41 -

    Annex VI: Proposed Institutional Design of Urban Resilience Unit .................................. - 43 -

    Annex VII: Number of Staffs Engaged with URU and URU Technical Staffs.................. - 44 -

    Annex VIII: Training Provided to URU Staffs under URP-RAJUK part .......................... - 45 -

    Annex IX: Illustration ......................................................................................................... - 46 -

  • - 10 -

    Annex I: Key Agreed Actions

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    All PIUs

    1.

    Upgradation of Financial

    Management System to Multi-User

    system

    On-going All IA’s are uploading financial data into

    IBAS++

    2. Submission of Sustainability Plan On-going DNCC organized a workshop on Sustainability

    plan on March 14, 2019

    3. Uploading all post review package

    documents in STEP On-going

    4. Adaptation of labor influx monitoring

    system and report quarterly On-going DNCC prepared the report

    5.

    Ensure that all payment vouchers on

    file are supported with relevant

    documentation and duly signed by the

    required personnel and officers of the

    government

    On-going

    6.

    Prepare Asset Registry and conduct

    annual physical count of inventory

    and project assets

    On-going

    7.

    Ensure complete and updated books

    of account such as cash book,

    advance register, monthly bank

    reconciliation statement

    On-going

  • - 11 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    DDM

    8.

    BD-DDM-29946 CS-QBS /

    Consultancy Services for Training

    Exercises and Drills (TED) Program

    Contract Signing Done: November 19, 2018

    Final Curriculum approved by Ministry on

    May 16. 2019. Tentative Training July 15,

    2019.

    Reviewing ongoing of budget for

    Comprehensive Budget Plan. Approval

    procedure needs to be confirmed.

    Prior concurrence from Bank to clear line item.

    Confirmation of the availability

    of the key personnel Done: November 26, 2018

    Contract Effectiveness Done: December 11, 2018

    Submission of Inception Report Done: January 21, 2019

    Submission of Draft Done: May 16, 2019

    Commencement of Training July 15, 2019

    9.

    BD-DDM-28928 CS-QBS

    /Consultancy Services for "Design

    and Supervision Consultancy" to

    outfit NDMRTI & ERCC Facilities in

    Dhaka

    Preparation of Tender

    Documents for NDMRTI and

    ERCC renovation works

    Done: January 7, 2019

    Approval from DG (DDM) Done: January 27, 2019

    10.

    BD-DDM-44875 CW-RFB

    /Renovation of the facility that would

    house ERCC (BD-DDM-44875-GO-

    RFB)

    Tender Floating Done: January 31, 2019

    Completion of Tender

    Evaluation NoA (Notification of Award) pending

    approval. Sent to MoDMR

    Contract Signing July 15, 2019

    Commencement of works July 30, 2019

    Completion of works December 1, 2019

  • - 12 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    11.

    BD-DDM-44877-CW-RFB

    /Renovation of the facility that would

    house NDMRTI (BD-DDM-44877-

    GO-RFB)

    Tender Floating Done: January 31, 2019

    Completion of Evaluation NoA pending approval. Sent to MoDMR

    Contract Signing July 15, 2019

    Commencement of works July 30, 2019

    Completion of works December 1, 2019

    12. Recruitment of Contract Management

    Specialist Done: April 1, 2019

    13.

    Draft Bid Documents including

    Clauses for Labor Management and

    Occupational Health and Safety

    Share with Task Team and

    Environment Safeguard Team Done: January 7, 2019

    14. Submission of Safeguard Screening

    Report

    Environmental Screening

    Report & Social Screening

    Report

    Done: December 9, 2018

    DNCC

    15.

    URP-DNCC/G-1-1 / Procurement of

    Specialized ICT Equipment (VHF

    and HF Radio Terminals and Related

    Installations) for FSCD (Lot-1: VHF,

    Lot-2: HF)

    Contract Signing Done: Lot 1: May 21, 2018

    Done: Lot 2: May 30, 2018

    Delivery of Equipment Done: Lot 1: January 6, 2019

    Done: Lot 2: April 11, 2019

    16.

    URP-DNCC/G-1-2 / Procurement of

    Specialized ICT Equipment (VHF

    and HF Radio Terminals and Related

    Installations) for City Corporations

    (Lot-1: VHF, Lot-2: HF)

    Contract Signing

    Done: Lot 1: October 17, 2018 For VHF, Frequency Allocation permit is

    obtained. But for HF the issue is still pending.

    After frequency allocation permit, delivery will

    commence.

    Done: Lot 2: October 22, 2018

    Delivery of Equipment

  • - 13 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    17.

    URP-DNCC/G-1-3 / Procurement of

    Specialized ICT Equipment (UHF

    Radio Terminals and Related

    Installations) for DSCC

    Contract Signing Done: August 19, 2018 Mission team visited DSCC to discuss need to

    expedite the Frequency Allocation permit as

    well as Import Permission and Release of

    Equipment permit. Delivery of Equipment

    18.

    URP-DNCC/G-1-4 / Procurement of

    Specialized ICT Equipment (Lot-01:

    DMR Network, UHF Radio

    Terminals and Related Installations,

    Lot-02: HF Radio Terminals and

    Related Installations) for SCC

    Tender Floating Done: November 7, 2018

    Lot 1: Contract Signed

    Lot 2: Frequency Allocation issue needs to be

    resolved first. PIU to push for permission.

    Completion of Tender

    Evaluation- Lot 1

    Completion of Tender

    Evaluation- Lot 2

    Contract Signing- Lot 01 Done: June 25, 2019

    Contract Signing- Lot 02

    Delivery- Lot 01

    Delivery- Lot 02

    19.

    URP-DNCC/G-1-5 / Procurement of

    ICT Equipment for Emergency

    Operation Center (EOC) at SCC

    Tender Floating Done: December 20, 2018

    Completion of Tender

    Evaluation July 30, 2019 NoA to be issued by July 30, 2019

    Contract Signing August 30, 2019

    Delivery of Equipment December 1, 2019

    Installation of Equipment February 15, 2020

  • - 14 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    20.

    URP-DNCC/G-1-6 / Procurement of

    ICT Equipment for Command and

    Control Room (CCR) at FSCD,

    Sylhet

    Tender Floating Done: December 20, 2018

    Completion of Tender

    Evaluation July 15, 2019 NoA to be issued by July 15, 2019

    Contract Signing August 30, 2019

    Delivery of Equipment December 31, 2019

    Installation of Equipment March 15, 2020

    21.

    URP-DNCC/G-1-7 / Procurement of

    ICT Equipment for Command and

    Control Room (CCR) at FSCD,

    Dhaka

    Tender Floating Done: December 20, 2018

    Completion of Tender

    Evaluation July 30, 2019

    Pending with consultant for technical

    evaluation

    Contract Signing August 30, 2019

    Delivery of Equipment December 31, 2019

    Installation of Equipment March 15, 2020

    22.

    URP-DNCC/G-1-8 / Procurement of

    Specialized ICT Equipment (DMR

    Network and Related Installations-

    VHF) for FSCD

    Tender Floating Done: May 14, 2019 Tender floated. Bid Closing date July 26, 2019

    Tender Evaluation Report Sent

    to the Bank August 15, 2019

    Contract Signing October 30, 2019

    Delivery and Installation of

    Equipment October 15, 2020

  • - 15 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    23.

    URP-DNCC/G-1-9 / Procurement of

    Specialized ICT Equipment (DMR

    Network and Related Installations-

    VHF/HF/UHF) for DNCC

    Tender Floating Done: November 8, 2018

    Completion of Tender

    Evaluation Done: May 25, 2019

    Contract Signing Done: June 25, 2019

    Delivery of Equipment January 1, 2020

    24.

    URP-DNCC/G-1-10 / Procurement of

    Specialized ICT Equipment (DMR

    Network and Related Installations-

    UHF) for DSCC

    Tender Floating

    Completion of Tender

    Evaluation Done: May 30, 2019

    Contract Signing Done: June 23, 2019

    Delivery of Equipment

    25.

    URP-DNCC/G-1-11 / Procurement of

    ICT Equipment for Warehouses for

    DNCC and DSCC

    Tender Floating

    Completion of Tender

    Evaluation June 30, 2019 NoA to be issued by July 15, 2019

    Contract Signing July 30, 2019

    Delivery of Equipment October 30, 2019

    26.

    URP-DNCC/G-1-12 / Procurement of

    ICT Equipment for Emergency

    Operation Center (EOC) at DSCC

    Tender Floating Done: December 27, 2018

    Completion of Tender

    Evaluation July 30, 2019

    Pending with consultant for technical

    evaluation

    Contract Signing August 30, 2019

    Delivery of Equipment February 1, 2020

  • - 16 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    27.

    URP-DNCC/G-2-1 / Procurement of

    Specialized Search and Rescue

    Equipment (Emergency Tenders) for

    FSCD

    Shipment/Delivery: Phase 1 Done: August 30, 2018

    Shipment/Delivery: Phase 2 Done: November 6, 2018

    28.

    URP-DNCC/G-2-3 / Procurement of

    Specialized Search and Rescue

    Equipment (Breathing Apparatus

    Tenders)

    Contract Signing Done: July 5, 2018

    Shipment/Delivery Date Done: March 27, 2019

    29.

    URP-DNCC/G-2-4 / Procurement of

    Specialized Search and Rescue

    Equipment (Personal Protective

    Equipment)

    Contract Signing Done: June 4, 2018

    Shipment/Delivery Date Done: March 20, 2019

    30.

    URP-DNCC/G-2-5 / Procurement of

    Specialized Search and Rescue

    Equipment (Rescuer Tools- Drone)

    Contract Signing Done: August 6, 2018

    Shipment/Delivery Date Done: November 20, 2018

    31.

    URP-DNCC/G-2-6 / Procurement of

    Specialized Search and Rescue

    Equipment (Lot-1: Ambulance, Lot-

    2: Mortuary Van)

    Contract Signing

    Done: Lot-1: January 31, 2018

    Done: Lot-2: January 31, 2018

    Delivery of Equipment:

    Lot-1: July 30, 2019 Shipping started on June 30, 2019.

    Done: Lot-2: Dec 15, 2018

    32.

    URP-DNCC/G-2-9 / Procurement of

    Turn Table Ladders Tender (60m) for

    FSCD

    Contract Signing Done: September 16, 2018

    Delivery of Equipment August 30, 2019 Shipment started from July 01, 2019.

  • - 17 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    33. URP-DNCC/G-2-10 / Procurement of

    HazMat Tender for FSCD

    Contract Signing Done: March 31, 2019

    Delivery of Equipment December 20, 2019 Awaiting FSCD approval on drawings. Will be

    shipped in September 2019

    34.

    URP-DNCC/G-2-11 / Procurement of

    Search and Rescue Equipment

    (Rescue Boat)

    Contract Signing July 30, 2019 NoA will be issued by July 15, 2019

    Delivery of Equipment March 1, 2020

    35. Procurement of MCCV

    Technical Specification and

    detailed estimate July 15, 2019

    Preparation of technical specification will be

    completed by July 15, 2019

    Include in Procurement Plan July 30, 2019

    Tender Floating August 15, 2019

    Contract Signing September 30, 2019

    36.

    URP-DNCC/S-7 / GIS- Phase 1:

    Need Assessment for Implementation

    of GIS Infrastructure in the Urban

    Resilience Project

    Contract Signing Done: March 11, 2019

    Completion September 1, 2019 Trainings started in DNCC office.

    37.

    URP-DNCC/S-8 / Enhancement the

    effectiveness of DRR Emergency

    Warehouses at DNCC

    Contract Signing Done: June 13, 2019

    Completion January 13, 2020

  • - 18 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    38.

    URP-DNCC/ S-9 / Preparation of

    GIS Based Maps (Ward level) at

    DNCC, DSCC & SCC

    RFP Issuance July 15, 2019 Proposals will be received by August 15, 2019

    Completion of evaluation September 15, 2019 Evaluation will be completed by September 15,

    2019

    Contract Signing October 30, 2019

    Completion October 30, 2020

    39.

    URP-DNCC/ W-1-1 / Construction of

    FSCD Command and Control Room,

    Dhaka (Vertical extension of 1st &

    2nd floor of newly constructed

    warehouse at FSCD Compound,

    Mirpur-10, Dhaka)

    Contract Signing Done: May 28, 2018

    Completion July 15, 2019 95% work completed (Finishing work ongoing)

    40.

    URP-DNCC/ W-1-2 / Construction of

    FSCD Command & Control Center

    including Warehouses at South

    Surma, Sylhet

    Contract Signing Done: March 31, 2018

    Completion July 30, 2019 75% work completed (Finishing work started)

    41.

    URP-DNCC/ W-2-1 / Construction of

    Emergency Operation Center (EOC),

    DRM Office and Urban Resilience

    Unit at SCC Sylhet (Vertical

    extension of 5th floor of SCC Nagar

    Bhaban, Sylhet)

    Contract Signing Done: May 28, 2018

    Construction Completion Done: April 30, 2018 Civil construction completed

    42.

    URP-DNCC/ W-2-2 / Construction of

    Emergency Operating Centre (EOC)

    at DRM Office and Urban Resilience

    Unit at DSCC, Dhaka

    Contract Signing Done: November 18, 2018 Mission team met with Hon. Mayor DSCC to

    discuss site handover issue. This will be

    expedited. Construction Completion September 30, 2019

  • - 19 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    43. Submission of Bi-Annual

    Environmental Monitoring Report Second EMR Submission Done: June 13, 2019

    44. Approval of Frequency Allocation for

    ICT equipment

    Approval for FSCD Done: May 14, 2018

    Approval for DNCC Status as of No. 13 and 14

    Approval for DSCC Status as of No. 13 and 14

    Approval for SCC Status as of No. 13 and 14

    45. Inclusion of all proposed procurement

    packages in STEP Done

    46. Discussion with NBR on the issue of

    CD & VAT for ICT Equipment Meeting with NBR July 20, 2019 PCMU to support DNCC

    47.

    Assign a deputy or technical staff in

    DNCC to sign vouchers and review

    work of FMS

    48. Submit revised IFR and review bank

    reconciliations statements

    PCMU

    49.

    URP/PCMU/S-1 / Monitoring and

    Evaluation Consultancy through a

    Firm

    Submission of PMIS Dashboard

    Development Report Done: December 31, 2018

    Establishment of PMIS

    Dashboard Done: June 13, 2019

    Submission of draft 3rd QPR Done: June 13, 2019

    50. URP/PCMU/S-2 / Internal Audit

    through a Firm

    Submission of Internal Audit

    Report June 30, 2019 Draft Final Report submitted on May 15, 2019.

  • - 20 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    51. Initiation of Restructuring Request June 20, 2019

    52. 10th Project Steering Committee

    (PSC) Meeting September 2019

    9th PSC chaired by Hon. Secretary on June 13,

    2019. Next PSC in September 2019

    53. Review VAT computation June 30, 2019

    RAJUK

    54.

    URP/RAJUK/S-4 / Consultancy

    Services for Vulnerability

    Assessment and Prioritized

    Investment Plan for Critical Assets in

    Dhaka for URU

    Confirmation of the availability

    of the key personnel

    Approval of Inception Report Done: March 27, 2019

    Submission of Situation

    Analysis Report Done: June 12, 2019

    Completion of RVA October 30, 2019

    Fist deliverable is of 2 million sqm of

    Vulnerability Assessment and Prioritized

    Investment Plan for Critical Assets in Dhaka

    55.

    URP/RAJUK/S-5 / Consultancy

    Services for Development of a Risk-

    sensitive Land Use Planning Practice

    for URU

    Confirmation of availability of

    key personnel Done: May 30, 2019

    PIU received replacement proposal of Team

    Leader and review process is ongoing.

    Approval of inception report Done: March 27, 2019

    Submission of Situation

    Analysis Report Done: June 14, 2019

    Submission of SEA Revised

    Inception Report Done: June 12, 2019

  • - 21 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    Submission of SEA Revised

    Interim Report July 15, 2019

    Final SEA Report Submission August 30, 2019

    Geotechnical and geological

    tests and reports January 2020

    Microtremor testing completed.

    Borehole plan for SPT (Standard Penetration

    Test) and CPT (Cone Penetration Test)

    submitted on June 13, 2019

    55.

    URP/RAJUK/S-6 / Consultancy

    Services for Operationalizing the

    URU in RAJUK

    Confirmation of availability of

    key personnel Done: February 25, 2019 Confirmed by PIU

    Approval of inception report Done: March 27, 2019

    Inception report and Situation Analysis report

    approved on March 26, 2019. Revised IDOS is

    submitted on May 22, 2019.

    Approval of Situation Analysis

    and feasibility study report Done: March 27, 2019

    IDOS (Intuitional Design and

    Organizational Study) Done: June 30, 2019

    Revised version of IDOS was received on June

    14, 2019.

    56.

    URP/RAJUK/S-7 / Consultancy

    Services for Assessing the Current

    State and Deploying a Web-based

    Integrated Information Management

    System for the Construction Permit

    System of RAJUK

    Approval of inception report Done: March 27, 2019

    Construction Permitting

    Assessment System report Sent to Bank on May 23, 2019

    Strategic Planning report July 31, 2019

    Will be considered after the approval of

    Construction Permitting Assessment System

    report

    57.

    URP/RAJUK/S-8 / Consultancy

    Services for Professional

    Accreditation Program in RAJUK

    Re-access requirement

    RAJUK shared ToR with the Bank on May 28,

    2019. On June 18, 2019 a meeting held with

    different stakeholders like IEB, IAB etc.

  • - 22 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    58.

    URP/RAJUK/S-9 / Consultancy

    Services for Building Code

    Enforcement

    Confirmation of availability of

    key personnel Confirmation verification pending by RAJUK

    Approval of inception report Done: March 27, 2019

    Submission of Situation

    Analysis Report Done: May 2, 2019

    59.

    URP/RAJUK/S-11 / Consultancy

    Services for Design and Supervision

    of Urban Resilience Unit (URU)

    Building including Research,

    Training, and Testing Laboratory

    facilities under RAJUK in Dhaka,

    Bangladesh

    Approval of Inception Report Done: March 27, 2019

    Survey Report, Preliminary

    Architectural Report and Draft

    feasibility report

    Done: May 15, 2019

    Approval of Final Architectural

    Design of URU Building July 25, 2019

    Remaining design and drawings July 30, 2019

    Preparation of Tender

    Documents August 10, 2019

    60. URP/RAJUK/W-2/ Establishment of

    URU Building

    Tender Floating August 30, 2019

    Contract Signing November 15, 2019

    Mobilization November 30, 2019

    Complete Construction November 30, 2021

  • - 23 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    61.

    URP/RAJUK/G-12 / Procurement of

    Field and Laboratory Equipment for

    URU

    Approval of procurement plan Done: December 17, 2018

    Tender Floating Done: January 3, 2019

    Completion of Evaluation Done: April 2, 2019

    Contract Signing Done: May 16, 2019

    Supply and Delivery December 1, 2019

    62.

    URP/RAJUK/G-13 / Procurement of

    Field and Laboratory Equipment for

    URU

    Approval of procurement plan Done: December 17, 2018

    Tender Floating Done: January 15, 2019

    Completion of Evaluation Board Approved. Minutes to be signed by

    Chairman of RAJUK

    Contract Signing July 20, 2019

    Supply and Delivery December 1, 2019

    63.

    URP/RAJUK/G-15 / Procurement of

    Field Equipment for Vulnerability

    Assessment Aspect of Structures &

    Geo physics (post review)

    Approval of procurement plan Done: December 17, 2018

    Tender Floating Done: January 3, 2019

    Completion of Evaluation Done: March 31, 2019

    Contract Signing Done: May 6, 2019

    Supply and Delivery December 1, 2019

  • - 24 -

    No. Activity Description Actions/ Sub-Activities Due Date as per ISR

    (June 16-20, 2019) Remarks

    64.

    URP/RAJUK/G-16 /Procurement of

    Equipment for Exploration of RSLUP

    Profile: 200 kN Truck Mounted CPT

    Equipment (post review)

    Approval of procurement plan Done: December 17, 2018

    Tender Floating Done: January 3, 2019

    Completion of Evaluation Under review by RAJUK procurement

    Contract Signing

    Supply and Delivery

    60 Submission of Draft EIA Report of

    URU Building

    Contract Signing Done: May 30, 2019

    Draft Final Report August 15, 2019

    Completion September 30, 2019

    61 Updated Detailed Work Plan Submission to Bank July 15, 2019

    62 Coordination with authorities and the

    consultants on BNBC 2017 Continuous

  • - 25 -

    Annex II: List of People Met

    Division, Ministry of Planning

    • Mr. Md. Nurul Amin, Secretary, Planning Division

    Economic Relation Department, Ministry of Finance

    • Mr. Tahmid Hasnat Khan, Joint Secretary, Finance Division

    • Mr. Najia Islam, Deputy Secretary, Economic Relation Department

    Project Coordinating Monitoring Unit (PCMU), Programming Division, Ministry of Planning

    • Mr. Zafar Ullah, PD-URP, DG-PCMU, Programming Division

    • Md. Khayrul Hasan, Director, URP, PCMU, Programming Division

    • Ms. Jahan Ara, Deputy Director, URP, PCMU, Programming Division

    Ministry of Housing and Public Works (MoHPW)

    • Mr. Md. Shahid Ullah Khandaker, Secretary, MoHPW

    Ministry of Local Government Rural Development & Cooperatives (MoLGRD&C)

    • Mr. Helal Uddin Ahmed, Secretary, LGD

    Ministry of Disaster Management & Relief (MoDMR)

    • Mr. Md. Shah Kamal, Secretary, MoDMR

    • Mr. M. Khalid Mahmood, Joint Secretary, MoDMR

    Dhaka North City Corporation (DNCC)

    • Md. Atiqul Islam, Hon’ble Mayor, DNCC

    • Dr. Tariq Bin Yousuf, Project Director, URP-DNCC Part

    • Mohammad Abul Kashem, Deputy Project Director (Procurement & Contract Management), URP-DNCC Part

    • Mr. Abdul Halim, Sr. Procurement Specialist, URP-DNCC Part

    Dhaka South City Corporation (DSCC)

    • Mr. Mohammad Sayeed Khokon, Hon’ble Mayor, DSCC

    • Mr. Md. Sirajul Islam, DPD-URP DNCC, DSCC

    • Mr. Abu Tayeb Rokon , System Analyst, Dhaka South City Corporation

    Department of Disaster Management (DDM)

    • Md. Abdul Mannan, PD, URP-DDM

    • Md. Hasan Zahid, Procurement Specialist, URP-DDM

    • Mr. Shyamal Chandra Shill, Accountant, URP-DDM

    Rajdhani Unnayan Kartripakkha (RAJUK)

    • Dr. Sultan Ahmed, Chairman, RAJUK

    • Mr. Abdul Latif Helaly, Project Director, URP-RAJUK

    • Mr. Md. Aminur Rahman, Deputy Project Director, URP-RAJUK

    • Mr. Md. Shahjahan, Sr. Financial Management and Planning Specialist, URP-RAJUK

    • Mr. Md. Mahboob Hassan, Sr. Procurement Specialist, URP-RAJUK

    • Mr. Md. Saifur Rahman Joarder, Procurement Specialist, URP-RAJUK

    Fire Service and Civil Defense (FSCD)

    • Brigadier General Md Sazzad Hussain, ndc, afwc, psc, Mphil, DG, FSCD

    • Mr. Zillur Rahaman, Lieutenant Colonel, Director (Operations), FSCD

    Monitoring and Evaluation Firm (GOPA Consultants, and Services and Solutions Int. Ltd.)

    • Mr. Richard Carlos Worden, Acting Team Leader, URP M&E. PCMU, Planning Commission

    • Mr. Shaker Ahmed, Deputy Team Leader, URP M&E. PCMU, Planning Commission

    • Mr. A.B.M. Shamsul Arefin, M&E Specialist, URP-PCMU, Planning Commission

    • Mr. Syed Muhammad Latif, Environmental Safeguard Specialist, URP M&E. PCMU, Planning Commission

    • Mr. Monzur Rahman, Social Safeguard Specialist, URP M&E. PCMU, Planning Commission

    • Mr. Md. Farid Uddin, Managing Director, Services and Solutions International Limited (SSIL)

  • - 26 -

    Annex III: Updated Results Framework

    Project Development Objective Indicators

    Indicator Name Unit of

    Measure Baseline

    Cumulative Target Values

    Frequency Data Source/

    Methodology

    Responsible

    for

    data

    collection

    Comments

    YR1 YR2 YR3 YR4 YR5

    Share of wards with decentralized

    emergency response services in

    Dhaka (DNCC/DSCC jurisdiction)5

    Number

    PAD

    Targets 0 0 0 23 45 68

    Annual

    DNCC, DSCC,

    FSCD/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 23 45

    Share of wards with decentralized

    emergency response services in

    Sylhet (SCC jurisdiction)6

    Number

    PAD

    Targets 0 0 0 7 14 20

    Annual

    SCC, FSCD/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 20

    Increased capacity of officials and

    emergency management response

    personnel7

    Composite

    Scale

    PAD

    Targets N/A

    Base

    line

    Base

    line

    Base

    line

    + 1

    Basel

    ine +

    2

    Base

    line

    + 3 Annual

    DDM/ Based on

    the training,

    exercises and

    drills consultant

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved N/A N/A N/A N/A N/A

    Systems established to reduce

    vulnerability of new buildings in

    Dhaka and Sylhet8

    Number

    PAD

    Targets 0 0 0 0 1 3

    Annual

    RAJUK, SCC/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 0

    5 Number of wards where corresponding zonal offices are equipped with ECT kits and are at least partially within five kilometers radius of at least one emergency management warehouse or one equipped FSCD control room

    6 Number of wards within five kilometers of at least one emergency management warehouse or equipped FSCD control room

    7Annual inter-agency exercise and drills program that tests and evaluates the skills and abilities of emergency personnel on an aggregate score of 1-10. The methodology for determining the baseline will be developed by the training,

    exercises and drills consultant prior to program commencement. 8 Systems include: Urban Resilience Unit, Electronic Construction Permitting, Professional Accreditation Program

  • - 27 -

    Indicator Name Unit of

    Measure Baseline

    Cumulative Target Values

    Frequency Data Source/

    Methodology

    Responsible

    for

    data

    collection

    Comments

    YR1 YR2 YR3 YR4 YR5

    Intermediate Results Indicators

    Component A

    DDM facilities renovated (ERCC,

    NDMRTI) Number

    PAD

    Targets 0 0 2 2 2 2

    Annual

    DDM/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 0

    FSCD facilites constructed and/or

    renovated9

    Number

    PAD

    Targets 0 0 10 20 29 31

    Annual

    FSCD/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 13 28

    DNCC/DSCC/SCC facilities

    constructed and/or renovated10 Number

    PAD

    Targets 0 0 10 15 24 26

    Annual

    DNCC/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 8 8 24

    DDM/DNCC/DSCC/SCC/FSCD and

    Satellite Control Room facilities

    equipped with ECT suites and/or

    kits11

    Number

    PAD

    Targets 0 0 0 25 53 57

    Annual

    DNCC/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 17

    9 Two fixed control rooms, 12 emergency management warehouses and 17 auxiliary control rooms 10 10 emergency management warehouses, two emergency operations centers, three disaster risk management offices, 10 zonal control rooms, one urban resilience unit 11 6 ECT suites and 51 “flyaway” communications kits

  • - 28 -

    Indicator Name Unit of

    Measure Baseline

    Cumulative Target Values

    Frequency Data Source/

    Methodology

    Responsible

    for

    data

    collection

    Comments

    YR1 YR2 YR3 YR4 YR5

    FSCD emergency management

    warehouses equipped with

    specialized search and rescue

    equipment

    Number

    PAD

    Targets 0 0 0 10 12 12

    Annual

    FSCD/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 13

    Multi-agency exercises and drills

    completed Number

    PAD

    Targets 0 0 2 4 8 12

    Annual

    DDM/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 0

    Component B

    Identification of critical and essential

    facilities and lifelines for Dhaka12 Percentage

    PAD

    Targets 0 0 50 100 100 100

    Annual

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress.

    Will be revised during

    upcoming

    restructuring.

    Database of critical and

    essential facilities

    developed

    Actual

    Achieved 0 0 0 0 100

    12 Consulting firm will first identify all critical and essential facilities and lifelines for Dhaka, then prioritize a limited list to survey and assess for the following stage

  • - 29 -

    Indicator Name Unit of

    Measure Baseline

    Cumulative Target Values

    Frequency Data Source/

    Methodology

    Responsible

    for

    data

    collection

    Comments

    YR1 YR2 YR3 YR4 YR5

    Vulnerability of prioritized critical

    and essential facilities and lifelines

    assessed for Dhaka

    Percentage

    PAD

    Targets 0 0 0 25 75 100

    Annual

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress.

    Will be revised during

    upcoming

    restructuring.

    Inception, Stakehoilder

    engagemenmt, and

    Situation Analysis

    completed. Survey

    completed.

    Methodology for

    vulnerability

    assessment established

    (RVA, PEA & DEA)

    10% RVA completed

    Actual

    Achieved 0 0 0 0 25

    Component C

    E-Permits for construction issued by

    RAJUK13 Number

    PAD

    Targets N/A 0 0 0

    Basel

    ine

    set

    Base

    line

    +30

    %

    Annual

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress. Will be

    revised during

    upcoming

    restructuring.

    Current construction

    permitting practice

    studies completed.

    Actual

    Achieved N/A 0 0 0 0

    13 Baseline will be set one year after system is publicly launched

  • - 30 -

    Indicator Name Unit of

    Measure Baseline

    Cumulative Target Values

    Frequency Data Source/

    Methodology

    Responsible

    for

    data

    collection

    Comments

    YR1 YR2 YR3 YR4 YR5

    RAJUK Urban Resilience Unit

    facility constructed Percentage

    PAD

    Targets 0 0 20 80 100 100

    Annual

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress. Will be

    revised during

    upcoming

    restructuring.

    All design and

    specifications for the

    URU construction is

    completed

    Actual

    Achieved 0 0 0 0 5

    RAJUK Urban Resilience Unit

    facility equipped with laboratory and

    field-testing equipment

    Percentage

    PAD

    Targets 0 0 0 50 75 100

    Annual

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    3 of the 4 packages for

    equipment are signed

    and to be delivered

    shortly. Technical

    evaluation of the

    remaining 1 package

    underway.

    Actual

    Achieved 0 0 0 0 0

    Professional Accreditation Program

    for Engineers, Architects and

    Planners established

    N/A PAD

    Targets

    N/A

    Consu

    ltat

    ion p

    roce

    ss w

    ith

    sta

    keh

    old

    ers

    com

    ple

    ted

    Res

    earc

    h a

    nd a

    nal

    yti

    cal

    form

    ula

    tio

    n

    com

    ple

    ted

    Acc

    redit

    atio

    n b

    oar

    d e

    stab

    lish

    ed

    Pla

    tform

    for

    conti

    nued

    ed

    uca

    tio

    n a

    nd

    trai

    nin

    g t

    o s

    upp

    ort

    cer

    tifi

    cati

    on

    est

    abli

    shed

    Outr

    each

    and E

    du

    cati

    onal

    Cam

    pai

    gn

    com

    ple

    ted

    Annual

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    Will be revised during

    upcoming

    restructuring.

  • - 31 -

    Indicator Name Unit of

    Measure Baseline

    Cumulative Target Values

    Frequency Data Source/

    Methodology

    Responsible

    for

    data

    collection

    Comments

    YR1 YR2 YR3 YR4 YR5

    Actual

    Achieved N/A

    N/A

    N/A

    N/A

    N/A

    Component D

    Monitoring Reports produced Number

    PAD

    Targets 0 4 8 12 16 20

    Quarterly PCMU

    PCMU and

    M&E

    Consultants

    In progress. Target will

    be revised during

    upcoming

    restructuring. Actual

    Achieved 0 0 0 1 4

  • - 32 -

    Annex IV: Proposed Results Framework for Restructuring

    Indicator Name

    Un

    it

    Ba

    seli

    ne Cumulative Target Values

    Fre

    qu

    ency

    Da

    ta S

    ou

    rce/

    Met

    ho

    do

    log

    y

    Res

    po

    nsi

    ble

    for

    da

    ta

    coll

    ecti

    on

    Comments

    YR1 YR2 YR3 YR4 YR5 YR6 YR7

    Project Development Objective Indicators

    Ex

    isti

    ng

    Share of wards with

    decentralized emergency response

    services in Dhaka

    (DNCC/DSCC jurisdiction)14

    Nu

    mber

    PAD

    Targets 0 0 0 23 45 68 68 68

    An

    nu

    al

    DNCC,

    DSCC,

    FSCD/ Monitoring

    Reports

    PCMU

    and

    M&E Consult

    ants

    In progress

    Actual

    Achieved 0 0 0 23 45

    Ex

    isti

    ng Share of wards with

    decentralized

    emergency response

    services in Sylhet

    (SCC jurisdiction)15

    Nu

    mber

    PAD

    Targets 0 0 0 7 14 20 20 20

    An

    nu

    al

    SCC, FSCD/

    Monitoring

    Reports

    PCMU and

    M&E

    Consult

    ants

    In progress

    Actual

    Achieved 0 0 0 0 20

    Ex

    isti

    ng Increased capacity of

    officials and emergency

    management response

    personnel16

    Co

    mpo

    site

    Sca

    le

    PAD

    Targets N/A N/A N/A

    Baseline

    Baseline + 1 Baseline + 2 Baseline + 2 Baseline + 3

    An

    nu

    al

    DDM/ Based on the

    training,

    exercises and drills

    consultant

    PCMU

    and M&E

    Consult

    ants

    Revised as

    follows Actual

    Achieved N/A N/A N/A N/A N/A

    Rev

    ised

    Increased capacity of officials and

    emergency

    management response personnel17

    Co

    mpo

    site

    Sca

    le

    Revised

    Targets N/A N/A N/A N/A N/A Baseline Baseline + 1 Baseline + 3

    An

    nu

    al

    DDM/ Based

    on the

    training,

    exercises and

    drills

    consultant

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved N/A N/A N/A N/A N/A

    14 Number of wards where corresponding zonal offices are equipped with ECT kits and are at least partially within five kilometers radius of at least one emergency management warehouse or one equipped FSCD control room 15 Number of wards within five kilometers of at least one emergency management warehouse or equipped FSCD control room

    16Annual inter-agency exercise and drills program that tests and evaluates the skills and abilities of emergency personnel on an aggregate score of 1-10. The methodology for determining the baseline will be developed by the training,

    exercises and drills consultant prior to program commencement.

    17Annual inter-agency exercise and drills program that tests and evaluates the skills and abilities of emergency personnel on an aggregate score of 1-10. The methodology for determining the baseline will be developed by the training,

    exercises and drills consultant prior to program commencement.

  • - 33 -

    Indicator Name

    Un

    it

    Ba

    seli

    ne Cumulative Target Values

    Fre

    qu

    ency

    Da

    ta S

    ou

    rce/

    Met

    ho

    do

    log

    y

    Res

    po

    nsi

    ble

    for

    da

    ta

    coll

    ecti

    on

    Comments

    YR1 YR2 YR3 YR4 YR5 YR6 YR7

    Ex

    isti

    ng Systems established to

    reduce vulnerability of

    new buildings in

    Dhaka and Sylhet18

    Nu

    mber

    PAD Targets

    0 0 0 0 1 3

    An

    nu

    al RAJUK,

    SCC/

    Monitoring

    Reports

    PCMU

    and

    M&E Consult

    ants

    Revised as

    follows Actual

    Achieved 0 0 0 0 0

    Rev

    ised

    Systems developed to

    increase resilience of

    built environment in Dhaka19 N

    um

    ber

    Revised

    Targets 0 0 0 0 0 0 1 3

    An

    nu

    al RAJUK,

    SCC/

    Monitoring Reports

    PCMU

    and M&E

    Consult

    ants

    In progress

    Actual

    Achieved 0 0 0 0 0

    Intermediate Results Indicators

    Component A

    Ex

    isti

    ng

    DDM facilities (ERCC, NDMRTI)

    renovated Nu

    mber

    PAD

    Targets 0 0 2 2 2 2

    An

    nu

    al

    DDM/ Monitoring

    Reports

    PCMU

    and M&E

    Consult

    ants

    Revised as

    follows

    Actual

    Achieved 0 0 0 0 0

    Rev

    ised

    DDM facilities

    (ERCC, NDMRTI) renovated and

    equipped Nu

    mber

    Revised

    Targets 0 0 0 0 0 1 2 2

    An

    nu

    al

    DDM/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 0

    18 Systems include: Urban Resilience Unit, Electronic Construction Permitting, Professional Accreditation Program 19 Systems include: Urban Resilience Unit, Electronic Construction Permitting System, Risk Sensitive Land Use Planning Practice

  • - 34 -

    Indicator Name

    Un

    it

    Ba

    seli

    ne Cumulative Target Values

    Fre

    qu

    ency

    Da

    ta S

    ou

    rce/

    Met

    ho

    do

    log

    y

    Res

    po

    nsi

    ble

    for

    da

    ta

    coll

    ecti

    on

    Comments

    YR1 YR2 YR3 YR4 YR5 YR6 YR7

    Ex

    isti

    ng

    FSCD facilities

    constructed and/or renovated N

    um

    ber

    PAD Targets

    0 0 10 20 29 31

    An

    nu

    al

    FSCD/

    Monitoring Reports

    PCMU

    and

    M&E Consult

    ants

    Revised as

    follows Actual

    Achieved 0 0 0 13 28

    Rev

    ised

    FSCD facilities

    constructed and/or renovated and

    equipped20 Nu

    mber

    Revised

    Targets 0 0 10 20 28 28 28 28

    An

    nu

    al

    FSCD/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 13 28

    Ex

    isti

    ng

    DNCC/DSCC/SCC facilities constructed

    and/or renovated Nu

    mber

    PAD Targets

    0 0 10 15 24 26

    An

    nu

    al

    DNCC/ Monitoring

    Reports

    PCMU

    and M&E

    Consult

    ants

    Revised as

    follows Actual

    Achieved 0 0 8 8 24

    Rev

    ised

    DNCC/DSCC/SCC

    facilities constructed and/or renovated and

    equipped21 Nu

    mber

    Revised

    Targets 0 0 10 15 24 30 30 30

    An

    nu

    al

    DNCC/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 8 8 24

    Ex

    isti

    ng

    DDM/DNCC/DSCC/S

    CC/FSCD and

    Satellite Control Room facilities equipped

    with ECT suites and/or

    kits

    Nu

    mber

    PAD

    Targets 0 0 0 25 53 57

    An

    nu

    al

    DNCC/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    Revised as follows

    Actual

    Achieved 0 0 0 0 17

    20 2 fixed control rooms, 13 emergency management warehouses and 13 auxiliary control rooms 21 8 emergency management warehouses, 3 emergency operations centers, 8 disaster risk management offices, 10 zonal control rooms, one urban resilience unit in Sylhet EOC

  • - 35 -

    Indicator Name

    Un

    it

    Ba

    seli

    ne Cumulative Target Values

    Fre

    qu

    ency

    Da

    ta S

    ou

    rce/

    Met

    ho

    do

    log

    y

    Res

    po

    nsi

    ble

    for

    da

    ta

    coll

    ecti

    on

    Comments

    YR1 YR2 YR3 YR4 YR5 YR6 YR7

    Rev

    ised

    DDM/DNCC/DSCC/S

    CC/FSCD and Satellite Control Room

    facilities equipped

    with Emergency

    Communication

    Technology (ECT)

    suites and/or kits22

    Nu

    mb

    er

    Revised

    Targets 0 0 0 0 17 57 57 57

    An

    nu

    al

    DNCC/ Monitoring

    Reports

    PCMU

    and M&E

    Consult

    ants

    In progress

    Actual

    Achieved 0 0 0 0 17

    Ex

    isti

    ng FSCD emergency

    management warehouses equipped

    with specialized search

    and rescue equipment

    Nu

    mber

    PAD

    Targets 0 0 0 10 12 12

    An

    nu

    al

    FSCD/ Monitoring

    Reports

    PCMU

    and M&E

    Consult

    ants

    In progress

    Actual

    Achieved 0 0 0 0 13

    Ex

    isti

    ng

    Multi-agency exercises

    and drills completed

    Nu

    mber

    PAD Targets

    0 0 2 4 8 12

    An

    nu

    al

    DDM/ Monitoring

    Reports

    PCMU

    and M&E

    Consult

    ants

    Revised as

    follows Actual

    Achieved 0 0 0 0 0

    Rev

    ised

    Multi-agency training,

    exercises and drills (TED) program

    completed Nu

    mber

    Revised

    Targets 0 0 0 0 0 6 9 12

    Qu

    arte

    rly

    DDM/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 0

    Component B

    Ex

    isti

    ng

    Identification of

    critical and essential

    facilities and lifelines for Dhaka P

    erce

    nta

    ge

    PAD

    Targets 0 0 50 100 100 100

    An

    nu

    al

    RAJUK/ Monitoring

    Reports

    PCMU

    and M&E

    Consult

    ants

    Merged with the

    next

    indicator and revised

    as follows Actual

    Achieved 0 0 0 0 0 100

    22 6 ECT suites and 51 “flyaway” communications kits

  • - 36 -

    Indicator Name

    Un

    it

    Ba

    seli

    ne Cumulative Target Values

    Fre

    qu

    ency

    Da

    ta S

    ou

    rce/

    Met

    ho

    do

    log

    y

    Res

    po

    nsi

    ble

    for

    da

    ta

    coll

    ecti

    on

    Comments

    YR1 YR2 YR3 YR4 YR5 YR6 YR7

    Ex

    isti

    ng

    Vulnerability of

    prioritized critical and essential facilities and

    lifelines assessed for

    Dhaka

    Per

    cen

    tage

    PAD

    Targets 0 0 0 25 75 100

    An

    nu

    al

    RAJUK/ Monitoring

    Reports

    PCMU

    and M&E

    Consult

    ants

    Revised as

    follows Actual

    Achieved 0 0 0 0 25

    Rev

    ised

    Vulnerability

    assessment of critical and essential facilities

    and development of

    vulnerability reduction strategy and program

    Per

    cen

    tage

    Revised

    Targets 0 0 0 0

    20%

    Database of critical

    and essential

    facilities developed

    60%

    1. Survey and Rapid Visual Assessment

    (RVA) completed

    2. Preliminary

    Engineering Analysis

    and Vulnerability

    assessment conducted

    80%

    Detailed Engineering

    Analysis and

    defining the structural

    performance

    standards are

    completed

    100%

    1. Detailed design and

    cost estimation for retrofitting of all the

    selected structures

    completed

    2. Design of long-term

    vulnerability reduction

    investment plan and

    Dhaka Urban Resilience Strategy completed

    An

    nu

    al

    RAJUK/

    Monitoring Reports

    PCMU

    and

    M&E Consult

    ants

    In progress

    Actual

    Achieved 0 0 0 0 20

    New

    Development of a risk-

    sensitive land use planning practice in

    Dhaka Per

    cen

    tage Revised

    Targets 0 0 0 0

    40%

    1. Assessment of

    plans and planning

    systems of RAJUK and stakeholders

    conducted

    2. Strategic

    framework and

    implementation plan for geotechnical and

    geological

    investigation prepared

    70%

    1. Strategic

    Environment Assessment (SEA)

    Report for Greater

    Dhaka area developed

    2. Develop

    methodology and framework for Risk-

    Sensitive Land Use

    Planning Practice (RSLUP) particularly

    suited for Dhaka

    3. Seismic

    Microzonation studies

    conducted

    90%

    1. Framework for

    mainstreaming Disaster Risk

    Reduction

    (DRR) into the greater Dhaka

    planning system

    developed

    2. Greater Dhaka

    Risk Sensitive Land Use

    Strategy

    developed.

    100%

    1. Risk Sensitive Land Use Planning practice

    developed for the

    greater Dhaka planning system

    2. Integrating and mainstreaming Hazard

    and Vulnerable Risk

    Assessment (HVRA) into the current planning

    practice

    An

    nu

    al

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 40

  • - 37 -

    Indicator Name

    Un

    it

    Ba

    seli

    ne Cumulative Target Values

    Fre

    qu

    ency

    Da

    ta S

    ou

    rce/

    Met

    ho

    do

    log

    y

    Res

    po

    nsi

    ble

    for

    da

    ta

    coll

    ecti

    on

    Comments

    YR1 YR2 YR3 YR4 YR5 YR6 YR7

    Component C

    Ex

    isti

    ng

    E-Permits for

    construction issued by RAJUK N

    um

    ber

    PAD Targets

    N/A 0 0 0 Baseline set Baseline +30%

    An

    nu

    al

    RAJUK/

    Monitoring Reports

    PCMU

    and

    M&E Consult

    ants

    Revised as

    follows Actual

    Achieved N/A 0 0 0 0

    Rev

    ised

    Electronic Construction

    Permitting (ECP)

    System developed by RAJUK

    Per

    cen

    tage Revised

    Targets N/A 0 0 0

    30%

    Assessment of

    current construction

    permitting practice

    70%

    1. System design completed

    2. Prototype/s of ECP System developed

    followed by end-user’s

    feedback, testing and bug-fixing completed

    90%

    1. ECP system

    implemented

    2. Trainings

    provided and Operational

    Acceptance Test

    (OAT) performed

    100%

    ECP integrated into RAJUK

    An

    nu

    al

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved N/A 0 0 0 30

    Ex

    isti

    ng

    RAJUK Urban Resilience Unit facility

    constructed

    Per

    centa

    ge PAD

    Targets 0 0 20 80 100 100

    An

    nu

    al

    RAJUK/ Monitoring

    Reports

    PCMU

    and M&E

    Consult

    ants

    Revised as

    follows Actual

    Achieved 0 0 0 0 5

    Rev

    ised

    RAJUK Urban Resilience Unit

    Constructed,

    Established and Functional

    Per

    cen

    tage Revised

    Targets 0 0 0 0

    20%

    All design and specifications for the

    URU construction is

    completed

    60%

    1. Institutional design and Organizational

    Study is conducted

    2. A comprehensive

    out-reach campaign is

    designed and implemented

    80%

    Capacity

    building and training for URU

    staffs conducted

    100%

    1. URU building

    construction completed

    2. URU set-up

    completed and

    functional

    An

    nu

    al

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    In progress

    Actual

    Achieved 0 0 0 0 20

  • - 38 -

    Indicator Name

    Un

    it

    Ba

    seli

    ne Cumulative Target Values

    Fre

    qu

    ency

    Da

    ta S

    ou

    rce/

    Met

    ho

    do

    log

    y

    Res

    po

    nsi

    ble

    for

    da

    ta

    coll

    ecti

    on

    Comments

    YR1 YR2 YR3 YR4 YR5 YR6 YR7

    Ex

    isti

    ng RAJUK Urban

    Resilience Unit facility

    equipped with

    laboratory and field-testing equipment

    Per

    cen

    tage

    PAD

    Targets 0 0 0 50 75 `100

    An

    nu

    al

    RAJUK/

    Monitoring

    Reports

    PCMU and

    M&E

    Consultants

    Revised as

    follows

    Actual

    Achieved 0 0 0 0 0

    Rev

    ised

    RAJUK Urban

    Resilience Unit facility equipped with

    laboratory and field-

    testing equipment

    Per

    cen

    tage

    Revised

    Targets 0 0 0 0 0

    70%

    Test equipm