BALISES FOR ATP – TRACK & CIVIL REQUIREMENTS 07/06/13 · 2019. 5. 23. · Any track work which...

3
Withdrawn - This document has been handed over to the Operator & Maintainer Page 1 of 3 I I I s s s s s s u u e e d d b b y y C C h h i i e e f f E E n n g g i i n n e e e e r r s s D D i i v v i i s s i i o o n n C C i i v v i i l l T T e e c c h h n n i i c c a a l l N N o o t t e e CTN 13/07 07/06/13 Expires 07/06/2014 Audience Civil Maintenance Engineers Planning Engineers Team Managers/ Team Leaders Production & Renewals Managers/ Engineers/ Team Leaders Project Engineers, Managers Main Points Balises must not be damaged or disturbed. Any damage must be reported to signals Contact Jason Firmstone (Signals) 02 85750513 Warwick Allison (Signals) 02 8922 1760 Distribution Open L ast Open Distribution CTN 13/06 BALISES FOR ATP – TRACK & CIVIL REQUIREMENTS Background The TfNSW Automatic Train Protection (ATP) Project is progressively installing balises (transponders) in the four foot at locations across the network. These balises send signalling information to trains as they travel over them. As at 13 May 2013, balises have been installed between Wyong and Asquith, and in the Blacktown area with some remaining at test sites in the Blue Mountains between Penrith and Mount Victoria. Description ATP balises are of a fibreglass construction and are bolted directly to the sleepers or slab. A rectangular location ID plate is fixed to the top of the sleeper adjacent to each balise and has the same ID description as the circular balise ID plate. ATP balises may be either yellow or grey when new. Some balises are connected to a trackside junction box via a surface laid cable in an orange hose and these are known as 'controlled' balises. Some balises do not have a cable and these are known as 'fixed' balises. Typically a pair of balises (usually one 'fixed' and one 'controlled' balise) will be installed before every signal, but balises will also be found at other locations between signals. Reporting Requirements The ATP balises are a signalling critical asset and must not be disturbed without prior approval. It is critical that Signalling maintenance staff are made aware of any damaged, disturbed or removed balises, as this may cause operational delays to trains once the ATP system becomes operative on a line. The alignment of the balise relative to the track is important and any damage, including knocking a balise out-of-square must be reported. In particular, care must be taken not to damage the cable or cable connection point at a 'controlled' balise or the adjacent trackside junction box. Disclaimer This document was prepared for use on the RailCorp Network only. RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the copy of the document it is viewing is the current version of the document as in use by RailCorp. RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes any liability which arises in any manner by the use of this document. Copyright The information in this document is protected by Copyright and no part of this document may reproduced, altered, stored or transmitted by any person without the prior consent of RailCorp. be

Transcript of BALISES FOR ATP – TRACK & CIVIL REQUIREMENTS 07/06/13 · 2019. 5. 23. · Any track work which...

Page 1: BALISES FOR ATP – TRACK & CIVIL REQUIREMENTS 07/06/13 · 2019. 5. 23. · Any track work which may impact on balises, balise cables or their junction boxes should be first discussed

With

draw

n - T

his

docu

men

t has

bee

n ha

nded

ove

r to

the

Ope

rato

r & M

aint

aine

r

Page 1 of 3

II Issssssuueedd bbyy CChhiieeff EEnnggiinneeeerrss DDiivviissiioonn

CCiivviill TTeecchhnniiccaall NNoottee

CTN 13/07 07/06/13

Expires 07/06/2014

Audience • Civil Maintenance

Engineers • Planning Engineers • Team Managers/ Team

Leaders • Production & Renewals

Managers/ Engineers/ Team Leaders

• Project Engineers, Managers

Main Points • Balises must not be

damaged or disturbed. • Any damage must be

reported to signals

Contact Jason Firmstone (Signals)

02 85750513 Warwick Allison (Signals)

02 8922 1760

Distribution

Open

Last Open Distribution

CTN 13/06

BALISES FOR ATP – TRACK & CIVIL REQUIREMENTS

Background The TfNSW Automatic Train Protection (ATP) Project is progressively installing balises (transponders) in the four foot at locations across the network. These balises send signalling information to trains as they travel over them.

As at 13 May 2013, balises have been installed between Wyong and Asquith, and in the Blacktown area with some remaining at test sites in the Blue Mountains between Penrith and Mount Victoria.

Description ATP balises are of a fibreglass construction and are bolted directly to the sleepers or slab. A rectangular location ID plate is fixed to the top of the sleeper adjacent to each balise and has the same ID description as the circular balise ID plate. ATP balises may be either yellow or grey when new.

Some balises are connected to a trackside junction box via a surface laid cable in an orange hose and these are known as 'controlled' balises. Some balises do not have a cable and these are known as 'fixed' balises.

Typically a pair of balises (usually one 'fixed' and one 'controlled' balise) will be installed before every signal, but balises will also be found at other locations between signals.

Reporting Requirements The ATP balises are a signalling critical asset and must not be disturbed without prior approval.

It is critical that Signalling maintenance staff are made aware of any damaged, disturbed or removed balises, as this may cause operational delays to trains once the ATP system becomes operative on a line.

The alignment of the balise relative to the track is important and any damage, including knocking a balise out-of-square must be reported. In particular, care must be taken not to damage the cable or cable connection point at a 'controlled' balise or the adjacent trackside junction box.

Disclaimer This document was prepared for use on the RailCorp Network only. RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the copy of the document it is viewing is the current version of the document as in use by RailCorp. RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes any liability which arises in any manner by the use of this document. Copyright The information in this document is protected by Copyright and no part of this document may reproduced, altered, stored or transmitted by any person without the prior consent of RailCorp.

be

Page 2: BALISES FOR ATP – TRACK & CIVIL REQUIREMENTS 07/06/13 · 2019. 5. 23. · Any track work which may impact on balises, balise cables or their junction boxes should be first discussed

With

draw

n - T

his

docu

men

t has

bee

n ha

nded

ove

r to

the

Ope

rato

r & M

aint

aine

rCTN 13/07

Civil Technical Note 07/06/13

7/06/2013 © Rail Corporation Page 2 of 3

If there is any damage to balises it should be reported via the Infrastructure Operations Centre (IOC) on (02) 9379 5555.

Trackwork Precautions Prior to commencement of ballast ploughing, re-sleepering, ballast cleaning or re-railing and any other activity where there is a high risk of damage, ATP balises and their cables will need to be removed from the track to a safe place and re-fitted, after the works have concluded by authorised persons.

Any track work which may impact on balises, balise cables or their junction boxes should be first discussed with the Signal Engineer, to determine work strategies.

Do not:

• drag a rail in the four foot, over or past a balise fitted on the track.

• run over a balise with vehicle wheels.

• step on a balise cable plug.

When storing rails in the four foot, do not:

• store more than two rails side-by-side.

• encroach within 1m of a balise

• allow the ends of a pair of stored rails to overlap by more than 10m, as the additional metal mass may be detected by the on-board ATP system resulting in an alarm and subsequent train braking application.

As part of the Possession Planning process, track activities need to be scheduled well in advance in order to ensure appropriate signalling and track resources are available.

Authorised for issue

Malcolm Kerr Warwick Allison Chief Engineer Track Chief Engineer Signals and Control Systems

Page 3: BALISES FOR ATP – TRACK & CIVIL REQUIREMENTS 07/06/13 · 2019. 5. 23. · Any track work which may impact on balises, balise cables or their junction boxes should be first discussed

With

draw

n - T

his

docu

men

t has

bee

n ha

nded

ove

r to

the

Ope

rato

r & M

aint

aine

rCTN 13/07

Civil Technical Note 07/06/13

7/06/2013 © Rail Corporation Page 3 of 3

Balise Types

1) Example of two 'fixed' Balises on open track between signals

2) Example of a pair of Balises ('controlled' and 'fixed') before a signal. Note the cable connected to the 'controlled' balise in the foreground.

3) Example of a pair of Balises between guard rails. Note the cable connected to the 'controlled' balise in the background.