Effective 01/24/17 Page 1 of 1 PSLUSD Doc. No. 123
Backflow Prevention Assembly Test ReportFacility NameMeter Test Report Due
Schedule Code
Assembly ID Account No. Service Address Assy Location Location No. Contact Name Map Page
Telephone
Assembly Info (Replacement/Correction)SNMfrTypeSizeModelInstall DatePermit No.Hazard LevelHazard Type
Protection
Line Pressure at Time of Test REPORT OF TEST RESULTS Approved BFP
Initial TestPass
Fail
Check Valve #1 Check Valve #2 Relief Valve PVB/SVB Shut Off Valves
Closed Tight
Leaked
#1 #2Air Inlet Opened at PSID
Did Not Open
PSID Held Check at
Opened at
PSID
Did Not Open
Held at
PSIDClosed Tight
LeakedLeaked
Held at
PSID
Closed Tight
Leaked
Cleaned
REPLACED
Disc
Spring
Guide
Seat
Hinge Pin
Diaphragm
Module
Cleaned
REPLACED
Disc
Spring
Guide
Seat
Hinge Pin
Module
Cleaned
REPLACED
Disc
Spring
Guide
Seat
O-Ring(s)
Module
Cleaned
REPLACED
Air Inlet Disc
Air Inlet Spring
Check Disc
Check Spring
Float
Diaphragm
CLEANED
REPLACED
REPAIRED
OTHER
Repairs
Other/Notes
Final TestPSID
Closed Tight
PSID
Closed Tight
Opened at Air Inlet PSID
CK Valve PSID
Closed Tight
PASS
Initial Test By
Final Test By
Repair By
Certificate Date Gauge No. Time In Time Out Company Telephone
PSIDTHE ABOVE REPORT IS CERTIFIED TO BE TRUE
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SW Ogden Lane, Port St Lucie, FL 34983
Effective 01xx17 Page 1 of 1 PSLUSD Doc. No. 48
Project Name
PSLUSD Project No.
Engineer of Record
Contractor
EOR/EOR Rep Date
To be completed by the Engineer of Record (EOR)/EOR Rep. and E-Mailed to [email protected]
Flushing Report
Pass Fail
Date Lines TestedGallons
Per MinuteMinutes Flushed
GallonsFlushed
Number of Pigs Used
Number of Pigs Retrieved
Residue in Bucket? Yes No
Water
Sewer
Reclaimed
Total Gallons Flushed
Pressure TestTo be completed by the Engineer of Record (EOR)/EOR Rep. and e-mailed to [email protected]
Project Name
PSLUSD Project No.
Engineer of Record (EOR)
Contractor
Allowable Leakage Formula:
Location/Limits of Test
Water Wastewater Re-claimed Water
Pass Fail
Start Time End Time
EOR/EOR Rep Date
148,000
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SE Ogden Lane, Port St Lucie, FL 34983
Print Signature
Inspector
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SE Ogden Lane, Port St Lucie, FL 34983
Effective 01xx17 Page 1 of 1 PSLUSD Doc. No. 73
Project Name
PSLUSD Project No.
Engineer of Record
Contractor
EOR/EOR Rep Date
To be completed by the Engineer of Record (EOR)/EOR Rep. and E-Mailed to [email protected]
Fire Hydrant Flow Test
Pass Fail
HYRDRANT REPAIR KIT RECEIVED:IF NOT, TEST FAILS UNTIL KIT RECEIVED
COEFFICIENT NUMBER*COEFFICIENT NUMBER REMAINS AT 0.88
DIAMETERDIAMETER OF HYDRANT DISCHARGE (TYPICALLY 2.5")
STATIC PRESSUREPRESSURE PRIOR TO FLUSHING HYDRANT
RESIDUAL PRESSUREPRESSURE DURING FLUSHING OF HYDRANT
PITOT PRESSUREPRESSURE READING ON PITOT GUAGE
RESIDUAL FLOWRF=29.83 X (CN X DIA TO THE 2 POWER) X (√PP)
FIRE FLOWFF= RF X ((SP-20) ÷ (SP-RP)) TO THE 0.54 POWER
*COEFFICIENT NUMBER IS BASED ON SHARPE SQUARE EDGE INLET TYPESCN= COEFFICIENT NUMBER DIA = DIAMETER
PP= PITOT PRESSURE RF = RESIDUAL FLOW FF = FIRE FLOW
COMMENTS
SP = STATIC PRESSURERP = RESIDUAL PRESSURE
YES NO
Print Signature
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SE Ogden Lane, Port St Lucie, FL 34983
Effective 01/20/17 Page 1 of 1 PSLUSD Doc. No. 93
Project Name
PSLUSD Project No.
Engineer of Record
Contractor
EOR/EOR Rep Date
To be completed by the Engineer of Record (EOR)/EOR Rep. and E-Mailed to [email protected] Continuity & Electronic Marker Verification Test Report
Pass Fail
Water Main Tested
Force Main Tested
Re-Use Water Main Tested
All Trace Wire Tested
All Electronic Markers Tested
Pass
Pass
Fail
Fail
Limits of Test
Comments
Print Signature
City of Port St Lucie
PSLUSD
Phone (772) 344-4320Email: [email protected]
Utility Systems Department
900 SE Ogden Lane, Port St Lucie, FL 34983
Project Name
PSLUSD Project No.
Engineer of Record
Contractor
Telespection Company
Verified Running Water Downstream for Each Test
page of
Date Tested
BeginningMH#
EndMH#
SVCL/R FT
SVCL/R FT
SVCL/R FT
SVCL/R FT
SVCL/R FT FailPass
OtherProblemFootageDIP
SVCL/R FT
SVCL/R FT
SVCL/R FT
SVCL/R FT
Other Problem(s):A Excessive Sand/SiltB Leaking ServiceC Damaged PipeD Bad Joint
Effective 01/18/17 PSLUSD Doc. No. 105
EOR/EOR Rep. Date
Yes No
Telespection Test ReportTo be completed by the Engineer of Record (EOR)/EOR Rep. and E-Mailed to [email protected]
Print Signature
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SE Ogden Lane, Port St Lucie, FL 34983
Effective 01/12/17 Page 1 of 1 PSLUSD Doc. No. 108
Project Name
PSLUSD Project No.
Engineer of Record
Contractor
EOR/EOR Rep Date
To be completed by the Engineer of Record (EOR)/EOR Rep. and E-Mailed to [email protected]
Deflection Test Report
Pass Fail
Date Tested:
Equipment Used: Mandrel
To Structure Pass or Fail
Calibrated Laser Camera
Start Time: End Time:
From Structure
Date Calibrated:
30 Days After Final Backfill?
Main Diameter Main Length
Print Signature
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SE Ogden Lane, Port St Lucie, FL 34983
Effective 01/12/17 Page 1 of 1 PSLUSD Doc. No. 109
Project Name
PSLUSD Project No.
Engineer of Record
Contractor
EOR/EOR Rep Date
To be completed by the Engineer of Record (EOR)/EOR Rep. and E-Mailed to [email protected]
Infil/Exfil Test Report
Pass Fail
Allowable Leakage Formula:Gravity Sewer 50 Gallons/Per Day (24 Hours)/Per Inch Diameter/Per Mile (5280 Feet) Wet Well & Interceptor - 0 Loss
Structures Tested Structure Diameter/Gal. Structure Depth Allowable Per Hour Test Allowable
Main Tested Main Diameter Main Length Allowable Per Hour Test Allowable
Services Tested Service Diameter Service Length Allowable Per Hour Test Allowable
Infil
Exfil
Start Time:
End Time:
Total Test Allowable Actual Leakage
Print Signature
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SE Ogden Lane, Port St Lucie, FL 34983
Effective 01/18/17 Page 1 of 1 PSLUSD Doc. No. 110
Project Name
PSLUSD Project No.
Engineer of Record
Contractor
Date
Pump Station Start Up Test
Pass Fail
Diameter
Depth
Voltage
Phasing
Full Load Amps
Pump HP
FPL Meter
Design GPM
Design TDHPump #1 Pump #2
Actual GMP
Actual TDH
Pump Manf/Model
Generator on Site
Repair Kit Turned Over
Plant Able to Communicate
Plant Can Read Guages
Yes
Yes
Yes
Yes
No
No
No
No
Start Up Fails Until Kit Turned Over
Attendees:
Deficiencies:
Signature
EOR/EOR REPPrint
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SE Ogden Lane, Port St Lucie, FL 34983
Effective 01/20/17 Page 1 of 1 PSLUSD Doc. No. 110
Pump Station Start-Up WorksheetA = The measurement from the top of the rim of the station after ending the pump draw down test.B = The measurement from the top of the water to the rim of the station before starting the pump draw down test. C = The measurement from the rim of the station to the center of the pressure gauge.D = The diameter of the station.PSI = Reading of pressure gauge.
Formula:
Pump #1 Pump #2
A =
B =
C =
D =
PSI =
inches
inches
inches
inches
feet
feet
feet
feet
A =
B =
C =
D =
PSI =
inches
inches
inches
inches
feet
feet
feet
feet
1. (A ft - B ft) x (D ft x D ft) x 7.481 x 0.7854 = Volume Displaced in Gallons2. A ft - C ft = Total Static Lift (TSL)3. PSI x 2.31 = Dynamic Head Pressure (DHP)4. TSL + DHP = Total Dynamic Head Pressure (TDHP)
Pump #1
1.((A ft) – (B ft) x (D ft) x (D ft) ) x 7.481 x 0.7854 = Volume Displaced
(A-B ft) x (DxD ft) x 7.481 x 0.7854 = Volume Displaced
2. (A ft) –/+ (C ft) = Total Static Lift (A-C if pressure gauge is below rim, A+C if pressure gauge is above rim.)
3. (PSI) x 2.31 = Dynamic Head Pressure
4. (TSL) + (DHP) = Total Dynamic Head Pressure
5. (PSI) x 2.31 = + Static Lift = Shutoff Head (Not for low pressure) (after start up, close valves in valve pit and pump against them for PSI)
Pump #2
1.((A ft) – (B ft) x (D ft) x (D ft) ) x 7.481 x 0.7854 = Volume Displaced
(A-B ft)(A-B ft) x (A-B ft) x (DxD ft) x 7.481 x 0.7854 = Volume Displaced
–/+ (C ft) –/+
(PSI) x 2(PSI) x 2.31 =
2. (A ft)
3. (PSI)
4. (TSL) + (DHP) = Total Dynamic Head Pressure
5.5. (PSI) x 2.31 = + Static Lift = Shutoff Head (Not for low pressure.)(after start up, close valves in valve pit and pump against them for PSI)
= Total Static Lift (A-C if pressure gauge is below rim, A+C is pressure gauge is above rim.)
Dynamic Head Pressure
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SE Ogden Lane, Port St Lucie, FL 34983
Effective 01/18/17 Page 1 of 2 PSLUSD Doc. No. 191
Project Name:
Type of Station:
Pump Station Inspection
1. Valve Vault at Correct Elevation
2. Pedestal at Correct Height
3. Red Light Visible from Roadway
4. Wetwell at Correct Elevation
5. Fall Protection Installed
6. Odor Scrubber Installed
7. Pump Out Connection is Correct Size
8. Dust Cap has a 1/4" SS Ball Valve Installed
11. Pipe Supports & Uni-strut Correct Material
10. Pressure Reducer Installed & Correct Material
12. Uni-strut Caps on Ends
9. Pipe Support Installed & Correct Material
13. All Components Installed on Pedestal/Uni-strut
13a. Components at Correct Height
14. Correct Materials for City/County
15. Hose Bib Installed Correctly
16. Seal Offs in Place
17. Hose Bib Installed & Secure
18. Water Meter & RPZ Installed
19. Fence Installed with Correct Materials
20. Fence Installed in Correct Location
Project No.:
Station No.:
Y N N/A
Effective 01/18/17 Page 2 of 2 PSLUSD Doc. No. 191
21. Lift Station ID Sign on Fence in Correct Location
22. Antenna in Correct Location
23. Flood Light Installed & Aimed Correctly
24. Driveway & Generator Pad Correct Size
25. Visqueen & Rock Installed at Correct Depth
26. Site Graded Sloping Away from Wetwell
27. First Manhole Inside of the Fenced Area
28. 12' x 48' Area for Vac Truck Within
29. 10' of the Center of Wetwell
30. Bollards Installed Where Required
31. All Piping above Ground & Inside Wetwell
32. Painted with Proper Paint & Thickness
Comments:
Photos:
EOR/EOR REP Date
Y N N/A
Print Signature
PSLUSD
City of Port St LucieUtility Systems Department
Phone (772) 344-4320Email: [email protected] 900 SW Ogden Lane, Port St Lucie, FL 34983
Effective 06/22/17 Page 1 of 1 PSLUSD Doc. No. 111
Project Name
PSLUSD Project No.
Engineer of Record
Contractor
EOR/EOR Rep Date
To be completed by the Engineer of Record (EOR)/EOR Rep. and E-Mailed to [email protected] Work Completion Inspection
Pass Fail
Initial Inspection Date Re-inspection Date
All Grading Complete
Valve Pads Level
Discs Correct
Valve Lids Painted Correct Color
Valves Turn Freely
Electronic Marker System- Balls in Place
Sample Points Removed & Plugged
Fire Service has hi/lo Flow Setup
Fire Service has Chains & Locks
Mains have Cover in Swale Aeeas
Reflective PavementMarkers in Place
All Necessary Valves Opened/Closed
Pumpstation Fence has no Damage
Fence Gates Open/Close Smoothly
All Padlocks in Place
Interceptors at GradeInterceptors Have Correct LidsInterceptor Lids Labeled Correctly
RPZ Plumb & Stable
Meters Set
Meters LockedAll Meters Have Separate Curb StopMeters Over 3" have hi/lo Flow Setup
Blow Off Assemblies CorrectFire Hydrant Paint Not Scuffed
Fire Hydrant Meets ClearancesHydrant Chains Intact
Air Release Valve (ARV)
ARV Lid Painted Correct ColorARV Lid Doesn't Hit Valve
Landscape/Tree IssuesConcrete Work has No Damage
Manholes at Correct Elevation
Manholes are Clean
Manholes Have Correct LidsClean-outs in Place with Covers
Comments
Attendees
Y N N/A Y N N/A
Remove Plug from Sanitary Sewer after Passing Inspection