B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave....

30
B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Traffic Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION ENGINEERING 227 SW Pine Street Suite 320 Portland, OR 97204 Prepared for Oregon Department of Transportation Region - 1

Transcript of B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave....

Page 1: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

B St

K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro)

Tra�c Management Plan For

Prepared by

May 2018

GLOBAL TRANSPORTATION ENGINEERING227 SW Pine StreetSuite 320Portland, OR 97204

Prepared for

Oregon Department of Transportation Region - 1

Page 2: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 1

Table of Contents TMP Goals .......................................................................................................................... 3

Project Background ............................................................................................................. 3

Project Area Boundaries .............................................................................................. 3

Proposed Improvements .............................................................................................. 3

Project Area Characteristics ................................................................................................ 6

Traffic Characteristics .................................................................................................. 6

Roadway Characteristics ............................................................................................. 7

Location of Other Construction Projects .............................................................................. 8

Factors Impacting Construction Staging .............................................................................. 8

Project Schedule .......................................................................................................... 8

Proposed Improvements and Potential Impacts to Traffic Flow .................................... 8

Existing Vehicle Restrictions ........................................................................................ 8

Work Zone Lane Closure Restrictions .......................................................................... 9

Seasonal Restrictions .................................................................................................11

Alternate Routes .........................................................................................................11

Construction Noise Regulations ..................................................................................11

Potential Mobility Issues .....................................................................................................12

Traffic Mobility during Construction .............................................................................12

Input from the Public and Stakeholders .......................................................................12

Agency Coordination ...................................................................................................12

Consideration of Over-Sized Vehicles .........................................................................13

Traffic Management and Operation Strategies ...................................................................13

Public Information and Outreach Strategies ................................................................13

Motorist Information/ITS Strategies .............................................................................13

Construction Strategies ...............................................................................................14

Alternate Route Strategies ..........................................................................................15

Proposed construction Staging ..........................................................................................15

OR8 (Oak Street) at OR219 (S 1st Avenue).................................................................17

Concept .............................................................................................................................17

Vehicle Detour ...................................................................................................................17

Pedestrians and Bicycle Accommodations .........................................................................17

OR8 (Baseline Street) at OR219(S 1st Avenue) .........................................................15

Concept .............................................................................................................................15

Vehicle Detour ...................................................................................................................16

Pedestrians and Bicycle Accommodations .........................................................................16

OR8: SE 44th Avenue to SE 45th Avenue Pedestrian Crossing ....................................18

Concept .............................................................................................................................18

Vehicle Detour ...................................................................................................................19

Pedestrians and Bicycle Accommodations .........................................................................19

Page 3: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 2

List of tables

Table 1. Existing Traffic volumes................................................................................................ 6

Table 2. Project Area Roadway Functional Classification ........................................................... 7

Table 3. Existing Roadway Conditions Within Study Area .......................................................... 7

List of Figures

Figure 1. Vicinity Map- OR99E Railroad Tunnel ......................................................................... 4

Figure 2. Vicinity Map-N Denver Ave NB Tunnel ........................................................................ 5

Figure 3. Construction Staging at OR8(Baseline Street) / OR219 (S 1st Avenue) .....................16

Figure 4. Construction Staging at OR8(Oak Street) / OR219 (S 1st Avenue) ............................18

Page 4: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 3

TMP Goals

The primary purpose of the TMP is to address the construction-related traffic impacts of the

OR8: Corridor Improvements Project in a cost-effective and timely manner. It also serves to

identify means and methods to minimize public inconvenience due to constructions activities.

This Traffic Management Plan (TMP) document will facilitate the development team’s

understanding of how traffic is planned to be managed and why these decisions were made

during project development along with details behind the Traffic Control Plans (TCP) and other

measures that will be put in place during construction to minimize disruptions to traffic without

compromising public and work zone safety. This Transportation Management Plan is a living

document, subjected to additions and modifications throughout the life of the project.

Goals of this Project-Level TMP include the following:

• Describe the project construction footprint.

• Aid in creating a project development and decision-making environment that looks at

options available to limit and mitigate anticipated construction impacts.

• Communicate what elements will be included in the project to mitigate for anticipated

disruptions to travelers and freight without compromising public or worker safety.

Project Background

The scope of the project includes removal and replacement of the existing traffic signal and

pedestrian flasher systems at the following locations:

• OR8 (Baseline Street) at OR 219 (S 1st Avenue) – traffic signal control intersection.

• OR8 (Oak Street) at OR219 (S 1st Avenue) – traffic signal control intersection.

• OR8 between SE 44th Avenue and SE 45th Avenue – pedestrian crossing with pedestrian

activated flashing beacon.

Project Area Boundaries

All project areas are within the City of Hillsboro boundaries and within Oregon Department of

Transportation (ODOT) Region 1 jurisdiction. Figures 1 and 2 show the project areas.

Proposed Improvements

The main improvements to be incorporated at each location are as follows:

• OR8 (Baseline Street) at OR219 (S 1st Avenue), the proposed improvement at this

location include:

o Installation of a new traffic signal system and illumination system. o Updated intersection signing.

o New curb ramps to meet current ADA standards.

Page 5: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

Figure 1: Vicinity Map

= Construction Area

N NOT TO SCALE• N

OT TO SCALE •

OR8 (SE Oak St.) OR8 (SE Oak St.)

OR8 (SE Baseline St.)OR8 (SE Baseline St.)

OR2

19 (S

1st

Ave

.)

= Tra�c Signal

Control Type:

= Intersections X1. OR8 (SE Baseline St.) / OR219 (S 1st. Ave.) 2. OR8 (SE Oak St.) / OR219 (S 1st. Ave.)

2

2

1

1

Page 6: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

Figure 2: Vicinity Map

= Construction Area= Pedestrian activated �ashing beacon

Control Type:

= Crossing X1. OR8 between SE 44th Avenue and SE 45th Avenue

1

N

NOT TO SCALE• NOT TO

SCALE •

OR8

(SE

Tual

atin

Val

ley

Hw

y)

SE 45th Ave.

SE 44th Ave.

1

Page 7: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 6

• OR8 (Oak Street) at OR219 (S 1st Avenue), the proposed improvement at this location

include:

o Installation of a new traffic signal system and illumination system. o Reconfiguration of the north approach to include an exclusive left turn and

through/right lane with updated signing and striping. o A striped island with candlesticks on the south approach. o Updated intersection guide signing. o New curb ramps to meet current ADA standards.

• OR8 between SE 44th Avenue and SE 45th Avenue:

o Removal of the existing pedestrian activated flashing beacon and installation of a

new pedestrian activated flashing beacon and illumination at the existing

pedestrian crossing.

o New curb ramps on the southside of OR8 to meet current ADA standards and

modifications to the existing bus stop. The existing raised median will remain.

Project Area Characteristics

This section includes a summary of existing transportation conditions within the project areas

relevant to this TMP, including traffic and roadway characteristics and location of other

construction projects.

Traffic Characteristics

Annual average daily traffic (AADT) volumes along OR8 and OR219 near the project sites were

researched to better understand the volume of vehicles that would need to be accommodated

during construction of each site. AADT’s are summarized in Table 1.

Table 1. Existing Traffic volumes

Segment Name Milepoint AADT1 Truck Percentage (%)

OR219 0.02 9,700 7.71

OR8 (Baseline Street) 13.27 14,100 2.96

OR8 (Oak Street) 13.23 17,000 2.96

OR8 between SE 44th Avenue and SE 45th Avenue

10.082 28,6003 2.60

1ODOT TransGIS http://gis.odot.state.or.us/transgis/ 2 The AADT was measured for the segment form M.P 9.86 to M.P. 11.28 3 AADT for two-way traffic

Page 8: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 7

Roadway Characteristics

The functional classifications of the project area roadways are summarized in Table 2.

Table 2. Project Area Roadway Functional Classification

Roadway

Functional Classification

(Federal functional class)1

ODOT

State Classification System (SCS)1

National Highway system

(NHS)1

National Network

(NN)2

OR219 Urban Minor Arterial District ---- ----

OR8 (Baseline Street) Urban Principal Arterial

Statewide NHS NN

OR8 (Oak Street) Urban Principal Arterial

Statewide NHS NN

OR8 between SE 44th Avenue and SE 45th

Avenue

Urban Principal Arterial

Statewide NHS NN

1ODOT TransGIS http://gis.odot.state.or.us/transgis/ 2 1999 Oregon Highway Plan, http://www.oregon.gov/ODOT/Planning/Documents/OHP.pdf

Existing roadway conditions within the limits of the project areas were evaluated and are

summarized in Table 3.

Table 3: Existing Roadway Conditions Within Study Area

Roadway Posted speed limit

Sidewalks Bike lanes

Lane Geometry On-Street Parking

Transit Routes

OR219 25 mph Yes No

Two lanes in each direction

No No

OR8 (Baseline Street) 30 mph Yes No

Three lanes in westbound direction.

No Trimet

Route # 57,48 & 47

OR8 (Oak Street) 30 mph Yes No

Three lanes in eastbound direction.

No No

OR8 between SE 44th Avenue and SE 45th Avenue 45 mph

Available on the north corner.

Buffered bike lanes

on the north and

south corners.

Two lanes on each direction. And a left turn

lane for eastbound traffic.

No Trimet

Route # 57

Page 9: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 8

Location of Other Construction Projects

To minimize construction impacts for motorists, other planned projects near the vicinity of these

projects have been identified. The following are known projects that will occur near or at the

same location with the proposed projects1:

K18794 - OR8: SW 10th – SW 110th

- Project Description: safety upgrades to install larger signal heads, reflective

backboards, pedestrian countdown signals and left turn phasing where feasible.

Proposed Construction Date: 2019

Factors Impacting Construction Staging

This section summarizes the factors that will impact construction staging that includes: project

schedule, proposed improvements and impacts to traffic flow, alternate routes, existing vehicle

restrictions, Work Zone Lane Closure Restrictions, environmental issues, seasonal restrictions,

and construction noise regulations.

Project Schedule

The project is tentatively scheduled to bid in February 2019. A detailed construction schedule

has been created as part of the project development process and will be available from the

agency. Refinements to the schedule will continue to evolve during the design process.

Additional schedule modifications are expected once a contractor has been selected.

Proposed Improvements and Potential Impacts to Traffic Flow

This project includes the proposed improvements listed in Section 2.2. Much of the construction

will be completed using single lane closures. However, short-term (20-minute) full closures may

be utilized to facilitate mast arm removal and installation at the OR8 (Baseline Street) / OR 219

(S 1st Street) and OR8 (Oak Street) / OR 219 (S 1st Street) intersections. They will also be

necessary at the OR8 pedestrian crossing between SE 44th Avenue and SE 45th Avenue to

facilitate the removal of the overhead pedestrian activated flashing beacons and span wire.

These closures will be during off peak periods at night. Alternatively, traffic control measures for

this work may be multi-lane closures with flagging during off peak hours.

Existing Vehicle Restrictions

Based on review of the current ODOT Motor Carrier Transportation (MCTD) Road and Bridge

Restrictions website2, no roadways have existing weight, height, or width restrictions for vehicles

within the project limit. The website will be periodically reviewed prior to bid letting. When

1 ODOT project Tracking http://gis.odot.state.or.us/odotprojecttracking/

2 ODOT Motor Carrier Transportation Division, “Road and Bridge Restrictions”, reviewed as of October 31, 2017.

https://www.oregontruckingonline.com/cf/MCAD/pubMetaEntry/restrictionsList/

Page 10: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 9

construction starts, the Contractor needs to coordinate with MCTD and obtain the most current

information on vehicle restrictions that may affect the project sites.

Work Zone Lane Closure Restrictions

Work zone lane restriction have been evaluated by ODOT’s traffic analysis staff. The following

lane restriction and special events have been provided by the agency and will be included in the

special provisions.

00220.03(a) Over-dimensional Vehicle Restrictions - Add the following to the end of this subsection: During times of anticipated over-dimensional vehicles presence, maintain a minimum usable roadway width on the Tualatin Valley Highway (OR8) and Hillsboro-Silverton Highway (OR219) as shown below, to allow for over-dimensional vehicles to pass through the work area. DAYTIME SINGLE LANE (ft.) TWO LANE (ft.) OR8 16 28 OR219 14 28 NIGHTTIME OR8 14 28 OR219 12 28 Anticipate daytime over-dimensional vehicles between the following sunrise and sunset periods:

• January: between 7:00 a.m. and 5:30 p.m.

• February: between 6:30 a.m. and 6:00 p.m.

• March: between 7:00 a.m. and 8:00 p.m.

• April: between 6:00 a.m. and 8:30 p.m.

• May: between 5:30 a.m. and 9:00 p.m.

• June: between 5:00 a.m. and 9:30 p.m.

• July: between 5:00 a.m. and 9:30 p.m.

• August: between 5:30 a.m. and 9:00 p.m.

• September: between 6:00 a.m. and 8:00 p.m.

• October: between 7:00 a.m. and 7:00 p.m.

• November: between 6:30 a.m. and 5:30 p.m.

• December: between 7:00 a.m. and 5:00 p.m.

00220.03(b) Closures - Add the following bullets to the end of the bullet list:

Bus Stops - A minimum of 14 calendar days before closing, relocating or modifying a TriMet

bus stop. Also notify the TriMet Field Operation Coordinator by e-mail at: [email protected].

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

Page 11: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 10

One or more Traffic Lanes may be closed on the Tualatin Valley Highway (OR8), Hillsboro-Silverton Highway (OR219) and intersecting side streets when allowed, shown, or directed during the following periods of time except as indicated in 00220.40(e)(2):

1) Tualatin Valley Highway (OR8) Westbound and Eastbound

a. OR8 (Oak Street & Baseline Road) at OR219 (S. 1st Avenue) For single lane closure:

• Daily, Monday morning through Friday afternoon between 9:00 a.m. and 3:00 p.m.

• Nightly, Monday night through Friday morning between 7:00 p.m. and 6:00 a.m.

• Friday night through Saturday morning between 7:00 p.m. and 10:00 a.m.

• Saturday night through Sunday morning between 6:00 p.m. and 11:00 a.m.

• Sunday night through Monday morning between 6:00 p.m. and 6:00 a.m. For two-lane closure:

• Nightly, Monday night through Friday morning between 8:00 p.m. and 5:30 a.m.

• Friday night through Saturday morning between 8:00 p.m. and 9:00 a.m.

• Saturday night through Sunday morning between 7:00 p.m. and 10:00 a.m.

• Sunday night through Monday morning between 7:00 p.m. and 5:30 a.m. b. OR8 at SE 44th & 45th Avenues

• Daily, Monday morning through Friday afternoon between 9:00 a.m. and 3:00 p.m.

• Nightly, Monday night through Friday morning between 8:00 p.m. and 5:30 a.m.

• Friday night through Saturday morning between 8:00 p.m. and 9:00 a.m.

• Saturday night through Sunday morning between 7:00 p.m. and 10:00 a.m.

• Sunday night through Monday morning between 7:00 p.m. and 5:30 a.m. 2) Hillsboro-Silverton Highway (OR219, S. 1st Avenue) and other side streets

• Daily, Monday morning through Friday afternoon between 9:00 a.m. and 3:00 p.m.

• Nightly, Monday night through Friday morning between 7:00 p.m. and 6:00 a.m.

• Friday night through Saturday morning between 7:00 p.m. and 9:00 a.m.

• Saturday night through Sunday morning between 7:00 p.m. and 10:00 a.m.

• Sunday night through Monday morning between 7:00 p.m. and 6:00 a.m. 3) For work requiring flagging at any intersection:

• Nightly, Monday night through Friday morning between 9:00 p.m. and 5:00 a.m.

• Friday night through Saturday morning between 9:00 p.m. and 7:00 a.m.

• Saturday night through Sunday morning between 9:00 p.m. and 8:00 a.m.

• Sunday night through Monday morning between 9:00 p.m. and 5:00 a.m. 00220.40(e)(2)(b) Special Events - Add the following to the end of this subsection: The following special events will occur during this Project:

Page 12: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 11

• Washington County Fair - July 25-28, 2019

• Oregon International Air Show - TBD 2019 Add the following subsection: 00220.40(f) Limited Duration Road Closure - The Contractor will be permitted to close all Traffic Lanes for periods not to exceed 20 minutes in duration during the signal pole mast arm installation or removal of the overhead span wire over the Traffic Lanes. This work will only be permitted at night between the hours of 10:00 p.m. and 5:00 a.m., Monday through Sunday, on the Tualatin-Valley Highway (OR8) at a single intersection or section at one time as shown below: (a) For removing or erecting signal pole mast arm

• Oak Street Eastbound (OR8) at OR219 (S 1st Avenue)

• Baseline Road Westbound (OR8) at OR219 (S 1st Avenue)

(b) For removing the overhead span wire

• OR8 between SE 44th and SE 45th Avenues Succeeding roadway closures will not be allowed until traffic clears from a preceding closure.

Seasonal Restrictions

There are no weather related seasonal restrictions for upgrading the traffic signal systems and

illumination systems at the project sites. Any cast in-place concrete related works such as the

construction of ADA approved curb ramps, sign support footings (If there will be any new

Breakaway Posts Anchored in Ground), and constructing the cast in place concrete foundation

when installing the signal pole support structure that carries the rectangular rapid flashing

beacon would be restricted during below freezing temperatures. Casting concrete during

freezing or below freezing temperature can cause the fresh concrete to freeze before it settles

and prevent it from attaining its desired strength.

Alternate Routes

Drivers who are familiar with the area can choose alternative routes to avoid each of the project

sites. Full road closures other than short-term (20-minute) closures during off-peak hours are

not anticipated at any of the project sites.

Construction Noise Regulations

The basic requirements of applicable noise regulations for City of Hillsboro are listed below:

Unless authorized by the manager, it is unlawful for any person to produce or allow to be

produced, with or from a sound-producing source, sound that:

A. Exceeds:

1. 50 decibels A-weighting (dBA) at any time between 9 p.m. and 6 a.m. the following day, or

2. 60 dBA at any time between 6 a.m. and 9 p.m.; or

Page 13: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 12

B. Is plainly audible at any time between 9 p.m. and 6 a.m. the following day:

1. Within a noise-sensitive building which is not the source of sound, or 2. On a public right-of-way from a distance of at least 100 feet from the source of the

sound.

ODOT’s 2011 Noise Manual has methods and procedures for abatements of highway traffic

noise and construction noise. The construction noise abatement section of the manual lists

methods and procedures that are typically implemented to limit the noise levels when

construction takes place near noise sensitive land uses. Section 2, Section 8, Appendix B and

Appendix H of the ODOT Noise Manual describes the standards and procedures for noise

abatement, construction equipment noise levels and mitigation for construction noise impacts.

Potential Mobility Issues

This section includes a discussion of traffic mobility issues during construction, input from the

public and stakeholders, agency coordination, holidays and special events, and consideration of

oversized vehicles.

Traffic Mobility during Construction

Traffic mobility for general traffic and annually permitted freight traffic will be maintained at all

times. Emergency vehicles will be permitted through the work zone at all times during the

construction.

For the construction phases at the intersections of OR8 (Baseline Street) / OR219 (S 1st

Avenue) and OR8 (Oak Street) / OR219 (S 1st Avenue) single lane closures will be used during

most off-peak hours.

At OR8 between SE 44th Avenue and SE 45th Avenue, single lane closures and short term full

roadway closures (20-minutes) are considered. Short-term full closures of the roadway will be

necessary for the removal of the overhead pedestrian activated flashing beacon and associated

span wire.

Input from the Public and Stakeholders

The scope of this project, as it affects the public, is guided primarily by technical factors and

ODOT policy. The primary goals of the communication effort for this project are to inform project

stakeholders, including affected property owners, tenants, and the adjacent community, of

construction activities and to gather feedback on factors that will affect them. The major

communication elements planned for this project will be determined by ODOT Region 1 staff.

Agency Coordination

Local agencies and other departments within ODOT need to be contacted and notified before

the start of project construction to coordinate any unknown issues that may not have been

identified during the design phase. Particularly close coordination with local agencies (City of

Hillsboro and Washington County) is necessary for the planning and use of the need for

Page 14: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 13

unforeseen detour routes and coordinating with other known projects in the area near the

project area (see Section 4).

Consideration of Over-Sized Vehicles

As mentioned on Section 3.2. OR8 within the project vicinity is a federally designated truck route

and is part of the National Highway System. It is essential that any temporary lane restrictions

can accommodate large trucks during construction to minimize impact to the timely and

dependable movement of goods.

When a project restricts the width, length, height, or weight of vehicles through a work zone or

detours trucks around a work zone, the MCTD must be notified by using the web based

electronic version of the "Highway Restriction Notice-Size and/or Weight" form (Form No. 734-

2357) at least 28 calendar days before the restriction or detour takes effect. As soon as the

restriction is lifted, notification must be sent to the same individuals on a revised copy of the

original Form #734-2357 so this information can be relayed to all affected parties. No such

restrictions are anticipated for either project site.

Traffic Management and Operation Strategies

To help meet the performance goals for congestion management and promote work zone

safety, several types of traffic management strategies were examined for implementation. A

range of common traffic management strategies is available for consideration on this project.

The strategies selected are described below. It should be recognized that before selecting a

strategy for application, an evaluation of the benefits provided versus the cost to implement

should be conducted. Project budgets may determine which strategies can be implemented.

ODOT’s Decision Tree Matrix (Form #734-5042) has been assembled to document traffic

management and operational strategies and the reasoning behind the decision for their use on

the project. The Decision Tree Matrix has been included in Appendix A.

Public Information and Outreach Strategies

Making the public aware of the potential delays incurred while traveling through the project area

or detour routes may encourage motorists to use alternate routes or plan trips to avoid peak

construction periods. This will help to manage congestion within the project area. Therefore,

public information and outreach is beneficial for maintaining public support for projects, as well

as for encouraging changes in travel behavior during construction.

Motorist Information/ITS Strategies

Providing motorists with real-time information helps notify drivers of upcoming work zones and

may alleviate congestion and delay. Existing Intelligent Transportation Systems (ITS) and other

strategies may be used to provide traveler information in the following ways:

• Variable message sign (VMS): Variable message signs are electronic signs that can

display changing messages. Permanent Variable Message Signs (VMS) may be

utilized at the discretion of Region 1 Traffic Management and Operations Center

Page 15: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 14

(TMOC) to notify motorists about incidents in the project area so that they can choose

to detour to an alternate route if needed.

• Portable changeable message signs (PCMS): PCMS is a portable electronic sign

that can display changeable messages. They are useful when informing drivers of

upcoming construction periods and warning drivers of construction activities as

needed.

• Ground mounted signs: Typically installed at the endpoints of work zones informing

motorists of road construction and the possibility of delay. Ground mounted signage

will be needed to alert motorists of the availability of Highway Advisory Radio

information if/when provided.

• 511 (Highway Advisory Telephone): Inclusion of this project on ODOT’s statewide

511 highway advisory telephone system will help provide travelers with up-to-date

information about construction activities and potential delays.

• TripCheck (ODOT’s ITS Website): Including this project on ODOT’s ITS website

(www.tripcheck.com) will help to inform users of construction activities. TripCheck

allows motorists to retrieve real time information and weather conditions via the

Internet. In addition to the Internet, motorists may also call 511 to receive this same

information. ODOT also shares this information with WAZE so users of the popular

application receive notifications when approaching construction zones.

Construction Strategies

Useful construction strategies as they pertain to this project are described below.

• Planned lane closures: Temporary lane closures, when required, will be limited to the

off-peak periods.

• Project phasing: Maintaining the existing travel lane configurations in each direction

during construction will create less delay for motorists. Phasing construction activities

to minimize the number of lane closures will minimize impacts to traffic. Although

phasing requires a longer construction period, its reduced impacts to traffic should be

beneficial.

• Truck Traffic/Permit Restrictions: No width or height restrictions have been identified

at any of the project locations.

• Coordination with adjacent construction: The coordination of this project with other

projects in the area, as discussed in Section 4, will help to avoid unnecessarily

compounding traveler delay.

• Full-time traffic control supervisor (TCS): Having a full-time TCS on-site allows one

person to be dedicated to traffic control and not be distracted by other construction

activities. Benefits include the ability to make quick decisions and to implement

contingency plans as needed.

Page 16: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 15

Alternate Route Strategies

Alternative routes for motorists should be identified whenever a full roadway closure is

anticipated during construction for more than 20-minutes. Based on the current staging strategy,

alternative routes (detours) should not be required.

Proposed construction Staging

Multiple staging options were explored for the proposed vehicle and pedestrian facility

improvements. The options considered included staged construction, temporary traffic

diversions and a full closure of roadway. The options considered have been included in ODOT’s

Decision Tree Matrix (Form #734-5042) to document the staging options and the reasoning

behind the decision for their use on the project. The Decision Tree Matrix has been included in

Appendix A.

The following outlines the preferred construction staging option for all project locations. Staging

has been developed to accommodate heavy vehicles at both locations. Complete plans for the

construction has been included in Appendix B.

OR8 (Baseline Street) at OR219(S 1st Avenue)

Concept

Allow reconstruction of the traffic signal system, illumination system and ADA pedestrian ramps

at up to one corner at time. Construction will be coordinated with the OR8 (Oak Street)/OR219

(S 1st Avenue) intersection construction. Up to two corners, one at each intersection on the

same side of OR 219, can simultaneously be under construction at any given time. Single lane

closures along OR8 and OR219 will be required to facilitate construction activities.

A six-stage construction strategy has been developed to facilitate both pedestrian and vehicular

traffic at the intersection. The southwest corner of the intersection will be reconstructed one half

at a time. This will allow the second half to remain open to pedestrian traffic and minimizes

disruptions to one direction of vehicular traffic at a time.

Construction for the northwest and southeast corners of the intersection will be completed using

pedestrian detours at adjacent intersections. Considerations for this type of temporary traffic

control includes:

• Northwest Corner: Shrubbery that prohibits temporary easement behind construction

zone and a single ramp design

• Southeast Corner: Existing business sign and extensive landscaping.

Since there is only a single ramp proposed on the northeast corner, it will also be constructed

under a single stage by providing a temporary alternative pedestrian accessible route behind

the existing curb ramp and by installing a temporary crosswalk along OR8 (Baseline St.).

This strategy allows for three legs of the intersection to remain open at all times. Lane closures

will follow ODOT’s TM800 Series Standard Drawings. The Temporary Pedestrian Accessible

Route Plans showing the staging is included in Appendix B.

Page 17: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 16

Temporary 20-minute full closures are anticipated for removal of the existing mast arm

associated with the traffic signal system.

Vehicle Detour

No vehicular detours are anticipated at this intersection.

Pedestrians Accommodations

Temporary accessible routes will be provided for pedestrian traffic at two of the four corners. At

these corners, temporary construction easements can be obtained to route pedestrian traffic

around the work zones, outside of the vehicular travel lanes.

On the northwest and southeast corner, due to site constraints a pedestrian detour route per

ODOT Standard Drawing TM844 will be implemented at adjacent intersections. Alternative

pedestrian routing can be provided by closing travel lanes on OR8 and OR219 to provide a

temporary accessible route within the vehicular travel lanes.

On the northeast corner, along with a temporary easement for routing pedestrians around the

work zone, the crosswalk on the east leg of the intersection will temporarily be relocated to the

east since OR8 (Baseline Street) is one-way westbound. This will keep the route open at all

times during reconstruction of the northeast corner.

Figure 3: Construction Staging at OR8(Baseline Street) / OR219 (S 1st Avenue)

Page 18: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 17

Bicycle Accommodations

There are no dedicated bike facilities that exist along OR8 (Baseline Street) or OR219. Bikes

will be required to share the vehicle lanes as they do under permanent conditions.

OR8 (Oak Street) at OR219 (S 1st Avenue)

Concept

Allow reconstruction of the traffic signal system, illumination system and ADA pedestrian ramps

at up to one corner at time and reconfigure the lane geometry of the north leg. Construction will

be coordinated with the OR8 (Baseline Street)/OR219 (S 1st Avenue) intersection construction.

Up to two corners, one at each intersection on the same side of OR219, can simultaneously be

under construction at any given time. Single lane closures along OR8 and OR219 will be

required to facilitate construction activities.

An eight-stage construction strategy has been developed to facilitate both pedestrian and

vehicular traffic at the intersection. Each corner will be reconstructed one half at a time. This

will allow the second half to remain open to pedestrian traffic and minimizes disruptions to one

direction of vehicular traffic at a time.

The exception to the half corner reconstruction staging, is the northwest corner of the

intersection. Due to restrictions from shrubbery and a private sign, this corner will be

constructed half at a time to limit impacts to traffic, but will require pedestrian detours setup at

adjacent intersections.

The strategy allows for three legs of the intersection to remain open at all times. Lane closures

will follow ODOT’s TM800 Series Standard Drawings. The Temporary Pedestrian Accessible

Route Plans showing the staging is included in Appendix B.

Temporary 20-minute full closures are anticipated for removal of the existing mast arm

associated with the traffic signal system.

Vehicle Detour

No vehicular detours are anticipated for construction at this intersection.

Pedestrians Accommodations

Temporary accessible routes will be provided for pedestrian traffic at three of the four corners

where the half corner staging is implemented. At these corners, temporary construction

easements will be obtained to route pedestrian traffic around the work zones, outside of the

vehicular travel lanes. On the northwest corner, due to site constraints a pedestrian detour

route per ODOT Standard Drawing TM844 will be implemented. Alternative pedestrian routing

can be provided by closing travel lanes on OR8 and OR219 to provide a temporary accessible

route within the vehicular travel lanes.

Bicycle Accommodations

There are no dedicated bike facilities that exist along OR8 (Oak Street) or OR219. Bikes will be

required to share the vehicle lanes as they do under permanent conditions.

Page 19: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 18

Figure 4: Construction Staging at OR8(Oak Street) / OR219 (S 1st Avenue)

OR8: SE 44th Avenue to SE 45th Avenue Pedestrian Crossing

Concept

Construction will be conducted under four stages. Single lane closures will be required to

facilitate construction. A full 20-minute closure is anticipated for removal of the existing

overhead flashers, signs and span wire.

• Stage 1: To allow for construction of the pedestrian ramp, rectangular rapid flashing

beacon system and improvements to the existing bus stop area on the southside of OR

8, the existing bus stop will be temporarily moved to the west under the first stage of

construction. A shoulder and/or single lane closure is anticipated.

• Stage 2: Under stage 2, the bus stop on the southside of OR8 will be moved back to its

existing location. Buses and pedestrians will use the new ADA ramp constructed under

Stage 1. A shoulder and/or single lane closure is anticipated.

Page 20: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

DRAFT - K18791: OR8 at OR219 & SE 44th Ave and SE 45th Ave (Hillsboro)

May 4, 2018

Traffic Management Plan

Page | 19

• Stage 3: Under Stage 3, improvements along the northside of the roadway will

constructed. Pedestrians will be routed along the existing sidewalk and pedestrian ramp.

Construction activities are planned to occur behind the sidewalk. A shoulder and/or

single lane closure is anticipated.

• Stage 4: Under Stage 4, improvements within the median will be constructed. This is

anticipated to consist of tactile warning surface replacement. Pedestrians will be routed

around the active surface replacement. A single lane closure is anticipated for one

direction of travel depending on the side of the median being worked on.

Vehicle Detour

No vehicular detours are anticipated at either intersection.

Pedestrians Accommodations

• Stage 1: Relocation of the bus stop will allow pedestrians to be routed from the west

along the shoulder to the existing crossing location to cross OR8.

• Stage 2: Pedestrians will be routed along the existing sidewalk and ADA ramp and

escorted past the work zone during construction hours. Construction activities are

planned to occur behind the sidewalk except for tactile warning surface replacement

and illumination pole footing installation.

• Stage 3: This is anticipated to consist of tactile warning surface replacement.

Pedestrians will be routed around the active surface replacement.

Bicycle Accommodations

• Stage 1: Eastbound bikes will be routed along the existing bike lane. Bike lane will be

used as a shared facility with pedestrians during this stage of construction.

• Stage 2: Westbound bikes will be using the existing permanent bike facility.

• Stage 3: Bikes will utilize existing permanent bike lanes in both the eastbound and

westbound directions.

Page 21: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION
Aman
Text Box
Appendix
Aman
Line
Page 22: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION
Aman
Text Box
Appendix A
Aman
Text Box
Decision Tree
Aman
Line
Page 23: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION
Page 24: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION
Page 25: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION
Page 26: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION
Aman
Text Box
Appendix B
Aman
Text Box
Traffic Control Plans
Aman
Line
Page 27: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

GG

GG

Review:

D. BeckwithChecker:Drafter:

Designer:

SHEET NO.

GTEng CAD

503.719.7997

Portland, OR 97204

Suite 320

227 SW Pine Street

A. Woldetinsae

EXPIRES:

OREGON

OE

E

R

ERIG

TS

EDG

EN

RPNI

53,044 LANR

EFE ISS

O

DEC. 31, 2019

DA

NA M. BECK

W

ITH

JA

NU

ARY 15, 2

0

02

PROJECTOR8 CORRIDOR SAFETY AND ACCESS TO TRANSIT

SW TUALATIN VALLEY HIGHWAYWASHINGTON COUNTY

D. BeckwithAD

VANC

E COP

Y

SUBJEC

T TO CHA

NGE

TZ_18791_tc01.dgn :: STAGEs 1-3 5/4/2018 10:56:33 AM Rick Scale: 1"=50'Rotation: 0°

FO

TN

E

MTRAPED N

OG

ER

O

NOI

TATROPS

NA

RT

320

321

322

323

320

321

322

323

EA01TRAFFIC CONTROL PLAN

SEQUENCE OF WORK:

Temporary sign on type (II) barricade

Pedestrian channelization device

28" Tubular markers on 10' max. spacing

LEGEND

Under construction

CLOSED

SIDEWALK

Temporary pedestrian surfaceing under traffic

NOTE:

SE 4

4T

H A

VE

TUALATIN VALLEY HWY (OR8)

STAGE 3

SE 4

4T

H A

VE

TUALATIN VALLEY HWY (OR8)

"L" Line

(Coordinate with Trimet)Temporary bus stop

"L" Line5' Min.

48"x48"

W21-5a

beacon. Pedestrians to use existing cut-through in median.

Construction of new tactile warning surfaces and flashing

Stage 3: Median Contruction:

TRAFFIC CONTROL

Perform additional stages necessary to complete the project.*

Temporary Sign Support (TSS)

Temporary pedestrian accessible route

STAGES 1 & 2

(AFTER AND DURING CONSTRUCTION HOURS)

TEMPORARY PEDESTRIAN ACCESSIBLE ROUTE

SECTION A - A

WORK ZONE PC

D

A

A

single postTSS)

(Mount on

30"x18"

R9-9

4' Min.

12' Min.

Travel Lane

Existing L

ane Lin

e

Existing E

dge Lin

e

1" Shy Distance

4' Min.

Zone

Ped./Bike

PCD

5' Min.

AHEAD

WORK

ROAD

48"x48"

W20-1

CLOSED

SHOULDER

RIGHT

2'2'

PC

D

BIKE

WALK

B

B

Temporary sign support

28" Tubular markers on 5' max. spacing

PC

D

12' Min.

Travel Lane

Existing E

dge Lin

e

1" Shy Distance

5' Min.

Zone

Ped./Bike

2'

SECTION B - B

(During and After Construction Hours)

Not To Scale

Shoulder

Sidewalk to remain open)(No TPAR required under this stage. Stage 2 Construction

R/

W

C

C

for pedestrians within bike lane.

stop relocation. Also Provide a temporary alternative route

of the construction site, coordinate with Trimet for bus

ramp and bus station. Provide a temporary bus stop west

Reconstruct curb ramps and sidewalk by closing the curb

Stage 1: Southside Contruction:

construction hours.

Contractor to escort pedestrians past work zone during

existing sidewalk and ADA ramps during construction.

tactile warning surface and pole foundation. Retain

All work to occur behind sidewalk except constructing new

Stage 2: Northside Contruction:

route through work zone

maintain accessible pedestrian

section 00230 as needed to

AC surfacing per Special Provisions

Provide aggregate base and 2" of

route through work zone

maintain accessible pedestrian

section 00230 as needed to

AC surfacing per Special Provisions

Provide aggregate base and 2" of

ConstructionStage 1

12' Min.

Travel Lane

Existing E

dge Lin

e

SECTION C - C

(During and After Construction Hours)

Not To Scale

route through work zone

maintain accessible pedestrian

section 00230 as needed to

AC surfacing per Special Provisions

Provide aggregate base and 2" of

6' Min.

Lane

Bike

R/

W

(Mod.)OBR-10-13

PCD

Under traffic operations, by email at [email protected] 14 days in advance.

Coordinate temporary bus stop location with TriMet field 4.

Section 00225.13(a).

to be delineated by blue tubular markers per Special Provisions

Business access affected by temporary traffic control measures are 3.

accommodate traffic during active construction periods.

See ODOT TM800 series drawings for temporary lane closures to 2.

Lane closures allowed during active construction periods only.1.

5' Min.

Stop Pad

Bus

Temp.

Shoulder

Paved

Edge of

Existing P

ave

ment

(After Construction Hours)

Not To Scale

*

*through constrained ped/bike zone.

pedestrians and bikes to be escorted

During construction hours

pedestrian surfaceNew temporary

ACCOMPANIED BY DWGS.:

TM843, TM844, TM850, & TM851.TM687, TM800, TM820, TM821, TM841, TM450, TM670, TM671, TM677, TM681,

Page 28: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

G G

G

Review:

D. BeckwithChecker:Drafter:

Designer:

SHEET NO.

GTEng CAD

503.719.7997

Portland, OR 97204

Suite 320

227 SW Pine Street

A. Woldetinsae

EXPIRES:

OREGON

OE

E

R

ERIG

TS

EDG

EN

RPNI

53,044 LANR

EFE ISS

O

DEC. 31, 2019

DA

NA M. BECK

W

ITH

JA

NU

ARY 15, 2

0

02

PROJECTOR8 CORRIDOR SAFETY AND ACCESS TO TRANSIT

SW TUALATIN VALLEY HIGHWAYWASHINGTON COUNTY

D. BeckwithAD

VANC

E COP

Y

SUBJEC

T TO CHA

NGE

TZ_18791_tc02.dgn :: STAGEs 1-3 5/4/2018 10:56:35 AM Rick Scale: 1"=50'Rotation: 0°

FO

TN

E

MTRAPED N

OG

ER

O

NOI

TATROPS

NA

RT

26

27

19

20

26

27

19

20

26

27

19

20

484 15

EA02TRAFFIC CONTROL PLAN

AD

AM

S A

VE

STAGE 8

(OR8) BASELINE ST

(OR8) OAK ST

LEGEND

STAGE 1

Existing sidewalk under pedestrian traffic

Existing sidewalk under pedestrian traffic

LEGEND

NOTE:

(OR8) OAK ST

(OR8) OAK ST6

5

3

1

4

6

5

2

6

5

2

Temporary sign on type (II) barricade

Pedestrian channelization device

28" Tubular markers on 10' max. spacing

LEGEND

Under construction

X

NOTE:

SEQUENCE OF WORK:

Verify surface conditionavailable for TPAR.Existing asphalt surface

Verify surface conditionavailable for TPAR.Existing asphalt surface

Under construction

Under construction

*

detour.

reconstruct curb ramps and sidewalks. Provide alternative

Stage 8: Temporarily close the curb ramp to perform signal installation,

Pedestrian channelization device

(Pedestrian Detour)

NW Corner Construction

Temporary pedestrian surfacing under traffic

construction easement

Temporary

easement

Temporary construction construction easement

Temporary construction at a time.one corner to be under ramps in a corner. Only time where there are dual Construct one ramp at a

STAGE 2 THRU 7

NOTE:

behind sidewalk. Temporary construction easements required.

Stage 1: Construct hard surface temporary accessible pedestrian route

Perform additional stages as necessary to complete the project.

Sign No. (X), see details on this sheet

Temporary sign support (TSS)

Stage 4

PCD

Stage 7

Stage 6

Stage 2 Stage 3

PCD

Stage 5

DETOUR

panelStyle:regulatory.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:0panelSizes:constructPanelMode:0constructPanels:36|24|18

DETOUR

panelStyle:regulatory.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:0panelSizes:constructPanelMode:0constructPanels:36|24|18

CROSSWALKCLOSED

SIDEWALK

1 2

CLOSED

3 4

(Mount on B(II)L)

30"x24"

M4-9b(R)

(Mount on B(II)R)

30"x24"

M4-9b(L)

65

AHEAD

SIDEWALK CLOSED

CROSS HERE

AHEAD

SIDEWALK CLOSED

CROSS HERE

post TSS)

(Mount on single

24"x12"

R9-9

(Mount on B(II)L)

24"x18"

R9-11 (R)

(Mount on B(II)R)

24"x18"

R9-11 (L)

(Mount on B(II)LR)

24"x24"

OR22-8 (LR)

CROSSWALK

CLOSED

(Mount on B(II)LR)24"X24"OR22-8

PCD

PCD

ramp at a time with six phases.

sidewalks through staged construction. Construct one

Perform signal installation, reconstruct curb ramps and Stage 2 thru 7:

TRAFFIC CONTROL

(AFTER AND DURING CONSTRUCTION HOURS)

TEMPORARY PEDESTRIAN ACCESSIBLE ROUTE

S 1

ST A

VE

(OR219)

S 1

ST A

VE

(OR219)

S 1

ST A

VE

(OR219)

Temporary Route Construction

00225.13(a).

tubular markers per Special Provisions Section

control measures are to be delineated by blue

Business access affected by temporary traffic 3.

construction periods.

lane closures to accommodate traffic during active

See ODOT TM800 series drawings for temporary 2.

One corner to be under construction at a time.1.

SIGN DETAILS - STAGE 8

markers per Special Provisions Section 00225.13(a).

measures are to be delineated by blue tubular

Business access affected by temporary traffic control 5.

periods only.

4. Lane closures allowed during active construction

construction periods.

closures to accommodate traffic during active

See ODOT TM800 series drawings for temporary lane 3.

times.

Temporary traffic control measures in place at all 2.

One corner under construction at a time.1.

per Special Provisions Section 00225.13(a).

measures are to be delineated by blue tubular markers

Business access affected by temporary traffic control 4.

only.

3. Lane closures allowed during active construction periods

construction periods.

closures to accommodate traffic during active

See ODOT TM800 series drawings for temporary lane 2.

closure. See Std. Dwg. TM844.

Provide pedestrian detour for the northwest curb ramp 1.

(Staged Single Ramp Closure Stage 2 Shown)

SW, SE & NE Corner Construction

hard surface 5' min

New temporary

Under traffic

Under traffic

Under traffic

Page 29: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

G

Review:

D. BeckwithChecker:Drafter:

Designer:

SHEET NO.

GTEng CAD

503.719.7997

Portland, OR 97204

Suite 320

227 SW Pine Street

A. Woldetinsae

EXPIRES:

OREGON

OE

E

R

ERIG

TS

EDG

EN

RPNI

53,044 LANR

EFE ISS

O

DEC. 31, 2019

DA

NA M. BECK

W

ITH

JA

NU

ARY 15, 2

0

02

PROJECTOR8 CORRIDOR SAFETY AND ACCESS TO TRANSIT

SW TUALATIN VALLEY HIGHWAYWASHINGTON COUNTY

D. BeckwithAD

VANC

E COP

Y

SUBJEC

T TO CHA

NGE

TZ_18791_tc03.dgn :: STAGEs 1-4 5/4/2018 10:56:38 AM Rick Scale: 1"=50'Rotation: 0°

FO

TN

E

MTRAPED N

OG

ER

O

NOI

TATROPS

NA

RT

484

485

14

15

484

485

14

15

483

484

14

15

480

19

EA03TRAFFIC CONTROL PLAN

LEGEND

(OR8) BASELINE ST

STAGE 1

SEQUENCE OF WORK:

B(II)LR

(OR8) BASELINE ST

TRAFFIC CONTROL

Existing sidewalk under pedestrian traffic

Existing sidewalk under pedestrian traffic

LEGEND

*

Temporary Route Construction

Under construction

Under construction

Temporary sign on type (II) barricade

CROSSWALK

CLOSED

NOTE:

NOTE:

"L" Line

"L2" Line"L2" Line

"L" Line

verify surface conditionExisting hard surface

ramps in a corner.time where there are dual Construct one ramp at a

Temporary pedestrian surfacing under traffic

on southwest corner of the intersection.

sidewalks. Requires 2 stages to construct one ramp at a time

Stage 2 & 3: Perform signal installation, reconstruct curb ramps and

behind sidewalk. Temporary construction easements required.

Stage 1: Construct hard surface temporary accessible pedestrian route

Perform additional stages as necessary to complete the project.

easementconstruction Temporary

(Mount on B(II)LR)24"X24"OR22-8

Stage 2

Stage 3

PCD

Pedestrian channelization device (PCD)

PCD

STAGES 2 & 3

(OR8) BASELINE ST

(OR8) OAK ST

STAGE 4

Temporary sign on type (II) barricade

LEGEND

Under construction

X Sign No. (X)

NOTE:

3

65

12

5

6

2

(Pedestrian Detour)

SE Corner Construction

6

5

4

"L" Line

"L2" Line

Temporary sign support (TSS)

Pedestrian channelization device (PCD)

PCD

PCD

DETOUR

panelStyle:regulatory.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:0panelSizes:constructPanelMode:0constructPanels:36|24|18

DETOUR

panelStyle:regulatory.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:0panelSizes:constructPanelMode:0constructPanels:36|24|18

CROSSWALKCLOSED

SIDEWALK

1 2

CLOSED

3 4

(Mount on B(II)L)

30"x24"

M4-9b(R)

(Mount on B(II)R)

30"x24"

M4-9b(L)

65

AHEAD

SIDEWALK CLOSED

CROSS HERE

AHEAD

SIDEWALK CLOSED

CROSS HERE

post TSS)

(Mount on single

24"x12"

R9-9

(Mount on B(II)L)

24"x18"

R9-11 (R)

(Mount on B(II)R)

24"x18"

R9-11 (L)

(Mount on B(II)LR)

24"x24"

OR22-8 (LR)

easementconstruction Temporary

reconstruct curb ramps and sidewalks. Provide pedestrian detour.

Stage 4, 5, & 6: Temporarily close the curb ramp to perform signal installation,

(AFTER AND DURING CONSTRUCTION HOURS)

TEMPORARY PEDESTRIAN ACCESSIBLE ROUTE

S 2

ND A

VE

S 1

ST A

VE

(OR219)

S 1

ST A

VE

(OR219)

S 1

ST A

VE

(OR219)

(Staged Single Ramp Closure Stage 2 Shown)

SW & SE Corner Construction

per Special Provisions Section 00225.13(a).measures are to be delineated by blue tubular markers Business access affected by temporary traffic control 5.

Lane closure during active construction periods only.4.

construction periods.closures to accommodate traffic during active See ODOT TM800 series drawings for temporary lane 3.

Temporary traffic control measures in place at all times.2.

One corner to be under construction at a time.1.

per Special Provisions Section 00225.13(a).

measures are to be delineated by blue tubular markers

Business access affected by temporary traffic control 3.

construction periods.

closures to accommodate traffic during active

See ODOT TM800 series drawings for temporary lane 2.

One corner to be under construction at a time.1.

SIGN DETAILS - STAGE 4

Under traffic

Under traffic

Under traffic

00225.13(a).

tubular markers per Special Provisions Section

control measures are to be delineated by blue

Business access affected by temporary traffic 4.

only.

Lane closure during active construction periods 3.

active construction periods.

lane closures to accommodate traffic during

See ODOT TM800 series drawings for temporary 2.

ramp closure. See Std. Dwg. TM844.

Provide pedestrian detour for the Southeast curb 1.

Page 30: B St - Oregon Document...2019/01/15  · B St K18791: OR8 at OR219 & SE 44th Ave. and SE 45th Ave. (Hillsboro) Tra˜c Management Plan For Prepared by May 2018 GLOBAL TRANSPORTATION

Review:

D. BeckwithChecker:Drafter:

Designer:

SHEET NO.

GTEng CAD

503.719.7997

Portland, OR 97204

Suite 320

227 SW Pine Street

A. Woldetinsae

EXPIRES:

OREGON

OE

E

R

ERIG

TS

EDG

EN

RPNI

53,044 LANR

EFE ISS

O

DEC. 31, 2019

DA

NA M. BECK

W

ITH

JA

NU

ARY 15, 2

0

02

PROJECTOR8 CORRIDOR SAFETY AND ACCESS TO TRANSIT

SW TUALATIN VALLEY HIGHWAYWASHINGTON COUNTY

D. BeckwithAD

VANC

E COP

Y

SUBJEC

T TO CHA

NGE

TZ_18791_tc03.dgn :: STAGEs 5-6 5/4/2018 10:56:42 AM Rick Scale: 1"=50'Rotation: 0°

FO

TN

E

MTRAPED N

OG

ER

O

NOI

TATROPS

NA

RT

484

485

14

15484

485

14

15

480

EA04TRAFFIC CONTROL PLAN

Temporary sign on type (II) barricade

LEGEND

Under construction

(OR8) BASELINE ST

AD

AM

S A

VE

STAGE 6

X

6

5

3

1

2 6

5

2

5

6

4

NOTE:(Pedestrian Detour)

NW Corner Construction

"L2" Line

"L" Line

TRAFFIC CONTROL

Temporary sign on type (II) barricade

STAGE 5

(OR8) BASELINE ST

LEGEND

Under construction

NOTE:

"L2" Line

"L" Line

Temporary sign support (TSS)

Pedestrian channelization device (PCD)

Sign No. (X), see details this sheet

Pedestrian channelization device (PCD)

Temporary sign support (TSS)

PCD

PCD

DETOUR

panelStyle:regulatory.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:0panelSizes:constructPanelMode:0constructPanels:36|24|18

DETOUR

panelStyle:regulatory.ssipanelName:namepanelQuantity:1panelStation:nonepanelMaterial:0legendMaterial:0panelMounting:0panelWidthLock:1panelHeightLock:1marginAlign:9panelRoundCorners:0panelSizes:constructPanelMode:0constructPanels:36|24|18

CROSSWALKCLOSED

SIDEWALK

1 2

CLOSED

3 4

(Mount on B(II)L)

30"x24"

M4-9b(R)

(Mount on B(II)R)

30"x24"

M4-9b(L)

65

AHEAD

SIDEWALK CLOSED

CROSS HERE

AHEAD

SIDEWALK CLOSED

CROSS HERE

post TSS)

(Mount on single

24"x12"

R9-9

(Mount on B(II)L)

24"x18"

R9-11 (R)

(Mount on B(II)R)

24"x18"

R9-11 (L)

SIGN DETAILS

(Mount on B(II)LR)

24"x24"

OR22-8 (LR)

NE 2

ND A

VE

SE 2

ND A

VE

S 1

ST A

VE

(OR219)

S 1

ST A

VE

(OR219)

SW WASHINGTON ST SW WASHINGTON ST

(Pedestrian Detour)

NE Corner Construction

PCD

PCD

12

6

5

2

36

4

6

5

(AFTER AND DURING CONSTRUCTION HOURS)

TEMPORARY PEDESTRIAN ACCESSIBLE ROUTE

5

per Special Provisions Section 00225.13(a).measures are to be delineated by blue tubular markers Business access affected by temporary traffic control 4.

Lane closure during active construction periods only.3.

construction periods.closures to accommodate traffic during active See ODOT TM800 series drawings for temporary lane 2.

closure. See Std. Dwg. TM844.Provide pedestrian detour for the northeast curb ramp 1.

per Special Provisions Section 00225.13(a).

measures are to be delineated by blue tubular markers

4.Business access affected by temporary traffic control

Lane closure during active construction periods only.3.

construction periods.

closures to accommodate traffic during active

See ODOT TM800 series drawings for temporary lane 2.

closure. See Std. Dwg. TM844.

Provide pedestrian detour for the northwest curb ramp 1.

Under traffic

Under traffic