B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi...
-
Upload
willis-tyler -
Category
Documents
-
view
213 -
download
0
Transcript of B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi...
![Page 1: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/1.jpg)
LNG and Power Sector Opportunities and Concerns
B. PradeepKSEB Officers’ Association
![Page 2: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/2.jpg)
2
Background LNG terminal being commissioned in Kochi
Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa
Laying of Gas pipeline network in Kochi in final stages
Gas pipeline to Mangalore and Bangalore under execution
Gas pipeline to Kayamkulam planned MoU between GAIL and KSIDC for City Gas
distribution etc GSA between Petronet and Exxon-Mobil for
supply of 1.44 mmtpa from 2015; FOB price 14.5% * JCC KSEB Officers' Association
![Page 3: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/3.jpg)
Natural gas in power sectorClean fuelLower Carbon footprintSeen as “bridge fuel” until transformation to
renewable energy is technically and commercially viable
Operational flexibility in responding to sudden changes in demand
Suitable as peaking station suitable for integration with infirm renewable power
Scope for decentralised plants at load centers
KSEB Officers' Association 3
![Page 4: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/4.jpg)
4
Opportunities in power sector Proposals under various stages include
1200 MW project at Puthuvypeen 1050 MW project at Brahmapuram 1050 MW Kayamkulam expansion 1200 MW project at Cheemeni Conversion of 350 MW Kayamkulam Stage I Conversion of 165 MW BSES plant at Kochi
Total natural gas requirement for these projects will be around 25 MMSCMD or 6.25 mmtpa – higher than terminal capacity
KSEB Officers' Association
![Page 5: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/5.jpg)
But, Some hard factsInadequate Long term tie-up for LNG supply to
terminal only for a fraction of the capacity (1.44 mmtpa against
capacity of 5 mmtpa) Price linked to crude oil price (Japanese Custom Cleared
crude price) Will commence only from 2015
LNG supply at spot prices Price is volatile; presently floating between 12 – 17 US$
per mmbtuThus there is no firmness in quantum or price for the
supply at Kochi terminalThe situation is entirely different from that at Dahej
terminal (price stability ensured through floor & caps in pricing formula)KSEB Officers' Association 5
![Page 6: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/6.jpg)
Some hard factsUnfavorable commercial conditions
“Take or Pay” even when LNG becomes unaffordable due to flaring up of crude oil prices
The technical advantage of “operational flexibility” lost due to inflexible commercial conditions
Planning Commissions observations By 2016-17 the import dependence of gas is expected to
increase to 28.4% from 19% in 2010-11 Unless the pricing issue is resolved, the scope of using LNG in
the price sensitive power sector is remote The high prices prevalent in LNG trade in Asia-Pacific region
can potentially kill the goose that lays the golden eggs Thus in the 12th plan capacity addition of 2539 MW only is
planned for the country as a whole using Natural Gas & LNG, that too as peaking stations alone (instead of base load stations)
KSEB Officers' Association 6
![Page 7: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/7.jpg)
7
Increase in Power Purchase cost Power procurement cost has abnormally
increased in Kerala in the backdrop of abnormal increase in fuel cost (Naphtha,
LSHS, Coal etc) de-licensing of generation sector through
Electricity Act, 2003 Imperfections in market revision of operation norms by CERC for
central sector stations and No major hydro projects being
commissioned
KSEB Officers' Association
![Page 8: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/8.jpg)
8
Increase in Power Purchase cost of KSEB
(Source: True up orders, ARR&ERC orders and ARR & ERC filings)
KSEB Officers' Association
2004-0
5
2005-0
6
2006-0
7
2007-0
8
2008-0
9
2009-1
0
2010-1
1
2011-1
2
2012-1
3
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
Power Purchase & fuel cost in Rs Cr
![Page 9: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/9.jpg)
9
Power purchase cost VS Revenue
Purchase cost is overtaking revenue from tariff
KSEB Officers' Association
2004-05
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
Power purchase cost vs Revenue
Power Purchase & fuel cost
Revenue from tariff and sale outsideR
s in
Cr
![Page 10: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/10.jpg)
10
LNG as replacement fuelOne of the reasons for the above situation is increase in
cost of Naphtha power Existing capacity of Naphtha stations
Kayamkulam – 350 MW, BSES – 165 MW; Total – 515 MW
Annual generation from these stations were restricted between Zero and 1200 MU against a potential of 3600 Mus
Conversion of fuel Per unit cost will come down - from present Rs 11 to
about Rs 7 per unit (considering crude price of 100 US$ per barrel); but is still higher than present average retail tariff – Rs 4.38 per unit
Thus, conversion to facilitate generation at current level could be beneficial, but any additional generation may be counter productive
KSEB Officers' Association
![Page 11: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/11.jpg)
11
LNG for new plants Energy demand in Kerala for 2013-14 is estimated as
22,117 MU, which is to be met by KSEB stations – 6,837 MU; Central Generating stations – 10,236
MU; Small IPPs in Kerala - 196 MU; Traders - 3,628 MU; Kayamkulam + BSES - 1,220 MU
Total power purchase cost is estimated as Rs 7,083 Crores The demand is expected to increase to 26,584 MU by
2016-17 and to 32,895 MU by 2020-21 Additional energy required – 10,778 MU Additional power purchase cost will be about Rs 9,200 crores if
the additional power is met from new LNG plants (FC Rs 1.5 + VC Rs 7)
The revenue of KSEB for 2013-14 is estimated as Rs 8,000 cores only
Power purchase cost will increase by 130% (at current prices) to meet increase of 48% in power procurement quantum
KSEB Officers' Association
![Page 12: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/12.jpg)
12
Impact of change in crude priceKochi LNG price is directly linked to Crude price
Between 2003 and 2012 crude price has increased at 16% annually.
Between 2003 -08 the increase was at 27% and between 2009-12 the increase is at 22%
LNG Projects considered are Puthuvypeen 1050 MW and Brahmapuram 350 MW alone
KSEB Officers' Association
Present cost At current prices
At 10% At 15% At 22%0
2
4
6
8
10
12
14
Change in pooled power purchase cost due to change in crude price
at 10%, 15% and 22%
Rs/
Unit
![Page 13: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/13.jpg)
13
Risk Mitigation Clearly Kerala cannot absorb such costly power in
huge quantum – reducing the quantum is important LNG plants as peaking stations
Peak demand is estimated to become 6093 MW by 2011-12 Additional capacity required to meet the peak demand is
about 3000 MW; at a plf of 85% LNG plants will deliver about 22,000 MUs
Whereas the additional energy requirement is about 11,000 MUs only
If capacity to the tune of 1000 – 1500 MW is created or contracted for base load operation the energy demand could be more or less met
Such base load stations may be on Coal and balance energy and capacity may be met from LNG plants
This could limit the exposure on LNG to the tune of 2000 – 3000 MUs
KSEB Officers' Association
![Page 14: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/14.jpg)
14
Risk MitigationAllocation of Domestic Natural Gas
Kerala not being endowed with any natural resources like Coal, Natural Gas etc and development of hydro projects is hampered due to environmental concerns has eligibility to get priority allocation of domestic natural gas, once gas pipeline infrastructure is in place
Due to price stability to certain extent, Kerala shall seek for domestic natural gas allocation for power projects on Swap basis
Gas price pooling Pooling the price of LNG with domestic natural gas could
bring down the cost as well as create some stability in price Kerala shall seek gas price pooling to ensure utilisation of
LNG facilities
KSEB Officers' Association
![Page 15: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/15.jpg)
15
Gas prices in different marketsDomestic natural gas
APM gas - 4.2 to 5.25 US$ /mmbtu Pre NELP fields – 3.5 to 5.73 US$ /mmbtu NELP fields - 4.2 US$ /mmbtu
LNG imported in India Qatar Gas (Dahej) - 9 US$/mmbtu Other term contracts - 6.97 to 9.06 US$ /mmbtu Spot LNG - 12 to 17 US$ /mmbtu Gorgon gas (Kochi) - 16 US$ /mmbtu at current crude price
International prices Henry Hub (US) - 3 to 4 US$ /mmbtu NBP (UK and Europe) - 6 to 7 US$ /mmbtu JCC based (Japan) - 14 to 15 US$ /mmbtu Canada - 3 to 4 US$/ mmbtu
KSEB Officers' Association
![Page 16: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/16.jpg)
16
Kochi Terminal landed in a disadvantageous position
The suppliers of Gas to be sensitised on the price factor
Globally the link between Crude price and Gas price is being broken (Dr C. Rengarajan Committee report 2012)
Our proposed power projects shall not be tied down with commercially unviable contracts for gas supply
But the highly urbanised Kerala context provides a great market for LNG as a substitute fuel through city gas distribution (domestic & commercial sectors) network, automotive fuel etc – piped gas
KSEB Officers' Association
![Page 17: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/17.jpg)
17
Looking forward Gas based projects has a major role to play in our power
supply landscape LNG terminal is a game changer – connecting Kerala to
the Natural gas market; ship route as well as pipe route In view of the present commercially unfavorable contracts
for supply of Gas, Kerala shall cautiously tap the market The strategies may include
Seeking domestic natural gas allocation on swap basis Seeking pooled prices for gas Limiting exposure to LNG by going for peaking stations
initially Work along with GAIL/Petronet etc to tap North American
market and other potential markets Gradually move away from the crude price linkage
KSEB Officers' Association
![Page 18: B. Pradeep KSEB Officers’ Association. 2 Background LNG terminal being commissioned in Kochi Initial capacity 2.5 mmtpa; ultimate capacity 5 mmtpa Laying.](https://reader035.fdocuments.us/reader035/viewer/2022071807/56649da85503460f94a957ae/html5/thumbnails/18.jpg)
18
THANKS
KSEB Officers' Association