August 2 and 3, 2010 ReSTAR: The Origins of KOSMOS David Sprayberry.
-
Upload
jocelyn-pierce -
Category
Documents
-
view
212 -
download
0
Transcript of August 2 and 3, 2010 ReSTAR: The Origins of KOSMOS David Sprayberry.
August 2 and 3, 2010
ReSTAR: The Origins of KOSMOS
David Sprayberry
2
References
• 2006 NSF AST Senior Review Report, http://www.nsf.gov/mps/ast/seniorreview/sr-report.pdf
• 2007 NOAO ReSTAR Committee Report, http://www.noao.edu/system/restar/files/ReSTAR_final_14jan08.pdf
3
Long, Long Ago…
• Nov 2006: NSF Senior Review report out• Relevant recommendations:
– NOAO should enlarge efforts to renew infrastructure and instruments at 4-m’s
– NOAO should partner with other institutions to do this
– NSF should give NOAO additional money to support this
4
Enter ReSTAR
• NOAO commissioned an effort to:– Survey forefront science for 4-m class scopes– Identify most critical community needs– Recommend a program for meeting them
• Carried out by committee from community– Included much community outreach
• Consultation with NSF throughout
5
ReSTAR Report
• Lots of science: Solar System to Cosmology
• Identified need for additional open-access time on 4-m-class
• Identified need for modern instruments:– Wide-field imagers (already done or underway)– Moderate R, high throughput spectrographs– High R, efficient spectrographs
6
ReSTAR Policy Goals
• Meet these needs as quickly and cheaply as possible (NSF resources limited)– Don’t reinvent wheels– Partner with other institutions to leverage
recent experience
7
Implementation Proposal• NOAO submitted unsolicited proposal to
NSF– $12.3M over three years– Enhance infrastructure related to science– Enlarge 4-m-class nights available (Hale, DCT)– Build 4 spectrographs– Study involvement in time-domain network– Etc
• Proposal listed pre-selected partners…
8
Post-Proposal
• Proposal submitted Nov 2008• Written reviews to NSF• Reverse site visit in May 2009• NOAO notified of initial decision late July
2009– $3M for one year only; future years not
assured– Revised proposal requested to fit
9
First Year Program
• Stick to things that could be completed from the first year’s funding
• NOAO solicited community input• Recommendations:
– Hale time– One adaptation of OSMOS, for Kitt Peak Mayall– Improvements to readout speed, efficiency of
existing instruments
10
And off we go…
• First year funding received late Aug 2009
• Began design adaptation study with OSU in September
• Negotiated and executed design phase contract in parallel with start of study
• Elected to have separate contracts for design and build phases
11
Postscript: COSMOS
• NOAO recently learned that more funding will be available for Year 2 of ReSTAR
• COSMOS is first priority for use of additional funds (and there should be enough…)
• OSU and NOAO planning to build both KOSMOS and COSMOS, programmed to minimize total cost and schedule (more later)