AUDITOR GENERAL'S REPORT - gac.gov.lr PROJECT FIELD VERIFICATION REPORT... · BOQ Bill of...
Transcript of AUDITOR GENERAL'S REPORT - gac.gov.lr PROJECT FIELD VERIFICATION REPORT... · BOQ Bill of...
On the Special Procurement Audit
of the Ministry of Public Works For
the Construction of Roads and
Bridges throughout Liberia
For Fiscal Periods 1 July 2010 to
30 June 2013
Volume II Field Verification Report
June 2015
Yusador S. Gaye, CPA, CGMA
Auditor General, R.L.
AUDITOR GENERAL'S REPORT
The Special Procurement audit of the Ministry of Public Works
for the construction of roads and bridges throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
1 Promoting Accountability of Public Resources
ACRONYMS USED
Acronym Meaning
AG Auditor General
AOM Audit Observation Memorandum
BOQ Bill of Quantities
CGMA Chartered Global Management Accountant
CHICO China Henan International Cooperation Group
CICO China Chongqing International Cooperation
COSO Committee of Sponsoring Organizations of the Treadway Commission
CPA Certified Public Accountants
CSA Civil Service Agency
DMA Deputy Minister for Administration
GAC General Auditing Commission
GOL Government of Liberia
GSA General Services Agency
IAA Internal Audit Agency
IFMIS Integrated Financial Management Information System
IIU Infrastructure Implementation Unit
IMC Internal Monitoring Committee
IPSAS International Public Sector Accounting Standards
ISSAI International Standards of Supreme Audit Institutions
ITC Information Technology and Communication
LRRRC Liberia Refugee Resettlement Repatriation Commission
MFDP Ministry Of Finance and Development Planning
MLM&E Ministry of Lands, Mines and Energy
MOU Memorandum Of Understanding
MPW Ministry of Public Works
PAPs Project Affected Persons
PFMU Project Financial Management Unit
PPCA Public Procurement & Concession Act
RAP Resettlement Action Plan
SIDA Swedish International Development Agency
SSF Shawki Sam Fawaz Entrepreneur, Inc.
WB World Bank
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
2 Promoting Accountability of Public Resources
Table of Contents
1 FIELD VERIFICATION REPORT .................................................................................... 4
1.1 Introduction ................................................................................................................ 4
1.2 Bopolu to Belle Yallah Road Project ............................................................................... 4
1.3 Incomplete Bailey bridge ............................................................................................... 5
1.4 Brewerville to Bopolu City Road ..................................................................................... 6
1.5 Klay to DC Clark Road Project ....................................................................................... 7
1.6 Incomplete Bailey Bridge .............................................................................................. 8
1.7 Lehkpeh Town to Beh to Votor Town Road .................................................................... 8
1.8 Gbarnga to Botota Road................................................................................................ 9
1.9 Gbarnga to Zorzor Road Project .................................................................................. 11
1.10 Gio Town to Little Kola Road ....................................................................................... 12
1.11 Weala to Isaac Farm Road .......................................................................................... 13
1.12 Bloumu to Nyanwuelle Road Project ............................................................................ 15
1.13 Marshall Road ............................................................................................................ 16
1.14 Todee Road ............................................................................................................... 17
1.15 Parker Paint, Pipeline, Neezoe, Somalia Drive Road Project ........................................... 18
1.16 Duport Road, Zizi Community, Parker Paint, Soul Clinic road project .............................. 19
1.17 SKD Boulevard Road ................................................................................................... 20
1.18 Police Academy Road .................................................................................................. 21
1.19 Asphalt patching of potholes on Somalia Drive ............................................................. 22
1.20 Rehabilitation of Clara Town Road ............................................................................... 23
1.21 Jamaica Road to Toyota Garage .................................................................................. 23
1.22 Logan Town Bye Pass Road ........................................................................................ 24
1.23 Brewerville Iron Gate to Clayashland to Arthington ....................................................... 25
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
3 Promoting Accountability of Public Resources
1.24 Amadu Town to Royceville Road .................................................................................. 26
1.25 Diggsville to Caldwell Road .......................................................................................... 27
1.26 Caldwell to Louisiana Road .......................................................................................... 28
1.27 Bahn to Loguatuo Road .............................................................................................. 29
1.28 Bahn- Lorplay Bridge ................................................................................................. 31
1.29 Kolahun to Vahun to Bomarue Road ............................................................................ 34
1.30 Zorzor to Voinjama Road............................................................................................. 36
1.31 Voinjama to Foya and Foya to Mendikorma Roads ........................................................ 37
1.32 Tuzon Town Box Culverts ............................................................................................ 38
1.33 Karweaken to Barclayville Road ................................................................................... 40
1.34 Sweaken to Glofaken Road, River Gee County .............................................................. 42
1.35 Zwedru to Greenville Road ......................................................................................... 44
1.36 Wiah Town to Planiabo Road ....................................................................................... 46
1.37 Nyafuah Town to Buchanan Road ................................................................................ 47
2 Exhibit ........................................................................................................................ 50
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
4 Promoting Accountability of Public Resources
1 PROJECT FIELD VERIFICATION REPORT
1.1 Introduction 1.1.1 On December 9, 2014, the General Auditing Commission (GAC) commenced a field
visit of roads and bridges constructed throughout Liberia from fiscal year 2010 to
2013. The objective of the project verification was to establish the existence and
completion of the projects and ensure that value for money was achieved during the
implementation of various projects. Also, the verification provided an opportunity to
ascertain the existing condition of the roads and bridges across the country. This
exercise marks the third field visits of the Government of Liberia Funded Road and
Bridges Projects and the first for the World Bank Funded Roads and Bridges Projects
by the GAC. The GAC hired the services of a local engineering consulting firm that
partnered with the GAC to conduct the field verification exercise.
1.1.2 During the field visit, a total of fifty two (52) projects were inspected, out of which
Government of Liberia funded projects were thirty four (34) while one (1) was
funded by the World Bank. The objective of the field visit was to authenticate
whether the construction of the roads and bridges for the audit periods were done in
line with the approved technical specifications by MPW.
Gbarpolu County
1.2 Bopolu to Belle Yallah Road Project
Observation
1.2.1 During our inspection tour of the construction project of the Bopolu to Belle Yallah
road, we observed several irregularities during the implementation of the project.
According to the BOQ of the project, the contractor was to remove all existing metal
culverts and replace them with reinforced concrete culverts. However, during the
verification, we observed at certain points along the road that contractor did not
remove existing damaged metal culverts during the construction
1.2.2 In addition, the project BOQ required that culverts should contain both head and
wing walls. Contrary to this provision, we observed at several locations of this 75km
road culverts installed by the contractor did not contain both head and wing walls on
both streams of the water.
1.2.3 Again, at some points of the road, we observed broken culverts, exposed culverts
not properly backfilled, and poorly connected culverts at certain points. In few
instances, we noticed that at some areas culverts installation was incomplete,
meaning that the culverts were not extended across the road. Some locations had
sinking culverts that could no longer accommodate free passage of water.
1.2.4 According to the BOQ of the project, the contractor was required to construct
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
5 Promoting Accountability of Public Resources
concrete pipe culverts with 20/70 grade, including excavation, formwork, and
reinforcement. We observed at some lower points of the road that culverts were not
installed.
1.2.5 We also sighted about 100 to 200 meters long depression points that need backfilling
and proper compaction. We observed that in locations of the depression, the earth
work was not properly done.
1.3 Incomplete Bailey bridge 1.3.1 In addition, it was observed that a Bailey bridge located at 55+km of the road had
not been completed. The metal plates to cover the bridge were being used on the
detour bridge. The 80ft long and 12ft wide Bailey bridge constructed over the Guma
River near Gungbeta is still incomplete. In the same token, a single box culvert
constructed at 8+ km does not have a guard rail to provide protection for
pedestrians and moving vehicles.
1.3.2 Based on the observation of the level of work performed by PEALAT on the Bopolu-
Belle Yalah Road for which an amount of US$13,253,245.00 has been paid, it was
noted that the company performed far below in relations to most of the
specifications in the contract.
Risk
1.3.3 The existence of the irregularities could be as a result of poor supervision of the
assigned consultant. The irregularities could deny the achievement of value for
money.
Recommendation
1.3.4 The Management of the Ministry of Public Works should ensure that a team of
engineers access all the work done on the Bopolu-Belle yalah Road for which PEALAT
was paid an amount of US$13,253,245.00.
1.3.5 Further, no further payment should be made to PEALAT until the end of the
inspection and appropriate recommendations to correct all the lapses on the
implementation of the project.
1.3.6 The consulting Engineer LAMDA Consult and MPW supervision who supervised the
Bopolu-Belleyalah Road construction should also be held responsible for the poor
quality of work and the high contract cost.
Management’s Response
1.3.7 The project is 80% complete. The remaining works is been considered as a check list
and will be considered within the remaining duration of the contract.
1.3.8 There is still 20% plus retention on this project.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
6 Promoting Accountability of Public Resources
1.3.9 This is a laterite road which should be assessed immediately upon completion.
These type of roads last for not more than two seasons.
Auditor General’s Position
1.3.10 We recommended in volume I of this report on the Belle Yallah Road, a joint
assessment by MPW Engineers and an independent engineering firm excluding
LAMDA Consult be done to ascertain whether the portion of work outstanding
represents 20% of the contract. Therefore, we maintain our recommendation.
1.4 Brewerville to Bopolu City Road
Observation
1.4.1 The inspection of the Brewerville to Bopolu City road was done on December 9,
2014. An interview with Gbarpolu County Resident Engineer, Mr. Aaron Jeboe,
revealed that the project was awarded to PGL Construction Company on a pre-
finance basis. He said up to the time of the inspection tour no payments were made
to the contractor. The earth work on the road was done 45 KM from Brewerville
Junction. After the 45 KM earth work, the Resident Engineer said the contractor
could no longer continue with the project since it could not receive any payment
from the government.
1.4.2 A review of documents in our possession revealed that the project was awarded to
the contractor on June 11, 2013 for a total contract value of US$5,526,275.12. It
was provided in the contract that upon signing of the contract, the amount of
US$1,934,196.29 constituting 35% of contract value would be paid to contractor as
startup and mobilization cost.
1.4.3 During the inspection, we established that all damaged existing metal culverts that
were to be removed and replaced if the contract had gone well were still being used
on the road. We observed that at 10KM from Brewerville double 4ft metal culverts
have corroded and being seriously undermined thus endangering vehicle movement
along the road.
1.4.4 We also observed at 41KM that a wooden bridge that was being maintained by the
contractor while the construction was ongoing is gradually wearing out. Another
wooden bridge at 72.3KM was almost down when we visited the site. The condition
of the bridge is becoming worse that if nothing is done to recondition it the soonest
possible time, the inhabitants of Bopolu will be disconnected.
1.4.5 The bill of quantity for the rehabilitation of the Brewerville to Bopolu road requires
the contractor to remove and replace all damaged metal culverts along the road.
Considering that in mind, the contractor pre-fabricated reinforced concrete culverts
but could not installed them to their rightful locations. An inquiry from the Resident
Engineer, Mr. Aaron Joboe as to why the culverts were not installed, he noted that it
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
7 Promoting Accountability of Public Resources
was due to the failure of the government to make payment to the contractor. A stock
pad of different dimensions of culverts intended to be installed at different locations
of the road were seen at certain point of the road.
Risk
1.4.6 The failure of the MPW to adhere to the payment terms as provided in the contract
could lead to abandonment of project.
Recommendation
1.4.7 MPW should make payment to the contractor for work already done and persuade
the company to continue with the project.
1.4.8 The Consultant Engineer, the County Resident Engineer along with construction
engineers from MPW should provide supervision during the construction of the roads
and bridges.
Management’s Response
1.4.9 The contract is ongoing. The contractor received mobilization fees in February 2015.
All defects on the road will be corrected under the contract before final completion
certificate is issued by the Ministry.
Auditor General’s Position
1.4.10 We acknowledge management’s response. We will validate management’s assertion
during the next audit of MPW.
Bomi County
1.5 Klay to DC Clark Road Project
Observation
1.5.1 On March 25, 2013, the Ministry of Public Works represented by its Acting Minister
Victor B. Smith entered into a contractual agreement with East International Group
Inc. represented by its Chairman Cao Yun Feng for the rehabilitation and
maintenance of the road from Klay to DC Clark in Bomi County for a total contract
value of US$1,270,124.24.
1.5.2 During the field inspection of Klay to DC Clark roads, it was observed that the head
and wing walls of some of the culverts installed by the contractor were not properly
backfilled. As a result the erosion is gradually wearing away the head and wing walls
of those culverts.
1.5.3 It was also established during the verification that some of the culverts installed
were broken at some points, exposed and poorly connected at certain points. We
also sighted some points along the road with depression length ranging from 50
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
8 Promoting Accountability of Public Resources
meters to 100 meters. Also, majority of the culverts do not have head walls, wing
walls and apron.
1.6 Incomplete Bailey Bridge
1.6.1 In addition to the above finding, it was also noticed at 14.8KM of the road a Baily
Bridge constructed over Po-River in Julayjuah Town that was still incomplete. The
120.9ft long and 12ft wide bridge does not have a center pier. According to the
Resident Engineer of Bomi County, Mr. Solomon Garpue, the only work outstanding
on the bridge is the center pier. He informed us that due to lack of funding this
aspect of the project had come to a standstill.
Risk
1.6.2 The existence of the deficiencies identified on the project could lead to deterioration
of the condition of the road thereby denying value for money.
1.6.3 The lack of center pier on this long bridge could cause collapse as heavy tonnage
trucks ply the route without restriction, thus resulting to waste of state resources.
Recommendation
1.6.4 The management of the Ministry of Public Works should pursue the contractor, East
International to revisit the road and make all necessary corrections at locations
where appropriate including the construction of the crucial center pier for the bridge,
failing the contractor should be debarred from all Government contracts.
Management’s Response
1.6.5 The contractor will carry out all Corrective measures during the
retention/maintenance period. According to the contract BOQ, there is no center pier
to be constructed under the 120.9 ft long bailey bridge constructed over the Po-river
in Julijuah Town.
Auditor General’s position
1.6.6 We acknowledge management’s assertion that the contractor will be made to carry
out all corrective measures during the retention period. However, the contract
document available to the GAC contains a section in the Bill of Quantities for the
construction of the center pier for the Bailey Bridge. We therefore urge the MPW
Management to ensure that the contractor be made to construct the center pier for
the Bailey bridge as per the BOQ.
1.7 Lehkpeh Town to Beh to Votor Town Road
Observations
1.7.1 During the inspection of the Lehkpeh Town to Beh Town to Votor Town Road
project, we observed several points along the road with long depression ranging
from 100 to 250 meters that need backfilling and proper compacting. In some
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
9 Promoting Accountability of Public Resources
instances, we noticed at some locations that the culverts installed did not contain
head and wing walls. We also identified existing damaged metal culvert that needed
to be removed and replaced by contractor.
1.7.2 At 5+ km from Beh Town to Votor, it was observed that a concrete bridge of 22 feet
long and 12.10 feet wide was constructed but the guard rail which serve as
protection for pedestrians was not properly installed. As a result, one side of the rail
is hanging.
Risk
1.7.3 The failure to ensure that the road is regularly maintained could lead to deterioration
and inaccessibility, thus denying value for money.
Recommendation
1.7.4 The Ministry of Public Works should ensure that routine maintenance plan is put in
place to maintain all laterite roads to avoid the condition going worst before
intervention.
Management’s Response
1.7.5 Maintenance Strategy is underway for the Fiscal Year 2015/16.
Auditor General’s Position
1.4.10 We acknowledge management’s response. We will validate management’s assertion
during the next audit of MPW.
Bong County
1.8 Gbarnga to Botota Road
Observation
1.8.1 On December 21, 2012, the management of the Atlantic Resources Limited
expressed the desire to rehabilitate the Gbarnga to Botota road, but proposed a cost-
sharing arrangement between the government and the company.
1.8.2 The Superintendent of Bong County, Selena Polson Mappy, on January 31, 2013
wrote a communication to the then Public Works Minister Hon. Samuel Kofi Woods
to engage the Atlantic Resources Company through an acceptable cost-sharing
arrangement with the Government of Liberia to rehabilitate the road since Atlantic
Resources had earlier expressed the desire to rehabilitate the road.
1.8.3 The Ministry of Public Works on March 6, 2013 communicated with the management
of Atlantic Resources Limited informing the company that the ministry has decided to
award it the contract for the rehabilitation of the Gbarnga to Botota road on a cost-
sharing basis. In the communication Atlantic Resources was informed that it would
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
10 Promoting Accountability of Public Resources
underwrite 60% of the contract value amounting to US$1,469,780.51 while the
Government of Liberia would fund the remaining 40% amounting to US$979,853.67.
1.8.4 However, while awaiting the contract details to be finalized, the management of
Atlantic Resources was given the authorization to proceed by Deputy Minister of
Public Works for Administration Stephen M. Yekeson, Jr on March 6, 2013 to proceed
with the rehabilitation of the road. Up to the time of this report, the contract was not
signed by the requisite parties. Confirmation from the company revealed that there
was no contract between the government and the contractor and no payment had
been made to the contractor.
1.8.5 During the inspection of this 51.5KM road, we observed three major discrepancies
along the road that worth noting. We noticed long distances of depression points
that require backfilling and proper compacting.
1.8.6 Additionally, during the inspection, we observed at several locations of the road log
bridges and damaged metal culverts that need to be removed and replaced.
Risk
1.8.7 The failure to conclude the procurement process before the commencement of
projects could deny the full implementation of the BOQ thus leading to substandard
construction.
1.8.8 The failure of MPW to meet its obligation under the cost sharing agreement could
lead to delay in the construction of the project thereby stalling vital development
projects.
1.8.9 The granting of Letter to Proceed to contractor without a signed contract could
obligate GoL, thus resulting in the waste of resources.
Recommendation
1.8.10 MPW should ensure that all those log bridges and damaged metal culverts are
removed and replaced by concrete culverts and concrete bridges by the contractor.
1.8.11 The Ministry of Public Works should notify the contractor to discontinue the project
until the procurement process is regularized before the contract can resume.
1.8.12 The Deputy Minister of Public Works for Administration, Stephen M. Yekeson, Jr
should provide material justification for issuing Letter to proceed to the contractor
without a written contract, failure he should be held accountable for the violation
Section 65 subsection 1 of the PPC Act of 2005 as amended in 2010.
Management’s Response
1.8.13 Management did not respond to this observation.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
11 Promoting Accountability of Public Resources
Auditor General’s Position
1.8.14 In the absence of a response by MPW Management, we maintain our
recommendation.
1.9 Gbarnga to Zorzor Road Project
Observation
1.9.1 The project for the rehabilitation and maintenance of the Gbarnga to Zorzor road
was awarded to Westwood Construction on March 25, 2013 for twelve months. The
contract for the 104KM road was awarded for US&4,388,060.00. The Bill of Quantity
of the project requires contractor to install 0.60 to 1.20cm reinforced concrete pipes
(RCP) at several locations of the road.
1.9.2 On December 17, 2014, the team of auditors and engineers inspected the road and
noted that the concrete culverts were installed by Finda Construction Company
without head and wing walls. It was also observed at several locations that the road
still contain damaged metal culverts that needed to be removed and replaced. We
also observed at several locations of the road that culverts were needed to be
installed but we could not find any installation.
1.9.3 During the inspection, it was also sighted at several locations box culverts still in
good condition but do not have guard rail. Even though, we were informed that the
box culverts were constructed by the initial contractor that constructed the road in
the 1960s.
1.9.4 We also noticed during the inspection newly installed culverts and earth works that
were done by the UNMIL Bangladeshi contingent assigned along the road. It was not
evident that Westwood Construction Company to whom the contract was awarded
did major work on the road. At 28.1KM of the road, we sighted a 16 meters long and
6.3 meters wide concrete bridge constructed by UNML after the collapse of the first
bridge. Currently, the abutment of the bridge is slightly disconnecting from the top
pavement something which needs serious attention.
Risk
1.9.5 The signing of contract for US$4,388,060.00 for rehabilitation work without the
installation of a single culvert line could lead to the rapid deterioration of the road.
1.9.6 The existence of already damaged metal culverts and slight disconnection of the
abutment could result to the collapse of the bridge thereby denying value for money.
1.9.7 The failure of Westwood Construction to perform the contract based on the terms
and conditions could lead to substandard construction and deny value for money.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
12 Promoting Accountability of Public Resources
Recommendation
1.9.8 The management of the Ministry of Public Works should provide substantive
justification for authorizing payments to Westwood Construction without evidence
that the project was completed based on the terms and conditions of the contract.
1.9.9 The management of the Ministry of Public Works should intervene to prevent the
bridge from imminent collapse.
Management’s Response
1.9.10 Culvert work by UNMIL and Finda Construction were not part of Westwood scope of
work, in fact most of these works were completed before contract with West Wood
was signed. The contractor is aware that all defective works indemnified during the
DLP will be corrected prior final payment of retention.
1.9.11 UNMIL has intervened on the reinforcement of the bridge
Auditor General’s Position
1.9.12 Our review of the BOQ for the rehabilitation of the road from Gbarnga to Zorzor by
West Wood Construction Company showed that seven (7) pieces of reinforced
concrete pipes of different dimensions (3 pieces of 0.60cm, 3 pieces of 0.90cm and 1
piece of 1.20cm) at a total cost of US$43,940.00. There was no evidence that West
Wood installed those culverts. Therefore, we maintain our recommendation.
Grand Bassa County
1.10 Gio Town to Little Kola Road
Observation
1.10.1 On December 19, 2014, we toured this feeder road from Gio Town to Little Kola in
Grand Bassa County undertaken by General Engineer & Technical Services in
2010/11. According to the BOQ of the project, the contractor was required to
excavate and remove unsuitable materials and install reinforced concrete pipes at
those locations.
1.10.2 During the inspection of the 10.8KM road, we sighted two things that worth
mentioning in this inspection report. We observed at some locations of the road that
damaged existing metal culverts are still being used. The surface of the road in
almost all locations was observed to be severely damaged. The road on which the
amount of US$253,000.00 was spent need serious maintenance or else the next
rainy season the road would be completely inaccessible.
1.10.3 We also observed at some of the locations that some culverts installed along the
route were exposed, undermined by erosion and some, the wing and head walls
were not properly backfilled. For instance, at 4.3km, the wing of the 5 feet concrete
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
13 Promoting Accountability of Public Resources
culvert has been seriously undermined downstream. Generally, vegetation has
seriously taken over the entire road sides both left and right.
Risk
1.10.4 The failure to implement projects based on the terms and conditions of agreement
could lead to substandard constructions and waste of public resources.
Recommendation
1.10.5 The Ministry of Public Works should institute a routine maintenance plan for all
laterite roads throughout the country to keep the roads in good condition at all
times.
1.10.6 The management of the Ministry of Public Works should ensure that the contractor
to properly backfill the exposed and undermined culverts in order to avoid serious
damage of the road.
Management’s Response
1.10.7 The contractor has received the total amount of US$290,337.80 as initial payment
for both projects according to the contract terms and conditions. A meeting is
pending with the contractor to recommence work on the roads.
Auditor General’s Position
1.10.8 The assertion that the initial payment of US$290,337.80 had been made to
contractor contradicts the total cost of the contract of US$253,000.00 as per the
BOQ. The contract for the reconstruction and rehabilitation of the Goi Town road
was entered into in February 2009. It is therefore a serious breach to pay the
contractor without evidence of work done on the road. Therefore, MPW Management
should ensure that the contractor commence the project or be made to account for
the amount.
1.11 Weala to Isaac Farm Road
Observation
1.11.1 On June 18, 2012, the Ministry of Public Works issued MDMC management a Letter
to Proceed with the rehabilitation of two access roads, namely, Weala to Isaac Farm
and Bloumu to Nyarnwuelle roads until the contract formalities are concluded. The
total cost of the two access road projects amounted to US$414,774.00.
Unfortunately, in response to auditor confirmation, the contractor said it has not
received any payment from the Ministry of Public Works since the commencement of
works.
1.11.2 The inspection on this 4.8KM feeder road was done on December 22, 2014. During
the verification, we observed that the entire length of the road lacks dish lines on
both sides of the road. We also observed long depression points of 100 to 200
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
14 Promoting Accountability of Public Resources
meters along the road. According to the Resident Engineer of the county, Mr.
Sylvester Zoker the finishing touches of the road have not been done due to the
failure of national government to make payment to contractor.
Risk
1.11.3 The existence of long depression points along the road and dish lines could make the
road flooded thus creating serious problem to the road during the rainy season.
1.11.4 The delay of government to make payment to contractor could lead to abandonment
of projects thus denying the public easy access to the road.
Recommendation
1.11.5 The Ministry of Public should ensure that the contract regarding the project is
concluded and that the contractor is paid as per the contract to enable the contractor
complete the road projects.
1.11.6 Ministry of Public Works should desist from issuing letters to proceed and continue
with the process of contract award. Additionally, the Ministry of Public Works should
ensure that there is funding available for projects before awarding contracts.
1.11.7 Deputy Minister for Administration, Stephen Yekerson who issued the letter to
proceed should be held accountable for breach of section 65 (1) of the PPC Act,
2010.
Management’s First Response
1.11.8 The contract is concluded and a total of $292,509.60 have been paid to date. There
was funding under the Legislative Initiative segment of the budget to cover this
project. The Letter to Proceed was issued because of the need to have gotten the
contractor mobilize prior to the coming rains. The timeliness and appropriateness of
maintenance intervention is critical in this industry especially on laterite roads.
Delays in actions may lead to a complete wipe out of the entire laterite surface
causing the Government even more money. The Letter to proceed accounted for the
fact that the contractual process had not ended a process which at times could take
several months thereby undermining the overall project.
Management’s Second Response
1.11.9 The contractor has received the total amount of US$290,337.80 as initial payment
for both projects according to the contract s terms and conditions. A meeting is
pending with the contractor to recommence work on the road.
1.11.10 The project was retendered and the contractor has completed the project on time. It
is now under retention for routine maintenance.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
15 Promoting Accountability of Public Resources
Auditor General’s Position
1.11.11 In contract management, a contract should be concluded before the commencement
of work. The action of MPW Management to issue a letter to proceed before
finalizing contract and BOQ could commit GoL to unrealistic cost; value for money
could be undermined. Therefore, we maintain our recommendation.
1.12 Bloumu to Nyanwuelle Road Project
Observation
1.12.1 Section 66 (2) of the PPCA states that procurement contract shall come into force for
a Procurement requiring the execution of a contract which shall be binding on the
bidder and the Procuring Entity when the contract is signed by the bidder and by the
Procuring Entity subject to the requirements of Section 31 and to the remedies in
Section 127 of this Act.
1.12.2 Contrary to this requirement, on June 18, 2012, the MDMC management was given a
letter to proceed with the rehabilitation of two access roads, namely, Bloumu to
Nyanwuelle and Weala to Isaac Farm road without signing a contract.
1.12.3 The total cost of the two access road projects amounted to US$414,774.00.
Unfortunately, in response to auditor confirmation letter, the contractor said it has
not received any payment from the Ministry of Public Works since the
commencement of work. From our verification it was revealed that the two roads
were abandoned because there was no binding document between the government
and the two contracting parties.
1.12.4 During our inspection of this 11.1KM road in Margibi County, we also identified 26
culvert points that did not contain culverts at all. At some locations, e.g. 2.1km and
6.9km, the streams crossed the main road. As a result, vehicles cross those points
driving through the water that could easily be controlled by culverts. We also sighted
100 to 200 meters of depressed distances that did not contain proper earth work.
When we inquired from the Resident Engineer why the condition of the road was still
deplorable, he informed us that the project was abandoned by the contractor due to
the failure by the government to make payment.
Risk
1.12.5 The failure by the Ministry of Public Works to go into written contract with the
contractor for the Rehabilitation of the road could lead to contracts being awarded to
contractors that lack the capacity to perform, thereby leading to substandard work.
1.12.6 Not entering into official contract could result to violation of the Public Procurement
& Concession Act of 2010, thus denying competition and the achievement of value
for money.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
16 Promoting Accountability of Public Resources
1.12.7 The failure to observe the procurement laws in the Issuance of letter to proceed
could lead to corruption in the awarding of contracts.
Recommendation
1.12.8 That in awarding any future contract, the Ministry of Public Works should ensure that
all provisions of the PPC Act regarding awarding of contract are considered and that
the ministry ensures the completion of the contract documentation with MDMC.
1.12.9 The Ministry of Public Works in collaboration with the Ministry of Finance and
Development Planning should ensure that the contractor is paid for work done and
further ensure that contractor return to project site to continue work. The MPW
should also ensure that the county Resident Engineer is empowered to provide
adequate supervision for the projects.
Management’s Response
1.12.10 The contractor has received the total amount of US$290,337.80 as initial payment
for both projects according to the contract s terms and conditions. A meeting is
pending with the contractor to recommence work on the road.
Auditor General’s Position
1.12.11 MPW Management failed to mention the date of the initial payment to the contractor.
In December 2014, when we inspected the project site, it was observed that the
project was abandoned. When we inquired as to why the project was abandoned, we
were informed that the abandonment of the project was due to the failure of the
Ministry of Public Works to make payment to the contractor. The Management of
MPW should ensure that the contractor return on the road do the work for which an
intial payment had been made.
1.13 Marshall Road
Observation
1.13.1 The project for the asphalt pavement of the Marshall road was awarded to SSF for
the cost of US$19,750,000.00. The contract for the construction of the 19.8 km road
was for 18 months beginning July 29, 2012 and ending December 29, 2013. The
initial payment of US$ 7,900,000.00 has since been made.
1.13.2 On December 23, 2014, the verification team toured the road to inspect the level of
work done by the contractor thus far. During the inspection, we observed that one
lane of the asphalt pavement ended at 2.4KM while the other lane went to 3.1KM.
We identified several depression points along the road that need backfilling and
proper compacting. We also sighted some culverts that are completely closed up
with the red earth used during backfilling.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
17 Promoting Accountability of Public Resources
Risk
1.13.3 The failure of the contractor to complete the project in accordance with the contract
terms and condition could lead to breach of the contractual agreement, thereby
denying value for money.
1.13.4 The blocking of some culvert lines along the road could lead to flooding of the road,
thus seriously contributing to the fast deterioration of the road condition.
Recommendation
1.13.5 The Ministry of Public Works should pursue the contractor to return to work and
complete the project as the time for completion has since expired. Contractor should
ensure that all the blocked culvert lines are clear to give free passage to water
during the rainy season.
Management’s Response
1.13.6 The work is still under contract. The work quality is been control by the Consultant.
All defects will be corrected by the closes of the contract.
Auditor General’s Position
1.13.7 During our inspection in December 2014, the project appeared to be abandoned.
The contract for the construction of the road ended since December 2013, exactly
one year to our visit. Therefore, we maintain our recommendation.
Montserrado County
1.14 Todee Road
Observation
1.14.1 On December 26, 2014, the project for the routine maintenance of the Todee Road
was inspected. During the inspection of this 32.1KM road, we observed several plank
bridges along the road. We also observed that those bridges do not have guard rails
which could serve as protection for both pedestrians and vehicles. The abutments of
all the plank bridges along the road were constructed of concrete. We also observed
several points of depression along the road need to be backfilled and proper
compaction.
Risk
1.14.2 The existence of plank bridges along the road could increase the routine cost of
maintenance as the plank could get decayed and required changing.
Recommendation
1.14.3 The Ministry of Public Works should prioritize the construction to concrete bridges
instead of the wooden bridges along the road to avoid the increment of maintenance
cost and wasteful spending. The Ministry of Public Works should ensure that on a
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
18 Promoting Accountability of Public Resources
yearly basis the road is maintained to avoid travelers experiencing difficulties during
the rainy season.
Management’s Response
1.14.4 The Plank Bridge with no guard rail was constructed accordance the contract scope
of work. CSA visit was conducted there raining season after the contract was signed.
Some of the compacted gravel surface might have worn out before the December
visit by GAC
Auditor General’s Position
1.14.5 The inclusion of Plank Bridge in the scope of work by the Management of MPW could
lead to a waste of resources and could undermine the achievement of value for
money. The routine maintenance of such laterite road could ensure durability of the
road. Therefore, we maintain our recommendation.
1.15 Parker Paint, Pipeline, Neezoe, Somalia Drive Road Project
Observation
1.15.1 On November 30, 2010, the Ministry of Public Works signed a construction contract
with SSF Entrepreneur to pave with asphalt the 3.9KM Parker Paint to Pipeline to
Neezoe Road at a contract value of US$3,106,131.42. The Bill of Quantity of the
project required that a standard 4 inch concrete sidewalk be constructed along the
road.
1.15.2 The verification of the asphalt pavement of the 3.9KM Parker Paint to Pipeline to
Neezoe Road on the Somalia Drive road was done on December 26, 2014. During
our inspection, we observed that the contractor did the entire road without sidewalk
on either side of the road. We also observed at some points that the contractor did
not construct drainage on both sides of the road. We also sighted potholes at some
points along the road.
Risk
1.15.3 Construction work not done in line with technical specification could deny the
achievement of value for money and waste of resources.
Recommendation
1.15.4 That the MPW Management should ensure that contractors perform contracts in line
with specification through proper supervision of projects during their implementation.
Management’s Response
1.15.5 The road work was done in accordance to the contract scope of works provided by
the Ministry of Public Works.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
19 Promoting Accountability of Public Resources
Auditor General’s Position
1.15.6 Management’s assertion that the road was constructed in accordance to the scope of
work is not backed by the BOQ of the project reviewed by the GAC. The BOQ
required that a standard 4 inch concrete sidewalk be constructed along the road.
Therefore, we maintain our recommendation.
1.16 Duport Road, Zizi Community, Parker Paint, Soul Clinic road project
Observation
1.16.1 On May 12, 2012, the Ministry of Public Works on behalf of the Government of
Liberia signed a contractual agreement with SSF for the Asphalt pavement of the
Duport Road to Zizi Community to Parker Paint Junction Road at contract value of
US$5,000,000.00.
1.16.2 The inspection of this 3.6KM road was conducted on December 26, 2014. During the
inspection, we observed that some of the slabs covering the drainage, also used as a
sidewalk are broken on both sides of the road. Some of the slabs have major cracks
that if no action is taken immediately will lead to total damage. We also noticed that
from 1KM to 3.6KM, the contractor did not construct drainage on both sides of the
road.
Risk
1.16.3 The failure to construct drainage and sidewalk slab along the road could lead
substandard work, which denies value for money.
Recommendation
1.16.4 The Management of MPW should notify the contractor to revisit and recondition
those broken slabs and sidewalks.
1.16.5 The Management of MPW should pursue the contractors to revisit the road and
Construct the drainage in the remaining distance of the road.
Management’s Response
1.16.6 The road work was done in accordance to the contract scope of works provided by
the Ministry of Public Works.
1.16.7 The road mark was done in addition to the scope of work. Any additional works will
required a change order and extra cost.
Auditor General’s Position
1.16.8 Management’s response did not address the deficiencies noted by the GAC.
Therefore, we maintain our recommendation.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
20 Promoting Accountability of Public Resources
1.17 SKD Boulevard Road
Observation
1.17.1 On November 23, 2012, the Ministry of Public Works and Chain Henan International
Cooperation Group Co. Ltd entered into a construction contract for the asphalt
pavement of the Samuel K. Doe Boulevard road for the amount of US$4,562,242.50
for the period of twenty-four (24) months. Barely three months after the signing of
the initial contract, on February 21, 2013 an addendum to the contract was signed
for the amount of US$4,729,757.50 thus increasing the total project cost to
US$9,292,000.00.
1.17.2 The inspection of the 4.8KM road was conducted on December 27, 2014. During the
verification exercise, we observed depression point of the road. At 2.5KM of the
road, the depression of the asphalt pavement is becoming grave to the extent that
hole is now created between the asphalt and the side curve connecting the sidewalk.
1.17.3 We observed two 100 meters long distances where the sidewalk of the road did not
cover. An inquiry from the Resident Engineer as to why the sidewalk was not
extended to these distances, he said that the government did not make payment to
the inhabitants as resettlement compensation in these distances so the structures
could not be broken down for sidewalk. He however said when the payment is made
the sidewalk would continue.
Risk
1.17.4 The existence of depression on the road could be a result of substandard materials
and could result into waste of government resources.
Recommendation
1.17.5 It is strongly recommended that the contractor revisits the road to make all
necessary corrections including reconditioning of all the depressed locations or sites
along the road.
Management’s Response
1.17.6 The work is still under contract. The work quality is been control by the Consultant.
All defects will be corrected prior to issuing final Completion Certificate without cost
to the client.
Auditor General’s Position
1.17.7 We acknowledge management’s response. Management’s assertion will be validated
during the next audit of the MPW.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
21 Promoting Accountability of Public Resources
1.18 Police Academy Road
Observation
1.18.1 During the examination of records, we observed that on February 21, 2013, the
Ministry of Public Works represented by its Acting Minister, Victor B. Smith entered
into a contractual agreement with Chain Henan International Cooperation Group Ltd
represented by its Vice President, Zhang Wei for the rehabilitation upgrading to
asphalt pavement of the 2.4KM road from Police Academy connecting Samuel K. Doe
Boulevard for the total contract cost of US$4,761,397.00.
1.18.2 Confirmation response from the contractor revealed that government had made
payment amounting to US$3,094,908.05 against the total contract value. On
December 27, 2014, the verification of the road was conducted. During the
verification exercise, we observed that the culvert that should contain top slab on
both sides connecting the sidewalk was left incomplete at several locations.
1.18.3 For instance, at 1.8KM, the three feet culvert line installed is completely blocked
upstream by eroding sand. At 2.3KM, we also observed that a mini bridge should
have been constructed but up to present there is no bridge at the point.
1.18.4 Inquiry from the Resident Engineer, Mr. Clarence S. Quaye as to why the condition
of the road is still as seen, he informed us that the government had not made
payment for structures along the road, and as such, those structures could not be
broken down to give way for the construction.
Risk
1.18.5 The failure of the MPW to resettle the inhabitants along the road could delay project
and even lead to waste of resources as 65% payment of the contract cost has been
made.
1.18.6 The blocking of culvert lines with eroding sand could lead to extra work that could
cost extra amount.
Recommendation
1.18.7 The Management of MPW should ensure that payment is made to the inhabitants for
their structures to allow the contractor continue with the project.
1.18.8 The Management of MPW should ensure that proper supervision is provided to
ensure that work is done in accordance with approved technical specifications.
Management’s Response
1.18.9 The work is still under contract. The work quality is been control by the Consulant.
All defects will be corrected prior to issuing final Completion Certificate without cost
to the client.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
22 Promoting Accountability of Public Resources
Auditor General’s Position
1.18.10 During our field visit in December 2014, the project appeared to be abandoned.
Payment for RAP should be made to enable contractor continue with the project for
which 65% payment has been made.
1.19 Asphalt patching of potholes on Somalia Drive
Observation
1.19.1 The Ministry of Public Works represented by its Acting Minister, Victor B. Smith on
June 13, 2013, entered into a contractual agreement with Eden Construction
Company represented by its Executive Officer, Humphrey Russell for the emergency
asphalt patching of Somalia Drive from Freeport of Monrovia Junction to Paynesville
Red light and along the main Boulevard to ELWA Junction at the cost of
US$539,150.00. The contract for the asphalt patching of potholes along the Somalia
Drive to Paynesville Red light up to ELWA Junction was awarded for the period of
twelve (12) calendar months.
1.19.2 During the inspection of the project on December 30, 2014, we observed at several
locations that potholes patching for which the contract was awarded to Eden
Construction Company have taken over the road as though there has been no work
on the road.
Risk
1.19.3 The existence of potholes on this major road could delay traffic in these areas. The
existence of these critical spots could also be a waste of state resources as the
contract for the intervention was awarded in June of 2013 for twelve (12) calendar
months. The condition of the road could suggest that the job done was substandard.
Recommendation
1.19.4 The Ministry of Public Works should ensure that the contractor is held accountable
for the level of substandard job done on the road since the retention period has not
yet elapsed.
Management’s Response
1.19.5 The contractor failed to meet its obligation under the contract. No payment has been
make to the contractor to date. Process to terminate the contract is in progress. The
contract has been awarded to another contractor.
Auditor General’s Position
1.19.6 We acknowledge management’s response. We will validate management’s assertion
during the next audit of the MPW.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
23 Promoting Accountability of Public Resources
1.20 Rehabilitation of Clara Town Road
Observation
1.20.1 On November 23, 2012, the Ministry of Public Works represented by its Acting
Minister, Victor B. Smith entered into a contract with China Henan International
Cooperation Group Ltd. represented by its President, Ma Peng for the emergency
repairs and rehabilitation of the Clara Town Road at the cost of US$2,232,500.00 for
the period of twenty-four (24) calendar months.
1.20.2 The verification of the Clara Town Road was conducted on December 30, 2014.
During the inspection, we sighted at several points that the slabs covering the
sidewalk are broken. Generally, the condition of the road is still deplorable, even
though the road is still under construction.
Risk
1.20.3 The broken spots could be an indication that substandard construction thereby
leading to the waste of resources.
Recommendation
1.20.4 The Management of MPW should ensure that the contractor revisit all the open spots
due to broken slabs be reconditioned to protect the community dwellers and other
pedestrians from mistakenly sustaining injury.
Management’s Response
1.20.5 The work is still under contract. The work quality is been control by the Consultant.
All defects will be corrected prior to issuing final completion certificate without cost
to the client.
Auditor General’s Position
1.20.6 We acknowledge management’s response. We will validate management’s assertion
during the next audit of the MPW.
1.21 Jamaica Road to Toyota Garage
Observation
1.21.1 The Ministry of Public Works represented by its Acting Minister, Victor B. Smith on
November 23, 2012, entered into a contract with West Africa Construction Company
represented by its General Manager, Mentee N. Padmore for the emergency repairs
and rehabilitation of Jamaica Road for the contract value of US$1,801,860.11 for the
period of twenty-four (24) calendar months.
1.21.2 During the inspection of the Jamaica to Toyota Garage road project, we observed at
two locations that the asphalt pavement has serious potholes that delay the
movement of traffic.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
24 Promoting Accountability of Public Resources
Risk
1.21.3 The existence of potholes on the road is an indication that substandard construction
was done which could lead to waste of government resources.
Recommendation
1.21.4 The Ministry of Public Works should provide proper supervision for all future
contracts to ensure that the constructions meet specification.
Management’s Response
1.21.5 The contract is under retention. Contractor is under contract to rectified all defects
prior to issuing final payment and final completion certificate.
Auditor General’s Position
1.21.6 We acknowledge management’s response. We will validate management’s assertion
during the next audit of the MPW.
1.22 Logan Town Bye Pass Road
Observation
1.22.1 The Ministry of Public Works represented by its Deputy Minister for Technical
Services, J. Jenkins Mends-Cole entered into a contractual agreement with Koman
Enterprises (SEK Liberia) Inc. represented by its Director General for the
rehabilitation and upgrade to asphalt pavement of the Logan Town to Mombo Town
road for the contract value of US$1,671,903.80 for the period of ninety working days
beginning November 30, 2010 and ending January 31, 2011.
1.22.2 During the inspection of the road, we noticed that the asphalt pavement had lot of
potholes at some points of the road. It was also observed that the sidewalk of the
road is not yet complete as pedestrians use the main street to commute.
Risk
1.22.3 The existence of potholes along the road and the lack of sidewalk could be an
indication of the level of substandard job done by the contractor thus resulting into
waste of public resources.
Recommendation
1.22.4 The Ministry of Public Works should ensure that the contractor revisit the road to
complete the project including the construction of the remaining sidewalk and
patching of all existing potholes on this newly constructed road.
Management’s Response
1.22.5 The contract is under period. Final completion certificate and final payment will only
be issued after all defect has been corrected by the contractor.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
25 Promoting Accountability of Public Resources
Auditor General’s Position
1.22.6 We acknowledge management’s response. We will validate management’s assertion
during the next audit of the MPW.
1.23 Brewerville Iron Gate to Clayashland to Arthington
Observation
1.23.1 The audit team on January 3, 2015 inspected the road project for the rehabilitation
of the Brewerville Iron Gate to Clay Ashland road. The 26.5KM road was rehabilitated
by two separate contractors, namely, General Engineering and Technical Services
Inc., and China Henan International Cooperation Group Ltd. The General Engineering
and Technical Services rehabilitated 5.3KM of the road while the remaining 21.2KM
was undertaken by Chain Henan International Cooperation Group Ltd.
1.23.2 On April 1, 2011 the Ministry of Public Works awarded a contract to General
Engineering and Technical Services for the rehabilitation of the entire length of the
road from Brewerville Iron Gate to Clay Ashland to Millsburg to Arthington for a total
contract value of US$243,461.65. Further review of documents revealed that General
Engineering & Technical Services had received 70% payment of the contract cost
amounting to US$170,422.00 in accordance with the contract terms of payment.
1.23.3 We were not provided the contract and other relevant documents regarding CHICO
involvement in the implementation of this project. However, according to the
Resident Engineer, Mr. Clarence S. Quaye, the 21.2KM of the road rehabilitated by
CHICO was financed by the Liberia Electricity Corporation. Review of the IFMIS
payment record revealed that CHICO received two payments on budget code 412.
On August 14, 2012, the amount of US$409,281.32 was paid on check number
32185 while the amount of US$491,136.80 was paid on check number 32186 on the
same date.
1.23.4 During the inspection, we observed at some locations that depression of 100 to 200
meters long has taken over the road that needs backfilling and compacting. We also
sighted point where there still exist damaged metal culverts that could have been
removed and replaced. We also sighted at some points that erosion has seriously
wore up the soil around the head and wing walls of culverts installed by CHICO. It
was also observed at some points where the wing and head walls of the culverts had
serious cracks.
Risk
1.23.5 The existence of long depression points and gully areas on the road could further
worsen the condition of the road thereby denying value for money.
1.23.6 The undermining of the culvert head and wing walls could disconnect the road
rendering accessibility of the road difficult.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
26 Promoting Accountability of Public Resources
Recommendation
1.23.7 The Management of MPW should ensure that the contractor recondition the road
including proper backfilling and compacting of depressed points, removal and
replacement of damaged metal culverts along the road.
Management’s Response
1.23.8 The contractor was given 14.2km to rehabilitate and not 26.50km. Later on LEC
contracted CHICO to rehabilitate the road from km 14.2 to km 26.5km. However,
MPW contractor have received the total amount of US$170,423.14 as initial payment
for the project according to the contract terms and conditions. A meeting is pending
with the contractor to recommence work on the road. However the contractor
requested for an addendum for additional work.
Auditor General’s Position
1.23.9 We acknowledge management’s response. We will validate management’s assertion
during the next audit of the MPW.
1.24 Amadu Town to Royceville Road
Observation
1.24.1 In March 2010, the Ministry of Public Works represented by its Deputy Minister for
Technical Services, J. Jenkins Mends-Cole entered into a contractual agreement with
General Fabrication and Construction Business Corporation represented by its Chief
Executive Director, James R. Potter, Sr., for rehabilitation of the Amadu Town to
Royceville road for a contract cost of US$289,609.97. A review of documents
revealed that the amount US$173,765.98 had been paid to the contractor
constituting 60% of the contract cost.
1.24.2 In order to establish the existence and completion of the project, a team of auditors
on January 3, 2015 inspected the road. During the inspection of the 14.3KM road, we
identified four irregularities that worth noting. We sighted at certain locations of the
road long depression points with broken culverts; culverts not properly installed and
backfilled; culvert points identified but no culverts installed and damaged metal
culverts still being used.
Risk
1.24.3 The existence of long depression points on the road and the non- installation of RCP
culverts could deny assurance that the road was completed based on the terms and
conditions of the contract.
Recommendation
1.24.4 The management of the Ministry of Public Works should pursue the contractor to
complete the project. Failure to complete the project, the Chief Executive Director,
James R. Potter should account for the amount received for the implementation of
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
27 Promoting Accountability of Public Resources
the project and be debarred by the PPCC.
Management’s Response
1.24.5 The contract was terminated in accordance with the contract terms and conditions.
The contract to be retendered for the remaining activities for the fiscal
FY2015/FY2016.
Auditor General’s Position
1.24.6 We acknowledge management’s response. We will validate management’s assertion
during the next audit of the MPW.
1.25 Diggsville to Caldwell Road
Observation
1.25.1 On March 22, 2010, the Ministry of Public Works entered into contractual agreement
with 21st Century Construction Company for the rehabilitation of the Diggsville to
Caldwell road for the amount of US$147,478.96.
1.25.2 The inspection of this 8.0KM road was conducted on January 5, 2015. During the
inspection, we observed depression length ranging from 300 meters to 1100 meters
long. Interview with community dwellers revealed that CICO had done two major
interventions since it uses the road to transport construction materials to their
project site along the Monrovia-Gbarnga highway. Despite CICO interventions, the
road is in a deplorable condition that if nothing is done during this dry season, the
road will be completely inaccessible comes the next rainy season.
1.25.3 It was also observed that the design of the pipe culverts installed on the road was
not done appropriately. The elevations seem to be wrong resulting in complete
siltation of the culverts. Headwalls and wing walls are incomplete.
1.25.4 At 3.6KM of the road, there is an existing steel bridge that needs to be urgently
changed. The 55.8ft long and 9.61ft wide bridge is resting on steel plate abutment
that is without guard rails on both sides of the bridge or other protective structures.
We also observed that heavy trucks ply the route transporting sand, red dirt, crushed
rocks and other heavy materials.
Risk
1.25.5 The blocking of the culvert lines could make the road inaccessible and deny
assurance that the road was completed based on the terms and conditions of the
contract.
Recommendation
1.25.6 MPW should ensure that the bridge be reconstructed to avoid total collapse.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
28 Promoting Accountability of Public Resources
1.25.7 The MPW should ensure that the contractor fixes the lapses noted including the
installation of the culverts, elevations and redo the headwalls and wing walls.
Management’s Response
1.25.8 The contract was completed accordance to the project scope of work issued by the
Ministry of Public Works. The road has deteriorated due to wear and tear of the
weather road user without any routine maintenance.
Auditor General’s Position
1.25.9 Management’s response did not address the issues noted by the GAC. Therefore, we
maintain our recommendation.
1.26 Caldwell to Louisiana Road
Observation
1.26.1 On May 10, 2011, the Ministry of Public Works represented by its Minister, Atty.
Samuel Kofi Woods entered into contractual agreement with the China Chongqing
International Construction Corporation represented by its Country Manager, Mr. Fu
Liangquan for the rehabilitation to upgrade to asphalt pavement of the Caldwell to
Louisiana Road for the contract value of US$18,914,795.40.
1.26.2 During the inspection of the 12.0KM road, we observed at several locations of the
road that the slabs covering the sidewalk were either cracked or completely broken.
1.26.3 It was also observed that the access to alleys and other access roads to the major
street were not properly done. Slabs placed over drainage channels are now
breaking up due to the action of turning vehicles.
1.26.4 Furthermore, the elevations to the culverts were not done properly, which could
prevent water from free flowing. In some instances there is no erosion protection for
the culverts, thus exposing it to wearing away. Also the outlet for the water or the
sub surface road side drainage is not completed. There is no basin for the flow of
water, resulting to water flowing into nearby communities, affecting private
properties.
Risk
1.26.5 The early breaking of the slabs could be an indication that sub-standard materials
were used which could lead to early spoilage of the entire road.
1.26.6 Failure to observe that the access to alleys, slab, culverts, roadside drainage and
other important features of the road are properly done could result to the road
experiencing damage in short period of time.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
29 Promoting Accountability of Public Resources
Recommendation
1.26.7 The Ministry of Public Works should ensure that the contractor revisit all the spots
identified to recondition those spoiled slabs before final payment on the contract.
1.26.8 Ministry of Public Works should ensure that a team of engineers inspect the road to
identify all deficiencies in order to ensure that the contractor recondition the road.
Management’s Response
1.26.9 The contract is under retention period. Final completion certificate and final payment
will only be issued after all defect has been corrected by the contractor.
Auditor General’s Position
1.26.10 We acknowledge management’s response. Management’s assertion will be validated
during the next audit of the MPW
Nimba County
1.27 Bahn to Loguatuo Road
Observation
1.27.1 During April of 2010, a contract was entered into by and between the Government of
Liberia through the Ministry of Public Works, represented by its Deputy Minister for
Technical Services, J. Jenkins Mends-Cole, hereinafter known and referred to as the
“Ministry”, and B & Sons Transportations/Construction Services, represented by its
Managing Director, David S. Barjibo, hereinafter known and referred to as the
“Company” for the rehabilitation of approximately 38.8 miles of the Bahn to
Loguatuo Road at a cost of One Million Fifty Seven Two Hundred Ninety Three
United States Dollars (US$1,057,293.19). The duration of the contract was one
hundred eighty (180) calendar days or six months beginning April 30, 2010 and
ending October 31, 2010.
1.27.2 During our inspection of the 38.8 miles Bahn to Loquatuo road rehabilitated by B &
Sons Transportation/Construction Services during the periods under audit, we
observed during our inspection that the road is in a deplorable state. The Bill of
Quantity (BOQ) for the Bahn to Loguatuo Road revealed that the Contractor was
required to carry out clearing of vegetation, culvert works and earth works.
1.27.3 However, during our interaction with some members of the communities along the
Bahn to Loguatuo Road, including the Quarter Chief of Bayleglay, K. Michael Mah
and the Acting Clan Chief, Blackie Garleh, they informed us that the Contractor did
not do any earth work along the road. We were only informed that the contractor
only did some culverts installation at some locations along the road. Our inspection
revealed that no full rehabilitation of the road was carried out by the Contractor as
specified in the contractual agreement and the BOQ.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
30 Promoting Accountability of Public Resources
1.27.4 We observed during the inspection that very few culverts installation was done in
some locations along on the road. During further inspection, we also observed that
several existing CMP culverts were damaged and were not replaced according to the
Bill of Quantity for the rehabilitation of the 38.8 miles Bahn to Loguatuo Road. We
further observed that the damaged CMPs were found within the vicinity of several
towns, such as; Larpea 1, Larpea 2, Duoplay etc. along the Bahn to Loguatuo road.
1.27.5 During the course of the audit, according to B & Sons response to the third party
confirmation request made by the GAC Audit Team, they said that the Ministry of
Public Works still owed them the amount of US$172,917.17 and US$184,447.53 for
the Bahn to Loguatuo Road project and for the extra work done on the Road.
We observed that a double lines 48” RCP culverts constructed by B & Sons near
Karnplay along the Bahn to Loquatuo road has completely damaged, as the head and
wing walls have totally collapsed due to the construction of sub-standard culverts.
We also observed that a single line 36” RCP culvert installed in Duo-play did not have
head and wing walls and as such the water is not being controlled.
1.27.6 During our inspection of the Bahn to Loguatuo Road, specifically from Karnplay to
Loguatuo, we also observed that this part of the road is also in a deplorable state.
We observed during the inspection that no earth work was done along the road as it
has been outlined in the contractual agreement between the Government of Liberia
through Ministry of Public Works and B & Sons. We observed major deviation from
the BOQ by the Contractor as damaged CMPs along the road were still been
retained, thus further damaging the road. Some Reinforced Concrete Pipe culverts
constructed lacked head and wing walls. The single line 36” RCP culvert in Kanlay,
Nimba County along the Bahn to Loguatuo Road lacks head and wing walls.
Risk
1.27.7 The failure of the contractor to remove the damaged CMPs near Larpea #2 along the
Bahn to Loguatuo Road could undermine the existence of the road.
1.27.8 The failure of the contractor to remove damaged existing CMPs along the roads
being rehabilitated may undermine the existence of the roads and also undermine
the government’s effort in providing better roads for its citizens.
1.27.9 The failure of contractor to perform the contract according to the technical
specification along the road may result in the lack of value for money, and could
further result in the collapse of the culverts along with its head and wing walls.
Recommendation
1.27.10 The Management of MPW should ensure that the Contractor, B & Sons should
remove all the damaged CMP and RCP culverts along the Bahn to Loguatuo Road
and re-install new RCP culverts according to BOQ of the road project to spots where
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
31 Promoting Accountability of Public Resources
these damages occurred and to also perform earthwork along the road, thereafter,
upon satisfactory inspection and report, the MPW shall then authorize the
appropriate authority for the balance payment of US$172,917.17 and
US$184,447.53to the contractor for completion of the work on the Bahn to Loguatuo
Road.
1.27.11 The MPW should ensure that its Engineers carry out regular inspection and
monitoring of all roads and bridges contracts awarded to various contractors by the
Government of Liberia with funding from the GOL and International Partners to avoid
project implementation without observing the technical specification.
Management’s Response
1.27.12 Management did not respond to this observation
Auditor General’s Response
1.27.13 In the absence of a response from the Management of MPW, we maintain our
recommendation.
1.28 Bahn- Lorplay Bridge
Observation
1.28.1 May 10, 2011, a contract was entered into by and between the Government of
Liberia through the Ministry of Public Works, represented by its acting Minister Victor
B. Smith hereinafter known and referred to as the “Ministry”, and B & Sons
Transportations/Construction Services, represented by its Managing Director, David
S. Barjibo, hereinafter known and referred to as the “Company” for the construction
of the Bahn to Lorplay Bridge at a cost of One hundred ninety-six thousand United
States Dollars (US$196,000.00). The duration of the contract was three (3) months
beginning May 2011 and ending August 2011.
1.28.2 As per project specifications the Bahn to Lorplay Bridge is a reinforced concrete
bridge. The design span of the bridge is given as 60’ – 0” and the width is 25’ – 0”.
The bridge is design to consist of Abutments, decking & support beams, wing walls
and approach slabs. Metal protective guard rails are to be provided on either sides of
the bridge.
1.28.3 It was observed from physical inspection that the span of the bridge constructed is
less than the dimension shown in the design drawings, while the width is the same.
As per the dimension the span should have been 60ft with the width 25ft x 8” thick.
But physical measurement observed that instead, the contractor constructed the
bridge with a dimension of 53.5ft span x 25ft width x 10” thick.
1.28.4 Also the concrete surface observed indicate a poor quality concrete. Inspection also
established that the sand / fine aggregate used for the construction works contains
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
32 Promoting Accountability of Public Resources
high contents of silts and other organic material (swamp sand). Formworks at the
soffit of the decking slab are not completely scratched / removed.
1.28.5 It was further observed that for the abutments the concrete surfaces shows that
concrete is of poor quality and badly poured. The formworks / shuttering works are
also bad leaving the concrete surface rough. The design dimensions as per drawings
are nevertheless adhered to. Vibration of concrete during pouring is observed to be
inadequate as concrete is porous.
1.28.6 Additionally, for the beam, the concrete & formworks as observed were constructed
of poor quality. Also the dimensions of the beam as measured are greater than the
design dimensions. Also, the approach slabs design drawings show reinforced
concrete approach slabs before and after the bridge. However, verification observed
that it was not done during construction.
1.28.7 Additionally, during our inspection we observed that the bridge constructed by B &
Sons has cracked from the Lorplay Town end. We observed that the Approaching
Slab is less than 8.5” thick. We further observed that the earth work over the 60mm
single line culvert constructed after the bridge heading to Lorplay Town is not
compacted.
Risk
1.28.8 The failure of the MPW to monitor the contract awarded to the Contractor could lead
to the execution and performance of sub-standard work by the Contractor.
Recommendation
1.28.9 Deputy Minister for Technical Services, Victor Smith who signed the Certificate of
Completion which served as the basis for the final payment of US$196,000 should
provide substantive justification for signing the Certificate of Completion for work
done to specification, failing he should be held accountable along with the
contractor.
1.28.10 Deputy Minister for Technical Services, Victor Smith and the Management of MPW
should provide the Resident Engineer Report used as the basis for the payment of
the US$196,000 for the project.
1.28.11 The MPW should ensure that its Engineers carry out regular inspection and
monitoring of all projects including bridges contracts awarded to various contractors
by the Government of Liberia with funding from the GOL and International Partners.
Management’s Response
Victor B. Smith Response
1.28.12 Within the Ministry of Public Works, there are distinct roles play by different persons
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
33 Promoting Accountability of Public Resources
and along with are specific responsibilities. As Deputy Minister for Technical Services,
I am the final signer of Completion Certificate. This is the process, upon inspection of
the project by the Resident Engineer, he or she generates a Report that is forward to
the Assistant Minister of Operation and Construction (Mr. William Slour in the
situation). He or she reviews the reports in accordance with the scope of works
along with the contract document and there after generates the Certificate of
Completion. The certificate is forward Deputy Minister for Technical Services (Victor
B. Smith in this situation) for the final check and approval. With all the document
attached after revision, it is forward to the Deputy Minister for Administration for
payment.
1.28.13 Now, there will not be any payment forwarded by the Ministry of Public Works for
processing at the Ministry of Finance when any these documents are missing. The
Deputy Minister for Technical Services has no authorizing power to request payment
for any project when any of these document are missing.
1.28.14 Henceforth, the Resident Engineer’s report that the GAC Audit Report requesting are
all in the archives of the any these offices at the Ministry of Public Works starting
from: Assist Minister for Operation and Construction office, Deputy Minister for
Technical Services office, Comptroller’s office, Deputy Minister for Administration and
even at the Ministry of Finance.
Auditor General’s Position
1.28.15 The MPW Management failed to provide the resident engineer reports despite
persistent requests from the GAC during the course of the audit. Therefore, we
maintain our recommendation.
Lofa County 1.28.16 During further inspection in Lofa County, we inspected eight roads and bridges
projects funded by the Government of Liberia through the Ministry of Public Works
during the periods under audit.
Table 3: GOL Funded Roads Projects Inspected in Lofa County
No. Road Description Contractor Length of Road
1 Emergency Repair of the Kolahun to Vahun to
Bomarue Road
SSF Entrepreneur, Inc. 14.4 KM
2 Kolahun to Vahun Road SSF Entrepreneur, Inc 63 KM
3 Repair & Maintenance of Voinjama to
Mendikorma
SSF Entrepreneur, Inc 8 KM
4 Voinjama to Foya Road SSF Entrepreneur, Inc 39.7 Miles
5 Zorzor to Voinjama City Road Westwood 96 KM
6 Voinjama to Banzenwein Westwood 49 KM
7 Fissibu to Zorzor Road Westwood 19 KM
8 Construction of Reinforced Cement Pavement
of Voinjama City
China Liberia Enterprise 2.53 KM
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
34 Promoting Accountability of Public Resources
1.28.17 During the inspection of all the roads funded by the Government of Liberia through
the Ministry of Public Works in Lofa County, we observed that there is no routine
maintenance carried out along these roads.
1.29 Kolahun to Vahun to Bomarue Road
Observation
1.29.1 On November 1, 2011, a contract was entered by and between Government of
Liberia through the Ministry of Public Works, represented by its Minister, Acting
Minister Jenkins Mends-Cole, hereinafter known and referred to as the “Ministry”,
and SSF Entrepreneur, Inc. represented by its Chief Executive Officer (CEO), Shawki
F. Fawaz, hereinafter known and referred to as the “Company” for the rehabilitation
of the 63 kilometers Kolahun to Vahun Road at a cost of US$5,150,000.00. The
duration of the contract is two hundred seventy calendar days or 9 months beginning
November 1, 2011 and ending July 31, 2012.
1.29.2 Our analysis of the Bill of Quantity for the rehabilitation of the 63 Kilometers Kolahun
to Vahun Road in Lofa County which was awarded to SSF Entrepreneur, Inc. it was
revealed that the Contractor was required to perform the followings: preliminary
works, which includes mobilization works, demobilization from site, demolish all
marked structures in the High way, side brushed and deshaded all trees and within
bushes ten (10) meters width on either side of the centerline; earth works, which
includes road formation, reshape road surface, cut to fill top soil materials other than
rock, cut and using rocky soil materials, excavate, haul, place and fill gravel surface
material to eight (8”) thick and drainage works.
1.29.3 On December 17th to 18th, 2014, we conducted the inspection of the 63 km Kolahun
to Vahun Road, which its rehabilitation was awarded to SSF Entrepreneur Inc. The
rehabilitation of this road commenced November 2, 2011 and ended July 31, 2013.
We observed during our verification that some of the culverts installed along the
Kolahun to Vahun Road were not properly backfilled. For instance, the double lines
48” Reinforced Concrete Pipe Culvert constructed in Nyenwazue was not backfilled,
thus exposing the culverts to damage. We further observed along the road that some
culverts were hidden in the bush due to the lack of side brushing of the road.
Additionally, the double lines 36” RCP culverts installed in Yandohun was not also
backfilled.
1.29.4 Moreover, we also observed that the double lines 24” RCP culverts constructed
between Yandohun and Vahun on the Kolahun to Vahun Road had damaged due to
the force of the river along the road. We observed that the culvert constructed could
not withstand the tension/force of the stream, as one side of the culvert is being
completely damaged. As a result of the damage of the head and wing walls of the
culvert, the water is seriously undermining the entire road at this location. Our
observation also revealed that the contractor did not use the appropriate type and
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
35 Promoting Accountability of Public Resources
size of materials at this location. The head and wing walls at this end have totally
collapsed.
1.29.5 Additionally, due to the collapse of the head and wing walls of the double lines 24”
RCP culverts along the Kolahun to Vahun Road, which lie precisely between
Yandohun and Vahun, we observed that a major crack has developed right above
the damaged culverts. This crack is so grave that it is gradually extending to the
other end of the road. If nothing is done by the MPW and the SSF to save the
situation, the road may become completely in accessible, thus denying people living
within that part of the county access to other areas.
1.29.6 During our inspection along the Kolahun to Vahun to Bomarue road, we observed
that the single line 36” RCP culvert constructed by the SSF Enterprise Inc. was poorly
connected. We further observed that the head and wing walls of the 36” RCP culvert
was not properly backfilled by SSF Enterprise as a result the head and wing walls
have been seriously undermined by the stream.
1.29.7 During further inspection along the Kolahun to Vahun to Bomarue Road, we
observed that a single line 60” RCP culvert between Vahun and Bomarue that the
culvert was not properly backfilled. As a result of lack of proper backfilling of the
culvert by the contractor, some part of the culvert is exposed to the surface. Further,
eleven double lines of 48’ RCP and one single lines of 60’ RCP amounting to US$
85,800.00 and US$8,000.00 respectively were not seen installed as required by the
approved BOQ. See Exhibit 1
1.29.8 During our analysis of SSF Entrepreneur, Inc. response to the third party
confirmation, we were informed that SSF Entrepreneur, Inc has completed the
contract up to 100% in line with the contractual agreement and MPW still due them
a balance of US$257,500.00. However, our inspection of the project revealed that
the contractor did substandard work at some locations and also did not properly
backfill some culverts installed as can be seen by pictorial evidence indicated above.
Risk
1.29.9 The lack of proper monitoring and evaluation of the works of the contractor by MPW
through its Road Engineers on a routine basis, may lead the contractor to doing sub-
standard work and further causing damage to the road and making it in-accessible.
1.29.10 The failure of the MPW to ensure that its Resident Engineers provide timely report on
the status of some roads and bridges projects funded by the Government of Liberia
may give rise to some contractors not living up to the technical specifications of said
projects.
1.29.11 The failure of the MPW Resident Engineer to give regular status reports on ongoing
projects could lead to payment for sub-standard work.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
36 Promoting Accountability of Public Resources
1.29.12 The Management of MPW failure to ensure that the contractors properly backfill the
culverts installed along the roads rehabilitated could lead to exposure of the culvert
and thus resulting into damage and making the road in-accessible.
Recommendation
1.29.13 The Management of MPW should ensure that the Contractor, SSF Entrepreneur Inc.
should be may to provide justification for failure to install the eleven double lines of
48’ RCP and one single lines of 60’ RCP amounting to US$ 85,800 and US$8000
respectively.
1.29.14 Furthermore, the management of MPW should ensure that the contractor revisit the
road and completely backfill all exposed culverts along the Kolahun to Vahun to
Bomarue Road and also reconstruct new culverts at locations where culverts are
damaged as a result of erosion.
1.29.15 The Management of MPW should further ensure that the Contractor, SSF
Entrepreneur, Inc. remove and replace the damaged double lines 24” RCP culverts
which was constructed right near the Vahun Town and should further replace the
cracked 36” RCP culverts.
1.29.16 The MPW should develop road usage regulation and should identify the tonnage for
vehicle plying the road and also the MPW management should develop road
maintenance policy to use as a guide for the maintenance of all roads, especially the
laterite roads.
Management’s Response
1.29.17 The contract is under retention period. Final completion certificate and final payment
will only be issued after all defects has been corrected by the contractor.
Auditor General’s Position
1.29.18 We acknowledge management’s response. We will validate management’s assertion
during the next audit of the MPW.
1.30 Zorzor to Voinjama Road
Observation
1.30.1 During our inspection of the 96 kilometers Zorzor to Voinjama Road rehabilitated by
the Westwood, we observed some critical spots along the road which requires
maintenance and the road lack side brushing as bush has closed up most parts of
the road. Further inspection also revealed that the bridge situated on the Zorzor to
Voinjama Road right after the Washington Village lacks approaching slab, thus
exposing and causing damage to the bridge at both ends.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
37 Promoting Accountability of Public Resources
Risk
1.30.2 The failure of the MPW through its Resident Engineers to carry out routine
monitoring and evaluation of roads and bridges and provide a timely report on the
status of these roads and bridges could result to early deterioration of the road.
Recommendation
1.30.3 The Management of MPW should conduct routine maintenance on roads and bridges
which have critical issues like the bridge on the Zorzor to Voinjama Road located
near Washington Village which has a deteriorating approaching slab.
1.30.4 The MPW should develop road usage regulation and should identify the tonnage of
vehicle to ply the road and also the development of road maintenance policy by the
Ministry of Public Works to use as a guide during the maintenance of roads.
Management’s Response
1.30.5 The contract was completed accordance to the project scope of work issued by the
Ministry of Public Works. The road has deteriorated due to wear and tear of the
weather road user without any routine maintenance.
Auditor General’s Position
1.30.6 We acknowledge management’s response. We will validate management’s assertion
during the next audit of the MPW.
1.31 Voinjama to Foya and Foya to Mendikorma Roads
Observation
1.31.1 During our inspection of Roads in Lofa County, we inspected the 39.7 miles Voinjama
to Foya Road and the emergency rehabilitation of the Foya to Mendikorma Road by
the SSF Entrepreneur, Inc. during the period under audit. The total amount for the
rehabilitation and emergency rehabilitation of the Voinjama to Foya Road and the
Foya to Mendikorma Road cost US$1,297,125.06 and US$119,663.61 respectively.
The Contractor was required to perform the following on both roads; preliminary
works, clearing works, earthwork and road works and drainage works.
1.31.2 During the course of our inspection, we observed some critical spots along the
Voinjama to Foya road. For instance, we observed damaged spots approaching
Kabata along the Voinjama to Foya Road. The condition of the road is so critical due
to the poor level of earth work done the Contractor and it makes movement along
the road by Motorists difficult.
1.31.3 During our inspection also along the Foya to Mendikorma Road rehabilitated by SSF,
we observed that some CMP culverts along the road were damaged and not removed
and replaced by the Contractor. The un-removed damaged CMP culvert is located
around Kilima Benu along the Foya to Mendikorma Road in Lofa County.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
38 Promoting Accountability of Public Resources
Risk
1.31.4 The substandard condition of the road could result into making the road inaccessible.
1.31.5 The Lack of routine inspection and report on the status of roads within the country
by the Ministry of Public Works could lead to damage roads within the country being
un-noticed in due time for possible maintenance and thus posing difficulties to
motorists.
Recommendation
1.31.6 The Ministry of Public Works should ensure that its Road Engineers on a regular
basis should carry out monitoring and supervision of all roads and bridges contracts
awarded to various contractors by the Government of Liberia.
1.31.7 The MPW should develop road usage regulation and should identify the tonnage of
vehicle to ply the road and also the development of road maintenance policy by the
Ministry of Public Works to use as a guide during the maintenance of roads.
Management’s Response
1.31.8 The contract is under retention period. Final completion certificate and final payment
will be issued after all defective works has been corrected by the contractor.
Auditor General’s Position
1.31.9 We acknowledge management’s response. Management’s assertion will be validated
during the next audit of the MPW.
Grand Gedeh County
1.32 Tuzon Town Box Culverts
Observation
1.32.1 On April 1, 2011, the Ministry of Public Works represented by its Acting Minister, J.
Jenkins Mends-Cole entered into a contractual agreement with SWAGS Engineering
Construction Inc. represented by its General Manager, Williams Banks for the
maintenance and drainage improvement on the Tuzon and Gbarblor Town Roads in
Grand Gedeh County. The parties agreed that for completion of the project in
compliance with the detailed scope of works, drawings and specifications prepared
by the Ministry, the Ministry shall pay the amount of US$49,771.28 to the company
as total project cost.
1.32.2 However, an addendum increasing the contract value by US$10,000.00 was entered
into on July 17, 2011 exactly four months after the initial contract.
1.32.3 On December 22nd, 2014, the Audit Team inspected a Box culvert constructed by
SWAGS on the Tuzon Town road in Grand Gedeh County. We observed during our
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
39 Promoting Accountability of Public Resources
inspection that proper maintenance is not taking place around the box culvert as
grass has grown around the box culvert, and as the box culvert is gradually being
closed up by the bush.
1.32.4 Additionally, we observed during the inspection of the Tuzon Town box culvert that
the Contractor, SWAGS, did not remove the existing detour which was installed right
in front of the box culvert. The contractor failure to remove the existing detour in
front of the box culvert has reduce the free flow of water in the channel which could
create turbulence that could result in scouring of the water channel. The auditors
could not verify the second aspect of the contract, for the maintenance of the
Gbarblor Town Road.
Risk
1.32.5 The failure of the management of MPW to prevail upon the contractor, SWAGS to
remove the existing detour installed in front of the box culvert along the Tuzon –Box
Culvert could undermine the existence of the Box Culvert thus rendering the road
inaccessible.
Recommendation
1.32.6 The Management of MPW should ensure that the existing detour bridge installed in
front of the Tuzon Box Culvert is removed by SWAGS to provide the free flow of
water through the channel and avoid future damage to the Box Culvert and the
Tuzon Town Road.
1.32.7 The Management of MPW should ensure that the contractor SWAGS performs the
second phase of the project, the maintenance of the Gbablor Town Road
Management’s Response
1.32.8 The maintenance contract was 100% complete. A meeting is pending with the
contractor to as to the removal of the existing detour installed at the front of the box
culvert.
Auditor General’s Position
1.32.9 We acknowledge management’s response. Management’s assertion will be validated
during the next audit of the MPW.
Grand Kru County
1.32.10 On December 23 and 24, 2014, the audit team conducted inspection of two roads
and bridges projects in Grand Kru County. The projects inspected included the 86
kilometers Kanweaken to Barclayville Road and the George Bush Bridge, with specific
focus on the center pier of the bridge. During the inspection in the county, we were
accompanied on the field by the Representative of the Resident Engineer of Grand
Kru County, Michael Tarwreh.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
40 Promoting Accountability of Public Resources
1.33 Karweaken to Barclayville Road
Observation
1.33.1 On July 31, 2012, a contract was entered into by and between the Government of
Liberia through the Ministry of Public Works, represented by its Minister, Acting
Minister, Victor B. Smith and the SSF Entrepreneur Inc. represented by its Chief
Executive Officer (CEO), Shawki Fawaz for the rehabilitation of 86 kilometers
Karweaken to Barclayville Road in Grand Kru County. The cost for the rehabilitation
of the 86 km Karweaken to Barclayville Road amounted to US$5,195,992.36 (Five
Million, One Hundred Ninety Five Thousand, Nine Hundred Ninety Two and 36/100
Thousand United States Dollars). The duration of the contract was twelve months
beginning from the date the contract was signed by the parties.
1.33.2 According to the BOQ of the contract, SSF Entrepreneur, Inc. was required to carry
out the following functions; preparatory/ clearing works, earth works including
mechanical grubbing, road side brushing, deshading of shaded section 9 meters from
centerline on both sides, removal of unsuitable materials, backfilling of all excavated
sections, bridges/ culverts approaches and huge potholes, reshape, upgrade and
compact entire roadway at 20meters depth in place with 7% camber compacted in
layers of 15cm using selected laterite materials, installed reinforced concrete pipe
culverts at various identified locations, extend existing box culverts at specified
locations, extend Reinforced Concrete bridge, construct reinforced concrete box
culverts to specified locations and drainage works.
1.33.3 Our review of the response to the third party confirmation by SSF Entrepreneur, Inc.
on the rehabilitation of the 86 km Karweaken to Barclayville Road, we were informed
by the Contractor that they have completed 75% of the work and has received the
amount of US$3,637,194.64 (Three Million, Six Hundred Thirty Four Thousand, One
Hundred Ninety Four and 64/100 United States Dollars) and the 25% in-complete
portion amount to US$1,558,797.72 (One Million, Five Hundred Fifty Eight Thousand,
Seven Hundred Ninety Seven and 72/100 United States Dollars). However, from our
inspection, the Contractor has over stayed in executing the contract. The contract
begins July 31st, 2012 and was to be completed within twelve months, precisely by
July 2013. We observed during the inspection that major work is still outstanding
along the road contrary to the SSF assertion that the balance work constitutes 25%.
1.33.4 During the inspection of the 86 km Karweaken to Barclayville Road, we observed that
the structural work along the road had not been done and at some locations they
remained incomplete. We also observed along the road that an incomplete double
barrel box culvert constructed by SSF Entrepreneur Inc. remains abandoned. Due to
the status of the double box culvert, a detour is being used at the location for
movement by motorists. Further inspection revealed that the 2.6 meters box culvert
constructed by SSF Entrepreneur Inc. is incomplete as one side of the box culvert
lacks head and wing walls.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
41 Promoting Accountability of Public Resources
1.33.5 We further observed along the Karweaken to Barclayville Road of an abandoned and
about 98 percent incomplete bridge. We also observed that the project is at a
standstill as no sign of any work is being done. The detour used around the bridge is
in a critical condition as the road is almost disconnected.
1.33.6 During the inspection, we observed that some parts of the road were low surface
areas, which require the installation of culverts. However, we observed along the
road, approaching Satiaken by way of Kanweaken that a shallow water is situated
along the road, which normally overflows during the rainy Season, thus damaging
the road and making the road inaccessible during the rainy season. Additionally, we
also observed during our inspection a low surface area which was not elevated.
According to the representative of the Resident Engineer, this point of the road
normally experience overflow during the rainy season. Due to the stretch of the low
surface area along the road around the Paroken Town, the contractor had not
upgraded the road above the level of the swamp and also we observed the non-
installation of chain of culverts along this stretch of swamp.
1.33.7 We further observed that during our inspection along this 86 km Road at a point of
the road closer to Joquiken, we observed that a very poor earth work was done at
this location, as no sign of laterite was used at this location. This part is so
deplorable and therefore needs improvement by the contractor to avoid the road
from being totally inaccessible as the next rainy season begins.
1.33.8 During our inspection of the road, we also observed that there still exist log bridges
along the road. The contractor had not constructed new bridges at the various site
identified for bridge construction. We observed along the road that there still exist
three log bridges which up to the time of our inspection had not been removed and
reconstructed. The log bridges along the Karweaken to Barclayville Road are all in
deplorable state.
Risk
1.33.9 The failure by the management of MPW to carry out inspection of roads and bridges
contracts awarded to contractors may undermine the effort of the government to
construct and rehabilitate roads and bridges within the country.
1.33.10 The failure of the contractor to perform the contract within the specified periods
according to the contract terms deny assurance that value for money was achieved.
Recommendation
1.33.11 The Management of MPW should ensure that contractors perform the contract
according to the Bill of Quantity, work inventory and the specified time period
stipulated in the contract agreement.
1.33.12 The Management of MPW should ensure that SSF Entrepreneur Inc. is not paid the
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
42 Promoting Accountability of Public Resources
balance contract cost of 25% unless a team of Engineers verify the 75% completion
as claim by the contractor.
Management’s Response
1.33.13 The contractor is under retention period. Final completion certificate and final
payment will only be issued after all defects have been corrected by the contractor.
Auditor General’s Position
1.33.14 We acknowledge management’s response. Management’s assertion will be validated
during the next audit of the MPW.
1.34 Sweaken to Glofaken Road, River Gee County
Observation
1.34.1 On April 1, 2011, a contract was made and entered into by and between the
Government of Liberia through the Ministry of Public Works represented by its Acting
Minister, J. Jenkins Mends-Cole and Korto Anis Teah Corporation (KATCO),
represented by its General Manager, Fadi-Homsi for the rehabilitation of
approximately 36.6 Kilometers of the Sweaken to Glofaken Roads in River Gee and
Maryland Counties. The rehabilitation of the 36.6 Kilometers road by KATCO cost
Eight Hundred Fifty Six Thousand Three Hundred Fifty One and 50/100 United States
Dollars (US$856,351.50). The duration of this contract was eight (8) months or two
hundred forty (240) calendar days beginning April 1, 2011 and ending November 30,
2011.
1.34.2 During our inspection of road and bridges rehabilitated in River Gee County during
the period under audit, we inspected the 36.6 Kilometers Sweaken to Glofaken road
which was rehabilitated by KATCO. According to the Bill of Quantity (BOQ) for the
rehabilitation of the Road, The Contractor was required to perform the followings:
Demud and backfill with selected laterite and compact in layers of 6 inches of all
muddy sections, construct reinforced concrete bridges or concrete box culvert to
where log bridges existed, install RCP culvert of various sizes with head and wing
walls and apron to sites where damaged log bridge existed and to resurface with
selected good laterite materials, compacted with 6 inches thinness layers to locations
along the road with slippery rocky hill section.
1.34.3 It was observed during the inspection that the Contractor did not do earthwork along
the road as it was required and indicated in the BOQ. We observed more muddy
sections along the road which were not removed by KATCO during the rehabilitation
of the 36.6 Kilometers Sweaken to Glofaken Road. We also observed that KATCO
only performed some structural works along the road, which focus on the installation
of RCP culverts to points indicated on the BOQ. On the other hand, the inspection
revealed that the contractor did not perform earth work in accordance with
specification enshrined in the contract document, as the condition of the road
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
43 Promoting Accountability of Public Resources
remains in a deplorable state.
1.34.4 Additionally, we observed that the road has been totally enclosed by the bush, as no
sign of side brushing was seen along the road. The road has become so narrow
making it impossible for vehicle to move. The condition of the road with reference to
the lack of side brushing is disappointing.
1.34.5 During further inspection of the Sweaken to Glofaken Road, we observed the
existence of Log Bridge along the road very close to Juluken One. The Contractor,
KATCO up to the point of our inspection had not replaced or changed the log bridge
to a concrete pavement bridge. We further observed that the portion of the road
beyond this log bridge up to Juluken one and beyond is in-accessible.
1.34.6 We observed from our inspection that KATCO did not live up to the time frame setup
to have the road rehabilitation completed. The Contractor claimed that they have
completed 60% of the road project, despite the duration of the project has since
elapsed and the road still remains in a deplorable state.
Risk
1.34.7 The lack of proper supervision and monitoring by the Ministry of Public Works during
the execution of the contract by the Contractor could lead to underperformance and
non-implementation of the project as indicated in the contractual agreement.
Recommendation
1.34.8 The Management of MPW should ensure that contractors perform their contract
according to the Bill of Quantity, work inventory and the specified time period
stipulated in the contract agreement.
1.34.9 The management of MPW should ensure that a team of Engineers conduct a full
inspection of the 60% completion claim by the contractor before any further
payment is made to the contractor.
Management’s Response
1.34.10 The Contractor has mobilized on the road to recommence works. An addendum of
the project duration was approved by Hon. Christian G. Herbert, late Deputy
Minister/Rural Development. The project was at a standstill due to two years of delay
in payment by GOL to the Contractor(2012 to 2014 December).
Auditor General’s Position
1.34.11 We acknowledge management’s response. Management’s assertion will be validated
during the next audit of the MPW.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
44 Promoting Accountability of Public Resources
Sinoe County
1.35 Zwedru to Greenville Road
Observation
1.35.1 During the conduct of field verification of roads and bridges rehabilitated in Sinoe
County, we were accompanied on the field by Sampson Chea, Representing MPW
Resident Engineer in the County. We conducted inspection of four roads and bridges
projects in the county. Our inspection covered Barclayville to Greenville Road,
Greenville to Zwedru Road, Wiah Town to Planiabo Road and Nyafuah Town to
Buchanan Road. The rehabilitation of three of the roads were fully funded by the
Government of Liberia and the other one, the Barclayville to Greenville was funded
through a cost sharing arrangement between the Government of Liberia and the
Atlantic Resources.
1.35.2 The Government of Liberia through the Ministry of Public Works, represented by its
Deputy Minister for Technical Services, J. Jenkins Mends-Cole on April 30, 2011,
awarded contract to Koman Enterprise (SEK Liberia) Inc. represented by its Director
General, Collins S. Siafa for the rehabilitation of approximately one hundred thirteen
(113) miles of the Zwedru to Greenville Road at a cost of Two Million United States
Dollars (US$2,000.000.00). The duration of the contract is two hundred forty (240)
calendar days or eight months beginning April 30, 2010 and ending December 31,
2010.
1.35.3 According to the technical specifications and Bill of Quantity for the rehabilitation of
the Zwedru to Greenville Road, it was required by the Contractor to perform
preparatory/Clearing Works which include side brushing and deshading of
vegetation, 7.6m from ditch line on both side of the existing road length, demolition
of marked structures and dispose of all debris along roadway; Earth Works which
include performing mechanical grubbing/ reshaping of Road surface at 10cm making
sure all organic materials are removed and disposed of 300m away from work site,
perform excavation of unsuitable materials 40cm deep, perform backfilling of
excavated sections using selected laterite and compact well in lift of 20cm at 3-5%
camber or as per site engineer instruction, perform side ditching and turn-out at all
cut section of roadway, perform re-gravelling of the carriageway at 10cm compacted
thickness at 5% camber and also perform roadbed scarification, reshape and
compact scarified surface at 5% camber.
1.35.4 Drainage works involving to excavate and removal of all stubs, old foundations,
unsuitable soil, growing vegetations and prepare mass concrete bedding thick, install
60’’ Ø x 36’, 48’’ Ø x 36’ and 24’’ Ø x 36’ reinforced concrete pipes with RCP head
and wing walls. Construct apron at entrance and exit points cross and perform
cleaning of all existing functioning culverts, reinforced box culverts, reinforced
bridges by removing debris, vegetation from the inlets and outlets.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
45 Promoting Accountability of Public Resources
1.35.5 However, it was revealed during our inspection on the rehabilitation of road and
bridges on the Zwedru to Greenville Road that the aspect of quality reinforced
concrete pipe (RCP) culverts to be constructed by Koman Enterprises (SEK Liberia)
Inc. in keeping with technical specification of the contract was lacking; there were
several culverts constructed by the contractor that were observed damaged during
the inspection. The single line 36” RCP culverts constructed by the contractor were
damaged due to the use of substandard materials. These damaged 36” RCP culverts
were located along the road approximately 3 km away from Greenville City. Our
observation further revealed that the 6” thickness of the RCP to be used as indicated
in the BOQ were not applied, thus resulting into damage of the RCP installed by
Koman Enterprise (SEK Liberia} Inc. These damaged RCP culverts along the Zwedru
to Greenville Road had made the road inaccessible for motorists.
1.35.6 Additionally, during our review of the BOQ, the contractor was required to perform
quality earth works. Our inspection revealed that the contractor did not adhere to the
specification enshrined in the contract document. Koman Enterprise (SEK Liberia) did
not perform excavation of unsuitable materials as evidence by the condition of the
road in a deplorable state. The contractor did not perform backfilling of excavated
sections using selected laterite in place and did not also compact the surface as
outlined in the technical specification of the contract. As a result of the poor earth
works done, damaged and critical spots were observed along the Greenville to
Zwedru Road in Jayploh, Morrisville. At some locations along the road motorists had
to take a detour to pass some critical spots along the Zwedru to Greenville Road.
Risk
1.35.7 The failure of the Management of MPW to conduct inspection of works awarded to
contractors and also the lack of monitoring and supervision by the MPW Resident
Engineers could lead to poor construction work, installation of substandard fabricated
culverts and substandard reinforced concrete box culverts resulting into the non-
achievement of value for money.
Recommendation
1.35.8 The Management of MPW should ensure that all roads and bridges Contracts
awarded by the Government of Liberia through the Ministry of Public Works are
properly monitored and supervised by the MPW Road Engineers to ensure that the
project is implemented according to technical specification. The management of the
MPW should ensure that status report is given at every stage of the project and such
report should be verified by internal audit and the ministry’s monitoring and
evaluation team.
1.35.9 The ministry’s monitoring and evaluation section along with the internal audit should
regularly visit projects sites and produce independent report informing the ministry
of the status of projects before processing payment.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
46 Promoting Accountability of Public Resources
Management’s Response
1.35.10 The contract was completed accordance to the project scope of work issued by the
Ministry of Public Works. The road has deteriorated due to wear and tear of the
weather road user without any routine maintenance.
Auditor General’s Position
1.35.11 Management’s response did not address the issues noted by the GAC. Therefore, we
maintain our recommendation.
1.36 Wiah Town to Planiabo Road
Observation
1.36.1 The Government of Liberia through the Ministry of Public Works, represented by its
Deputy Minister for Technical Services, J. Jenkins Mends-Cole, on April 30, 2010,
awarded contract to Westwood Cooperation, represented by its General Manager,
Samuel B. Cooper III, for the rehabilitation of approximately thirty (30) miles of the
Wiah Town to Planiabo Road in Sinoe County at a cost of Three Hundred Forty
Thousand Four Hundred Sixty Seven 57/100 United States Dollars (US$340,467.57).
The duration of the project is one hundred eighty (180) calendar days or six (6)
months beginning April 30, 2010 and ending October 30, 2010.
1.36.2 The Bill of Quantity for the rehabilitation of the Wiah Town to Planiabo Roads
outlined that Westwood Corporation was required to perform clearing of vegetations,
culvert installation and earth works. The clearing of vegetations include the
performance of mechanical grubbing, roadside brushing, deshading of vegetations of
trees 8 meters from centerline on both sides of existing road length. The drainage or
culvert works entailed the removal of unwanted bedding material or excavate and
stabilize bedding with crushed stones, sand, or if possible concrete (mass or
reinforced) before installing the culverts with concrete head and wing walls, with
aprons specified on the attached drawings: i) 0.6m x 6m, ii) 0.9m x 6m, iii) 1.2m x
6m and iv) 1.5m x 6m. In addition, the contractor was required to perform the
following earthworks; excavate unsuitable materials, backfilling and compaction in lift
of 0.15meter with selected laterite, re-grade, re-shape, perform road side ditching in
V-shape as required on both sides of the road length and compact carriageway and
perform re-gravelling of selected sections on carriageway and compact in lift of
0.15meter as required.
1.36.3 However, contrary, our inspection revealed that Westwood Corporation did not install
culverts as specified in the BOQ to locations identified. During the inspection we
observed that log bridges were still being seen along the Wiah Town to Planiabo
Road, despite, having awarded the road rehabilitation to Westwood Corporation. We
further observed that the contractor did not remove and replace the log bridges with
Reinforced Concrete Pipes with head and wing walls over streams that require
culvert installation. The maintenance work currently on the road as evidence by the
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
47 Promoting Accountability of Public Resources
log bridge below is being carried out by Golden Veroleum Limited. The objective for
the rehabilitation of the Wiah Town to Planiabo Road along with other secondary and
feeder roads was for the achievement of the poverty reduction strategy (PRS) in
Liberia. However, we observed during the inspection of the Wiah Town to Planiabo
Road that the objective has not been achieved.
.
1.36.4 During further inspection along the Wiah Town to Planiabo Road, we observed at
certain location that some fabricated RCPs were still stock pad along the road
without being installed by Westwood Corporation. The stock pad of 48” reinforced
concrete pipes intended to be installed over the Sayninee stream were seen without
being used by the Contractor.
Risk
1.36.5 The lack of proper monitoring and supervision by the management of MPW could
give rise to the poor performance by contractors during the execution of contract.
Recommendation
1.36.6 The Management of MPW should ensure that contractor be debarred for failing to
perform the contract according to the technical specifications.
Management’s Response
1.36.7 Management did not respond to this observation.
Auditor General’s Position
In the absence of a response from the Management of MPW, we maintain our
recommendation.
1.37 Nyafuah Town to Buchanan Road
Observation
1.37.1 A contract for the emergency rehabilitation of the 107 kilometers road from
Buchanan in Grand Bassa County to Nyafuah Town in Sinoe County was made and
entered into on December 17, 2012 by and between the Government of Liberia,
through the Ministry of Public Works, represented by its Acting Minister Victor B.
Smith and Solid Rock Investment, represented by its President William Seton at a
total cost of Seven Million Two Hundred Six Thousand Six Hundred Fifty Six United
States Dollars (US$7,206,656.00). The parties both agreed that the contract shall be
executed within a period of twenty four (24) calendar months beginning from the
date of signing the contract, December 17, 2012.
1.37.2 According to the technical specifications and the BOQ, it was the requirement of
Solid Rock Investment to perform preliminary works by mobilizing personnel and
equipment. The contractor was required to perform earth works, including clearing
and grubbing the entire road, supply of boulders to stabilize base at major critical
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
48 Promoting Accountability of Public Resources
sections, backfilling and compaction of all critical sections, grading and reshaping of
the entire road length creating ditching and camber, compaction of materials along
the entire road, hauling of selected materials from suitable borrow pit, cut steep hill
and backfill pot holes to a minimum depth of 2 meters and excavate buried logs used
as mat in swampy terrain in the carriage way. Solid Rock Investment was also
required to perform the construction of drainage line which involved the supply and
installation of 24”, 36”, 48”, and 60” diameters reinforced concrete culverts along the
road length and the construction of reinforced concrete bridges including the 32m x
7.5m and 12m x 7.5m with guide rails, construct detour using logs to facilitate
movement of vehicles and pedestrians.
1.37.3 During our field visit, we observed contrary to the technical specification and the
BOQ for the rehabilitation of the Buchanan to Nyafuah Town Road that Log Bridge
was still along the road as no reinforced concrete bridge was constructed at this
location. This log bridge over the Worhn River is used as a detour as the main route
at this location is inaccessible.
1.37.4 Additionally, during our field visit along the road, we observed an incomplete 36” RCP
culvert without head and wing walls at both ends along the Buchanan to Nyafuah
Town Road. Moreover, the 36” RCP culvert was not properly backfilled and
compacted by the contractor, thereby exposing the culvert to early damage. These
deviations by the Solid Rock Investment are in total violation and adherence to the
contractual agreement along with the technical specification and BOQ.
1.37.5 Additionally, the requirement of contractor was to perform quality earth work on the
Buchanan to Nyafuah Town Road as specified in the BOQ such as clearing and
grubbing of entire road length, supply of boulders to stabilize base at major critical
section, backfilling and compaction of all critical sections along road length with
selected laterite, grading and reshaping of entire road length creating ditching and
camber, compaction of materials along the entire road, hauling or selected materials
from suitable borrow pit along the road, cut steep hill and backfill pot holes to a
minimum depth of 2 meters, and excavation of buried logs used as mat in swampy
terrain in the carriage way.
1.37.6 Contrary to this, the contractor failed to adhere to the specification in keeping with
contractual agreement as the inspection revealed Critical Spots (poor earth work)
along the Buchanan to Nyafuah Town road. We observed that the Solid Rock
Investment did not perform grubbing/reshaping of road surface in making sure that
all organic materials were removed and disposed of along the road. We further
observed that the contractor did not use suitable laterites to every location that were
critical to smooth movement and also failed to perform excavation of unsuitable
materials along the Buchanan to Nyafuah Town Road.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
49 Promoting Accountability of Public Resources
Risk
1.37.7 The failure of the MPW Management to conduct proper monitoring and supervision
over contract during the execution phase of contracts may result into the poor
performance thereby denying the achievement of value for money.
Recommendation
1.37.8 The Management of MPW should carry out routine repairs and maintenance of all
roads within the country to avoid major collapse of the road network within the
country.
1.37.9 The Management of MPW should notify the contractor to revisit the work done and
should perform and complete all abandoned or incomplete aspects of the project and
finalize the project as specified in the technical specification.
1.37.10 The Management of MPW should through the Resident Engineer should provide
monitoring and supervision of the road project upon re-commencement of the
project. The monitoring and evaluation section of the ministry should constantly
monitor all projects to ensure quality of work.
Management’s Response
1.37.11 The work is still under contract. The work quality is being monitored by the Ministry
of Public Works. All defects will be corrected prior to issuing final completion
certificate without cost to the client.
1.37.12 The project was 100% completed by strong supervision from MPW.
1.37.13 Besides the R/E supervision, we also have a project engineer who work along with
the contractor ad to verify for payment
Auditor General’s Position
1.37.14 MPW Management’s assertion that the road was 100% complete is inconsistent with
GAC’s findings. During our field visit, we observed that the rehabilitation of the
Buchanan to Nyafuah Town Road was incomplete as Log Bridges were seen at some
locations along the road. Therefore, we maintain our recommendation.
The Special Procurement audit of the Ministry of Public Works
for the Construction of Roads and Bridges Throughout Liberia
for fiscal periods 1 July 2010 to 30 June 2013
50 Promoting Accountability of Public Resources
2 Exhibit
Exhibit 1
Exhibit 1Cont'd