1 A.C. STEENBRINK DUBAI 6 j une 2012 25 NOVEMBER 2014 ATLANTIS II DEEP SEABED MINING SCOPING IDEAS

Transcript of Atlantis II Deep - Sander Steenbrink 20141121

Page 1: Atlantis II Deep - Sander Steenbrink 20141121

\

1

A.C. STEENBRINK

DUBAI 6 june 2012

25 NOVEMBER 2014

ATLANTIS II DEEP SEABED MINING SCOPING IDEAS

Page 2: Atlantis II Deep - Sander Steenbrink 20141121

\

2

INDEX 01 COMPANY OVERVIEW

02 MINING TRACK RECORD

03 SOCIAL RESPONSIBILITY

04 ATLANTIS II DEEP SCOPING

05

06

07

08

09

Page 3: Atlantis II Deep - Sander Steenbrink 20141121

\

3

01. COMPANY OVERVIEW

Page 4: Atlantis II Deep - Sander Steenbrink 20141121

\

4

§ Provide Solution: innovative, sustainable and all-round for infrastructural challenges in the maritime, coastal and delta areas of the world

§ Sustainability and safety are a top priority

§ Wide range of maritime services comprising dredging, dry infrastructure, towage, salvage, transport and heavy lift

§ Founded in 1910

§ Main clients include oil and gas companies, port operators, shipping companies, EPC contractors, government agencies, international project developers, insurance companies and mining firms.

PROFILE

Page 5: Atlantis II Deep - Sander Steenbrink 20141121

\

5

§ Leading global dredging & maritime experts

§ With 11,000 employees and 1,000 vessels

§ Active in 75 countries across 6 continents

§ Customers in Energy, Ports and Infra

§ Headquarters in Papendrecht, The Netherlands

§ Revenue 2013: EUR 3.5 bln

§ Net profit 2013: EUR 366 mln

§ EBITDA 2013: EUR 800 mln

§ Order book EY13: EUR 4.0 bln

§ Listed in AEX Euronext

COMPANY OVERVIEW

Page 6: Atlantis II Deep - Sander Steenbrink 20141121

\

6

§ 1910: est. in Sliedrecht, roots of the Dutch dredging industry

§ 1933: est. Westminster Dredging Company followed by major land reclamation projects in West Africa

§ Post WW II; strong growth related to reconstruction and work in Australia, Canada and Middle East

§ 1953: Delta Works following flood disaster in the Netherlands

§ 80’s and 90’s: Various acquisitions (Breejenbout, Zanen Verstoep, Heinrich Hirdes, Baggermij Holland, Terramare). Also large land reclamation projects such as Chek Lap Kok airport Hong Kong and various developments in Singapore

§ Recent Acquisitions: SMIT Internationale (2010 ), MNO Vervat (2011), Dockwise (2013), Fairmount (2014)

OUR HISTORY

Page 7: Atlantis II Deep - Sander Steenbrink 20141121

\

7

ENERGY

§ EPC contractors, O&G companies, O&G construction companies, national oil companies, mining companies

PORTS

§ Terminal operators, private and independent port authorities, government owned port authorities, shipping companies & agents

INFRA

§ National government agencies, public and private project developers, local and regional government agencies

Transport, Logistics & Installation of floating and fixed structures for E&P, refineries, pipeline & cables; onshore & offshore mining; renewables and IRM

OUR CLIENTS OUR SOLUTIONS

Port design and maintenance; port protection; port infrastructure; port services; waterway construction, deepening and maintenance

Land reclamation; coastal and riverbank protection; road, rail and bridge construction

Page 8: Atlantis II Deep - Sander Steenbrink 20141121

\

8

OUR WORLD

§ Leading global dredging & maritime expert

§ 11,000 employees

§ 1,000 vessels

§ Active in 75 countries across 6 continents

Page 9: Atlantis II Deep - Sander Steenbrink 20141121

\

9

DREDGING & INLAND INFRA

TOWAGE & SALVAGE

OFFSHORE ENERGY

OUR ACTIVITIES

Page 10: Atlantis II Deep - Sander Steenbrink 20141121

\

10

EQUIPMENT OVERVIEW

* barges excluded

Page 11: Atlantis II Deep - Sander Steenbrink 20141121

\

11

Oil & Gas Import/export facilities

Exploration and Production - fixed

Onshore and offshore mining

Pipelines and Cables Exploration and Production - floating

Port development

Renewale energy: Wind, tidal and wave

Port protection Port infrastructure

Port services Land reclamation Coastal Protection Tunnels and bridges

Environmental Services Roads and railways Inland ports and waterways

BOSKALIS SERVICE OVERVIEW

Page 12: Atlantis II Deep - Sander Steenbrink 20141121

\

12

OUR ORGANIZATION

Page 13: Atlantis II Deep - Sander Steenbrink 20141121

\

14

REVENUE BY SEGMENT 2013

(EUR millions)

2012

54% 31%

15%

67%

16%

17%

3,081 3,539

Dredging & Inland Infra Offshore Energy Towage & Salvage

Page 14: Atlantis II Deep - Sander Steenbrink 20141121

\

15

02. MINING TRACK RECORD

Page 15: Atlantis II Deep - Sander Steenbrink 20141121

\

16

ONSHORE AND OFFSHORE MINING

OUR SOLUTIONS

1. Removal of overburden

2. Open pit mining of minerals

3. Deepsea (mineral) mining

4. Ultra deepsea (mineral) mining

5. Oil sands mining and transport

6. Soil separation and remediation by soil washing plant

7. Processing of Mature Fine Tailings through capping and drains

8. Logistal management with floating super pallets

Page 16: Atlantis II Deep - Sander Steenbrink 20141121

\

17 Baggermaatschappij Boskalis bv

OFFSHORE MINING OVERVIEW

20-60

200-500

1000-2000

water depth (m)

SMS deposits

Manganese

Iron sands Diamonds

Rock Phosphates

3000-5000

Page 17: Atlantis II Deep - Sander Steenbrink 20141121

\

18

PROJECT EXECUTION

PROJECT DEVELOPMENT

CONCEPT DEVELOPMENT

MINING TRACK RECORD

Page 18: Atlantis II Deep - Sander Steenbrink 20141121

\

19

BAUXITE MINING LELYDORP I - SURINAM

Page 19: Atlantis II Deep - Sander Steenbrink 20141121

\

20

MOBILIZATION FOR LELYDORP BAUXITE MINING

Page 20: Atlantis II Deep - Sander Steenbrink 20141121

\

21

WORK SEQUENCE LELYDORP I PROJECT

Page 21: Atlantis II Deep - Sander Steenbrink 20141121

\

22 Royal Boskalis Westminster nv

CHATHAM RISE, NEW ZEALAND

CHATHAM RISE ROCK PHOSPHATES

TSHD WITH SUSPENDED PUMP SECTION

Page 22: Atlantis II Deep - Sander Steenbrink 20141121

\

23

GEOPHYSICS

PRODUCTION CALCULATION

COST ESTIMATION

SEPARATION TECHNOLOGY

MARITIME DYNAMICS

MECHANICAL DESIGN

ECOLOGY

HYDROGRAPHIC SURVEY

DREDGING RESEARCH

PROJECT MANAGEMENT

BUSINESS UNIT MANAGEMENT

MULTI-DISCIPLINARY PROJECT TEAM

Page 23: Atlantis II Deep - Sander Steenbrink 20141121

\

24

CHATHAM RISE ROCK PHOSPHATES

§ Mining concept developed based on trailing suction hopper dredger

§ On board separation and controlled return of tailings

§ Mining 250 nm offshore, waterdepth 400m

§ Production capacity 1.5 million tonnes per annum

SUCTION DREDGER: DEEP TRAIL CONCEPT

Page 24: Atlantis II Deep - Sander Steenbrink 20141121

\

25

DEEP TRAIL CONCEPT

Page 25: Atlantis II Deep - Sander Steenbrink 20141121

\

26

§ Remove sandy/silt layer from chalk/ooze

SUCTION SYSTEM - JETTING

Page 26: Atlantis II Deep - Sander Steenbrink 20141121

\

27

§ Vertical and tilted riser

SUCTION SYSTEM VERTICAL HYDRAULIC TRANSPORT

Page 27: Atlantis II Deep - Sander Steenbrink 20141121

\

28

ON BOARD SEPARATION

Page 28: Atlantis II Deep - Sander Steenbrink 20141121

\

29

SEPARATION SYSTEM

Page 29: Atlantis II Deep - Sander Steenbrink 20141121

\

30

CONTROLLED RELEASE OF TAILINGS PLUME MODELLING

Page 30: Atlantis II Deep - Sander Steenbrink 20141121

\

31

CONTROLLED RELEASE OF TAILINGS DIFFUSER DESIGN

Conventional draghead, release above seabed Special diffuser, release at seabed

Page 31: Atlantis II Deep - Sander Steenbrink 20141121

\

32

MINING PATTERN

Page 32: Atlantis II Deep - Sander Steenbrink 20141121

\

33

EXCAVATED DRILL CENTRES

FPV ROCKPIPER

FALL PIPE ROV ROV CONTROLLED GRAB

DEEP WATER EXCAVATION

Page 33: Atlantis II Deep - Sander Steenbrink 20141121

\

34

Ripper draghead

Deep dredging

Blockbuster

Spreader Cable Trencher

EXAMPLES OF INNOVATIVE DEVELOPMENT

Page 34: Atlantis II Deep - Sander Steenbrink 20141121

\

37

CUTTING EDGE TECHNOLOGY

CUTTER TEETH TECHNOLOGY

CSD FOR HARD ROCK DRUMCUTTER DRAGHEAD

DRUMCUTTER ATTACHMENT

Page 35: Atlantis II Deep - Sander Steenbrink 20141121

\

38

BOSKALIS SURVEY

Page 36: Atlantis II Deep - Sander Steenbrink 20141121

\

39

REAL TIME UNDERWATER ACOUSTIC IMAGING

Drill tower positioning (boulder removal)

Removing old blocks for re-use at Maasvlakte 2

Page 37: Atlantis II Deep - Sander Steenbrink 20141121

\

40

03. CORPORATE SOCIAL RESPONSIBILITY

Page 38: Atlantis II Deep - Sander Steenbrink 20141121

\

41

Our CSR policy seeks to achieve a healthy balance between economic value creation on the one hand, and care for the environment and societal and social responsibility on the other by:

1. promoting the safety, personal development and well-being of our employees

2. providing eco-dynamic ‘Building with Nature’ designs

3. ongoing R&D in environmentally friendly equipment and techniques

4. pooling resources with our partners to optimize our sustainable supply chain

5. contributing to local communities

CORPORATE SOCIAL RESPONSIBILITY

Page 39: Atlantis II Deep - Sander Steenbrink 20141121

\

42

Page 40: Atlantis II Deep - Sander Steenbrink 20141121

\

43

Building with Nature (2008-2013)

Page 41: Atlantis II Deep - Sander Steenbrink 20141121

\

44

Paradigm shift

From: Building in Nature Via: Building of Nature To: Building with Nature

• Fit projected infrastructure into dynamics of local system • If possible, utilize power of natural processed • Promote development of new nature if possible

Page 42: Atlantis II Deep - Sander Steenbrink 20141121

\

45

PILOT SAND ENGINE DELFLAND

Building with Nature Successes

Page 43: Atlantis II Deep - Sander Steenbrink 20141121

\

46

Building with Nature Programme Te

mpe

rate

Tr

opic

al

soft solutions hard solutions

focus on ecosystem functioning

focus on infrastructure development

Eastern Scheldt Underwater garden

Singapore ‘rich levee’

ES: oyster reefs as shore protection

BwN design Singapore Labrador Park

IJsselmeer foreshore nourishment

Pilot Sand Motor Delfland Coast

Coastal protection Mangroves

Coastal protection Sea grass

Page 44: Atlantis II Deep - Sander Steenbrink 20141121

\

47

LANDSCAPING OF SAND MINING AREAS

Building with Nature Successes

Page 45: Atlantis II Deep - Sander Steenbrink 20141121

\

49

FUTURE CASES: HYBRID ENGINEERING (INDONESIA)

Page 46: Atlantis II Deep - Sander Steenbrink 20141121

\

50

Building with Nature Spin-off (1)

Page 47: Atlantis II Deep - Sander Steenbrink 20141121

\

51

• Hands-on collaboration and knowledge sharing between industry / consultants

• Improved understanding of dredging processes results in more realistic environmental constraints on projects

EDUCATED CONSULTANTS

Building with Nature Spin-off (2)

Page 48: Atlantis II Deep - Sander Steenbrink 20141121

\

52

• Various strategic R&D programs underway

• STW NatureCoast (12 PhD, 3 postdoc) • NWO Building with Nature (4 PhD, 2

postdoc)

• Building with Nature in curriculum at TU Delft / Wageningen UR

• Many BSc/MSc students from TUD / WUR / UT / HZ / HTS R’dam / …

• Excellent access to young professionals

RESEARCH / EDUCATION

Building with Nature Spin-off (3)

Page 49: Atlantis II Deep - Sander Steenbrink 20141121

\

53

Attitude Change

Page 50: Atlantis II Deep - Sander Steenbrink 20141121

\

54

• Decommissioning and opportunities for artificial reef construction

• Rock protection of e.g. pipelines

• Underwater sound during construction and operation (e.g. wind turbines)

• Gravity Based Structures

• Turbidity

• Revetment works (‘imported’ materials)

…and many more….

ISSUES IN OFFSHORE

Building with Nature Offshore

Page 51: Atlantis II Deep - Sander Steenbrink 20141121

\

56

UNDERWATER SOUND AND MARINE MAMMALS

Building with Nature Offshore

Page 52: Atlantis II Deep - Sander Steenbrink 20141121

\

57

§ Largest coral reef relocation company in the world

§ We have a factory making geo-hooks, which can be used in mangrove creation

§ We wrote the book on environmental dredging

§ We are CO2 certified in the Netherlands & the UK saving us up to 10% on every contract

§ We are certified in marine mammal observation

§ First dredging company writing a CSR report

OUR COMMITMENT

Page 53: Atlantis II Deep - Sander Steenbrink 20141121

\

62

04. ATLANTIS II DEEP SCOPING

Page 54: Atlantis II Deep - Sander Steenbrink 20141121

\

63

MINING PROJECT PREPARATION

Concept Engineering

Basic Engineering

Detailed Engineering

Construction & Commissioning Operation

Scoping Preliminary Feasibility Feasibility

JORC PROJECT PHASES

ENGINEERING AND CONSTRUCTION

OPTION 1 (hydraulic)

OPTION 2 (mechanical)

Page 55: Atlantis II Deep - Sander Steenbrink 20141121

\

64

OFFSHORE MINING PROJECT DEVELOPMENT

RESOURCE ANALYSIS GEOTECHNICAL ASSESSMENT

MINING FUNCTIONS Excavation/extraction

Vertical transport Separation

Tailings return Transhipment

Transport Offloading Processing

MINING PLAN Workability analysis

Production estimation Cost calculation

MINING EQUIPMENT Vessel requirements

Vessel selection or design Equipment design

ENVIRONMENTAL MANAGEMENT

PROJECT FINANCE

Page 56: Atlantis II Deep - Sander Steenbrink 20141121

\

65

WAVE CONDITIONS ATLANTIS II DEEP

Page 57: Atlantis II Deep - Sander Steenbrink 20141121

\

66

WAVE CONDITIONS - WORKABILITY

Page 58: Atlantis II Deep - Sander Steenbrink 20141121

\

67

ISSUES § Excavation (unconsolidated sediment) § Maneuvering mining vehicle § Powering § Vertical transport § VIV § Wear § Active hydrothermal regime (salinity and

temperature) § Bathymetry measurements and underwater

positioning § Wave conditions § Turbidity generation and plume development § Underwater sound

MINING FUNCTIONS

Page 59: Atlantis II Deep - Sander Steenbrink 20141121

\

68

SEABED VEHICLE MOTION

Page 60: Atlantis II Deep - Sander Steenbrink 20141121

\

69

MINING VESSEL OPERATIONS

Page 61: Atlantis II Deep - Sander Steenbrink 20141121

\

70

§ Lowering skips − Travel time approx 6200 sec

§ Filling skips − Skip cycle 7.5 min based on Terra Nova

§ Lifting skips − Travel time approx 11700 sec

§ Sailing loaded − 65 nm @ 10kn = 6.5 hrs

§ Offloading

§ Sailing empty

§ Skips volume 175 m3

§ Grab volume 10 m3

§ Vessel dimensions 150x23m

§ Simultaneous skip and grab operation, single vessel

§ USBL transponder mounted on skip to meet with grab / spider frame. Acoustic and/or video camera as needed

§ Annual production 416 ktpa

KEY STEPS