Atlantic Street Bridge Project Update CTDOT Project Nos. 135-301 & 301-163 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement | Track & Station Infrastructure Improvements City of Stamford www.AtlanticStreetBridge.com Spring 2019

Transcript of Atlantic Street Bridge Project Update Spring...

Atlantic Street Bridge Project Update CTDOT Project Nos. 135-301 & 301-163 (Phase 2)

Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement | Track & Station Infrastructure Improvements City of Stamford www.AtlanticStreetBridge.com

Spring 2019

CONNECTICUT DOT PROJECT TEAM

CTDOT District 3 Office:

Domenic LaRosa, P.E. - District Engineer Matthew S. Cleary, P.E. - Assistant District Engineer John Antonucci, P.E. - Supervising Engineer Mohammad Masoud - Project Engineer

ATANE Engineers P.C. (Construction Engineering & Inspection):

Kevin Conroy, P.E. - Resident Engineer

Atlantic Street - Phase 2 Improvements

Replace

MNR Bridge

Lower/Widen

Atlantic St

Extended

Platform

Catenary

Replacement

Construction Track #7

Construction

Track #7

Platform &

Stairs

5

4

3

2

``

1

2

3

4

5

1

2019 Construction Milestones

• New Center Pier Installed

• South Assembly Area Bridge Decks Constructed

• Construct Abutments and Bearings to Accept New

Superstructure

February 2019-June 2019: Atlantic Street Underpass Closed

• Old Bridge Demolished in Stages

• Two Track Rail Service Maintained

• New Bridge Spans Rolled into Place via SPMT

• All Tracks Restored after 9 Days

June 28-July 8, 2019: S. State Street Closed/Detours

South Assembly Area

July 8-Sept. 9, 2019 Atlantic St. Lowered/Roads Re-Open

• Atlantic Street Lowered to Increase Bridge Clearance

to 14’ 6”

• Atlantic Street widened with dedicated turning lanes

• Complete All Paving, Drainage, Lighting, Signals,

Markings, Signage and Sidewalks

SPMT Transports Bridge Into Place

Current Schedule

ACTIVITY DATES

JUMP SPAN INSTALLATION COMPLETE

ATLANTIC STREET CLOSED COMPLETE

CENTER PIER CONSTRUCTION COMPLETE

NEW BRIDGE ROLL-IN JUNE 28 – JULY 8, 2019

LOWER ATLANTIC STREET JULY 8 - SEPT 7, 2019

REOPEN ATLANTIC STREET SEPTEMBER 7, 2019

PHASE 2 COMPLETE NOVEMBER 2020

Bridge Roll In : June 28 - July 8, 2019

• Roll-in via SPMT over a 9 day

period

• South side decks will be

installed first with the demo

of Tracks 1, 2, & 4

• Tracks 3 & 5 remain in service

• Rail service restored to

Tracks 4 & 2 on July 2; work

continues on the Tracks 1, 3

& 5

• Traffic Detoured around site

• Rail service restored July 8 to

Tracks 1, 3, 5

Bridge Location

SPMT Route

North Assembly Area

South Assembly Area

Atlantic Street Construction Detours June 28th – September 9th, 2019

Road Closures:

• South State Street

(Guernsey Ave to Exit 8 off-ramp)

• Atlantic Street

(Dock St to N. State St)

Detours:

• Guernsey Avenue

(NB to N. State Street ONLY)

• Washington - Henry - Canal St.

• Dock Street / North State Street

• Station Place North Side Station Drop Off Open

Enter via Washington Blvd; Exit Via Guernsey Ave. to N. State Street

Pedestrian Detour June - September 2019

Sidewalk Closures:

• Atlantic Street (btw N. and S.

State St & Dock St)

Detours:

• Guernsey Avenue

• Via Train Station

Tunnel/Overpass

• Station Place

South Side Bridge Roll In Schedule June 28 - July 2, 2019

June 28:

• Tracks 4, 2, & 1 Out of service

• South State Street Closed

June 29:

• Demo Tracks 4, 2, & 1; Remove

Temporary Work

June 30: Erect Pier Columns/Set Bearings

• Transport and Set West Track 4/2 Span

• Transport and Set East Track 4/2 Span

July 1: Install New Ballast and Rail

July 2: Return Tracks 4 & 2 to service;

South Side Roll-in

Demo Tracks 1, 2 & 4

Stage Closure Walls

Train Service on 5 & 3

July 2(cont.):

• Tracks 5, 3, & 1 Out of service

• Demo Tracks 5, 3, & 1; Remove

Temporary Work

July 3: Demo Fascia

July 4:

• Erect Pier Columns/Set Bearings

• Transport & Set West Track 1/3

Span

• Transport & Set East Track 1/3

Span

North Side Roll-in

Stage Closure Walls Ties, Rails, Ballast

Train Service on 4 & 2

North Side Bridge Roll In Schedule July 2 – July 4, 2019

July 5: Install New Ballast and Rail

July 6:

• Erect Pier Columns/Set Bearings

On Abutments

• Transport & Set West Track 5/7

Span

• Transport & Set East Track 5/7

Span

July 7:

• Install New Ballast and Rail

July 8:

• Tracks 1, 3, 5 Returned To

Service

North Side Bridge Roll In Schedule July 5 – July 7, 2019

Lower Atlantic Street: July 8-September 8, 2019

Atlantic Street will be widened for 3

lanes NB/3 lanes SB with dedicated

turning lanes and lowered providing

clearance of 14’6”.

Roadway, pavement markings,

illumination, signage and, brick pavers

completed.

All roads re-opened by Sept. 8, 2019

Catenary, Platform & Track 7 Construction Sept 2019 – Nov 2020

Stage 1 - Completed During Phase 1

South Side Catenary Foundations and

Poles (Mainline, East and West Yard)

Stage 2 - North Side Foundations,

Poles and Trusses, Drop Tubes, Truss

Extensions

Stage 3 - Install Crossover Wires &

Removal of Existing Catenary Trusses

Stage 4 - Track 7 Track & Platform

Construction, Catenary, and

Crossovers

Current Schedule

ACTIVITY DATES

JUMP SPAN INSTALLATION COMPLETE

ATLANTIC STREET CLOSED COMPLETE

CENTER PIER CONSTRUCTION COMPLETE

NEW BRIDGE ROLL-IN JUNE 28 – JULY 8, 2019

LOWER ATLANTIC STREET JULY 8 - SEPT 7, 2019

REOPEN ATLANTIC STREET SEPTEMBER 7, 2019

PHASE 2 COMPLETE NOVEMBER 2020

Public Outreach and Social Media Outlets

Regular Updates:

Web: http://atlanticstreetbridge.com

Facebook: atlanticstreetbridge

Twitter: @Atlantic_Street

Outreach Events:

Stamford Transportation Center

Stakeholder Meetings

Local Business Door Knocking

Flyers and Signage

Sign up for Email Announcements:

[email protected]

Atlantic Street Bridge Project Update CTDOT Project Nos. 135-301 & 301-163 (Phase 2)

Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement | Track & Station Infrastructure Improvements City of Stamford www.AtlanticStreetBridge.com

SPRING 2019