This presentation will take 40 minutes and feel free to ask questions at any time
© Acando
One of the leading actors on the ERP-market in the
Nordics with approx. 220 SAP-consultants
• Appr 120 consultants in
Sweden
• 40 consultants in Stockholm
• 40 consultants in Göteborg
• 15 consultants in Malmö
• 25 consultants in Västerås
• 60 consultants in Germany
• 40 consultants in Finland
Service Partner
Channel Partner
Certified PCoE
© Acando
Management Consulting Enterprise Solutions Digital Solutions
ALM Concept
Asset Life Cycle Management
13/11/2014
© Acando
ALM Background
We have identified the most common issues...
11/09/20148
• Fragmented system landscapes without
structured, controlled or missing data
transfer between different systems.
• Fragmented processes, without
consideration of the core process
and/or missing optimization of the
investment lifecycle.
• Missing connections between Assets and
Plant Maintenance
• Missing total control of
cost the structures
• Fragmented information.
© Acando
Asset Lifecycle Management by Acando
11/09/20149
The ”ALM by Acando” concept are built upon a
complete view and will give the business an
increased efficiency for the asset life cycle.
© Acando
ALM by Acando
This is what it´s all about!
11/09/201410
efficiency
asset intensive
various viewpoints
core process
businees driven
total process perspective
applied at any point
© Acando
ALM by Acando
Business advantage
11/09/201411
By considering all sub processes in an asset total lifecycle process, there will be
an structured and optimized overall asset efficiency with improved business case
for the investment.
© Acando
ALM by Acando
Customer Benefits
11/09/201412
Improved Overall Cost Control
Improved information
base for decisions
Improved utilization of your
investment in SAP System
Improved support from
your SAP System in
different areasSecure your
investments over time
© Acando
ALM by Acando
The typical business
11/09/201413
• The ALM Concept primary applies to following businesses :
• Capital intensive
• Asset intensive
• Investment intensive
© Acando
ALM by Acando
Possibilities
11/09/201414
• The concept can be applied from various viewpoints and will support your
business model.
• Provides the process perspective of the complete asset life cycle.
© Acando
ALM by Acando
Feasibility study
11/09/201415
• The ALM concept gives the opportunity to address the processes, from a
prioritized point of view, towards any of the sub-processes.
• The ALM concept will clarify and prioritize the areas of highest potential for
improvements in different aspects.
© Acando
ALM by Acando
Method
11/09/201416
• An analysis is made through one or several work-shops and interviews.
• This results in a report with a road-map for the steps to come.
• The solution is based on the main process but with technical solutions
according to the current ERP system.
Preparations Analyze Report Prioritize
© Acando
ALM by Acando
Success factors
11/09/201418
• Delivered by senior resources with excellent business experience as well as
deep ERP competence.
• Ensures a business driven solution rather than an IT solution.
Business
Finance
Technique
Vattenfall VattenkraftBU Hydro
En presentation av Vattenfalls vattenkraftverksamhet
SAPSA 2014-11-13
Lars-Åke Engström
+46 76 78 77 147
BU Hydro i siffror
BU Hydro är en del av Vattenfall Region Norden
Antal anställda ~ 500 i Norden
Produktion och kapacitet
Hydro Norden 30 - 35 TWh/år – 8300 MW
Investeringar
Hydro Norden 1,2-1,5 miljarder SEK/ år. Totalt 13 miljarder SEK under 2013-2023
0
20
40
60
80
100
120
140
160
180
1970
1972
1974
1976
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
Gas
Kondenskraft
Kraftvärme
Kärnkraft
Vindkraft
Vattenkraft
Elproduktion [TWh]
Vattenkraft – en ryggrad i svensk elproduktion
BU Hydro i Norden
- Vattenfall är en av de ledande
vattenkraftproducenterna i Norden och
den tredje största i Europa
- I Sverige och Finland finns det 110
större och mindre vattenkraftverk
- Vattenkraften levererar viktiga
funktioner:
• Förnybar el
• Reglerkraft för att klara
elanvändningen samt
vindkraftens variation54 storskaliga
vattenkraftverk
Skellefte älv
Dalälven
Göta älv
Ume älv
Ångermanälven
Indalsälven
Stockholm
Lule älv
Management Consulting Enterprise Solutions Digital Solutions
Vattenfall Hydro
Asset Life Cycle Management
2014-11-13
© Acando
Vattenfall Hydro
Background
11/09/201424
• After a review and analysis of Vattenfall Hydro Nordic’s system landscape (approx 60 IT
systems) the IT department came to the conclusion that several IT systems are
redundant, i.e. they perform activities that could be performed in SAP.
• Vattenfall Hydro does not utilize SAP in an optimal way and master data is stored in
several places and is unnecessarily shuffled (manually or automatic) between different IT
systems.
© Acando
Vattenfall Hydro
Background
11/09/201425
• A pre study was made that pointed out the following areas in SAP to address
while waiting for a decision regarding the global group template:
• Implementation of Down time/ Shut Down Planning leads to a possibility to close
down external systems
• Optimization of preventive maintenance which can lead to replacement of external
system
• Pre study of PPM, Project Portfolio Management, can replace external system
• Pre study of Supply Chain functionality regarding central warehouse and
development of the material master.
• Establish and implement the refurbishment process.
© Acando
Vattenfall Hydro, “Reorder of the PM technical structure”
Purpose
11/09/201426
• The purpose of the project was to develop and decide on a new simple and
transparent technical asset structure, with clear definitions and master data
objects, that is built on SAP standard technique and that will last into the future.
• The project was prioritized as a starting point and estimated to get the fastest
result and is expected to “trigger” other processes/projects such as:
• Supply Chain
• Shut Down Planning
• Preventive Maintenance
• PM order process (planning)
© Acando
Vattenfall Hydro, “Reorder of the PM technical structure”
As is To Be
11/09/201427
• From
• An technical structure that:
• Is experinced to be hard to understand, both by internal and external users. Thus generating extra
work for projects, on-going activities and support/administration.
• Is not able to handle all parts of a water power plant whitout complicated guidelines for adjustments
and interpretations.
• Is hard to apply which leads to large quality deficiencies in master data.
• Has a technical structure with functional locations on a very detailed level and a programmed
functionality that is not SAP standard.
• Has a built-in logic that makes it impossible to implement the recurring changes in the power plants.
• Makes it difficult to develop maintenance by adding other PM-functionality in an efficient way.
© Acando
Vattenfall Hydro, “Reorder of the PM technical structure”
As is To Be
11/09/201428
• To
• An technical structure that:
• Is clear and easy to understand and enables an efficient work with power plant changes, as well in on-
going activites as in projects.
• Can handle all parts of a water power plant without adjustments and interpretations.
• Is easy to apply which leads to higher quality on master data.
• Is built on SAP standard functionality regarding the technical structure.
• Is adapted to an ”eventual” future merge to new technical platform.
• Will enable efficient processes by using SAP standard functionality (eg preventive maintenance,
material and resource planning etc)
• Will enable a one-to-one connection between the technical and financial asset registry, which will
enhance the quality in the financial monitoring.
© Acando
Vattenfall Hydro, “Reorder of the PM technical structure”
The project
11/09/201429
• Project goals
• To establish a Master Data Management team
• Extend the outcome of an investment project regarding documentation, technical
structure, capitalization of assets
• Two pilot activities
• Implement the outcome of an investment project according to the new MDM
process.
• Define, develop and implement a model for migration of existing technical structures
by SAP standard, plant by plant
© Acando
Vattenfall Hydro, “Reorder of the PM technical structure”
A project aligned to Acando:s ALM concept
11/09/201430
• By considering the total life cycle process and prioritizing
• Investment process
• Activation of the project
• Maintain
• Modify
MDM
koncept
Final Asset
Project
handover
Maintenance
MDM
koncept
© Acando
Vattenfall Hydro, “Reorder of the PM technical structure”
Project summary
11/09/201431
• The overall goal with the project is to reach a level of understanding how to extend the
usage of a more “total” SAP solution and to build the foundation for further process
development within the EAM area. This project is just the start of the journey towards
the overall goal.
• The project is initialized by using the Acando ALM concept and this will help the Hydro
organization to increase the business benefits of SAP and in addition develop the
organization.
• The project has been prioritized as a very important project by VF Hydro management.
• Due to the fact that the organization is large, complex and geographically scattered it is
likely that the time line for the roll out will be extended.
• We have now reached approximately 70% of the project and are confident that this will
be a success story.
© Acando
Management Consulting Enterprise Solutions Digital Solutions
Tommy [email protected]