Assessing the Costs Attributed to Project Delays · Assessing the Costs Attributed to ... 2009 and...

37
Assessing the Costs Attributed to Project Delays Texas Transportation Institute The Texas A&M University System College Station, Texas September 2011 0-6581

Transcript of Assessing the Costs Attributed to Project Delays · Assessing the Costs Attributed to ... 2009 and...

     

  Assessing the Costs Attributed to Project Delays

Texas Transportation Institute

The Texas A&M University System College Station, Texas

September 2011

 

0-6581

     

Assessing the Costs Attributed to Project Delays 

 

by 

 

Curtis Beaty, P.E. 

Associate Research Engineer 

 

David Ellis, Ph.D. 

Research Scientist 

 

Jon Epps, Ph.D., P.E. 

Executive Associate Director 

 

Brianne Glover 

Associate Transportation Researcher 

 

Nicolas Norboge 

Assistant Transportation Researcher 

 

and 

 

Bill Stockton, Ph.D., P.E. 

Executive Associate Agency Director 

 

Project 0‐6581 

 

Performed in cooperation with the 

Texas Department of Transportation 

 

 

September 2011 

 

TEXAS TRANSPORTATION INSTITUTE 

The Texas A&M University System 

College Station, Texas 77843‐3135 

    P a g e  | 1 

EXECUTIVE SUMMARY 

All departments of transportation (DOTs) face delays on highway projects. They often have anecdotal accounts of 

the significant financial impact that the delay of a highway project had on project costs, local businesses and 

commuters, and other users of the highway. But in many cases hard data on the financial impact are lacking. This 

project for the Texas Department of Transportation (TxDOT) aims to develop a simple but sound methodology for 

estimating the cost of delaying most types of highway projects. The project draws on two main resources to 

produce reliable estimates of impacts: 

Existing data from projects completed in fiscal year (FY) 2009 and reported in TxDOT’s Design Construction 

Information System (DCIS). 

Methodologies developed for other applications that can be applied to estimating the cost of project delay. 

DelayduringProjectPhases

Delay can occur in any phase in the project: 

Planning/scoping phase: Delay can be significant when litigation is initiated. 

Development phase: Permitting (environmental, fish and wildlife, railroad, etc.), right‐of‐way acquisition, and 

utility agreements can be significant causes of delay. 

Contracting phase: Generally, this phase has less incidence of delay but can still have issues. 

Construction phase: This phase has numerous opportunities for delay and is often the delay most visible to 

the public. 

Project delay almost always has costs associated with it, which is not to say that all project delay is a waste of time 

and public money. In many instances of project delay initiated by TxDOT, the reason for the delay is to make an 

improvement in the design or construction of the project that will ultimately deliver better value to the public.  

EstimationModel

This project developed a simplified model that incorporates 16 user‐controlled variables and produces estimates of 

the effect of project delay on personal and commercial travel and the cost to the general economy. Three projects 

of varying size were used as examples: 

The “small project” illustrates delay to an $11.4 million, four‐lane roadway project in a rural setting. The 

project’s 33‐month delay produced an additional $3.5 million cost to the economy, or $96,000 for every 

month of delay.  

The “medium project” illustrates delay to a $49.6 million, urban freeway project. The project’s 58‐month 

delay produced an additional $17.8 million cost to the economy, or almost $300,000 for every month of 

delay.  

The “large project” illustrates delay to an $82.2 million interstate highway improvement in a large metro 

area. The project’s 11‐month delay produced an additional $5.1 million cost to the economy, or $447,000 

for each month of delay. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

     

CaseStudies

Finally, the report includes three atypical case studies that demonstrate a range of delay issues, all with costs 

attached including litigation costs and termination fees paid to contractors. These costs are in addition to the types 

of costs calculated in the model discussed above. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

     

PURPOSE AND SCOPE OF THE REPORT 

This report helps identify the costs of delays to completing roadway projects, and a methodology for estimating 

those additional costs to the state and to users. The report also addresses three basic elements related to project 

delay: 

Definitions and types of project delay. 

Methodology for estimating project‐specific delay costs. 

Case studies that demonstrate the application of the methodology. 

For this report, the Texas Transportation Institute (TTI) examined recent TxDOT projects that meet the following 

requirements: 

Construction projects (e.g., new construction, reconstruction, and rehabilitation). 

Projects that had sufficient data requirements in order to be analyzed (e.g., projects in metropolitan 

planning organization [MPO] jurisdictions with readily available travel demand data). 

The following types of transportation projects were excluded from this analysis: 

Projects that experienced delays due to lack of funding. 

Transportation projects with a total project investment of less than $7 million. 

Maintenance projects. 

 

In most cases examined in this study, delay occurred because the project missed a milestone according to the project schedule dates established by the project engineer and the respective TxDOT district. This study did not examine the scheduling process that occurs during the planning/scoping phase of the project life cycle to see if that aspect of a project (i.e., overly optimistic schedules) might be an inherent source of delay.  

TERMINOLOGY 

The following glossary defines certain terms and phrases used within this report. It also clarifies what is and is not 

included in the various types of costs associated with project delays. Appendix A contains a list of acronyms used in 

this document. 

Direct Costs of Project Delay—actual out‐of‐pocket costs borne by any stakeholder affected by a delay in project 

delivery. Most of the direct costs accrue to TxDOT and, therefore, are passed on to the public in the form of less‐

efficient use of taxpayer resources. 

Indirect Costs of Project Delay—hidden costs that are borne by stakeholders, often a much greater amount than 

the direct costs of project delay. Indirect costs include: 

Wasted traveler fuel and time. 

Economic impacts in the vicinity of the project. 

Loss of business efficiency for those businesses that rely on the transportation system for their 

productivity.  

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

     

Project Delay—In estimating the difference in planned and actual project completion date, this report assumes 

that the planned completion date is the date from the notice to proceed plus the number of days allowed for 

construction. The actual completion date is when the project is open for public use. 

Project Stages—usually divided into four distinct stages: planning, development, contracting, and construction. 

Delays that occur during the various stages typically affect different stakeholders (e.g., the state, contractors, 

businesses, or the public) in different ways. Once a project has been identified, its life cycle includes defined stages 

and milestones. Figure 1 illustrates the general project stages, basic activities that occur in each stage, and some of 

the major milestones. 

 

Figure 1. Life Cycle of a Typical Roadway Project.1 

                                                                 

1 C.A. Quiroga, E. Kraus, J.H. Overman, and N.A. Koncz. Integration of Utility and Environmental Activities in the 

Project Development Process. Report 0‐6065‐1, Texas Transportation Institute, http://tti.tamu.edu/documents/0‐

6065‐1.pdf. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | 5 

WHO BEARS THE COST OF PROJECT DELAY? 

Ultimately, the public bears the cost of project delay. 

Three major groups of stakeholders are affected by project delay: 

The agency. 

The public. 

Contractors (and their suppliers). 

Figure 2 provides a conceptual schematic diagram of how direct and indirect costs at various stages of the project 

timeline can affect these stakeholders.  

The costs of project delays can be classified as either direct or indirect costs to the public, the agency, or 

contractors. Some costs to the agency or contractors associated with contract delay are recoverable by the entity 

incurring the cost; others are not. As shown in Figure 2, ultimately, all costs are eventually borne by the public. 

Direct costs are divided into three categories: 

1. Agency costs. The cost cited in Figure 2 is the expense associated with additional engineering services. 

These costs may or may not be recoverable. In some cases, the agency can recover the costs if they are 

due to errors by others. If the costs are not recoverable, the expense becomes an indirect cost that is 

ultimately paid by the public. 

2. The cost in extra fuel and time wasted by the public because of project delay. The public is not 

reimbursed for that cost. 

3. Contractor costs. The contractor absorbs costs due to unproductive labor (e.g., the contractor is told by 

the agency or some other authority to cease construction or has to, for some other reason, pay labor 

costs on a standby basis). The agency may reimburse the contractor. But for the agency, the cost is likely 

not reimbursable and is ultimately borne by the public. If the cost is not reimbursable to the contractor 

directly, it becomes an indirect cost to the contractor that is ultimately transferred to the agency or the 

public in some other form (e.g., higher contract prices in the future).   

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | 6 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 2. Stakeholder Impacts of Direct and Indirect Project Costs.

Who Pays?Is it Reimbursable?Who Pays?Is it 

Reimbursable?Who Pays?Is it Reimbursable?Who Pays?Type of Cost

Cost of Project Delay

Direct Cost

Public (Fuel/Time)

No

Agency (Engineering 

Costs)

Yes Contractor Yes, Indirectly Agency No Public

No, Becomes Indirect

Public

Contractor (Unproductive 

Labor)

Yes Agency No Public

No, Becomes Indirect

Agency No Public

Indirect Cost

Public (Economic Loses)

No

Agency (Reallocation of Funds)

No Public

Contractor (Opportunity 

Cost)Yes Agency No Public

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

      P a g e  | 7 

CoststothePublic

Direct and indirect costs paid initially by the agency are ultimately borne by the public. For example, when a 

project is delayed early in the process, engineering, right‐of‐way, material, labor, or other cost elements may 

increase because of the delay. This is a direct cost of project delay that is ultimately paid by the public. 

Additionally, because TxDOT has a finite supply of funds with which to operate in a given year, the increased costs 

will likely mean that other previously scheduled and budgeted projects will have to be postponed and their 

benefits delayed. These are considered indirect costs to the public. 

CoststoTravelersintheAffectedCorridor

Two of the most recognized costs to the public are associated with wasted time and fuel cost. We all place a value 

on our time. When a project is delayed and improvements to the particular corridor postponed, the benefits 

associated with that improvement (e.g., higher speeds and shorter commute times) are not realized. Furthermore, 

with the slower commute speeds, fuel efficiency may be reduced, resulting in higher fuel costs for travelers. 

CoststoBusinessesandTheirConsumers

One of the most important cost aspects of project delay is the impact on businesses and consumers. Businesses 

are affected by roadway congestion in much the same way as motorists. As speeds are reduced, operating costs 

(i.e., driver time, vehicle operating costs, fuel costs, etc.) are increased. Ultimately, these costs are passed on to 

the consumer. But there can be other, more pervasive impacts as well. 

Almost all surveys that ask businesses about factors that influence location decisions show similar results. They 

indicate that businesses most value the following when deciding where to locate a facility: 

A fair and reasonable tax system. 

An educated and available workforce. 

Access to markets.  

Reduced mobility affects businesses in two ways: it reduces the supply of qualified workers who live within a 

reasonable commute distance, and it increases the cost of accessing markets, causing increased shipping costs for 

both raw materials and finished products. 

With respect to labor markets, as mobility is reduced and commute times lengthen, the labor pool within a 

one‐hour commute to a particular location is reduced. To attract a wider number of potential employees, some 

companies may find it necessary to offer higher wages to offset the higher costs of commuting. If they do, those 

higher wages are potentially reflected in higher finished product cost, hindering the company’s ability to compete 

in a market. If the costs of higher wages are not reflected in higher product costs, then income to the company’s 

shareholders is reduced.  

Similarly, reduced mobility affects the cost of finished goods when fuel cost, driver time, and vehicle‐operating 

costs are increased because of lower speeds on the roadways.  

CoststoContractors

Contractor costs also increase because of project delay. If a project is delayed after a contractor has mobilized a 

workforce and obtained equipment, consumables, and other materials, the contractor must often absorb those 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

      P a g e  | 8 

costs. This reduces income to the company and to its shareholders. To the extent that those costs are recoverable, 

they are passed on to consumers during a subsequent project. 

In addition, the uncertainty associated with project delays can impede a contractor from bidding on other projects. 

These lost opportunities can reduce competition, which may result in higher construction bids on other projects. 

Conclusion

With few exceptions, the public ultimately bears the cost of delays—traveler costs, added transportation costs in 

retail products, loss of business efficiency (resulting in higher costs and lower profits), and fewer public (TxDOT) 

dollars available to spend on a variety of project needs. 

SAMPLE METHODOLOGY FOR ESTIMATING COST IMPACTS 

OF PROJECT DELAY 

TypesofExampleProjects

Table 1 shows three different example projects: 

“Small projects” range in cost from $7 million to $20 million. 

“Medium projects” range in cost from $20 million to $80 million. 

“Large projects” cost more than $80 million. 

The small project illustrates the costs associated with a four‐lane roadway in a rural setting. In this example, the 

roadway is a 2.7‐mile‐long widening project on FM 1488 in the Houston District. The project stretched from just 

east of SH 242 to just west of IH 45. The two‐lane roadway was widened to a four‐lane divided roadway. The 

project began in March 2009 after 33.5 months of delay. The cost associated with this delay is estimated at 

$96,000 per month, or a total of more than $3.5 million. 

The medium project depicts the cost associated with an urban freeway project, in this instance a 2.6‐mile‐long 

widening project on US 59 in the Houston District. The project segment stretched north of FM 1314 to just north of 

Northpark Drive. The freeway was widened to consist of eight main lanes with two three‐lane frontage roads. After 

almost five years of delay, the project began in August 2002. The estimated cost of delay per month was $297,000 

per month, or a total of $17.8 million over the entire delay period.  

The final example is the large project, showing costs associated with an interstate project in a large metro area—

an interchange reconstruction project at IH 10 and IH 410 in the San Antonio District. The 1.5‐mile‐long project was 

from south of Callaghan Road to south of North Crossroads. This project began in July 2002 and experienced an 

11‐month delay during construction. The cost of delay per month was an estimated $447,000 per month, or 

$5.1 million for the entire 11‐month period. 

   

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

      P a g e  | 9 

Table 1. Sample Costs to the Public Resulting from Project Delays. 

Estimated Cost of Project Delay 

Project Description 

Project‐Related Variables 

   Small Project  Medium Project  Large Project 

Project Cost (Millions)  $11.4  $49.6   $82.2 

Total Months Project Was Delayed  33.5  58.8  11.1

Change in Highway Cost Index (HCI) (during Delay)  11%  29%  3%

Travel‐Related Variables 

Length of Project  2.7  2.6  1.5

Average Daily Traffic—Before Improvement  21,000  91,000  158,000

Average Daily Traffic—After Improvement  26,000  99,000  196,000

Travel Speed—Before Improvement  46  58  59

Travel Speed—After Improvement  50  60  61

Percent Trucks—Before Improvement  4.5%  10.0%  3.9%

Percent Trucks—After Improvement  4.5%  10.5%  3.9%

Commonly Used Assumptions 

Persons per Vehicle  1.25  1.25  1.25

Value of Time—Cars  $16.28  $16.28   $16.28 

Value of Time—Trucks  $107.42  $107.42   $107.42 

Cost of Fuel—Cars  $3.78  $3.78  $3.78

Cost of Fuel—Trucks  $3.95  $3.95  $3.95

Return on Investment Associated with Economic Impacts 

8.0%  8.0%  8.0%

Monthly Cost of Project Delay 

Wasted Time from Project Delay—Personal  $26,363  $31,248   $63,902 

Wasted Fuel from Project Delay—Personal  $19,260  $8,510   $7,421 

Wasted Time from Project Delay—Commercial  $6,557  $18,410   $13,689 

Wasted Fuel from Project Delay—Commercial  $1,094  $3,334   $1,413 

Total Direct Cost to Travelers  $52,180  $58,167   $85,012 

Construction Cost Increase per Month (based on HCI)  $32,957  $191,956  $283,624

Sub‐total, Direct Costs  $85,137  $250,123  $368,636

Economic Impact of Project Delay  $10,841  $47,170  $78,172

Total Cost of Project Delay per Month  $95,978  $297,293  $446,808

Total Cost of Project Delay  $3,551,431  $17,764,387   $5,127,080

 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

     P a g e  | 10 

DiscussionofMediumProjectExample

Using the medium project as an example illustrates how project delays can ultimately cost the public. In this 

example, a $49.6 million project was delayed a total of 58.8 months. The following conditions on the roadway 

were present: 

91,000 vehicles in average daily traffic. 

Commercial trucks making up 10 percent of vehicles. 

1.25 persons per automobile. 

58 miles per hour average speed before the improvements. 

60 miles per hour average speed after the improvements. 

a 29 percent increase in the price of construction during the time the project was delayed.2 

The medium project, as shown in Table 1, demonstrates that when applying standard values of time for both 

individuals and commercial vehicles—and assuming a conservative 8 percent return on investment in roadway 

infrastructure3 (national studies indicate the return is more likely in the 10 to 12 percent range)—the 58.8‐month 

delay had a total cost of $17.8 million, or almost $300,000 per month. 

Of that cost, slightly over $250,000 per month was the result of construction price increases estimated by using the 

HCI. Almost all of this increase resulted from the significant increases in commodity prices (e.g., cement, base 

material, steel, asphalt, and fuel) experienced during the period. Almost $50,000 per month was the result of 

delays in commuter and business delivery times, while almost $12,000 per month was the result of increased fuel 

costs associated with higher consumption at slower speeds. Finally, almost $50,000 per month was associated with 

the economic impact of delay. 

The expansion of the roadway allowed substantially more throughput, though only modest changes in speed. 

Because of the induced demand associated with expanded roadways, speeds can actually stay the same or slightly 

decrease as more vehicles use the freeway. When that occurs, vehicles are drawn to the new/expanded facility 

from other highways and/or arterial streets, thereby improving travel times, reducing wasted fuel, and generating 

a positive economic effect on those particular roadways. In general, however, the magnitude of the impact of 

project delay depends on traffic volume and speed, percent trucks, spikes in construction costs, and duration of 

delay. 

Also, because of the number of variables involved (and their relative importance depending upon roadway 

location, roadway type, availability of transportation alternatives, traffic mix, cost of materials, etc.), in almost 

every instance where a project is delayed, the cost of delay can vary significantly. As a result, every instance of 

construction delay, even on roadways that appear to be similar in nature, can result in a different cost of delay 

estimate. See Appendix B for a description of the variables and methodology used for the cost calculations. 

                                                                 2 Project inflation calculations taken from the Highway Cost Index produced by the Texas Department of 

Transportation (http://ftp.dot.state.tx.us/pub/txdot‐info/cst/hci_binder.pdf). 

3 M. Ishaq Nadiri and Theofanis P. Mamuneas. “Contribution of Highway Capital to Output and Productivity Growth 

in the US Economy and Industries.” http://www.fhwa.dot.gov/policy/gro98cvr.htm. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

     P a g e  | 11 

SUMMARY 

This brief research project examined the costs that result when a roadway project is delayed. It examined both 

direct and indirect impacts of project delays and found that the public almost always bears the costs, either 

directly through wasted fuel and time or indirectly through less‐efficient use of the limited supply of roadway 

funds. This project did not directly examine the value of any of the delays, though it was evident while examining 

the data that many delays actually produced benefits that equaled or exceeded the cost of the delay. 

The simple methodology developed in this project allows TxDOT to quickly estimate the cost of delay to a roadway 

project. Using that methodology, researchers examined three actual projects. The smallest of the three resulted in 

project delay costs of $96,000 per month, while the largest project resulted in project delay costs of $447,000. 

While the methodology is simple, there is no rule of thumb because project delay costs depend on several 

variables, primarily location, traffic, construction costs, and travel speeds.  

The methodology also includes a monthly local economic impact component, which for the three examples ranged 

from $10,000 per month to $78,000 per month. 

The appendices to this report contain data, terminology, and methodologies developed in this research: 

Appendix A—List of Acronyms. 

Appendix B—Description of Calculations Used in Estimating Project Delay Costs. 

Appendix C—General Information Regarding Delays. 

Appendix D—Additional Examples of Project Delay. 

Appendix E—Typical Causes of Delay. 

Appendix F—Delayed Projects Studied. 

Appendix D illustrates case examples of projects or circumstances that either have a largely undefined impact or 

are too complex for this straightforward methodology to assess the delay impacts. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | A ‐ 1 

APPENDIX A—LIST OF ACRONYMS 

AGUA  Aquifer Gardens for Urban Areas 

CAMPO  Capital Area Metropolitan Planning Organization 

CE  Categorical Exclusion 

DCIS  Design Construction Information System 

DEIS  Draft Environmental Impact Statement 

EA  Environmental Assessment 

EIS  Environmental Impact Statement 

FEIS  Final Environmental Impact Statement 

FHWA  Federal Highway Administration 

FONSI  Finding of No Significant Impact 

FY  Fiscal Year 

HCI  Highway Cost Index 

MPO  Metropolitan Planning Organization 

NEPA  National Environmental Policy Act 

PS&E  Plan, Specification, and Estimation 

RMA  Regional Mobility Authority 

ROD  Record of Decision 

ROW  Right of Way 

TTI  Texas Transportation Institute 

TURF  Texans United for Reform and Freedom 

TxDOT  Texas Department of Transportation 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | B ‐ 1 

APPENDIX B—DESCRIPTION OF CALCULATIONS USED IN ESTIMATING 

PROJECT DELAY COSTS 

Variables

The output of the model provides both direct and indirect cost estimates. Direct cost estimates include wasted 

time and fuel for both personal and commercial travel. Indirect cost includes the economic impact of project delay.  

The spreadsheet‐based model uses 17 variables divided into three categories to calculate direct and indirect costs 

associated with project delay. Those variables include the following. 

CalculationsTab

Project Cost—in millions of dollars. This is the contracted amount. 

Average Annual Daily Traffic before the Improvement—determined for the segment that most closely 

represents the roadway segment under construction.  

Average Annual Daily Traffic after the Improvement—determined for the segment that most closely 

represents the roadway segment under construction.  

Percent of Trucks before Improvement—determined for the segment that most closely represents the 

roadway segment under construction.  

Percent of Trucks after Improvement—determined for the segment that most closely represents the 

roadway segment under construction.  

Persons per Vehicle—a default value of 1.25 persons per personal vehicle. 

Average Speed before Improvement—determined for the segment that most closely represents the 

roadway segment under construction.  

Average Speed after Improvement—determined for the segment that most closely represents the 

roadway segment under construction.  

Length of Segment in Miles—determined from the construction contact. 

Personal Value of Time—determined by using the value of personal time used in the most recent Urban 

Mobility Report published by TTI. 

Commercial Value of Time—determined by using the value of personal time used in the most recent 

Urban Mobility Report published by TTI. 

Return on Investment—the default is 8 percent annually, based on a Federal Highway Administration 

report by Nadiri and Mamuneas.3 

Percent of Increase in Highway Cost Index—determined by using the Highway Cost Index published 

monthly by TxDOT. 

Total Months of Delay—determined using the dataset of highway construction projects furnished for this 

study by TxDOT. 

FuelTab

Fuel Price—the current fuel price. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | B ‐ 2 

EconomicImpactTab

Multiplier—an estimate of the general multiplier for economic activity based on the state’s economic 

profile. 

Percent Profit—the average profit margin across all business based on the state’s economic profile. 

Calculations

The following general steps are used in calculating an estimate of the cost of project delay: 

1. Convert daily traffic into monthly traffic volume. 

2. Calculate the travel time for the segment under construction for both before the improvement was 

started and after it was completed. 

3. Calculate the total hours of travel over the segment for both before the improvement was started and 

after it was completed. 

4. Calculate the total personal hours of travel using the number of personal vehicles traveling the segment 

multiplied by average occupancy. Calculations are performed for both before and after the improvement. 

5. Calculate the total vehicle hours of travel for commercial vehicles. Calculations are performed for both 

before and after the improvement. 

6. Calculate the net hours of delay by subtracting the “before” and “after” delay for both personal and 

commercial travel. 

7. Multiply the excess hours of delay for personal and commercial travel by the respective value of time to 

obtain the delay cost associated with the construction delay. 

8. Determine the net cost of fuel for commercial vehicles using a fuel/speed curve developed for use in TTI’s 

Urban Mobility Report, comparing the amount of fuel consumed at the “before” speed versus the “after” 

speed, and using the respective volumes for the two periods. 

9. Multiply the difference in fuel consumption at the “before” speed and the “after” speed by the prevailing 

retail fuel price to obtain the fuel cost for personal and commercial travel associated with the 

construction delay. 

10. Calculate the economic impact by multiplying the capital investment by the rate of return (assumed to be 

8 percent per annum) plus the annual return multiplied by the assumed rate returned to profit. 

11. Calculate the cost of construction inflation by taking the difference between the contract amount at the 

date the project begins minus the discounted value of the contract at the date the project was originally 

scheduled to begin. Use the HCI to calculate the discount rate. 

 

 

 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | C ‐ 1 

APPENDIX C—GENERAL INFORMATION REGARDING DELAYS 

This appendix contains a general explanation of three typical areas in which projects can be delayed: regulatory 

delays, environmental review delays, and legal actions. Because of the statutory nature of these processes, TxDOT 

must follow defined procedures throughout each area until the final resolution. 

RegulatoryDelays

The National Environmental Policy Act (NEPA) requires federal agencies to outline the environmental impact their 

proposed actions will have and to assess the impacts of alternative actions.4 TxDOT projects funded in any part by 

federal monies are required to gain environmental approval through the NEPA regulatory process defined by three 

levels of analysis as shown in Table C‐1.  

Table C‐1. NEPA Levels of Analysis. 

NEPA Level  Description

Categorical Exclusion (CE) 

 

This status is given to those projects that do not significantly impact the environment. 

Environmental Assessment (EA) 

 

An EA must be conducted when the environmental significance is unknown. The results of an EA can lead to one of the following: 

Finding of No Significant Impact (FONSI). 

Environmental Impact Statement. 

Environmental Impact Statement (EIS)

 

An EIS is a more in‐depth report that must include consideration of alternatives and public involvement. The EIS consists of four steps: 1. Notice of Intent (NOI). 2. Draft EIS (DEIS). 3. Final EIS (FEIS). 4. Record of Decision (ROD). 

 

If a final EIS is not submitted within three years from the date of the draft EIS, or there have been no major steps 

to advance the action three years after a final EIS (e.g., authority to begin final design or to acquire right of way), a 

written evaluation should be prepared to determine if a supplemental EIS is warranted.5 A supplemental EIS is 

necessary if considerable changes have been made to the project, or there is significant new information available. 

A supplemental EIS is developed like any other EIS, excluding the need for scoping. Furthermore, once a project 

                                                                 4 U.S. Environmental Protection Agency. Environmental Impact Statement Process. 

http://www.epa.gov/compliance/nepa/eisdata.html. 

5 CFR Title 23, §771.129. http://ecfr.gpoaccess.gov/cgi/t/text/text‐

idx?c=ecfr&tpl=/ecfrbrowse/Title23/23cfr771_main_02.tpl. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | C ‐ 2 

has received an ROD, FONSI, or CE, a verification that the designation remains in place should be made prior to any 

major approvals or grants.5 

EnvironmentalReviewDelays

Projects that do not necessarily fall under NEPA regulations may still have environmental impacts that must be 

addressed. The safety of roadway users and the cost of avoiding environmental impacts are factors that must be 

weighed against environmental and aesthetic interests. A concerned citizen or environmental group may delay the 

project by requesting changes that mitigate the harm or by bringing suit in a state court (as opposed to a NEPA suit 

in federal court).  

LegalActions

When a lawsuit is filed in reference to a proposed or active project, the party bringing suit may seek an injunction 

to bring current work to a halt regardless of the stage of progress. If the court grants the injunction, the project will 

be suspended in its entirety or in part until a court can hear arguments from both sides and rule on the matter. If 

the injunction is denied, the opposing party can still file suit with the hope of either receiving a favorable ruling 

before damage has been done or TxDOT addressing the problem to avoid the additional cost and delay.

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 1 

APPENDIX D—ADDITIONAL EXAMPLES OF PROJECT DELAY 

TTI selected three additional projects as examples to illustrate the different causes of delay, costs associated with 

the delay, and potential complexity in estimating delay costs from one project to another. The following projects 

were selected: 

• US 281 (Bexar County) in the San Antonio District (major highway expansion delayed several years). 

• SH 45 Southeast (Travis County) in the Austin District (new connector highway delayed several years). 

• SH 16 (Bandera County) in the San Antonio District (safety improvements delayed several months). 

Each case study examines the type of delay incurred, a timeline of actions taken, and the ultimate result of the 

delay, as of 2009. Researchers did not select projects because they represent the typical delayed project or signify 

usual resolutions to overcome delays. Rather, researchers chose these projects because they illustrate the 

magnitude and complexity of actions taken to resolve the issues that cause project delay. Project delays examined 

in these cases fit into one or more of the following categories: regulatory, environmental, and/or legal. Appendix C 

contains a general description of the processes associated with each category and how they can cause project 

delays.  

US281—SanAntonio

The US 281 project is an example of an initially straightforward project that became very complex because of 

multiple and fractured delays. TxDOT employed a variety of improvements to reduce the impacts of the various 

delays.  

The segment of US 281 in San Antonio studied stretches north from Bitters Road (south of Loop 1604) to Borgfeld 

Road (Figure D‐1).6 Major intersections included in this improvement are Loop 1604, Sonterra Boulevard, Encino 

Rio Road, Evans Road, Stone Oak Parkway, and Marshall Road.  

                                                                 6 Map source: Alamo Regional Mobility Authority, http://www.alamorma.org/index.cfm/projects/us‐281‐eis/. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 2 

 

Figure D‐1. Map of US 281 Expansion Project. 

While the project involved multiple legal battles, this study focuses primarily on delays caused by the 

environmental regulatory process. Lawsuits filed by citizens’ groups required the environmental studies to be 

repeated and, at times, restarted the regulatory process required to gain environmental clearance.  

Because of the delays, several short‐term fixes have been proposed as separate projects requiring no 

environmental analysis to help alleviate the congestion. Improvements to the US 281/Loop 1604 interchange were 

eventually developed as one of these separate projects, independent of the sizeable US 281 North expansion 

project.  

Timeline

OriginalEnvironmentalAssessment

In 1984, the US 281 North expansion from Bitters Road to Evans Road was given environmental clearance after an 

EA was conducted.  

In the early 1990s, a segment of this project was constructed from Bitters Road to Sonterra Boulevard.  

In 2000, the environmental clearance for construction from Sonterra Boulevard to Evans Road was reevaluated 

because more than 15 years had passed since the first EA was conducted.  

In 2001, development from Loop 1604 to Evans Road was approved by the MPO. The MPO dedicated about half of 

the estimated needed funds ($42 million) in its 2002–2004 Transportation Improvement Program.  

In 2003 and 2004, the US 281 North project was studied to determine whether tolling new lanes would be a 

practical funding solution, and the following year the MPO voted to construct the new lanes as privately funded 

toll facilities.  

In 2005, TxDOT received unsolicited bids for a privatized toll project. That same year environmental clearance was 

granted for the segment stretching from Evans Road to Borgfeld Road.  

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 3 

2005:FirstLawsuit

Construction of an $80 million expansion segment from Loop 1604 to Marshall Road was halted at the end of 2005 

when local environmental groups—Aquifer Guardians for Urban Areas (AGUA) and Texans Uniting for Reform and 

Freedom (TURF)—sought a court order enjoining the continuation of construction. The Federal Highway 

Administration (FHWA) withdrew environmental approval because of the lawsuit, and a new EA commenced.  

2007:SecondEnvironmentalAssessment7

In 2007, TxDOT completed a two‐year, $2 million EA that combined all projects on US 281 from Loop 1604 to 

Borgfeld Road. As a result, FHWA published a FONSI that ended the construction moratorium. That same year, 

Texas passed legislation that changed the way privatized transportation tolling operated, and the Alamo Regional 

Mobility Authority (RMA) took control of the US 281 project.  

2008:SecondLawsuit

In 2008, AGUA and TURF once again brought suit to question the environmental clearances that were currently in 

place. During the suit, TxDOT requested a 60‐day stay to review the records. During this period of review, TxDOT 

found irregularities in the procurement of scientific services, leading FHWA to retract the previously issued 

environmental clearance. Any future expansion projects in the US 281 corridor would be required to prepare a 

more complex EIS. Three weeks after the FHWA pronouncement, the Alamo RMA began pursuing an EIS that they 

estimated would take three to five years to complete. Consequently, the district judge administratively closed the 

second lawsuit.  

2009:CategoricalExclusions

With the US 281 North expansion projects on hold awaiting a new EIS, the Alamo RMA continued to search for new 

ways to relieve congestion and improve safety within the limits of the law. In March 2009, the Texas 

Transportation Commission approved $80 million in federal stimulus funding to aid a separately proposed 

$130 million improvement project at the US 281/Loop 1604 interchange. The project would include construction of 

four direct connectors from Loop 1604 to US 281. The Alamo RMA conducted new biological surveys of the area 

and held two public hearings. In February 2010, FHWA and the U.S. Fish and Wildlife Service approved a CE by 

granting the interchange project environmental clearance. A portion of the federal stimulus funds must be spent 

by 2015.  

In the fall of 2009, another project to transform a segment of US 281 into a “Super Street” received environmental 

clearance through a CE. This conversion will aid in congestion relief without the addition of new lanes until the EIS 

is completed.  

                                                                 

7 Alamo RMA. Alamo RMA Responds to Latest Lawsuit Filed by TURF, February 26, 2008. Memorandum, FY 06 

Lettings, Dianna F. Noble, P.E., January 3, 2007. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 4 

2010:ThirdLawsuit

In August 2010, AGUA filed suit claiming that the US 281/Loop 1604 interchange project violates the Endangered 

Species Act and endangers the Edwards Aquifer. In December, AGUA filed an injunction to stop the impending 

construction for the duration of the suit.  

CurrentStatus

A district judge issued an advisory in February 2011 stating that he would rule on the injunction to halt the 

interchange project within six months. On March 2, 2011, construction began on the US 281/Loop 1604 

interchange and will continue while awaiting the court’s ruling. Furthermore, the EIS for the US 281 North 

expansion project is underway, and final approval is estimated for 2013. Figure 7 displays the project timeline, 

when the original delay began, and when the short‐term projects were implemented to help reduce congestion. In 

addition to the project timeline, Figure D‐2 also shows the length of delay the agency and the public encountered 

because of the project.  

 

Figure D‐2. Historical Timeline of US 281 North Expansion Project Delay. 

Costs

US281NorthExpansionProject

Before the first lawsuit in 2005, the low bid to construct the expansion was $83,653,101. The cost to terminate the 

project that same year was $7 million excluding litigation expenses. Today, the low bid for the same scope of work 

is estimated to be $2.5 million more than the 2005 bid.  

1984 1989 1994 1999 2004 2009

Project

Agency

Travelers

Timeline of Delay

Project in Progress

Delay

Short‐Term Projects

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 5 

US281/Loop1604InterchangeProject

The Loop 1604 interchange project was a short‐term project created to help relieve congestion while the US 281 

North expansion project was put on hold. The interchange, which is not a tolled project, was partially funded with 

federal stimulus dollars. The Alamo RMA stated that if the injunction is granted, the delay could cost them up to 

$30,000 a day.8  

In addition to the $9.5 million costs specifically mentioned above, additional personal, business, and economic 

costs are also associated with the project delay.  

SH45Southeast—Austin

The SH 45 Southeast project is an example of a project on a new alignment, which is generally not suitable for a 

simplified analysis. This project connects two major highways in a growing network. In the absence of “before” 

conditions for comparison, a delay impact analysis on a project of this type would require the use of the local 

travel demand model maintained by the MPO to identify the number of prospective users. 

The segment of SH 45 in Austin studied is a 7.4‐mile stretch running east/west between IH 35 at FM 1327 and the 

junction of SH 130 and US 183 (Figure D‐3).9 Major intersections along the four‐lane tolled highway include IH 35, 

North Turnersville Road, FM 1625, and SH 130/US 183. The roadway was proposed as an alternate route for 

through traffic that would aid in relieving congestion on other major routes (such as IH 35 through downtown 

Austin). This project encountered delays involving a lawsuit based upon the NEPA’s EIS requirements.  

                                                                 8 Vianna Davilla, quoting RMA Director of Community Development Leroy Alloway. “Interchange Work Starts in 

Face of Controversy.” San Antonio Express‐News, March 3, 2011. 

9 Map source: TxDOT, http://www.texastollways.com/austintollroads/english/map.htm.  

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 6 

 

Figure D‐3. Map of SH 45 Southeast Project. 

Timeline

OriginalSchedule

In 2003, the DEIS required by NEPA was completed, and a public hearing was held that summer. That fall, the FEIS 

was submitted, and FHWA granted the project environmental clearance in 2004. That same year, TxDOT awarded a 

contract to design and build the highway in the following two years to Zachry Construction Company.  

2004:Lawsuit

In 2004, local environmental groups Save Our Springs Alliance and Save Barton Creek Association brought suit in 

federal district court to stop the project. Together the membership of these two groups totals approximately 

4,500 people. They claimed the EIS failed to consider an adequate range of alternate routes and did not fully 

examine the impacts (direct, indirect, secondary, and cumulative). They argued that to completely assess the 

secondary and cumulative impacts of the southeast project, the future southwest project would need to be 

analyzed in conjunction. The future southwest segment (segment 3) would cross the Edwards Aquifer recharge 

zone. The suit and project were put on hold so a new environmental study of the southeast segment could be 

performed.  

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 7 

2007:ProjectRestarted

The new environmental study was completed two years later, reaching the same conclusions as the previous 

analysis. FHWA approved the new study in the summer of 2006, and the federal court dismissed the case. In April 

2007, a new contract was awarded to Balfour Beatty Infrastructure, Inc., and T.J. Lambrecht Construction, Inc., and 

construction began the following July. SH 45 Southeast opened in June 2009. Figure D‐4 illustrates the project 

timeline including when the delay began and when the project restarted. Also shown is the length of delay 

encountered by the agency and the public because of the lawsuit. 

 

Figure D‐4. Historical Timeline of SH 45 Southeast Project Delay. 

Costs

The project was originally estimated at $154.3 million as part of a $2.2 billion toll road package approved by the 

Capital Area Metropolitan Planning Organization (CAMPO). The estimate included $137.4 million for construction 

costs. TxDOT paid $1.6 million to terminate the project in 2004. The ensuing environmental analysis cost an 

additional $300,000. During the two years the environmental analysis was being conducted, the cost to acquire 

right of way rose roughly $5.2 million. Since the project was originally awarded as a design/build project as 

opposed to design/bid/build, the engineering plans remained incomplete. This meant that an additional $950,000 

had to be spent to finalize the engineering plans.10 The new low bid for the construction portion of the project was 

$139.7 million—$2.3 million more than the original estimate.  

                                                                 

10 Texas Department of Transportation. Draft Testimony, “Accelerating the Project Delivery Process: Eliminating 

Bureaucratic Red Tape and Making Every Dollar Count.” House Transportation and Infrastructure Committee 

Subcommittee on Highways and Transit, February 15, 2011.  

2003 2004 2005 2006 2007 2008 2009

Project

Agency

Travelers

Timeline of Delay

Project in Progress

Delay

New Schedule

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 8 

Additionally, a project under construction on SH 130 was impacted by the SH 45 Southeast delay, and expenses to 

settle the matter with the developer cost TxDOT approximately $15.5 million. 

In total, the costs associated with project delay on this project exceed an estimated $22.6 million plus an 

uncalculated amount of commercial and personal delay and economic costs.  

SH16—Bandera

This SH 16 road safety improvement project runs 8 miles from Winans Crossing toward Medina in Bandera County 

(Figure D‐5).11 The rural state highway originally consisted of two 10‐foot‐wide lanes with no shoulders. The 

improvements would widen the existing lanes to 12 feet and add 5‐foot shoulders to each side. The current TxDOT 

standards call for 7 feet of clear zone. The clear zone provides a safe area for drivers to stop or recover their 

vehicle after veering off the travel lane and is measured from the edge of the travel lane.12 This project was 

challenged with a state lawsuit concerning the removal of five mature pecan and black walnut trees located at the 

intersection of SH 16 and Kyle Ranch Road. These trees, estimated to be 180 to 310 years old, sit directly adjacent 

to the original road and were scheduled for removal to facilitate the widening of the road.  

Timeline13

2005:RuralTransportationMeeting

In late 2005, a rural transportation meeting was held to present local projects to the community. TxDOT had 

performed an environmental study that identified these trees on state property. The original proposal called for 

removal of five trees, with TxDOT planting 10 new trees in the surrounding grove on state land. 

                                                                 11 Copyright 2010 Navteq; copyright 2010 Microsoft. 

12 TxDOT Glossary. http://onlinemanuals.txdot.gov/txdotmanuals/glo/c.htm. 

13 Texas Department of Transportation v. Kyle, No. 04‐06‐00762‐CV, May 9, 2007. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 9 

 

Figure D‐5. Map of SH 16 Project. 

2006:Lawsuit

In February, TxDOT’s Environmental Affairs Division classified the project as a CE needing no further environmental 

study.  

In May, local landowners whose property is adjacent to the intersection met with TxDOT to voice their concerns. 

TxDOT amended the plans to include a guard rail that would run between the road and the trees, thus reducing 

the number of trees to be removed to two.  

On June 1, the landowners filed suit in state court seeking to stop TxDOT from removing any of the trees and 

classifying the project as a CE. A temporary restraining order was granted, and a hearing was held on June 26.  

On June 26, at the hearing’s conclusion, the judge requested the parties agree on a temporary injunction. TxDOT 

immediately requested the case be removed to federal court. The state court denied TxDOT’s request and granted 

the temporary injunction, stopping TxDOT from removing any tree within one‐half mile of the intersection in 

question.  

On October 31, the federal court also denied TxDOT’s request for removal to federal court, stating that TxDOT is 

not a federal agency and was not subject to federal rules. The project’s funds did not include federal monies that 

would require NEPA approval.  

On November 1, the temporary injunction was renewed. Construction was completed for the remainder of the 

project with the exception of the contested intersection.  

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | D ‐ 10 

2007:StateAppeal

In early 2007, TxDOT filed an appeal stating that the state trial court was not the correct court to decide the 

matter. TxDOT argued that it has sovereign immunity. However, sovereign immunity does not exist if the state is 

depriving the other party of a vested property right. The court agreed with TxDOT that the landowners do not have 

a vested interest because the trees are located on state land. The Fourth Court of Appeals of Texas reversed the 

decision of the trial court and removed the injunction, thus allowing TxDOT to proceed. On August 1, 2007, the two 

trees in question were removed. Figure D‐6 illustrates the project timeline showing when the delay began and 

when the project was allowed to resume in the contested area. Additionally, Figure D‐6 shows the length of delay 

the agency and the public encountered.  

 

Figure D‐6. Historical Timeline of SH 16 Project Delay. 

Costs

The project was originally estimated at $5.4 million, funded from the sale of $600 million in bonds in 2004 for 

safety projects across the state.14 There was also additional cost to TxDOT that could not be explicitly identified by 

this research project. In addition to those unidentified costs, the public was denied the additional safety benefits 

provided by wider lanes and paved shoulders while awaiting the court’s ruling.

                                                                 14 Jessica Hawley. “Trees Cause Debate in Root of Community.” The Bandera Bulletin, May 9, 2006. 

2004 2005 2006 2007 2008

Project

Agency

Travelers

Timeline of Delay

Project in Progress

Delay

New Schedule

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | E ‐ 1 

APPENDIX E—TYPICAL CAUSES OF DELAY 

During each stage of a project, numerous events can cause project delays. Table E‐1 summarizes the typical causes 

of delay for a roadway construction project during the four major phases of a project. While the nature of delays 

can vary among the four stages of a project (planning, development, contracting, and construction), the results are 

quite similar: impacts on travelers and businesses. 

First, with respect to delays during the planning/scoping phase, while the number of potential reasons for delay is 

relatively small, the length of delay associated with these reasons can be significant. This is particularly the case if 

the project becomes the subject of litigation.  

Although delays during the project development phase can have numerous causes, they are typically invisible to 

the public unless they have been told a project would start construction by a certain time (e.g., summer 2012). If 

the construction has not started as anticipated, local stakeholders, citizens, and local media may want to know the 

causes of the delay. One exception to the concept that delays during development are invisible to the public is 

when litigation occurs. Such litigation mostly occurs during a statutory review process (e.g., environmental 

clearance or U.S. Corps of Engineers clearance) or during right‐of‐way acquisition. 

Delay during the contracting phase is typically minimal, with a project only being delayed one or two months from 

the original letting date due to last‐minute procedural missteps and/or project management inefficiencies.  

The public generally understands that once a project begins construction, there will be a period of inconvenience 

while the project is underway. As TxDOT and local media announce the anticipated duration of construction, the 

public takes a grin‐and‐bear‐it attitude, looking forward to the completion of the project. Delays during 

construction, however, are the most visible and draw substantial attention.  

   

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | E ‐ 2 

Table E‐1. Typical Causes of Project Delay.15 

Planning/Scoping • Project priority changes in relationship to other projects • Federal/state legislation • Interagency coordination • Project management issues: 

o Poor project definition o Lack of documentation of assumptions o Missed milestones 

• Funding • Litigation 

Development • Project management issues: 

o Poor project definition o Lack of documentation of assumptions o Missed milestones 

• Railroad permits not obtained as anticipated • Acquisition of necessary right of way (ROW) not completed as anticipated • Utility accommodation agreements not completed as anticipated • Mandatory review processes (e.g., environmental and fish and wildlife) not completed as anticipated • U.S. Corps of Engineers permits not obtained as anticipated • Local funding agreements not executed as anticipated • Delay in plan, specification, and estimation (PS&E) preparation (either in‐house or by consultant) • Litigation 

Contracting • Unanticipated letting events (e.g., bids greatly exceeding engineer’s estimate) • Delayed assembly of PS&E/letting package • Projects pulled from letting schedule • Bid protests • Litigation 

 

   

                                                                 15 The information contained it Table E‐1 is a compilation of data from multiple sources: 

Meeting with TxDOT, Associated General Contractors of Texas, and Highway Contractors in Austin, Texas, 

June 8, 2011. 

R.D. Ellis and H.R. Thomas. “The Root Causes of Delays in Highway Construction.” Transportation Research 

Board 82nd Annual Meeting, Washington, D.C., January 2003. 

J. Ahn and R.E. Minchin, Jr. “Identifying Causes for Delay in Highway Construction Projects.” 

Transportation Research Board 87th Annual Meeting, Washington, D.C., January 2007. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | E ‐ 3 

Table E‐1. Typical Causes of Project Delay (Continued). 

Construction (after Contract Award) • Additional work desired by TxDOT • Additional work desired by another party • Contractor delays • Project management issues: 

o Lack of communications, collaboration, and cooperation o Lack of approval authority o Coordination with stakeholders (local governments and other agencies) 

• Utility conflicts/untimely utility accommodations • Unacquired ROW • Railroad conflicts (scheduling of work and project prioritization) • Permitting issues/approvals • Unforeseen project site conditions: 

o Differing subsurface conditions o Archeological impacts o Endangered species impacts o Environmental impacts 

• Design errors/omissions • Unfavorable weather • Insufficient work effort: 

o Skilled workforce shortages o Equipment shortages o Material shortages/price increases 

• Events (e.g., holidays, special events, and local events) 

• Changes solely for public convenience • Act of God • Litigation 

 

Figure E‐1 shows the percentage of total days of construction delay by cause of delay. This information was 

gathered from data collected by TxDOT’s Construction Division. In FY 2009, 26.1 percent of the total days of delay 

is attributable to additional work desired by TxDOT. The second biggest percentage of total days of delay is 

attributable to contractor delay. In total, these two categories of delay accounted for almost half of all days of 

delay. 

With respect to the additional work desired by TxDOT, in most cases, the delay is more specifically associated with 

having the opportunity to address a known issue (e.g., other repairs and expanding the limits) while a contractor is 

on site and a contracting mechanism is in place. Contractor delays are most often associated with weather and 

waiting for resolutions regarding utility relocation, ROW acquisition, and other agreements/clearances (e.g., U.S. 

Corps of Engineers, potential wildlife area impacts, and unknown/potential archeological sites).  

Figure E‐2 shows the same dataset distributed simply by the number of projects affected by delay without respect 

to the number of days involved. For example, of the approximately 870 projects closed in FY 2009, 223 had at least 

one day of delay associated with additional work desired by TxDOT.  

Of course, projects that experience delay may have delay caused by more than one factor. Figure E‐3 shows the 

distribution of delay by cause. For example, if a project suffered a delay because of a design error by the consulting 

engineering firm and then later experienced a delay due to weather, both reasons for delay are shown in this 

graph. As a result, the total frequency of delay across all causes will sum to greater than 100 percent. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | E ‐ 4 

Finally, while project delay almost always has cost associated with it, not all project delay is a waste of time and 

public money. In many instances of project delay initiated by TxDOT, the reason for the delay is to make an 

improvement in the design or construction of the project that will ultimately deliver better value to the public.  

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

      P a g e  | E ‐ 5 

 

Figure E‐1. Breakdown of Total Days of Delay by Cause, FY 2009. 

 

26.1%

23.5%

13.2%

10.9%

6.2%4.9%

3.9% 3.8% 3.3%

1.6% 1.4% 0.8% 0.4%

0%

5%

10%

15%

20%

25%

30%

AdditionalWork

Desired byTxDOT

ContractorDelays

UntimelyUtility

Relocation

Design Error(Consultant)

Design Error(TxDOT)

AdditionalWork

Desired by3rd Party

Other UnforeseenProject SiteConditions

UnfavorableWeather

UnacquiredRight of Way

MaterialShortage

Changessolely forPublic

Convenience

Act of God

% of Total W

ork Days Delayed

Cause of Delay

Breakdown of Total Days of Delay by CauseFY 2009

Note: This chart shows the percent of projects delayed for each cause. 

Projects that experienced two different causes of delay during the 

project life cycle appear once in each category. Therefore, some 

projects may appear twice. This analysis only includes projects that 

had the Final Estimate approved in FY 2009. Delay information 

obtained from TxDOT.

Total Days of Delay: 35,141 

Total Bid Days for Projects with Delay: 84,365 

Total Bid Days for All Projects: 164,288 

Note: This chart shows the percent of projects delayed for each 

cause. Projects that experienced two different causes of delay during 

the project life cycle appear once in each category. Therefore, some 

projects may appear twice. This analysis only includes projects that 

had the final estimate approved in FY 2009. Delay information 

obtained from TxDOT. 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

      P a g e  | E ‐ 6 

 

Figure E‐2. Number of Delayed Projects by Cause, FY 2009. 

223

201

72 70 70 70

50 50

3324

186 4

0

50

100

150

200

250

AdditionalWork

Desired byTxDOT

ContractorDelays

UntimelyUtility

Relocation

Design Error(TxDOT)

Design Error(Consultant)

UnforeseenProject SiteConditions

UnfavorableWeather

Other AdditionalWork

Desired by3rd Party

MaterialShortage

Changessolely forPublic

Convenience

Act of God UnacquiredRight of Way

Number of Projects

Cause of Delay

Number of Delayed Projects by Cause in FY 2009

Note: This chart shows the number of projects delayed for each cause. Projects 

that experienced two different causes of delay during the project life cycle 

appear once in each category. Therefore, some projects may appear twice. This 

analysis only includes projects with the final estimate approved in FY 2009. 

Delay information obtained from TxDOT.

Total Projects Delayed: 424  

Total Projects: 868 

Percentage of Projects with Delay: 49% 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

      P a g e  | E ‐ 7 

 

Figure E‐3. Percent of Delayed Projects by Cause, FY 2009.

52.5%

47.3%

16.9% 16.5% 16.5% 16.5%

11.8% 11.8%

7.8%5.6%

4.2%1.4% 0.9%

0%

10%

20%

30%

40%

50%

60%

AdditionalWork Desiredby TxDOT

ContractorDelays

UntimelyUtility

Relocation

Design Error(TxDOT)

Design Error(Consultant)

UnforeseenProject SiteConditions

UnfavorableWeather

Other AdditionalWork Desiredby 3rd Party

MaterialShortage

Changessolely forPublic

Convenience

Act of God UnacquiredRight of Way

Percent of Projects

Cause of Delay

Percent of Total Delayed Projects by Cause in FY 2009

Note: This chart shows the percent of project delayed for each cause. 

Projects that experienced two different causes of delay during the project 

life cycle appear once in each category. Therefore, some projects may 

appear twice. This analysis only includes projects with the final estimate 

approved in FY 2009. Delay information obtained from TxDOT. 

Total Projects Delayed: 424 

Total Projects: 868 

Percentage of Projects with Delay: 49% 

 

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | F ‐ 1 

APPENDIX F—DELAYED PROJECTS STUDIED  

Project location information, before‐and‐after average vehicle speed, and other information were required to 

determine both direct and indirect costs associated with project delay. Therefore, TTI researchers analyzed 

projects in the Austin, San Antonio, El Paso, Houston, and the Dallas/Fort Worth areas only because the MPOs in 

these regions provided the minimum data requirements needed for a robust analysis. The list of projects examined 

is included in Table F‐1. 

TTI researchers obtained travel demand data provided by large MPOs to calculate speed differentials from 

improved vehicle movements. Researchers used travel demand data obtained from these projects to develop total 

cost of delay scenarios for small, medium, and large projects. The specific projects with reported delays used in 

this analysis were obtained from DCIS, TxDOT’s Construction Division, and select TxDOT districts. Note that “TTA” 

in Table F‐1 refers to the Texas Turnpike Authority.  

    ASSESSING THE COSTS ATTRIBUTED TO PROJECT DELAYS 

    P a g e  | F ‐ 2 

 

Table F‐1. List of 26 Delayed Projects Studied by Total Bid. 

Rank  District  CSJ  Highway Length (Miles) 

Project Description Bid (Total Obligated Amount) 

Project Phase When Delay Occurred 

Total Days of Delay 

1  TTA  3136‐01‐126  LP 1 1.7 Convert non‐freeway to freeway $107,960,584 Construction 99

2  TTA  0683‐06‐015  SH 45 1 Convert non‐freeway to freeway $103,017,730 Construction 528

3  TTA  0683‐01‐069  SH 45 2.5 Widen non‐freeway $101,577,358 Construction 187

4  Dallas  1068‐04‐083  IH 30 4.7 Widen from six to eight lanes and add interchanges $96,841,618 Construction 156

5  San Antonio  0072‐12‐159  IH 10 1.5 Reconstruct IH 10 410 Interchange (crossroads) (Phase 2) $82,237,875 Construction 332

6  Dallas  0048‐08‐037  IH 35E 9.8 Upgrade to standards freeway $62,597,022 Construction 273

7  San Antonio  0072‐12‐130  IH 10 3.1 Upgrade to standards freeway $61,990,150 Construction 256

8  Houston  0177‐05‐057  US 59 2.6 Widen to eight main lanes and two three‐lane frontage roads $49,231,631 Design

9  Houston  0177‐05‐057  US 59 2.6 Widen to eight main lanes and two three‐lane frontage roads $49,231,631 Construction

10  Houston  0027‐08‐108  US 90A 0.9 Widen to eight‐lane divided with improvements at ditch H $39,243,649 Construction 51

11  Fort Worth  0134‐08‐030  US 380 10.5 Reconstruct two lanes to four‐lane divided rural  $36,540,038 Design

12  Houston  0027‐08‐144  US 90A 1.3 Widen to eight‐lane divided with diamond interchange at Dulles $21,881,454 Construction 86

13  Houston  0179‐03‐024  SH 35 7.7 Widen to four‐lane divided rural $19,702,202 Construction 201

14  Fort Worth  0902‐48‐708  CS 3.4 Widen from two‐lane to four‐lane divided urban highway $19,069,431 Design

15  Fort Worth  0081‐02‐045  US 377 2.9 Reconstruct to four‐lane divided urban $12,983,276 Construction

16  San Antonio  0521‐06‐124  IH 410 3.7 Rehab existing main lanes and reconstruct shoulders $12,388,367 Construction 243

17  Houston  0523‐10‐033  FM 1488 2.7 Widen two lanes to four‐lane divided (Pass Through Financing) $11,463,848 Design

18  Houston  0179‐01‐028  SH 35 4 Widen to four‐lane divided, widen bridges, and install new bridges $10,716,917 Design

19  Houston  0179‐01‐028  SH 35 4 Widen to four‐lane divided, widen bridges, and install new bridges $10,716,917 Construction

20  Austin  0114‐04‐048  US 290 3.8 Widen to four‐lane divided rural section  $10,716,016 Construction 162

21  Fort Worth  3125‐01‐010  FM 3029 1.1 Reconstruct and widen from five to six lanes with raised median $9,873,767 Construction

22  Austin  0204‐01‐049  US 79 1.5 Widen non‐freeway $9,351,883 Construction 384

23  Houston  0027‐08‐108  US 90A 0.9 Widen to eight‐lane divided with improvements at ditch H $9,238,220 Design

24  Fort Worth  1068‐01‐187  IH 30 1.6 Reconstruct to four‐lane divided with raised median $8,559,000 Construction 434

25  Dallas  2374‐04‐046  IH 20 12.3 Rehab existing freeway $7,870,576 Construction 69

26  Fort Worth  0718‐02‐025  FM 156 1 Widen to four lanes with continuous left‐turn lane  $7,502,998 Construction