ASSENT Prequalification Document

96
 STRUCTURAL STEEL PREQUALIFICATION DOCUMENT Page 1 of 95  A SSENT  A l Sh af ar St eel En g ineerin g  Prequalification Document

Transcript of ASSENT Prequalification Document

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 1/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 1 of 95 

 ASSENT Al Shafar Steel Engineering 

Prequalification Document

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 2/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 2 of 95 

I N D E X

Introduction … … … … … … … … 4

 Al Shafar Group … … … … … … … … 6

Quality Policy … … … … … … … … 7

Market Sectors & Products … … … … … … 8

Construction & Site Services … … … … … … 9

Legal Status … … … … … … … … 10

Branch Office … … … … … … … … 15

Registrations … … … … … … … … 17

ISO Certifications … … … … … … … 35

Engineering Capabilities … … … … … … 38

Manufacturing Facility … … … … … … … 40

Quality Control & Quality Assurance … … … … … 49

General Description of Work Flow Procedures … … 50

EngineeringDesign OutputDesign ReviewDesign ValidationDesign Changes

SoftwareR F I ‘ sPre-Production Planning

Example … … … … … … … … … 54

Material PreparationIdentificationHandling, Storage and StackingConsumable StorageFabrication DrawingsBeam ProcessingBeam Preparation EquipmentPlate Processing

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 3/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 3 of 95 

Plate Processing Equipment Assembly

Welding

Curving and StraighteningNon-Destructive TestingSurface Preparation and PaintingDelivery of Finished Product

 Attachments … … … … … … … … 59

Process Control ProceduresInspection and Test Plan (Sample)Welding Procedure Specifications

Health Safety & Environment … … … ….. ……. … .. ... 76

Our Projects … … … … … … … 77

Organization Chart … … … … … … … 87

Manpower List … … … … … … … … 88

Equipment List … … … … … … … … 93

Our Location Map … … … … … … … 95

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 4/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 4 of 95 

Introduction

ASSENT, a member of the long-established AL Shafar Group of Companies, is one of the MiddleEast's leading companies in the field of structural steel design, engineering, fabrication, painting and

erection of all types of steel projects.

Having a fully covered and insulated area over 50,000 square-metres, allows ASSENT to be able to

 produce a very large volume of fabricated steel, ranging from 8,500 to 10,000 tons per month. This

 plant is equipped with the latest technology of CNC, blasting and other types of equipment to ensure

the quality, speed of production accuracy, and proper control.

The Workshop is equipped with four (4) Automatic CNC beams and plates processing lines in an area

of 66m x 180m, for sizing, comprising of :

  CNC Beam Sawing Lines‐  CNC Beam Drilling Lines

‐  CNC Coping Equipment

‐  CNC Plates Processing Lines

‐  CNC Angle Masters

‐  CNC Profiling Machines

All raw material is pre-blast before processing using three (3) automatic blasting machines capable to

of processing 3000 tonnes/month each (total 9000 tonnes/month)

The fabrication area covers an area of 145m x 178m, fully equipped with all necessary welding

equipment, overhead cranes varying from 5 to 15 tonnes in capacity etc… In total the facility is

equipped with 89 overhead travelling cranes.

Post-blasting, after fabrication is done through two (2) 10-turbine blasting machines capable of

 processing in excess of 8000 tonnes/month

All blasting is done to Sa 2 1/5

All painting is done under controlled conditions under cover in an area of 60m x 145m

An additional area of 72m x 240m has been dedicated to raw material project storage and can

accommodate up to 40,000 tonnes of steel sections

In addition to the production capabilities described above, all the engineering and quality control iscarried out in-house, with the additional independent third party testing of welds, in compliance with

approved specific project ITP (Inspection and Test Plans), undertaken by Internationally Recognised

and Approved Testing Agencies.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 5/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 5 of 95 

ASSENT’s products and services are available for all types of steel projects. The Senior Management

Personnel have a wealth of experience in all areas from high-rise towers to storage sheds; from oil and

gas projects to large-scale commercial buildings; from hangars to showrooms and moreover all typesof prefabricated residential houses, office complexes and labour camps.

ASSENT's quality control and assurance program comply with the international requirement, which

closely governs all engineering, manufacturing and construction standards. We also apply strict health,

safety and environmental policies to safeguard the protection of all employees and subcontractors. We

always work with the aim of having a zero-accident environment.

After sales supports facilities in Abu Dhabi,

ASSENT main facilities are located in Dubai Industrial City, at a convenient location at about 100 km

from Abu Dhabi, and is in a position to provide all necessary after-sales services required within and

around Abu Dhabi area.

Such services include:

 –   Stock of spare parts: In case additional structural members or related accessories, such

items can easily and conveniently be provided on short notice.

 –   Repair facilities: The workshop facilities are within short distance of Abu Dhabi. Any

repairs can be accommodated within the workshop facilities or at the client’s premises

depending on the nature of the repairs

 –   Technical support: Can be made available either at Main Dubai Facilities or Abu Dhabi

Office

Satisfy Abu Dhabi regulations concerning Local Agency Requirements

ASSENT is a fully registered Limited Liability company registered in Dubai and fully compliant with

all Legal and Local Agency Requirements of the United Arab Emirates.

Please refer to the “Legal Status section” of this document for copies of the Industrial License,

Chamber of Commerce Registration and Commercial Register as well as Registrations with other

Authorities.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 6/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 6 of 95 

 Al Shafar Group

A reputation for high quality and reliability

Al Shafar Steel Engineering (ASSENT) is the most recent addition to Al Shafar Group of Companies,

which was established in 1989, and in a period of 20 years has now grown to incorporate a total of 18

companies (including ASSENT), all related to different aspects of the construction and related

manufacturing industries.

Al Shafar Group currently employs approximately 25,000 people overall.

Through its 20 years in existence, Al Shafar Group has earned the respect and loyalty of its “repeat”

clients such as Government Agencies, Dubai Police and others, through the quality of its products as

well as its transparency and reliability in its business approach.

For additional information on Al-Shafar Group of companies, please visit the web site

http://www.alshafar.com

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 7/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 7 of 95 

Quality Policy 

Our Vision

We are confident in our strategies for growth in the Structural Steel ProjectsEngineering, Manufacturing, Painting and Erection within the United Arab Emirates

and other Gulf Countries.

Our Mission

Our mission is to be the most effective and respected manufacture of industrial products

 by practicing our strategy which is based on improving quality productivity.

Our Quality PolicyTo realize our vision and mission we shall exert every effort to achieve the following in

all our activities:

  To have a close working relationship with all our Clients / Customers on all aspects of

engineering, quality and service to expedite the contract;

  To be aware of the latest technological aspects related to our scope of works and to continually

evaluate this technology and its potential impact on manufacturing capability and company

quality requirements;

  To continually strive to satisfy the requirements of our Clients & Customers by completing the

 projects in compliance with their specifications, contract and quality requirements;

  Gaining the confidence and trust of our supervising bodies, employees, stakeholders,

customers, and the public through strict adherence to all applicable laws, regulations, best

 practices, international standard for quality management system ISO 9001:2008;

  Continually improving the effectiveness of our Quality Management System through periodic

monitoring and review of its performance and suitability ; and

  Protecting our environment by effectively utilizing our resources and reducing / preventing the

 pollution that may be associated with ASSENT activities through effective waste management

activities; and

  Communicating our Policy to all our employees, stakeholders, partners, customers, interested

 parties and the public.This Policy provides the framework and sets the basis for establishing and reviewing our objectives at

the relevant functions of ASSENT. It will be reviewed periodically for continuing stability and

suitability.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 8/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 8 of 95 

Market Sectors & Products  

The following is an indication, but is not limited to, of the market sectors serviced and the types of

structures undertaken by ASSENT.

The flexibility, expertise and equipment allows the company to customize and provide the right

 products or mix of products as required by the clients’ projects.

Market Sectors Structures

Heavy Industries Oil & Gas Pipe Racks

Petrochemical Rectangular Platforms

Aluminum Smelters Circular Platforms

Fertilizer Plants Pipe Supports

Cement Plants Main Workshop Structures

Raw Material Storage

Buildings

Floor Gratings

Staircases

Handrails

Ladders

Temporary Structures

Infrastructure Bridges Steel Bridges

Power & Desalination Heavy Duty BuildingStructures

Airports & Seaports Platforms

Railways Equipment Support Structures

Passenger Terminals

Cargo Terminals

Aircraft Hangars

Buildings Segment Residential / Commercial Hi-rise Towers

Shopping Malls Tower Crowns

Leisure Centres Atrium Structures

Multi-storey Car Parks

Roof Structures

Sports Centres

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 9/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 9 of 95 

Construction & Site Services 

ASSENT aims to provide a complete, integrated solution for customers including site installation and

services. We employ a highly qualified construction team, and can provide construction equipment

capable of installing 4,000 tons of steel per month.

ASSENT is part of AL Shafar Group Of Companies, The parent company ASGC (AL Shafar General

Contracting) is a well established and well reputed company in the field of general contracting and

registered and qualified in Steel Erection

Manpower Strength is around 12,000 and equipped with a long fleet of site construction equipments,

cranes, lifting and access equipments and scaffolding.

This gives us clients the privilege of offering our clients very competitive prices for complete package

of supply and erection.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 10/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 10 of 95 

Trade License

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 11/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 11 of 95 

Chamber of Commerce

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 12/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 12 of 95 

Commercial Register

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 13/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 13 of 95 

 Abu Dhabi Commercial License andChamber of Commerce Certificate

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 14/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 14 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 15/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 15 of 95 

Certi ficate of Office Registration - Kazakhstan

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 16/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 16 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 17/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 17 of 95 

 Abu Dhabi Supreme Petroleum Council

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 18/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 18 of 95 

 ADNOC

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 19/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 19 of 95 

TAKREER

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 20/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 20 of 95 

GASCO

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 21/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 21 of 95 

 ADCO

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 22/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 22 of 95 

 ADMA-OPCO

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 23/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 23 of 95 

 ADGAS 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 24/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 24 of 95 

BOROUGE

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 25/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 25 of 95 

FERTIL

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 26/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 26 of 95 

Saudi Aramco

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 27/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 27 of 95 

Qatar Petroleum

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 28/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 28 of 95 

MARAFIQ

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 29/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 29 of 95 

Saudi Electricity Company

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 30/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 30 of 95 

Kuwait National Petroleum Company

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 31/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 31 of 95 

Farabi Petrochemicals

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 32/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 32 of 95 

Ministry of Oil and Gas – Oman

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 33/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 33 of 95 

Federal Electr ici ty and Water Authority (FEWA)

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 34/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 34 of 95 

Saudi Basic Industries Corporation (SABIC)

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 35/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 35 of 95 

ISO 9001:2008

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 36/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 36 of 95 

ISO 14001:2004

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 37/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 37 of 95 

OHSAS 18001:2007

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 38/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 38 of 95 

Design and Engineering 

The engineering section employs a team of designers and detailing engineers equipped with the

latest and most advanced software for both of these disciplines. All work is closely monitored to

ensure that it conforms to all project specifications and standards.

The engineering department services are available for:

Completing design for statical systems and connections

Composing general-arrangement drawings andfoundation details

Shop drawings

Material take-off

Construction and assembly drawings

Full and close co-ordination with the customer's engineers.

Design proposals and Value Engineering for all types of steel projects

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 39/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 39 of 95 

Design and Engineering Cont… 

The Drafting office is also fully computerized and utilizes the following main software

 packages:

Package Description Specifications / Code

 AutoCad Preparation of GA Drawings &Fabrication Drawings –Miscellaneous Works

N/A

Strucad 3D Modelling – Detailing ofConnections – AutomaticGeneration of Fabrication Drawings,Production & Material Listings

N/A

Tekla - Xsteel 3D Modelling – Detailing ofConnections – Automatic

Generation of Fabrication Drawings,Production & Material Listings

N/A

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 40/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 40 of 95 

Manufacturing Facilities & Equipment

The plant facility is div ided into the foll owing areas: 

 Area Name: Inventory Stock Area

Dimensions: 50m x 172m

Details: Material handling by 2 No’s of Gantry Cranes, 10 ton each.

 Area Name: Open yard for Heavy Fabricat ion

Dimensions: 50m x 172m

Details: Open yard Heavy fabricatio n and assembly, with Gantry Cranes.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 41/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 41 of 95 

 Area Name: Project Stock Area

Dimensions: 238m x 75m

Details: Handling of material by 15 No’s of over head cranes, each has capacity of 10 tons .

 Area Name: Pre-Blasting Area

Details: In feed Conyers - 44m length for feeding the material to pre-blasting through shot blastingmachine, out feed Conyers - 24 m length to feed this material to the CNC beam/plate sizing bays. 

Pre-Blasting Machines

Brand: Geitart Model: GW

2500 

Width (mm) 2500

Height (mm) 600

Speed (m/min) 0.6 to 10

Brand: Geitart Model: GW 2500 

Width (mm) 2500

Height (mm) 600

Speed (m/min) 0.6 to 10

Brand: Geitart Model: GW

2500 

Width (mm) 2500

Height (mm) 600

Speed (m/min) 0.6 to 10

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 42/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 42 of 95 

Production Lines

 Area Name: Product ion Line 1

Details: CNC Sizing Bay S01, S02 for f ully

automatic cutt ing, drilling and copying forSection profiles and plates for Heavy weightstructures. 

Heavy Fabrication Bay F01

Length 120m, width 23m equipped with5 no’s x 15 tons capacity over head cranes

2 no’s x 30 tons ground trolleys

Heavy Fabrication Bay F02

Length 120m, width 23m equipped with5 no’s x 15 tons capacity o ver head cranes

2 no’s x 30 tons ground trolleys 

Production Bay 1 : CNC Machines

Machine: CNC Band SawMachine

Brand: FICEP 

Model: 1260 LBH Technical Specifications:

Sawingcapacityat 90°

(mm) 1250 x600

Sawingcapacityat 45°

(mm) 800 x600

Sawingcapacityat 60°

(mm) 500 x500

Miteringangles

+45°/-60°

Machine: CNC Drilling MachineBrand: FICEP 

Model: 1203 DF 

Technical Specifications:Web

height(mm) 1220

Flangewidth

(mm) 510

Thickness

(mm) 100

Diameter (mm) 50

3 axis drilling.

Machine: CNC Thermal CopingBrand: FICEP 

Model: 1201 RC 

Technical Specifications:Volume ofsections tobeprocessed

(mm) 1220 x600 x800

Copingstroke

(mm) + 400 / -400

Controlledaxes

(no.) 5 + 1

Machine: CNC Drilling &Thermal Cutting Brand: FICEP 

Model: TIPO A31Technical Specifications:

Length (mm) 6000

Width (mm) 3100

Thickness (mm) 130

2 drill heads + 2 thermal cuttingheads

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 43/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 43 of 95 

Production Lines

 Area Name: Product ion Line 2

Details: CNC Sizing Bay S03, S04 for f ully

automatic cutt ing, drilling and copying forSection profiles and plates for Medium weightstructures. 

Medium Fabrication Bay F03

Length 120m, width 23m equipped with5 no’s x 10 tons capacity over head cranes

2 no’s x 20 tons ground trolleys

Medium Fabrication Bay F04

Length 120m, width 23m equipped with5 no’s x 10 tons capacity over head cranes

2 no’s x 20 tons ground trolleys 

Production Bay 2 : CNC Machines

Machine: CNC Band SawMachine

Brand: FICEP Model: 1260

LBH Technical Specifications:

Sawingcapacityat 90°

(mm) 1250 x600

Sawingcapacityat 45°

(mm) 800 x600

Sawingcapacityat 60°

(mm) 500 x500

Miteringangles

+45°/-60°

Machine: CNC Drilling MachineBrand: FICEP Model: 1203 DF 

Technical Specifications:

Webheight

(mm) 1220

Flangewidth

(mm) 510

Thickness

(mm) 100

Diameter (mm) 50

3 axis drilling.

Machine: CNC Thermal CopingBrand: FICEP Model: 1201 RC 

Technical Specifications:

Volume ofsections to

beprocessed

(mm) 1220 x600 x

800

Copingstroke

(mm) + 400 / -400

Controlledaxes

(no.) 5 + 1

Machine: CNC Punching&Thermal Cutting 

Brand: FICEP Model: TIPOB251

Technical Specifications:Length (mm) 6000

Width (mm) 2540Thickness (mm) 100

PunchingThickness

(mm) 25

DrillingThickness

(mm) 130

PlasmaThickness

(mm) 60

ThermalCuttingThickness

(mm) 130

1 drill + 1 thermal cutting + 1 punching + 1 plasma

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 44/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 44 of 95 

Production Lines

 Area Name: Product ion Line 3

Details: CNC Sizing Bay S05, S06 for f ully

automatic cutt ing, drilling and copying forSection profiles and plates for Medium weightstructures. 

Medium Fabrication Bay F05

Length 120m, width 23m equipped with5 no’s x 10 tons capacity over head cranes

2 no’s x 20 tons ground trolleys

Medium Fabrication Bay F06

Length 120m, width 23m equipped with5 no’s x 10 tons capacity over head cranes

2 no’s x 20 tons ground trolleys 

Production Bay 3 : CNC Machines

Machine: CNC Band SawMachine

Brand: FICEP Model: 1260

LBH 

Technical Specifications:

Sawingcapacityat 90°

(mm) 1250 x600

Sawingcapacityat 45°

(mm) 800 x600

Sawingcapacityat 60°

(mm) 500 x500

Miteringangles

+45°/-60°

Machine: CNC Drilling MachineBrand: FICEP Model: 1203 DF 

Technical Specifications:

Webheight

(mm) 1220

Flangewidth

(mm) 510

Thickness

(mm) 100

Diameter (mm) 50

3 axis drilling.

Machine: CNC Drilling MachineBrand: FICEP Model: 1203 DF 

Technical Specifications:

Webheight

(mm) 1220

Flangewidth

(mm) 510

Thickness

(mm) 100

Diameter (mm) 50

3 axis drilling.

Machine: CNC Punching&Thermal Cutting 

Brand: FICEP Model: TIPOB251

Technical Specifications:Length (mm) 6000

Width (mm) 2540Thickness (mm) 100

PunchingThickness

(mm) 25

DrillingThickness

(mm) 130

PlasmaThickness

(mm) 60

ThermalCuttingThickness

(mm) 130

1 plasma + 1 punching

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 45/95

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 46/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 46 of 95 

Production Lines

 Area Name: Product ion Line 5Built Up Assembly Line

Dimensions:48m x 75m Details: Specialist workshop for heavy /medium assembly of built-up Girders / Columns /Trusses and BoxesFully automated using hydraulic jacks systemand gantry automatic welding lines. 

Production Bay 5 : CNC Machines

Machine Name: Built Up Assembly Machine 

Brand: CMM  Model: BWF 2000

Technical Specifications:

Web height (mm) 2000

Flange width (mm) 700

Length (mm) 18000

Speed (m/min) 0.3 to 6

Machine Name: Plate Cutting Machine 

Brand: ESAB  Quantity: 3

Technical Specifications:

Length (mm) 28000

Width (mm) 4000

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 47/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 47 of 95 

 Area Name: Post-Blasting

Dimensions: 238m x 18m

Details: 115m in feed Conyers & collecting this material from all fabrication bays to post blast beforepainting.

60m out feed Conyers to feed this material to the painting area.

Brand: Geitart Model: CM 3100 

Width (mm) 3000

Height (mm) 1500

Speed (m/min) 0.6 to 4

Brand: Geitart Model: CM 3100 

Width (mm) 3000

Height (mm) 1500

Speed (m/min) 0.6 to 4

 Area Name: Painting Area

Dimensions:120m x 20m (no’s x 3) Details: Equipped with 5 no’s over head cranes

10 ton capacity each, CNC ground trolley forswift movement.

Each Bay is having 1 x 10 tons ground trolley 

Machine Name: Spray Painting Machine

Brand: Graco Model: NXT Xtreme King 70:1

Painting Bay 1  Painting Bay 2  Painting Bay 3 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 48/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 48 of 95 

 Area Name: Generators Area

Details:

Machine Name: Generator Brand: Caterpillar

Model: 500 kVA  Quantity: 3 

Model: 365 kVA  Quantity: 3 

Model: 455 kVA  Quantity: 3 Model: 410 kVA  Quantity: 1 

 Area Name: Gas Station Area

Details: Argon Tank 4500 kg

CO2  Tank

Oxygen Racks 3

 Acetylene Racks 2

CO2 tanks, Argon Tanks 100 no’s of gas outlets for 100 MIG Welding Machines

every shift

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 49/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 49 of 95 

Quality Control & Quality Assurance 

Meeting the essential requirement of ISO 9001:2008

ASSENT has established and implemented ISO 9000 based procedures and has a completeISO compliant QA Manual that includes all the following procedures:

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 50/95

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 51/95

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 52/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 52 of 95 

Design Validation

All design packages, as detailed in the contractual requirements are forwarded to the client

for review comment and approval prior to the start of fabrication. Should any comments orstatus codes be applied to the submitted design package other than approved, these comments

are addressed and another submittal is made to the client. This process is repeated until the

design is acceptable to the client. 

Design Changes

When a change or modification to the design is required, the originator of the change

documents the required modification and forwards written instructions to the relevant

departments. Depending on the source of the change notice, the information is transmitted as

follows :

  Internal Change notice Information to be forwarded to the Design Supervisor for

review and action

  External (Client) notice Information to be forwarded to the Design Supervisor for

review and action

All change notices either in the form of commented drawings or written instructions are filed

in the Project File for future reference.

Software

ASSENT has standardized the computer software used in order to ensure compatibility with

clients and other third parties involved in the project:

  Microsoft Office General Office

  Primavera / Microsoft Project Planning

  Autocad 2D Drafting

  Strucad 3D modeling and drafting

  Tekla - Xsteel 3D modeling and drafting

  Staad Pro 2D & 3D Design

  Master Key Connections Design

  ProKon Connections Design  PMS system Production Tracking & Monitorng

RFI ‘ s

If during the review, engineering design, or drafting cycles, additional information or

clarifications are required, a formal RFI is raised and issued to the client. The issue and

return of the RFI is recorded.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 53/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 53 of 95 

Pre-Production Planning

On award of the contract the Planning Department review the overall structure to establish

the following :

  Overall production requirements per week and month

  Sequence of contract execution in order to support the clients program

  Priority for each sub structure

  Engineering and Drafting planning

  Procurement planning

The 3D modeling & drafting systems utilized by ASSENT produce a full Bill of Quantities

during the "3 D" modelling phase of the drafting cycle. This information is transferred to the

Stru M.I.S evolution Software Program where the pre-determined priority ratings for each

Sub-structure are automatically assigned to the individual item

This allows the Stru M.I.S evolution Software Program to automatically generate a detailed

(item by item) production program which is then grouped together to give the daily

 production requirements for all fabrication activities.

Due to the modular format of the Stru M.I.S evolution Software Program the individual

module and the relevant information required to control a specific activity can be downloaded

onto the computer system of any associate company. This allows them to conduct their area

of the operation in parallel with the overall project requirements.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 54/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 54 of 95 

Example

Material Preparation

The relevant material preparation modules of the Stru M.I.S evolution Software Program is

forwarded to the relevant departments and all the production scheduling information

downloaded.

The engineering department also issues the plates and beam shafts drawings in the format

required to program the CNC equipment used in the material preparation.

As the material is processed in accordance with the production schedule, the Stru M.I.S

evolution Software Program is regularly updated by the computer system controlling the

CNC equipment or by manual entry periodically through the shift. This updated information

allows monitoring the progress of the contract piece by piece.

This example is applicable to each individual stage of the fabrication process.

Identification

All material received either from the mill or merchants stock is inspected on receipt for:

  Completeness of order

  Compliance with Purchase Order requirements

  Transport Damage

  Identifiable to valid mill certificate

As the material is processed through the preparation stage of the fabrication process the heat

number of the individual piece is logged onto the cutting schedule against its unique position

/ item number. This information is then transferred to the Stru M.I.S evolution Software

Program providing material trace-ability for each individual piece back to the mill

certification

Handling, Storage and Stacking

Steel plates and sections are either delivered to the preparation facility on a JIT basis or

stored and stacked in a ASSENT designated area. All material is stored and stacked in such amanner as to prevent distortion twisting or bending.

Consumable Storage

All welding rods painting and blasting material are stored in accordance with the

anufacturer's recommendations.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 55/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 55 of 95 

Fabrication Drawings

Material preparation drawings are issued to the Preparation Facility in electronic format and

are identified by phase substructure and cutting schedule.

The assembly drawings are issued either in electronic format or paper copy again they are

identified by phase substructure and assembly schedule

Beam Processing

During the cutting operation each beam is marked with it's item / position number to allow

identification and trace-ability through the rest of the fabrication process.

After the beam has been marked and cut, and depending on the requirements, the beam is

either moved directly to the transit lay-down area or processed thorough the CNC drillstation.

Beam Preparation Equipment

Please refer to the list of equipment attached.

Plate Processing

Plates are processed using various methods depending on thickness contract requirements and

end usage

If the thickness of the plate is 12 mm or less, the plates can be sheared to the required size,

however the end usage and contract requirements are also considered before work is detailed

to these machines.

Once the plate has been cut to the correct size and shape the final operation is producing the

holes. This can be done either by drilling or punching. Again thickness, hole dia, and

contract requirements are considered before allocating the work to the various machines

During the cutting operation, each plate is marked with it's item / position number to allow

identification and trace-ability through the rest of the fabrication process.

All cut edges can be dressed to remove burrs, dross and irregularities. Holes are dressed

as required to provide a smooth contoured surface.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 56/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 56 of 95 

Plate Processing Equipment

Please refer to the list of equipment attached.

Once the preparation of the material has been completed the material is then ready for

assembly.

 Assembly

When the material has passed it's inspection, it is released to the assembly / welding yard

were it is segregated in the lay down yard prior to release to assembly.

The material is assembled in accordance with the fitting schedule issued by Stru M.I.S

evolution Software Program.

The material is assembled in accordance with the fabrication drawings in such a manner that

they are not bent, twisted or otherwise damaged, and any deformation is within the stated

tolerances.

All items, after assembly, are fully dimensionally checked, any deviations are corrected

immediately.

The results of the dimensional check are logged onto the Stru M.I.S evolution Software

Program.

Welding

All welding operations are carried out in accordance with ASSENT’s approved welding

 procedures by independently qualified welders.

All procedures and welder qualifications are in accordance with AWS D 1.1 (2010) as well as

British standard BSEN 15614-1:2004 and BSEN 287-1:2004.

During the welding operation all welders are continually monitored to ensure that the welding

 parameters, as detailed in the relevant procedure, are adhered to and that the level of

workmanship is maintained.

All items, after completion of welding are visually inspected against the requirements of

AWS D 1.1 (2010) for compliance. Any visual discontinuity is marked and repaired

immediately. Only when the item has been fully passed and accepted will it be released to

 blasting and painting

All welding inspections are entered onto the Stru M.I.S evolution Software Program.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 57/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 57 of 95 

Curving and Straightening

When it is necessary to curve or straighten components one of the following methods may be

used:

  Mechanical - taking care not to cause indentations or changes in cross section

  Local Application of Heat - ensuring that the temperature does not exceed 650°C

Non-Destructive Testing

 Non destructive testing is carried out in accordance with the contract requirements, all NDT

inspections are conducted by an independent 3rd party specialist company with AWS

D1.1(2010) acceptance standards used for determining the acceptability of the weld.

The results of all NDT examinations are entered on the Stru M.I.S evolution Software

Program.

Surface Preparation and Painting

The surface preparation / blast cleaning produces the required anchor pattern and cleanliness

level as detailed by the paint manufacturer to ensure paint adhesion to the surface.

The Painting Inspector carries out profile checks at the start of each blasting run to ensure

that the required profile and cleanliness levels are met.

All material once blasted are primed within 4 hours to prevent rust bloom.

The painting operation is conducted ony if the following conditions are met:(as specified by the paint manufacturer)

  The surface temperature shall be at least 3 degrees centigrade above the dew point and

the Relative Humidity (RH%) shall not exceed 85%.

  Visual checks on the surface shall be carried out to ensure none of the following point

exist oil, grease, dirt, loose paint, rust and other surface contamination.

  There is protection from adverse weather conditions, such as wind that may blow

sand, or other foreign bodies on the painted surface or it may disrupt the paint pattern

or cause dry spray.

  Paint stripe-coating shall be applied to all welds and corners if required.

  Primers, intermediate coats and top coats shall be contrasting colours, if more than

one application is required to achieve the required film thickness, then the same

colour should be used. Reference to Client's specifications must be made before

implementation.

  Finished coatings shall be free of runs, drips, dry spray etc. Areas that are cracked,

damaged or below minimum thickness shall be repaired prior to dispatch

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 58/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 58 of 95 

All defective areas are to be cleaned with solvents, detergents or clean water as required

All repair areas blast cleaned to the metal surface, with the edges being feathered back atleast 50 mm beyond the clean metal surface. For areas less than 1000 mm2, brush coating

may be acceptable, but with reference to Client's specifications , areas greater than 1000 mm2

the paint shall be applied as to the original specification.

Painted items shall be handled with proper care so that damage to the paint is minimised.

Structural steel items shall not be handled until paint has thoroughly dried.

Care shall be taken to avoid abrasions and other damage.

 Nylon / Canvas slings shall be used for handling the coated steelwork or when steel slings are

to be used, they shall not be choked with wood to avoid / limit contact with coated steelwork.

Delivery of Finished Product

Each piece of steelwork shall be distinctly marked with Item No and bar code before dispatch

in accordance with the fabrication drawing . Steelwork shall be stacked on timbers in order to

 provide easy handling

All attachments and fittings shall be securely attached. Loose plates and smaller items shall

 be either boxed or wired together and then wired to larger parts.

Floor plates shall be bundled for shipment

Bolts, Nuts and Washers shall be packed in strong bags with the Nuts and Washers assembled

on the Bolts.

The client should be informed of the time of delivery and delivery notes shall accompany all

deliveries.

The sequence of shipment shall be such as to expedite erection and minimise field handling

of material

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 59/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 59 of 95 

SAMPLE DOCUMENTATION ONLY

PROCESS CONTROL PROCEDURE

Document No. ASSENT-QMS-P09

Revision 01

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 60/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 60 of 95 

1.0  PURPOSE

The purpose of this procedure is to identify and define the steps to be taken for

controlling and monitoring the workmanship, fabrication and surface preparationactivities in order to meet the specified quality requirements

2.0  SCOPE

This procedure outlines the responsibilities, method to control workmanship and

fabrication activities to achieve the required quality during the fabrication of all

structural steel products.

3.0  TERMS AND DEFINITIONS

ASSENT Al Shafar Steel Engineering L.L.C

QC Quality Control

ITP Inspection and Test Plan

WPS Welding Procedure Specification

PQR Procedure Qualification Record

 NDE Nondestructive Examination (Third Party Testing)

4.0  RESPONSIBILITIES

4.1  QA ManagerTo develop and implement the management of the Quality Procedures which will

govern the standard of quality on the contract

4.2  Material Control EngineerEnsures that applicable procedures for procurement of material, receipt, checking

quality of material coordinating with QC Engineer, storage and issue of material,

comply with the Contract requirements.

4.3  QC Engineer

Commissioning and overseeing third party inspection services (NDT) and ensuring

that all relevant shop floor inspections and checks are conducted and documented.

Coordinating inspection of purchaser supplied materials. Coordinating the collationand storage of all project specific quality records and documentation;

4.4  QC Inspector

To ensure that all welding and fabrication activities which are undertaken conform to

the approved procedures, and to notify the QC engineer of any non-conformances. To

conduct patrol inspections to monitor the welding parameters, consumables and

techniques being used are in accordance with the approved procedures to conduct

visual and weld dimensional checks for conformance to requirements.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 61/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 61 of 95 

4.5  Dimensional Checker

To ensure that the overall dimensions of a specific piece or item of a structure comply

with those stated on the drawing.

4.6  Fabrication Workshop Supervisor

To compile and issue cutting schedules in conjunction with the Project Coordinator

and Drawing office. Verify that all cutting schedules are completed and all the items

listed are within the specified tolerances. Deploy the workforce for maximum

efficiency and ensure the standard of workmanship meets requirements. Raise orders

to purchase in conjunction with the Materials Controller to ensure adequate stock

levels are maintained.

4.7  Discipline Foreman (Cutting Fabrication Welding Painting)Each discipline foreman is directly responsible to the Fabrication Workshop

Supervisor. They are responsible for the level of workmanship, shop floor

organization and control of their individual discipline.

5.0  PROCEDURE

5.1  Identification

5.1.1  Traceability of Steel

All steels materials received, ex-mils or from Merchant’s stock, shall have a valid

material (Mill) certificate

The material shall be received into stock with the manufacturers heat number marked

on to the item, this heat number traceability shall be maintained on cutting list for

each item.

5.1.2  Fabrication/Shop DrawingsThe fabrication / shop drawings shall be prepared by our in-house drafting department

all drawings shall be checked and signed as Checked by ASSENT Draughts men for

accuracy prior to issue to the Client for Approval, if contractually required

Fabrication & Shop drawings shall show all the necessary details and dimensions to

enable fabrication of components to proceed, and will be controlled in accordance

with the Document Control Procedure "ASSENT-QMS-P01"

A latest controlled copy of fabrication / shop drawings shall be issued to the

Fabrication Workshop Supervisor and QC Engineer.

5.2  Marking5.2.1  All Steel material received into stock shall be marked with the manufactures heat

number ref Material Control Procedure "ASSENT-QMS-P16".

5.2.2  All material used in the fabrication shall maintain full traceability.

5.2.3  The Fabrication Supervisor shall make a requisition to the Material Control Engineer

for material to be issued to Fabrication Shop, by means of beam and plate cutting

schedules.

5.2.4  Steel sections will be marked prior to cutting and shaping as detailed in the fabrication

drawings and cutting schedules.

5.2.5  QC Inspector shall randomly check individual parts to ensure correct marking prior to

cutting, shaping or drilling and sign the cutting schedule to record his check

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 62/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 62 of 95 

5.3  Cutting and Shaping, Bending and Bolt Holes

5.3.1  Beams will be cut in accordance with Beam Cutting Schedule.

5.3.2  Cutting and shaping of steel may be carried out by shearing, sawing, grinding,

machine flame cutting except that where machine flame cutting is impractical, hand

flame cutting may be used.5.3.3  Deformation and burrs resulting from cutting shall be corrected and ground smooth.

5.3.4  Where cutting surfaces are required to transfer compressive loads by bearing (e.g.

column on base plates), they shall be milled to provide an adequate bearing surfaces.

5.3.5  Holes may be made by drilling and punching. Slotted holes shall be made by one of

the following methods:

  Punch in one operation

  Formed by drilling two holes and completed by gas cutting and grinding

5.3.6  Holes in steel plates over 10 mm thick shall be drilled. The diameter of the holes for

 bolts (other than anchor bolts) shall not exceed nominal bolt diameter by more than

1.6 mm unless otherwise specified by Client.

5.3.7  Tolerance of the holes shall be in accordance with the approved drawings and Client’s

specifications.

5.4  Machining

The thickness of elements shown on the drawings as requiring machining shall mean the

minimum thickness after the machine operation.

5.5  Dressing

Cut edges shall be dressed to remove burrs, dross and irregularities. Holes shall be

dressed as required to remove burrs and protruding edges.

Sharp edges shall be dressed, but a 90 deg. rolled, cut, sheared or machined edge is

acceptable without further treatment.

5.6  Assembly

5.6.1  General

All components shall be assembled in a manner such that they are not bent, twisted or

otherwise damaged. (Ref Inspection and Test Plan ASSENT-QMS-18). Drifting of

holes to align the components shall be permitted, but must not cause damage or

distortion to the final assembly.

5.6.2  Curving and Straightening

When it is necessary to curve or straighten components, one of the following methods

may be used (or as stated in the project specifications):

  Mechanical means, taking care of indentations or change of cross sections;  The local Application of heat, ensuring that the temperature is carefully

controlled, by using crayon type temperature stick and does not exceed 650

deg. Centigrade;

These operations will be monitored and recorded by the Quality Control Engineer or

Inspector After curving or straightening, welds within the area of curving or

straightening shall be visually inspected. Welds which are to be subject to Non-

destructive Examination shall have these tests carried out after curving or

straightening.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 63/95

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 64/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 64 of 95 

5.7.5  Preheat and Interpass Temperature

Minimum Preheat and Interpass Temperature shall be exercised as detailed in the

approved WPS.

5.8  InspectionThese activities shall be controlled in accordance with procedure of Inspection and

Testing "ASSENT-QMS-P18" and governed by the Test and Inspection Plan

All items forming part of the welded assemblies will be checked for freedom from

distortion and straightness, dimensional accuracy and conformity to the drawings and for

compliance with project specifications and ITP to ensure that the manufacturing process

is correctly implemented.

 NDE inspection of welds shall be carried out in accordance with the requirements stated

in the project specifications and ITP

On completion of welding and testing, final inspection of assembled pieces shall bemade by QC Engineer or nominee prior to being dispatched for blasting and painting.

The results and report numbers of all inspections carried out during fabrication shall be

recorded in the fabrication check-list (Form # ASSENT-QMS-P17F02)

5.9  Surface Preparation, and Painting

All surface preparation, pruning and top coating, will be in accordance with the

ASSENT’ s procedure of Paint Control " ASSENT-QMS-23".

6.0  RETENTION PERIOD OF RECORDS:

Record No. Retention Period

 NDT Request and Report Log ASSENT-QMS-P17F01 One Year

Fabrication Check List ASSENT-QMS-P17F02 One Year

Release for Painting ASSENT-QMS-P17F03 One Year

Daily Dimensional Control Reports ASSENT-QMS-P17F04 One Year

Patrol Inspection Reports ASSENT-QMS-P17F05 One Year

Daily Painting Inspection Report ------ One Year

Plate Sizing & Cutting Check List ------ One Year

Beam cutting Schedule ------ One Year

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 65/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 65 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 66/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 66 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 67/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 67 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 68/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 68 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 69/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 69 of 95 

WPS  – WELDING PROCEDURES SPECIFICATIONS 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 70/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 70 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 71/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 71 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 72/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 72 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 73/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 73 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 74/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 74 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 75/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 75 of 95 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 76/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 76 of 95 

Environment, Health & Safety

ASSENT EHS STATEMENT

ASSENT’s Environment, Health and Safety (EHS) Policy and Management System is

committed to:

  Develop, implement and manage Environmental, Health and Safety policies and

work processes at all ASSENT facilities.

  Provide a safe and healthy work place and environment, to avoid injury or damage

to our employees, contractors, visitors and the public, the environment and

company assets.

  Comply with applicable EHS regulatory requirements at each location.

  Audit EHS activities at regular intervals at each facility to monitor its effective

implementation and to take corrective actions, wherever required.

  Create a proactive EHS culture through awareness, training and motivation, to

achieve continual improvement in EHS performance.

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 77/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 77 of 95 

List of Current Projects by ASSENT

PROJECT TITLE END USER ROLE SCOPE OF WORK TONNAGE

Western 

Range 

DSO 

Iron Ore ‐ SMPP 

Arcelor Mittal

 SUBCONTRACTOR

 

SUPPLY & 

FABRICATION OF

 

STRUCTURAL STEEL 3,300

 

LR2 Refinery Project Laffan Refinery 

Company Limited 2 

SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 4,500 

Sadara Desalination 

Plant Marafiq  SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 1,200 

Abu Dhabi Plaza  Aldar  SUBCONTRACTOR SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 12,000 

Al‐Zour North Power 

Plant HHI  SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 

9,400 

BHS Link Bridge 

Backbone 

Dubai Aviation 

Engineering Projects 

Corporation 

SUBCONTRACTOR SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 585 

CMT Expansion 

Dubai Aviation 

Engineering Projects 

Corporation 

SUBCONTRACTOR SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 1,900 

Louvre Abu Dhabi 

Tourism 

Development & 

Investment Company 

SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 3,500 

Western Range  DSO 

Iron Ore ‐ Buildings Arcelor Mittal  SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 1,800 

Ras Abou

 Fontas

 2 

Desalination Plant 

Qatar Electricity

 and

 

Water Company 

SUBCONTRACTOR 

SUPPLY &

 FABRICATION OF 

STRUCTURAL STEEL 800 

KOC Telemetry 

Project Kuwait Oil Company  SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 1,096 

SSAGS  Shell  SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 3,200 

West Qurna 1  Exxon Mobil  SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 10,000 

Badra Oil

 Filed

 Gazprom

 SUBCONTRACTOR

 

SUPPLY & 

FABRICATION OF

 STRUCTURAL STEEL 4,500

 

Rabigh 2  Saudi Aramco  SUBCONTRACTOR 

SUPPLY & 

FABRICATION OF 

STRUCTURAL STEEL 12,000 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 78/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 78 of 95 

List of Completed Projects by ASSENT

PROJECT TITLE END USER ROLE SCOPE OF WORK TONNAGE

Maaden Alumina 

Refinery 

Maaden  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

5,000 

Shah Gas PKG 2  Al Hosn Gas  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

900 

Rumaila Field  British Petroleum  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

400 

Booster Station 171  Kuwait Oil Company  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

5,000 

Qusahwira Field  ADCO  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

3,500 

Shah Gas PKG 1  Al Hosn Gas  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

900 

Western Range

 DSO

 

Iron Ore 

Arcelor Mittal  SUBCONTRACTOR 

FABRICATION OF

 

STRUCTURAL STEEL 

760 

Qurayyah Power 

Plant 

Hajr Electricity 

Company 

SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

12,750 

Shah Sulphur Station 

and Pipeline 

Al Hosn Gas  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

5,300 

Green Anode Plant & 

Rodding Shop 

EMAL  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

4,000 

Aktau Desalination 

Plant Maek Kazatompron  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

170 

RRE 7 Expansion  TAKREER  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

1,300 

Shah Gas

 PKG

 4 

GASCO/Al Hosn

 gas

 SUBCONTRACTOR

 FABRICATION

 OF

 STRUCTURAL STEEL 

9,400 

BOROUGE III  – O & U  BOROUGE  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

12,550 

Bab Thamama  ADCO  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

6,400 

South Yoloten  Turkmengas  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

8,000 

Maaden Rolling Mill  Maaden  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

8,000 

RRE 1 Expansion  TAKREER  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

17,500 

Gas Sweetening

 Qatar

 Petroleum

 SUBCONTRACTOR

 

FABRICATION OF 

STRUCTURAL STEEL

 4,150

 

The One Tower  Al Mazroei  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

1,000 

RRE 3  TAKREER  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

7,550 

Booster Station 132  Kuwait Oil Company  SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

4,500 

Sohar II & Barka III Oman Power and 

Water Company 

SUBCONTRACTOR 

FABRICATION OF 

STRUCTURAL STEEL 

200 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 79/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 79 of 95 

Sample Projects

Project Name: Booster Station 132 

Location: Kuwait

 Client: Kuwait Oil Company 

EPC Contactor: SK Engineering & Construction 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 80/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 80 of 95 

Project Name: Gas Sweetening Facilities 

Location: Qatar 

Client: Qatar Petroleum 

EPC Contactor: Petrofac 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 81/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 81 of 95 

Project Name: Qurayyah Power Plant 

Location: Saudi Arabia 

Client: Hajr Electricity Co. 

EPC Contactor: Samsung C&T Corporation 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 82/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 82 of 95 

Project Name: South Yoloten Field Development 

Location: Turkmenistan 

Client: Turkmengas 

EPC Contactor: Petrofac 

Project Name: Louvre Museum 

Location: UAE 

Client: Tourism Development Investment Company 

EPC Contactor:

 Waagner

 Biro

 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 83/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 83 of 95 

Project Name: Borouge 3 Utilities & Offsites 

Location: UAE 

Client: BOROUGE 

EPC Contactor: Hyundai Engineering & Construction 

Project Name: Shah Gas Development Pkg 4 

Location: UAE 

Client: Al Hosn Gas 

EPC Contactor: Samsung Engineering 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 84/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 84 of 95 

List of Projects Executed by ASSENT Senior Management  

ASSENT is a recent addition to Al-Shafar Group of Companies, but has the advantage of a Senior

Management Members who have a large experience in the structural steel fabrication business in theMiddle East and in particular, the UAE and GCC countries, in all major market sectors and in

 particular the Oil & Gas and Petrochem Sectors.

As an indication of the background and experience of the management in these fields, we are pleased

to attach the list of projects been executed by ASSENT’s Senior Management Team

S1  Project Title  Client End User Location Steel Tonnes  Year

1  Yansaleb Olefin  Technip‐ Italy SABIC Saudi 9,200  2006

2  Common Sulphur Project  Al Jaber Energy Qatar Gas Qatar 4,800  2006

3  Taweelah Extension‐ GAS 

Trubine Building 

Arabian 

Construction 

Co. 

Siemens Power Abu Dhabi 800  2006

RGX6‐

RASGAS Onshore

 

Expansion‐ Train 6 & 7 

Chiyoda‐

Technip Joint 

Venture 

RASGAS Qatar 13,832 

2006

5  OGD‐ III  Bechtel  GASCO Abu Dhabi 21,400  2005

6  Dubai Airport Expansion 

Phase II‐ Duty Free 

Expansion 

DCA  Dubai Civil 

Aviation 

Dubai 2,500  2005

7  Dubai Airport Expansion 

Phase II‐ Cargo Mega 

Terminal 

DCA  Dubai Civil 

Aviation 

Dubai 6,500  2005

8  Dubai Aiport Expansion‐

Phase II 

Cargo Mega Terminal ULD 

Structure 

SD Middle East Dubai Civil 

Aviation 

Dubai 4,000  2004

9  Dubai Aiport Expansion 

Ohase II‐ CUC 

Group Five Dubai Civil 

Aviation 

Dubai 1,000  2005

10  Sohar Refinery Project  JGC  JGC Abu Dhabi 828  2004

 

11  AX 149‐ Structural Steel 

works for the 

Dubai Airwing 

Dar Al 

Handasah 

Dept. of  Civil 

Aviation 

Govt.of  Dubai 

Dubai 21,000  2004

12  Mall of  the Emirates 

Develop 

WP 4150‐ Snow Centre 

Al Nabodah 

Laing O' 

Rourke 

Mall of  Emirates Dubai 4,250  2004

13  Umm Al Nar IWPP  Arabian 

Construction 

Co. 

IWPP Abu Dhabi 4,300  2004

14  Amran Cement Plant  IHI  Armant Cement Yemen 1,340  2004

15  Arzew Desalination Plant  Hitachi Zosen Algeria 

Government 

Algeria 450  2004

16  Kestrel Boiler Supports  CMI  DUBAL Dubai 450  2004

17  Sahara Mall Interchange  Athena SA/ 

NCTC 

Government of  

Sharjah 

Sharjah 170  2003

18  Sajja/ Dhaid Interchange  China Harbor 

Engineering 

Government of  

Sharjah 

Sharjah 290  2003

 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 85/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 85 of 95 

S1  Project Title  Client  End User  Location  Steel Tonnes  Year 

19  Kestrel Project‐ Phase II  DUBAL  DUBAL Dubai 8,500  2003

20  Gas Metering Skids  Alderly FZE ARAMCO Saudi 

Arabia 

80  2003

21 

Al Udied

 Package

 4 Hangar

 Qatar

 ACC Qatar

 MOD Qatar 400

 2003

22  GAMCO Hangar  Al Hamed 

Development 

Construction 

GAMCO Abu Dhabi 2,000  2003

23  Sharjah Cement  IHI  Sharjah Cement Sharjah 1,250  2001

24  Al Bateen Airbase‐

MW2273 

Sideco Gen. 

Contracting 

DMW‐ Dubai Abu Dhabi 550  2001

25  Ruwais Upgrading Facilities  Technip‐ Abu 

Dhabi 

GASCO Ruwais 1,450  2000

26  Al Taweelah A2 Power 

Station 

Arabian 

Construction Co. 

Abu Dhabi Water 

& Electricity 

Abu Dhabi 3,000  1999

27  Hawiyah Gas Plant  JGC 

Corporation 

Saudi Aramco KSA 2,500  1999

28  Aramco R & D Laboratory  Jaffar Al 

Hamood Est. 

Saudi Aramco KSA 850 

29  OGD‐2 Package 1,2,3,4,5  Technip/ 

Bechtel 

ADNOC Abu Dhabi 1,200  1999

30  ASAB Gas‐ Gather & Inj 

Project 

Mannesmann 

Demag AG 

ADCO Abu Dhabi 1,440  1999

31  TD‐ 48 DCA Expansion  HMR JV  Dubai Civil 

Aviation 

Dubai 16,500  1998

32  Codor Project‐ Pipe Rack  Alstom Power Dubai Aluminum 

Co. 

Dubai 1,125  1998

33  Codor Project‐Boiler 

Supports 

CMI‐ Belgium Dubai Aluminum 

Co. 

Dubai 805  1998

34  Ras lafan‐ Qatar Gas  William Hare 

Ltd. 

Qatar Gas Qatar 1,400  1997

35  Oman LNG Building  Bhawan Engg. 

Co. 

Oman LNG Oman 800  1997

19  Kestrel Project‐ Phase II  DUBAL  DUBAL Dubai 8,500  2003

20  Gas Metering Skids  Alderly FZE ARAMCO Saudi 

Arabia 

80  2003

21  Al Udied Package 4 Hangar  Qatar ACC Qatar MOD Qatar 400  2003

22  GAMCO Hangar  Al Hamed 

Development 

Construction 

GAMCO Abu Dhabi 2,000  2003

23  Sharjah Cement  IHI  Sharjah Cement Sharjah 1,250  2001

24  Al Bateen Airbase‐

MW2273 

Sideco Gen. 

Contracting 

DMW‐ Dubai Abu Dhabi 550  2001

25  Ruwais Upgrading Facilities  Technip‐ Abu 

Dhabi 

GASCO Ruwais 1,450  2000

26  Al Taweelah A2 Power 

Station 

Arabian 

Construction 

Co. 

Abu Dhabi Water 

Electricity 

Abu Dhabi 3,000  1999

 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 86/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 86 of 95 

S1  Project Title  Client  End User  Location  Steel Tonnes  Year 

27  Hawiyah Gas Plant  JGC 

Corporation 

Saudi Aramco KSA 2,500  1999

28  Aramco R & D Laboratory  Jaffar Al 

Hamood Est.

 

Saudi Aramco KSA 850 

29  OGD‐2 Package 1,2,3,4,5  Technip/ 

Bechtel 

ADNOC Abu Dhabi 1,200  1999

30  ASAB Gas‐ Gather & Inj 

Project 

Mannesmann 

Demag AG 

ADCO Abu Dhabi 1,440  1999

31  TD‐ 48 DCA Expansion  HMR JV  Dubai Civil 

Aviation 

Dubai 16,500  1998

32  Codor Project‐ Pipe Rack  Alstom Power Dubai Aluminum 

Co. 

Dubai 1,125  1998

33  Codor Project‐Boiler 

Supports 

CMI‐ Belgium Dubai Aluminum 

Co. 

Dubai 805  1998

34  Ras lafan‐ Qatar Gas  William Hare 

Ltd. 

Qatar Gas Qatar 1,400  1997

35  Oman LNG Building  Bhawan Engg. 

Co. 

Oman LNG Oman 800  1997

 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 87/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 87 of 95 

Organization Chart

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 88/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 88 of 95 

Manpower List – Category: Staff

ASSENT OFFICE STAFFDepartment

 Designation

 Number

 Total

 

Executive's Office  Managing Partner  1 

Executive Assistant  1 

Operations  General Manager  1 

Finance  Finance Manager  1 

Chief  Accountant  1 

Accountants  3 

HR 

Administration 

HR 

Admin 

Manager 

HR Executive  1 

PRO  1 

Receptionist  1 

Document Controller  1 

Transport‐in‐Charge  1 

Camp Boss  2 

Sales and Estimation  General Sales Manager  1 

Area Sales Engineer  3 

Estimation Engineer  3 

Steel Detailer

 1 

Marketing Executive  1 

Sales & Marketing Assistant  1 

10 

Project Management  Projects Director  1 

Contracts Manager  1 

Project Managers  4 

Project Engineers  5 

Site Engineer  2 

Construction Manager  1 

Quantity Surveyor

 1 Document Controller  1 

16 

Engineering  Engineering Manager  1 

Design Engineer  6 

Steel Detailers  20 

Steel Checkers  6 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 89/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 89 of 95 

CNC Programmer  1  

Document Controller  2  

36 

IT  IT Manager  1  

IT Engineers

 2

 

Attendance Officer  1  

Procurement  Procurement Auditor  1  

Sr. Procurement Officer  1  

Procurement Executive  1  

Procurement Officer  1  

Custom Coordinator  1  

Inventory &

 Warehouse

 Inventory

 &

 Warehouse

 Manager

 1

 

Material Planner  1  

Material Expeditor  2  

Store Foreman  1  

Storekeepers  8  

Store Clerk  1  

14 

Production  Head of  Production  1  

Production Engineer  2  

Assistant Engineer (MPS)  1  

Welding Foreman  9  

CNC Programmers

 2

 

CNC Foreman  1  

Production Coordinator  1  

MPS Supervisor  1  

MPS Chargehand  1  

MPS Foreman  1  

Blasting & Painting Foreman  1  

Blasting Foreman  1  

Painting Supervisor  3  

Painting Foreman  3  

Fabrication Foreman

 15

 

Erection Foreman  1  

Site Formean  1  

Preparation Foreman  1  

Office Clerk  1  

Charge hand  8  

Erection Charge hand  1  

Document Controller  1  

57 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 90/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 90 of 95 

Facilities/Maintenance  Facility Manager  1  

Maintenance Manager  1  

Maintenance Supervisor  1  

Maintenance Foreman  3  

Maintenance Engineer

 1

 

Electrical Foreman  3  

10 

QA/QC  QA/QC Manager  1  

QC Engineers  4  

QC Inspector (Painting)  2  

Document Controller  2  

Printing  Area  Printing Officer  1  

HSE 

HSE Manager

 1

 

Safety Supervisor  1  

Safety Officer  1  

Asst. Safety Officer  2  

Site HSE Officer  1  

Company Nurse  3  

Dispatch/Delivery  Dispatch Supervisor  1  

Dispatch Clerk  1  

Driver ‐ Heavy Truck  3  

Driver  10  

Document Controller

 3

 

Dispatch Foreman  1  

Office Staff  Total  196 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 91/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 91 of 95 

Manpower List – Category: Labor

ASSENT WORKSHOPDesignation  Number 

Asst. Safety officer  1 

Asst. Fabricator  22 

Asst. Maintenance  6 

Asst. Spray Painter  1 

Asst. Steel Erector  2 

Asst. Storekeeper  1 

Blasting Operator  1 

CAG Welder  1 

Charge hand  15 

Clerk 

CNC Machine Operator  35 

Crane Operator  22 

Diesel Mechanic  1 

Dimensional Inspector  22 

Dispatch Chargehand  2 

Dispatch Clerk  1 

Dispatch QC  1 

Electrician  9 

Fabrication Charge hand  1 

Fabricator  170 

Forklift Driver  1 

Forklift Operator  1 

Gardener  1 

Gas Cutter  1 

Helper  252 

Housekeeping  1 

Industrial Wiring Technician  1 

Land Surveyor  1 

Machine Operator  2 

Machine Operator ‐ Blasting  1 

Maintenance Electrician

 1 

Maintenance Technician  1 

Mason  8 

Material Clerk  2 

Material handler  1 

Mechanical Helper  19 

Mechanical Technician  2 

Maintenance Chargehand  1 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 92/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 92 of 95 

Mig Welder  31 

Mixer  4 

Office Boy  2 

Painter  35 

Painting Inspector  2 

Plumber  2 

QC Document Controller  1 

QC Inspector  2 

Radial Drill Operator  2 

Rigger  22 

Security Guard  10 

Shearing Operator  1 

Spray Painter  1 

Steel Erector  46 

Steel Erector

 Chargehand

 1 

Storekeeper  1 

Tack Welder  6 

Team Leader  1 

Technician  1 

Touch‐up Painter  2 

Welder  200 

Welding Charge hand  1 

Welding Inspector  6 

Workshop Total  998 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 93/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 93 of 95 

Equipment List

SN  EQUIPMENT  MAKE  MODEL  CAPACITY 

YEAR OF 

PURCHASE  QTY 

CNC BEAM 

SAWING 

FICEP  1260 LBH 

SAW CAPACITY 1250 X 600mm (max),80 x 

10mm(min) 2009  4 

CNC BEAM 

DRILLING 

FICEP  1203 DF 

SECTION LENGTH(2500‐18000)MM,WEB 

HEIGHT(80‐1220)MM,FLANGE HEIGHT(42‐

510MM) 

2009  4 

3  CNC BEAM COPING  FICEP  1201 RC 

SECTION LENGTH(2500‐12000)MM,WEB 

HEIGHT(80‐1220)MM,FLANGE HEIGHT(42‐

600MM) 

2009  2 

CNC PLATE 

PROCESSING 

FICEP  TIPO A31 

PROCESS PLATE THICKNESS(10‐

130MM),MINIMUM WORK PIECE SPECIFICATION 

L=200,W=150 

2008  1 

FICEP 

TIPO 

B251 

PROCESS PLATE THICKNESS(6‐25MM),MINIMUM 

WORK PIECE

 SPECIFICATION

 L=200,W=150

 2009

 

6  ESAB  EXA 5000 

CUTTING THICKNESS (8‐100MM) 2009  1 

7  ESAB  EXA 4500  2009  1 

8  CNC ANGLE 

PROCESSING 

FICEP  A 164  PROCESS ANGLE DIMENSIONS ( 40 X 40 X 4)‐

(200 X 200 X 20) MAX DIA OF HOLE =32MM 

2008  1 

9  FICEP  A 206  2009  1 

10 

CNC HYDRAULIC 

PUNCH PRESS 

FICEP  801 

PUNCH STROKE LENGTH=40MM,PUNCHING 

POWER=800 KN,MAX THICKNESS=20MM 

2011  2 

11 

CNC PROFILING 

SPC 1000 

HGG  SPC 1000 

PUNCH STROKE LENGTH=40MM,PUNCHING 

POWER=800 KN,MAX THICKNESS=20MM 

2009  1 

12  CNC SHEARING  GIZELIS  G CUT 3010  CUTTING THICKNESS (6‐10MM)  2010  1 

13  CNC BENDING  GIZELIS  G BEND 3290  BENDING THICKNESS 6‐10MM)  2010  1 

14 

RADIAL ARM 

DRILLING MAC 

SIMCO  Z3050 X 16/1 

50MM PLATE THICKNESS DRILLING 

2009  1 

15  SIMCO  RD5016  2010  1 

16  LAROSA  Z3050 X 16/1  2009  1 

17  LAROSA  Z3050 X 16/1  2009  1 

18 

CNC BUILT‐UP 

SECTION 

CMM  BW2000 

WEB HEIGHT 250‐2000MM,WEB THICKNESS 6‐

40MM,FLANGE HEIGHT 150‐600MM,FLANGE 

THICKNESS6‐80MM 

2010  1 

19  PRE‐BLASTING  GIETART  AGW2500  BLASTING WITH 6 WHEEL  2009  3 

20  POST‐BLASTING  GIETART  AGCM3100  BLASTING WITH 10 WHEEL  2009  2 

21 

GENERATOR 

CATERPILAR  3046  PRM  365 KVA  2008  3 

22  CATERPILAR  C15_PRM  500 KVA  2008  3 

23  CATERPILAR  500  500 KVA  2008  3 

24 

CATERPILAR 

LC6 

500KVA 

2008 

25 

COMPRESSOR 

SULLAIR  3710  150‐160 PSI  2010  2 

26  COMP AIR  L37‐10  11 BAR,37KW,3000RPM  2010  2 

27 

DRYER 

SULLAIR  0‐30 BAR (REFERIGERANT 134A)  2010  3 

28  COMP AIR  DC150AX  16‐20BAR (REFERIGERANT 134A)  2010  1 

29  MIG WELDING  ESAB  MIG402C 

230/400‐415/500V,60%DUTY CYCLE 

56/32(43)/26A,100% DUTY CYCLE 43/25/20A 

2009  120 

30  PLASMA MACHINE  ESAB 

POWER CUT‐

1600 

CUT 1‐1/2"(38MM),SEVERS 1‐3/4"(45MM) 

,60%DUTY CYCLE 90AMP 

2010  4 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 94/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Page 94 of 95 

SN  EQUIPMENT  MAKE  MODEL  CAPACITY 

YEAR OF 

PURCHASE  QTY 

31 

GAS MIXING 

MACHINE 

SHARJAH 

OXYGEN 

CO2 

AND 

ARGON 

AT 

BAR 

2010 

32 

ARC WELDING 

ESAB  LHF400 

400V,340W,.90 P.F,35% D.S=400 A/36V,60% 

D.S=315 A/ 33V,100% D.S 250A/30V 

2010  83 

33  LINCOLN 200i DC  220V/1/50/60HZ+/‐10% IP21S/F  2010  60 

34 

GOUGINGMACHINE

MILLER GOLD STAR 602 

20‐590 AMP DC,OPEN CIRCUIT VOLTAGE 

(71),IP=21M,INPUT AMP 51A/3PHASE 

2010  3 

35  SUB ARC LINCOLNIDEAL ARC‐

DC600 

415V/50HZ,80A/64A  2010  2 

36  SUB ARC ESAB LAF‐1000DC  415V/50HZ,74A/67A  2009  2 

37 

OVER HEAD CRANE 

(5 TON) ABUS 

SINGLE GIRDER CROSS TRAVEL 19065MM,HOIST 

WORKING 7200MM 

2009  10 

38 

OVER HEAD CRANE 

(10 TON) ABUS 

SINGLE GIRDER CROSS TRAVEL 19070MM,HOIST 

WORKING 7770MM 

2009  61 

39 

OVER HEAD CRANE 

(15 TON) ABUS 

SINGLE GIRDER CROSS TRAVEL 22070MM,HOIST 

WORKING 7700MM 

2009  14 

40 

ELECTRIC TOLLEY 

(10 TON) WUXI  F21‐E1B TX  10 TON ,8 HOUR BACK UP 36VOLT  2009  9 

41 

ELECTRIC TOLLEY 

(30 TON) WUXI  F21‐E1B TX  16 TON ,8 HOUR BACK UP 75VOLT  2009  8 

42 

ELECTRIC TROLLEY 

CHARGER 

WUXI  DF‐4860D11  36V CHARGING  2009  9 

43 

ELECTRIC TROLLEY 

CHARGER 

WUXI  DF‐4860D11  75V CHARGING  2009  13 

44 

SPRAY PAINTING 

MACHINE 

EXTREME  GRACO‐60:1  220CC(900) PUMP  2009  15 

45 THREADING

 

MACHINE 

RIDGID  1224  1/2" ‐ 2"  2010  3 

46  GRINDER 4 1/2"  MAKITA  GA5010  2010  90 

47  GRINDER 4 1/2"  DEWALT  D28143  2011  100 

48  GRINDER 7"  MAKITA  GA7020  2010  70 

49  GRINDER 7"  DEWALT  D28413  2011  100 

50  GRINDER 7"  DEWALT  D28495  2011  18 

51  DIE GRINDER  MAKITA  GD800C  2011  40 

52  DIE GRINDER  DEWALT  DW887  2011  70 

53  DIE GRINDER  DEWALT  DW28886  2011  20 

7/24/2019 ASSENT Prequalification Document

http://slidepdf.com/reader/full/assent-prequalification-document 95/95

 

STRUCTURAL STEEL 

PRE‐QUALIFICATION DOCUMENT 

Our Location Map