ASME Boiler and Pressure Vessel Code SECTION XI INTERPRETATIONS Volume 36 The Interpretations to the Code will be issued twice a year upto the publication of the 1998 Edition of the Code: each July (designated 7/95, 7/96, and 7/97) and with each Addenda (designated A95, A96, and A97). TheInterpretationsforeachindividualSection are published separately and are part of the update service to that Section; Interpretations of Section 111, Divisions 1 and 2, are part of the update service to Section Ill, Subsection NCA. Interpretations are not part of the Code or the Addenda. Interpretations Volumes 30 through 35 were included with the update service to the 1992 Edition of the Code; Volume 36 is the first Interpretations volume to be included with the update service tothe 1995 Edition. Section Vol. 36 VOl. 37 VOl. 38 VOl. 39 Vol. 40 Vol. 41 I 7/95 I I-A 7/95 It-B 7/95 It-c 11-D Ill-NCA 7/95 IV 7/95 V VI VI1 VIII-1 7/95 Vlll-2 7/95 IX 7/95 X 7/95 XI 7/95 ~ ~~ ~~~ ... ... *.. ... ... Copyright 0 1995 THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS All Rights Reserved Poll15 COPYRIGHT American Society of Mechanical Engineers Licensed by Information Handling Services COPYRIGHT American Society of Mechanical Engineers Licensed by Information Handling Services

description

Asme Sec Xi Int Vol 36

Transcript of Asme Sec Xi Int Vol 36

Page 1: Asme Sec Xi Int Vol 36

ASME Boiler and Pressure Vessel Code SECTION XI

INTERPRETATIONS Volume 36

The Interpretations to the Code will be issued twice a year up to the publication of the 1998 Edition of the Code: each July (designated 7/95, 7/96, and 7/97) and with each Addenda (designated A95, A96, and A97). The Interpretations for each individual Section are published separately and are part of the update service to that Section; Interpretations of Section 111, Divisions 1 and 2, are part of the update service to Section I l l , Subsection NCA. Interpretations are not part of the Code or the Addenda.

Interpretations Volumes 30 through 35 were included with the update service to the 1992 Edition of the Code; Volume 36 is the first Interpretations volume to be included with the update service to the 1995 Edition.

Section Vol. 36 VOl. 37 VOl. 38 VOl. 39 Vol. 40 Vol. 41

I 7/95 I I-A 7/95 It-B 7/95 It-c 11-D Ill-NCA 7/95 IV 7/95 V VI VI1 VIII-1 7/95 Vlll-2 7/95 IX 7/95 X 7/95 XI 7/95

~ ~~ ~~~

. . .

. . .

* . . . . . . . .

Copyright 0 1995 THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS

All Rights Reserved Poll15

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 2: Asme Sec Xi Int Vol 36

INTERPRETATIONS NO. 36 - SECTION XI

Replies to Technical Inquiries July 1, 1994, through December 31, 1994

FOREWORD

General Information

This publication includes all written interpretations issued between the indicated dates by the ASME Staff on behalf of the ASME Boiler and Pressure Vessel Committee in response to inquiries concerning interpretations of the ASME Boiler and Pressure Vessel Code. A contents is also included which lists subjects specific to the interpretations covered in the individual volume. These interpretations are not a part of the Addenda or the Code.

These interpretations are taken verbatim from the original letters, except for a few typographical and editorial corrections made for the purpose of improved clarity. In some instances, a review of the interpretation revealed a need for corrections of a technical nature. In these cases, a revised interpretation is presented bearing the original Interpretation Number with the suffix R and the original file number with an asterisk. Following these revised interpretations, new interpretations and revisions to them issued during the indicated dates are assigned Interpretation Numbers in chronological order. Interpretations applying to more than one Code Section appear with the interpretations for each affected Section.

ASME procedures provide for reconsideration of these interpretations when or if additional information is available which the inquirer believes might affect the interpretation. Further, persons aggrieved by an interpretation may appeal to the cognizant ASME committee or subcommittee. As stated in the Statement of Policy in the Code documents, ASME does not “approve,” “certify,” “rate,” or “endorse” any item, construction, proprietary device, or activity.

Each interpretation applies to the Edition and Addenda stated in the interpretation, or if none is stated, to the Edition and Addenda in effect on the date of issuance of the interpretation. Subsequent revisions to the Code may supersede the interpretation.

For detailed instructions on preparation of technical inquiries to the ASME Boiler and Pressure Vessel Committee, refer to Appendix V in Division 1, Appendix I11 in Division 2, and Appendix VI in Division 3.

Subject and Numerical Indexes

Subject and numerical indexes have been prepared to assist the user in locating interpretations by subject matter or by location in the Code. They cover interpretations issued from Volume 12 up to and including the present volume, and will be updated with each volume.

295

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 3: Asme Sec Xi Int Vol 36

SECTION XI

Subject

Appendix VII, Supplement 1. Part 9; Qualification of NDE Personnel; Supplemental Training - Level III (1986 Edition With 1988 Addenda Through 1992 Edition With 1993 Addenda) ............................................................ (1989 Edition With 1989 Addenda Through 1992 Edition With 1993 Addenda). ................

Appendix VIII, VIII-2100; Piping Welds: Examination of - Calibration Method

Code Case N-416-1; NDE Requirements .................................................... IWA-2600; Weld Reference System - Identification of (Winter 1981 Addenda

IWA-4000/7000; RepairlReplacement Program - Initiation of (1977 Edition With

IWA-4130, IWA-4140; Owner’s Responsibility; RepairlReplacement Activities -

and Later Editions and Addenda Through 1992 Edition) .................................... Summer 1978 Addenda, and Later Editions and Addenda Through 1989 Edition) ...............

Off Site (1983 Edition With Summer 1983 Addenda, and Later Editions and Addenda Through 1989 Edition and Addenda) .........................................

IWA-4130/4150; Construction Code: RepairlReplacement - Design Requirements (1992 Edition With 1993 Addenda) ......................................................

IWA-5300; Records and Reports: Documentation - Test Temperature (1980 Edition and Later Editions and Addenda Through 1993 Addenda) ...................................

IWA-7220; Records and Reports: Documentation - Installation of Replacement (1977 Edition With Summer 1978 Addenda Through 1990 Addenda). .........................

IWB-2200(c) and Tables IWB-2412-1, IWC-2412-1, and IWD-2412-1; Inspection Interval; Inspection Completion Percentages - Calculation of (1983 Edition With Summer 1983 Addenda) ...........................................................

IWB/IWC-2430; Additional Examinations - Similar Components (1977 Edition With Summer 1978 Addenda) ...........................................................

IWC-1221 (1983 Edition With Winter 1983 Addenda Through 1993 Addenda) and Code Cases N-408, N-408-1, N-408-2, and N-408-3; Volumetric and Surface Examinations - Exemptions to (1974 Edition Through 1983 Edition) .........................

IWC-2430; Weld: Additional Examinations - Piping (1989 Edition With 1991 Addenda and Later Editions and Addenda Through 1993 Addenda) ...........................

IWF-2410(b), IWBIIWCIIWD-2410; Inspection Interval; Support Examinations - Percentage Requirements (1983 Edition With Summer 1983 Addenda) .........................

Interpretation

XI-1-95-08

XI-1-95-04 XI-1-95-12

XI-1-95-05

XI-1-95-14

XI-I -95-09

XI-1-95-01

XI-1-95-07

XI- 1-95-02

XI-1-95-11

XI-1-95-13

XI-1-95-03

XI-1-95-06

XI-1-95-10

File No.

IN94-015

IN94-009 IN94-028

IN93-035

IN93-029

IN94-014

IN93-003

IN94-0 1 1

IN93-026

IN94-024

IN93-027B

IN93-042

IN94-002A

IN94-023

297

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 4: Asme Sec Xi Int Vol 36

Section XI - Interpretations No. 36 XI-1-95-01, XI-1-95-02

Interpretation: XI-1-95-01

Subject: Section XI, IWA-4130/4156; Construction Code: Repair/Replacement - Design Requirements (1992 Edition With 1993 Addenda)

Date Issued: October 12, 1994

File: IN93-003

Question (1): If the Owner, during the process of performing a repair or replacement, determines that the current loading(s) for the item being evaluated is more severe than what was originally evaluated and documented in the Owner’s Specification or original Construction Code Design or Stress Report (if applicable), is it a requirement of IWA-4130 and IWA-4150 that the repair or item to be used for replacement be evaluated to determine if Construction Code design requirements are satisfied for the new or revised loadings?

Reply (1): Yes.

Question (2): If the Owner, through the normal course of performing routine design review activities, determines that the current loading(s) for an item presently installed in the plant is more severe than what was originally evaluated and documented in the Owner’s Specification or the original Construction Code Design or Stress Report (if applicable), is it a requirement of Section XI that such conditions be evaluated to determine if Construction Code design requirements are satisfied for the new or revised loadings?

Reply (2): Section XI currently does not address this situation.

Interpretation: XI-1-95-02

Subject: Section XI, IWA-7220; Records and Reports: Documentation - Installation of Replace- ment (1977 Edition With Summer 1978 Addenda Through 1990 Addenda)

Date Issued: October 12, 1994

File: IN93-026

Question: Is it a requirement of IWA-7220 that the evaluation be documented prior to authorizing installation of the replacement?

Reply: No, the requirement does not specify the time for documentation.

299

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 5: Asme Sec Xi Int Vol 36

XI-1-95-03, XI-1-95-04 Section XI - Interpretations No. 36

Interpretation: XI-1-95-03

Subject: Section XI, IWC-1221 (1983 Edition With Winter 1983 Addenda Through 1993 Addenda) and Code Cases N-408, N-408-1, N-408-2, and N-408-3; Volumetric and Surface Examinations - Exemptions to (1974 Edition Through 1983 Edition)

Date Issued: October 12, 1994

File: IN93-042

Question (1): Does IWC-l221(c) exempt piping located between a refueling water storage tank and pump suction side isolation valves in statically pressurized, passive (i.e., no pump) portions of safety injection systems of pressurized water reactor plants from the surface and volumetric examination requirements of examination categories C-F-1 or C-F-2?

Reply (1): No.

Question (2): Do Code Cases N-408, N-408-1, N-408-2, and N-408-3 para. (a)(5) exempt piping located between a refueling water storage tank and pump suction side isolation valves in statically pressurized, passive (i.e., no pump) portions of safety injection systems of pressurized water reactor plants from the surface and volumetric examination requirements of examination categories C-F-1 or C-F-2?

Reply (2): No.

Interpretation: XI-1-95-04

Subject: Section XI, VIII-2100; Piping Welds: Examination of - Calibration Method (1989 Edition With 1989 Addenda Through 1992 Edition With 1993 Addenda)

Date Issued: October 12, 1994

File: IN94-009

Question: Does a system calibration which provides for a calibrated sweep and establishes a criterion for sensitivity based upon the minimum noise level from the I.D. surface satisfy the requirements of VIII-2100(c) for a calibration method for examination of piping welds, provided the calibration method is successfully demonstrated in accordance with the applicable Appendix VI11 Supplement?

Reply: Yes.

300

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 6: Asme Sec Xi Int Vol 36

Section XI - Interpretations No. 36

Interpretation: XI-1-95-05

XI-1-95-05, XI-1-95-06, XI-1-95-07

Subject: Section XI, IWA-2600; Weld Reference System - Identification of (Winter 1981 Addenda and Later Editions and Addenda Through 1992 Edition)

Date Issued: Ocotober 13, 1994

File: IN93-035

Question: Is it the intent of IWA-2610 to physically mark piping with reference points designating regular intervals along the weld length?

Reply: No.

Interpretation: XI-1-95-06

Subject: Section XI, IWC-2430; Weld: Additional Examinations - Piping (1989 Edition With 1991 Addenda, and Later Editions and Addenda Through 1993 Addenda)

Date Issued: October 13, 1994

File: IN94-002A

Question: Does IWC-2430 require the number of additional examinations to be twenty percent of the number of piping welds included in the inspection item scheduled to be performed during the interval?

Reply: Yes, however, the number of additional examinations shall also be limited to the welds of similar material and service.

Interpretation: XI-1-95-07

Subject: Section XI, IWA-5300; Records and Reports: Documentation - Test Temperature (1980 Edition and Later Editions and Addenda Through 1993 Addenda)

File: IN94-0 1 1

Question: Does IWA-5300 require the documentation of test temperature?

Reply: No.

301

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 7: Asme Sec Xi Int Vol 36

XI-1-95-08, XI-1-95-09 Section XI - Interpretations No. 36

Interpretation: Xl-1-95-08

Subject: Section XI, Appendix VII, Supplement 1, Part 9; Qualification of NDE Personnel; Supplemental Training - Level I11 (1986 Edition With 1988 Addenda Through 1992 Edition With 1993 Addenda);

Date Issued: October 13, 1994

File: IN94-0 15

Question: Is it the intent that a qualified NDE instructor who produces the course outline, researches and determines course content, develops and presents course lectures and practical exercises (laboratory or classroom activities), and composes examinations to assess the assimilation of information by students may claim one-time credit for the Appendix VII, Supplement 1, Part 9 Level I11 supplemental training as received by students under his tutelage, if permitted by his organization’s written practice?

Reply: Yes.

Interpretation: XI-1-95-09

Subject: Section XI, IWA-4130 and IWA-4140; Owner’s Responsiblity; Repair/Replacement Activities - Off Site (1983 Edition With Summer 1983 Addenda, and Later Editions and Addenda Through 1989 Edition and Addenda

Date Issued: October 14 1994

File: IN94-0 14

Question (1): When a vendor performs off-site Section XI repair/replacement activities (e.g., repair welding) on existing plant equipment which has been removed with the intention of reinstallation, and further Section XI repair/replacement activities (e.g.. nondestructive examination or hydrostatic testing) will be performed by the Owner prior to or concurrent with reinstallation, is the Owner responsible for imposing Section XI requirements on the vendor?

Reply (1): Yes.

Question (2): When a vendor performs repair/replacement activities off-site on removed plant equipment and further repair/replacement activities by the Owner or repair organization prior to reinstallation of the item will not be required, is the Owner responsible for imposing Section XI requirements on the vendor?

Reply (2): Yes, for items removed from systems which have been placed in operation see Interpretation XI-1-83-10.

302

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 8: Asme Sec Xi Int Vol 36

Section XI - Interpretations No. 36 XI-1-95-10, XI-1-95-11

interpretation: XI-1-95-10

Subject: Section XI, IWF-2410(b), IWB-2410, IWC-2410, and IWD-2410; Inspection Interval; Support Examinations - Percentage Requirements (1983 Edition With Summer 1983 Addenda)

Date Issued: October 14, 1994

File: IN94-023

Question: Does IWF-241O(b) require support examinations be subject to the requirements of IWB- 2410, IWC-2410, and IWD-2410?

Reply: No.

Interpretation: Xi-1-95-11

Subject: Section XI, IWB-2200(c) and Tables IWB-2412-1, IWC-2412-1, and IWD-2412-1; Inspection Interval; Inspection Completion Percentages - Calculation of (1 983 Edition With Summer 1983 Addenda)

Date Issued: October 14. 1994

File: IN94-024

Question (1): When new components are added to the inspection program, at what time are new examinations to be included in the inspection program for the purpose of calculating completion percentages in accordance with Tables IWB-2412-1, IWC-2412-1, and IWD-2412-l?

Reply (1): Section XI does not address addition of new components to the inspection program. However, requirements were added to the 1994 Addenda of the 1992 Edition.

Question (2): When new components are added to the inspection program, does preservice examination performed in accordance with IWB-2200(c) count as a completed examination in calculating completion percentages in accordance with Table IWB-2412- 1 ?

Reply (2): No.

303

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 9: Asme Sec Xi Int Vol 36

XI-1-95-12, XI-1-95-13, XI-1-95-14 Section XI - Interpretations No. 36

Interpretation: XI-1-95-12

Subject: Section XI, Code Case N-416- 1 ; NDE Requirements

Date Issued: October 14, 1994

File: IN94-028

Question: When using Code Case N-416-1 is it a requirement that, in addition to the NDE specified in the Case, the NDE requirements specified in the Owner’s requirements shall also be met?

Reply: Yes, the Owner’s requirements are defined in the 1993 Addenda to the 1992 Edition.

Interpretation: XI-1-95-13

Subject: Section XI, IWB /IWC-2430; Additional Examinations - Similar Components (1977 Edition With Summer 1978 Addenda)

Date Issued: October 20, 1994

File: IN93-027B

Question: Is it the intent of IWB/IWC-2430(a) to limit the required number of additional examinations to an equal number of examinations as performed initially on similar vessels, piping, pumps, or valves within the system which contained the indication?

Reply: Yes. -

Interpretation: XI-1-95-14

Subject: Section XI, IWA-4000/7000; Repair/Replacement Program - Initiation of (1977 Edition With Summer 1978 Addenda, and Later Editions and Addenda Through 1989 Edition)

Date Issued: December 14, 1993

File: IN93-029

Question (1): Does Section XI specify when to begin a repair or replacement activity?

Reply (1): Section XI provides rules for specific repair and replacement activities but not when to begin a repair or replacement activity.

Question (2): Is it a requirement of IWA-4OOO and IWA-7OOO that a repair or replacement plan be initiated for obtaining items intended to be installed, at a later date, in Section XI components or systems?

Reply (2): No.

304

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 10: Asme Sec Xi Int Vol 36

Location

Subsection IMA IMA-5200 IMA-5210

Subsection IMB Table IMB-2500-1 IMB-5000 IMB-5100

Subsection IMC IMC-2500

Subsection IMF

IMF-2500

Subsection IWA

IMF-1500

I WA- 1200 IWA-1310 IWA-1320

IWA-1400

I WA-2000

I WA-2 1 00 IWA-2120

IWA-2130 IWA-2200 IWA-2214 IWA-2222 IWA-2232

IWA-2240 IWA-2300

Interpretation

XI-3-89-02 XI-3-89-02

XI-3-89-01 XI-3-89-01 XI-3-86-01

XI-3-89-01

XI-3-83-01 XI-3-83-01

XI-1-86-07 XI-1 -83-78 XI-1 -83-44 XI-1 -83-77 XI-1-83-78 XI-1 -89-64 XI-1-89-64R XI-1 -92-02 XI-1-83-71 XI-1-83-71 R XI-1-86-22 XI-1-83-48 XI-1-86-64 XI-1 -83-79 XI-1 -89-02 XI-1 -83-69 XI-1-83-64 XI-1 -83-29 XI-1 -83-31 XI-1-83-84 XI-1-86-71 XI-1-86-72 XI-1-89-09 XI-1-89-1 3 XI-1 -89-49 XI-1 -86-28 XI-1 -83-1 6 XI-1 -83-1 8 XI-1-83-23 XI-1-83-24 XI-1 -83-29 XI-1 -83-40

NUMERICAL

File No. -

IN86-024B lN86-0248

IN86-024C IN86-024C IN86-024A

IN86-024C

BC81-330 BC81-330

BC85-481 BC84-682 BC83-448 BC84-603 BC84-682 IN89-0178 IN89-017B' IN91 -01 2 BC80-583 BC80-583' IN86-010 BC84-177 11'487-028A BC84-684 IN88-001 BC84-616 BC84-562 BC82-050 BC82-630 BC83-654 IN87-005A IN87-005B IN87-019 IN89-005 IN90-013 lN86-008 BC82-775 BC83-060 BC83-056 BC83-178 BC82-050 BC84-043

Cumulative Index - Interpretations Vols. 12-36

Page No. -

21 1 21 1

169 169 153

169

11 11

94 76 50 76 76

231 241 242

71 90

108 52

147 77

165 69 60 32 33 80

156 156 168 176 21 7 111

20 21 29 29 32 42

INDEX

Location

IWA-2300(a) IWA-2300(a)(l)

IWA-23OO(C) IWA-2300(d) IWA-2300(e)

IWA-2324 IWA-2325

IWA-2400

IWA-2410 IWA-2430(d) IWA-2600

IWA-3100

IWA-3200 IWA-3400

IWA-3410 IWA-4000

Interpretation

XI-1-83-40R XI-1 -83-45 XI-1 -83-63 XI-1-83-82 XI-1-86-40 XI-1-86-56 XI-1 -86-66 XI-1-89-06 XI-1-89-26 XI-1 -92-39 XI-1-92-42 XI-1 -92-70 XI-1 -86-1 6 XI-1 -86-1 9 XI-1-86-73 XI-1-92-28 XI-1 -86-1 9 XI-1-83-01 XI-1-83-36 XI-1 -92-54 XI-1 -92-54 XI-1-92-70 XI-1-86-54 XI-1-89-58 XI-1-83-41 XI-1-92-57 XI-1-92-06 XI-1-95-05 XI-1 -89-1 6 XI-1 -89-45 XI-1-92-38 XI-1-86-52 XI-1-86-52R XI-1-83-1 7 XI-1 -83-1 0 XI-1 -83-1 3 XI-1-83-28 XI-1 -83-28R XI-1 -83-50 XI-1-83-50R XI-1 -83-65 XI-1-83-66 XI-1-86-1 3R XI-1-86-36 XI-1 -86-41 XI-1-86-44 XI-1 -86-47 XI-1 -86-44R XI-1 -86-59

File No. -

BC84-043; BC83-535 BC84-310 BC83-176 BC85-571 lN86-028 IN87-015 lN88-006 BC80-231* lN92-032 lN92-030 lN93-022 BC85-142 BC85-071 lN87-029 IN92-019 BC85-071 BC80-582 BC83-585 IN93-015 IN93-015 lN93-022 IN87-001 lN90-025 BC84-064 lN93-002 IN91 -01 9 lN93-035 IN89-001 B IN90-006 lN92-031 BC85-524 BC85-524* BC82-597 BC82-277 BC82-407 BC83-344 BC83-344* BC84-175 BC84-175* BC84-647 BC84-652 BC85-111* lN86-021 lN86-005 IN86-015 lN86-0258 IN86-015. BC85-550

Page No.

67 50 60 78

123 137 153 167 194 267 268 293 105 106 157 257 106

5 40

276 276 293 136 228 43

282 244 301 178 209 266 135 187

20 17 18 31

185 54 68 61 61

225 121 1 24 126 127 144 145

-

(a)

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 11: Asme Sec Xi Int Vol 36

Location Interpretation

Subsection IWA (Cont'd) XI-1 -86-55 XI-1-86-55R XI-I -89-28 XI-1 -89-30 XI-1 -89-40 XI-1-89-56 XI-I -89-64 XI-I -89-64R XI-1-92-21 XI-1-92-31 XI-1-92-68 XI-1 -95-09 XI-1-95-14

IWA-4100 XI-81-1 1 R XI-1 -83-26 XI-1-83-26R

IWA-4120 XI-1-83-40 XI-1 -83-40R XI-1 -83-57 XI-1 -86-38 XI-1 -92-32 XI-1 -92-60

IWA-4130 XI-1-83-57 XI-1-92-06

IWA-4150 XI-1-95-01 IWA-4200 XI-1-83-57

XI-1-92-35 XI-1-92-35R

I WA-42 1 0 XI-1 -89-01 IWA-4300 XI-1-83-43

XI-1-83-55 XI-1-83-81 XI-1 -89-01 XI-1 -92-08 XI-I -92-59

IWA-4310 XI-1 -83-83 IWA-4330 XI-1-89-35 IWA-4400 XI-1-83-05

XI-1-83-28 XI-1-83-34 XI-1 -83-35 XI-1 -83-37 XI-1-83-37R2 XI-1 -83-54R XI-1-83-58 XI-1-86-25 XI-1 -86-75 XI-I -89-1 8 XI-I -89-1 9

IWA-4400(a) XI-I -83-3513 XI-1 -89-31

IWA-4400(b)(5) XI-1 -83-351 XI-1 -83-58 XI-1-86-35

IWA-4500 XI-1-86-51 IWA-4600 XI-I -83-26

XI-1-83-26R XI-1 -83-54R XI-1 -83-85 XI-1-83-86 XI-1-83-86R XI-1-86-51

File No. -

lN87-002 lN87-002' IN89-021 IN89-011 IN89-017A IN90-022 IN89-0178 IN89-017B* IN92-009B IN91 -01 8 lN94-005 lN94-014 lN93-029 BC81-369* BC83-244 BC83-244' BC84-043 BC84-043' BC84-392 BC85-141 IN91-031 lN93-024 BC84-392 IN91 -01 9 IN93-003 BC84-392 lN92-023 lN92-023* lN87-036 BC84-179 BC84-322 BC84-687 lN87-036 lN91-024 lN93-023 BC83-179 lN89-006 BC82-425 BC83-344 BC83-587 BC83-588 BC82-425 BC82-425** BC84-321* BC84-422 BC85-528 lN87-032 lN86-031 lN88-009 BC83-588* lN89-023 BC83-588* BC84-422 lN86-019 lN86-027 BC83-244 BC83-244* BC84-321* BC84-683 BC85-113A BC85-113A* lN86-027

Page No. - 137 153 195 202 207 227 231 241 254 263 292 302 304 87 30 87 42 67 57

122 263 283

57 244 299

57 265 289 165 44 56 78

165 245 282

79 204

7 31 39 40 41

185 186

57 110 158 188 188 67

203 67 57

120 129 30 87

186 81 82

102 129

Location

IWA-5000

IWA-5200

Table IWA-5210-1

IWA-5211

IWA-5212 IWA-5213 IWA-5214

IWA-5220 IWA-5224

IWA-5240

IWA-5241 IWA-5242

IWA-5244

IWA-5250

Interpretation

XI-1-92-65 XI-1-83-05 XI-1-83-54 Xi-1-86-35 XI-1-89-08 XI-I -89-1 8 XI-1-83-35 XI-I -86-1 3 XI-1-83-70 XI-1-83-70R XI-1-92-19 XI-1-83-1 9 XI-1 -83-34 XI-I -83-49 XI-1-83-63 XI-1-83-70 XI-1-83-70R XI-I -86-03 XI-1 -86-03R XI-1-86-13R XI-1 -86-34 XI-1-86-53 XI-1-89-1 5 XI-1-89-33 XI-1-92-04 XI-I -92-18 XI-1-92-23 XI-1-86-46 XI-1-86-46 XI-1-83-63 XI-1-83-63R XI-I -83-70 XI-1-83-70R Xi-1-86-1 3R XI-1-86-27 XI-1-86-27R XI-1-86-29 XI-I -86-2913 XI-1 -89-08 XI-1-89-37 XI-1-89-42 XI-1-89-52 XI-1 -92-30 XI-1-89-45 XI-1-83-67 XI-1-89-54 XI-1-83-63 XI-1-92-34 XI-1 -92-64 XI-1-89-39 XI-I -89-39R XI-1 -92-64 XI-I -92-47 XI-1-92-64 XI-1-83-1 9 XI-1 -92-52 XI-1 -89-64 XI-I -89-6413 XI-1-92-01 XI-1-92-03 XI-1-92-1 9 XI-1-92-31 XI-1 -92-48

File No. -

IN94-001 BC82-425 BC84-321 lN86-019 IN87-018 lN86-031 BC83-588 BC85-111 BC84-198 BC84-198' lN92-005 BC82-607 BC83-587 BC82-776 BC84-310 BC84-198 BC84-198* BC83-112 BC83-112* BC85-111* IN86-0178 IN86-017A IN88-002A IN88-017 IN91 -009 lN92-003 IN86-017B 1N86-023 lN86-023 BC84-310 BC84-310* BC84-198 BC84-198' BC85-111* lN86-007 lN86-007* lN86-009 lN86-009* lN87-018 IN88-002C IN90-001 lN88-0028 IN92-015 IN90-006 BC82-606 IN90-018B BC84-310 lN92-020 lN93-038 IN89-013A IN89-013A' lN93-038 lN92-046 lN93-038 BC82-607 lN93-005 IN89-0176 IN89-017B8 lN90-023 IN91-017 lN92-005 IN91-018 IN93-001

Page No.

290 7

55 120 168 188 40

104 70

201 253

27 39 53 60 70

201 92

103 225 120 136 178 203 243 253 255 127 127 60

101 70

201 225 111 187 112 143 168 205 208 21 9 258 209

62 226

60 2 64 290 206 289 290 274 2 90

27 276 231 241 242 242 253 263 2 74

-

Cumulative Index - Interpretations Vols. 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 12: Asme Sec Xi Int Vol 36

Location Interpretation

Subsection IWA (Cont'd) XI-1 -92-64

IWA-5260 XI-1 -89-74 XI-1 -92-1 0

IWA-5262 XI-1 -83-49 XI-1 -83-49R

IWA-5265 XI-1 -86-75 XI-1 -89-54 XI-1 -89-66

IWA-5300 XI-1 -95-07 IWA-5350 XI-1 -92-51 IWA-6000 XI-1-86-14

XI-1 -86-1 4R XI-1 -89-64 XI-1 -89-64R XI-1 -92-02

IWA-6230 XI-1-83-03 XI-1-83-08 XI-1 -83-1 5

IWA-6300 XI-1 -89-48 IWA-7000 XI-1 -83-28

XI-1-83-28R XI-1-83-38 XI-1 -83-42 XI-1-83-46 XI-1 -83-47 XI-1 -83-50 XI-1 -83-50R XI-1 -83-52 XI-1 -83-54 XI-1-83-65 XI-1 -83-66 XI-1 -86-1 3R XI-1 -86-44 XI-1 -86-44R XI-1 -86-47 XI-1 -86-55 XI-1 -86-55R XI-1 -86-58 XI-1 -86-65 XI-1-89-22 XI-1 -89-40 XI-1-89-56 XI-1 -89-64 XI-1-89-64R XI-1-92-31 XI-1-95-09 XI-1-95-1 3 XI-1-89-34 XI-1-83-83 XI-1 -83-20 XI-1 -83-21 XI-1 -83-21 R XI-1 -83-40 XI-1 -83-4013 XI-1 -83-72 XI-1 -86-08 XI-1 -86-1 2 XI-1 -86-59 XI-1 -89-07 XI-1-89-20 XI-1-89-24 XI-1-89-29

IWA-7120 IWA-7121 IWA-7210

File NO. -

lN93-038 IN91-008 IN91-029 BC82-776 BC82-776. lN87-032 IN90-0188 IN90-018A IN94-011 IN93-011 BC85-112 BC85-112* IN89-0178 IN89-0178' IN91-012 BC82-406 BC82-523 BC82-610 IN90-011 BC83-344 BC83-344* BC84-122 BC84-123 BC83-595 BC84-197 BC84-175 BC84-175' BC83-625 BC84-321 BC84-647 BC84-652 BC85-111* IN86-015 IN86-015* lN86-0258 lN87-002 IN87-002* IN87-010 lN87-031 IN89-009 IN89-017A lN90-022 IN89-017B IN89-0178* IN91 -01 8 lN94-014 lN93-0278 IN89-012 BC83-179 BC82-430 BC82-434 BC82-434* BC84-043 BC84-043* BC81-568A BC81-5688 BC85-098 BC85-550 IN88-011 lN88-014 IN89-014 lN89-008

Cumulative Index - Interpretations Vois. 12-36

Page NO. - 290 235 246

53 89

158 226 232 301 275 104 118 231 241 242

6 9

19 21 7

31 185 41 43 51 52 54 68 55 55 61 61

225 126 144 127 137 153 138 148 191 207 227 231 241 263 302 3 04 204

79 27 28

117 42 67 72 94

103 145 167 189 193 202

Location

IWA-7210(~)

IWA-7220

IWA-7300

IWA-7310 IWA-7320 IWA-7330

IWA-7400

IWA-7400(d)

IWA-7520

IWA-7530

Subsection IWB IWB-l220(a)

IWB-l22O(b) IWB-2200

IWB-2410 IWB-2412 Table IWB-2412-1

IWB-2430(a) IWB-2430

IWB-2500 Fig. IWB-2500-7 Fig. IWB-2500-8

Interpretation

Xi-1 -89-34 XI-1-89-46 XI-1 -89-461 XI-1 -89-68 XI-1 -86-1 8 XI-1 -86-38 XI-1 -86-38R XI-1 -86-39 XI-1 -86-39R XI-1 -89-41 XI-1 -92-1 5 XI-1-95-02 XI-1 -83-72 XI-1-86-03 XI-1 -86-03R XI-1 -86-08 XI-1-83-50R XI-1 -83-72 XI-1 -83-02 XI-1-83-46 XI-1-83-72 XI-1-89-24 XI-1-83-37 XI-1-83-37R2 XI-1 -83-54R XI-1-89-36 XI-1 -92-27 XI-1-83-26 XI-1 -83-83 XI-1 -83-85 XI-1-83-86 XI-1-83-86R XI-1-86-65 XI-1-89-04 XI-1-92-32 XI-1-92-44 XI-1-92-66 XI-1-83-38 XI-1-86-68 XI-1-83-37 XI-1-86-51 XI-1-89-36

XI-1 -92-40 XI-1 -92-45 XI-1 -86-45 XI-1 -86-20 XI-1 -86-50 XI-1 -89-63 XI-1 -86-24 XI-1 -83-71 XI-1-95-1 1 XI-1 -95-1 0 XI-1 -86-74 XI-1-92-1 2 XI-1-92-24 XI-1-92-61 XI-1-95-1 3 XI-1-92-40 XI-1-86-71 XI-1-83-75 XI-1-89-49

File No. -

IN89-012 IN90-008 IN90-008* IN90-015 BC85-254 BC85-141 BC85-141* BC85-525C BC85-525C' lN89-025 IN91-040 lN93-026 BC81-568A BC83-112 BC83-112* BC81-5688 BC84-175* BC81-568A BC81-476 BC83-595 BC81-568A lN89-014 BC82-425 BC82-425** BC84-321* lN89-024 IN92-016 BC83-244 BC83-179 BC84-683 BC85-113A BC85-113A' IN87-031 lN88-004 IN91-031 IN91 -031 B lN93-041 BC84-122 lN87-024 BC82-425 lN86-027 lN89-024

IN92-022A lN92-0228 lN86-020 lN86-006 IN86-026C IN90-034 BC85-526 BC80-583 lN94-024 lN94-023 IN86-003A IN91 -025 IN91-014 IN93-027A lN93-0278 IN92-022A IN87-005A BC83-055 IN90-013

Page NO.

204 210 225 232 106 122 143 123 144 207 252 299

72 92

103 94 68 72

6 51 72

193 41

185 186 205 257

30 79 81 82

1 02 148 166 263 273 291

41 154 41

129 205

-

267 273 126 107 128 230 1 09

71 303 303 157 251 255 283 304 267 156

75 21 7

(C)

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 13: Asme Sec Xi Int Vol 36

Location Interpretation

Subsection IWB (Cont'd) Fig. IWB-2500-13

Fig. IWB-2500-14 Fig. IWB-2500-15

Table IWB-2412-1 Table IWB-2500-1

Table IWB-2600-1

IWB-3000

IWB-3112 IWB-3142 IWB-3144 Table IWB-3410-1 IWB-3500

Table IWB-3510-1 IWB-3512 IWB-3514.2 Table IWB-3514-2 IWB-3517.1

XI-1 -83-75 XI-1-89-21 XI-1 -89-27 XI-1 -89-21 XI-1 -89-21 XI-1 -89-27 XI-1 -95-1 1 XI-1-83-1 1 XI-1-83-12 XI-1-83-33 XI-1-83-39 XI-1-83-40R XI-1-83-51 XI-1 -83-56 XI-1 -83-69 XI-1 -83-76 XI-1 -86-04 XI-1 -86-1 0 XI-1-86-20 XI-1-86-21 R XI-1-86-24 XI-1-86-34 XI-1-86-45 XI-1 -86-62 XI-1 -86-71 XI-1 -86-74 XI-1 -89-1 1 XI-1 -89-1 4 XI-1 -89-21 XI-1-89-27 XI-1 -89-33 XI-1 -89-43 XI-1 -89-49 XI-1-89-50 XI-1-92-05 XI-1-92-09 XI-1 -92-1 2 XI-1-92-1 3 XI-1-92-23 XI-1 -92-43 XI-1 -92-46 XI-1-92-56 XI-1 -83-51 XI-1 -86-1 0 XI-1-86-07 XI-1-86-52R XI-1-89-67 XI-1 -92-1 9 XI-1-92-35 XI-1 -92-35R XI-1 -86-37 XI-1-86-62 XI-1 -86-62 XI-1 -92-24 XI-1-83-29 XI-1-86-52 XI-1-86-52R XI-1-83-06 XI-1-83-32 XI-1-92-58 XI-1 -83-07 XI-1-89-45

File No. -

BC83-055 IN89-004A IN89-004C IN89-004A IN89-004A IN89-004C lN94-024 BC82-304 BC82-230 BC83-589 BC83-527 BC84-043* BC83-240 BC84-388 BC84-616 BC84-390 BC83-438 BC84-393 lN86-006 lN86-004* BC85-526 IN86-017B lN86-020 lN86-032 IN87-005A IN86-003A lN88-016 IN86-003B IN89-004A IN89-004C IN88-017 IN90-003 IN90-013 IN90-014 IN91 -01 6 IN91 -027 lN91-025 IN91 -026 IN86-0178 lN92-033 lN92-043 IN93-013 BC83-240 BC84-393 BC85-481 BC85-524. IN89-017C lN92-005 lN92-023 lN92-023' lN86-022 lN86-032 lN86-032 IN91-014 BC82-050 BC85-524 BC85-524' BC82-428 BC82-437 lN93-021 BC82-429 IN90-006

Page No. -

75 1 90 195 190 190 195 303

17 18 39 42 67 54 56 69 75 92 95

107 186 109 120 126 146 156 157 175 176 190 195 203 208 21 7 21 8 243 245 251 251 255 268 2 74 281

54 95 94

187 232 253 265 289 121 146 146 255

32 135 187

8 33

282 8

209

Location

IWB-3600 IWB-4000

IWB-4212 IWB-4300 IWB-4340

IWB-4400

IWB-5000 IWB-5200

IWB-5210 IWB-5222

Subsection IWC IWC-1200 IWC-1220

IWC-1221

IWC-2000 IWC-2 100 IWC-2200 IWC-2410 IWC-2411 IWC-2412 Table IWC-2412-1 IWC-2430

Table IWC-2500-1

Fig. IWC-2500-5 IWC-2520 Table IWC-2520

Table IWC-2600-1

Interpretation

XI-1 -83-29 XI-1 -86-41 Xi-1 -92-21 XI-1 -89-70 XI-1 -92-32 XI-1 -83-09 XI-1-83-09R XI-1-83-41 XI-1-83-41 R XI-1-89-08 XI-1-86-34 XI-1-92-23 XI-1 -83-25 XI-1 -89-74

XI-1-83-27R XI-1-83-27 XI-1-86-43 XI-1-86-43R XI-1-89-53 XI-1-89-61 XI-1 -86-05 XI-1-86-42 XI-1-95-03 XI-1-86-57 XI-1-86-22 XI-1-89-42 XI-1-95-1 0 XI-1-83-68 XI-1 -86-74 XI-1 -95-1 1 XI-1-83-04 XI-1 -92-24 XI-1-95-06 XI-1-92-61 XI-1-95-1 3 XI-1-83-39 XI-1-83-40R XI-1-83-51 XI-1 -83-53 XI-1 -83-69 XI-1 -83-80 XI-1-83-80R XI-1-86-57 XI-1-86-74 XI-1-89-21 XI-1-89-30 XI-1-89-43 XI-1-89-51 XI-1-89-53 XI-1 -89-57 XI-1-89-58 XI-1-89-61 XI-1 -89-75 XI-1-92-05 XI-1-92-47 XI-1-92-62 XI-1-89-38 XI-1-83-27 XI-1-83-51 XI-1-83-68 XI-1-83-51

File No. -

BC82-050 lN86-005 IN92-009B IN91 -005 IN91-031 BC82-604 BC82-604' BC84-064 BC84-064* lN87-018 IN86-0178 IN86-0178 BC83-219 IN91 -008

BC83-437* BC83-437 IN86-012 IN86-012' IN90-019 IN90-032 BC84-686 IN86-011 lN93-042 lN87-007 IN86-010 IN90-001 lN94-023 BC83-441 IN86-003A lN94-024 BC82-427 IN91-014 IN94-002A IN93-027A lN93-0278 BC83-527 BC84-043* BC83-240 BC83-656 BC84-616 BC84-685 BC84-685* lN87-007 IN86-003A IN89-004A IN89-011 IN90-003 IN90-017 IN90-019 IN90-024 IN90-025 IN90-032 IN91 -01 0 IN91 -01 6 lN92-046 lN93-030 lN89-007 BC83-437 BC83-240 BC83-441 BC83-240

Page No.

32 124 254 233 263

9 10 43 88

168 120 255

30 235

-

88 31

125 125 219 229 93

124 300 138 108 208 303

62 157 303

7 255 301 283 304 42 67 54 55 69 77

241 138 157 190 202 208 21 8 21 9 227 228 229 235 243 274 284 206

31 54 62 54

Cumulative Index - Interpretations Vols. 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 14: Asme Sec Xi Int Vol 36

Location Interpretation

Subsection IWC Kont'd)

IWC-3000

IWC-3112 IWC-4000 IWC-5000

IWC-5210

IWC-521 O(a) IWC-5222

IWC-5223 IWC-7000

Subsection IWD IWD-1220 IWD-2000 IWD-2410 Table IWD-2412-2 Table IWD-2500-1

IWD-2600 IWD-2620 IWO-3000

IWD-4000 IWD-5000

IWD-5210 IWD-5223

IWD-7000

Subsection IWE Table IWE-2500-1

IWE-3519.3

Subsection IWF IWF

XI-1 -83-68 XI-1-83-68R XI-1-89-67 XI-1-92-19 XI-1-92-24 XI-1 -92-35 XI-1-92-35R XI-1-86-37 XI-1-86-27R XI-1 -86-32 XI-1-89-08 XI-1 -92-34 XI-1-83-25 XI-1 -92-1 8 XI-1-92-62 XI-1-83-67 XI-1-86-09 XI-1-89-30 XI-1-89-66 XI-1-89-74 XI-1-83-67 XI-1-86-27R

XI-1 -89-47 XI-1 -86-67 XI-1-95-10 XI-1 -95-1 1 XI-1-83-40R XI-1 -83-69 XI-1 -86-1 5 XI-1 -86-1 5R XI-1-86-69 XI-1-89-43 XI-1-89-58 XI-1 -89-75 XI-1 -92-05 XI-1-83-27 XI-1 -89-47 XI-1-89-67 XI-1-92-19 XI-1 -92-35 XI-1 -92-35R XI-1-86-27R XI-1 -86-32 XI-1 -89-08 XI-1-92-34 XI-1-92-1 8 XI-1-83-67 XI-1-89-66 XI-1-89-74 XI-1-86-27R

XI-1-86-70 XI-1 -89-43 XI-1 -92-33 XI-1 -92-33

XI-1 -86-02 XI-1-86-11

File No. -

BC83-441 BC83-441* IN89-017C lN92-005 IN91-014 lN92-023 lN92-023* lN86-022 lN86-007' BC85-5258 IN87-018 lN92-020 BC83-219 lN92-003 lN93-030 BC82-606 BC84-391 IN89-011 IN90-018A IN91 -008 BC82-606 lN86-007'

IN90-009 lN87-022 lN94-023 lN94-024 BC84-043' BC84-616 BC85-130 BC85-130* IN87-008 IN90-003 IN90-025 IN91 -01 0 IN91 -01 6 BC83-437 IN90-009 IN89-017C IN92-005 lN92-023 lN92-023' lN86-007' BC85-5258 lN87-018 lN92-020 lN92-003 BC82-606 IN90-018A IN91 -008 lN86-007'

IN87-011 IN90-003 IN91-043 lN91-043

BC82-753 BC85-253A

Cumulative Index - Interpretations Vols. 12-36

Page No. -

62 101 232 253 255 265 289 121 187 119 168 264

30 253 284

62 94

202 232 235

62 187

21 0 154 303 303

67 69

105 135 155 208 228 235 243

31 21 0 232 253 265 289 187 119 168 2 64 253 62

232 235 187

155 208 264 264

91 96

Location

IWF-1100 IWF-1300

IWF-2000 IWF-2200

IWF-2410(b) IWF-2430

IWF-2500

Table IWF-2500-1

Table IWF-2500-2 IWF-2510

Table IWF-251O(b) IWF-3000

IWF-4000

Subsection IWP IWP

IWP-3100 IWP-3210 IWP-3500 IWP-4110 Table IWP-4110-1

IWP-4120

Subsection I W V IWV

Iwv-1000 Iwv-1100

Iwv-1200

IWV-1300

Interpretation

XI-1 -86-1 7 XI-1 -86-50 XI-1 -83-30 XI-1 -89-69 XI-1 -92-20 XI-1-92-22 XI-1-92-29 XI-1-92-55 XI-1-86-48 XI-1-89-44 XI-1-95-1 0 XI-1-86-30 XI-1-89-60 XI-1-83-12R XI-1-83-12R-2 XI-1-89-59 XI-1 -83-1 2 XI-1-83-12R XI-1-83-12R-2 XI-1 -89-69 XI-1-86-48 XI-1-83-12 XI-1-83-1 2R XI-1-83-1 2R-2 XI-1-86-26 XI-1-86-49 XI-1-86-69 XI-1-89-47 XI-1 -89-61 XI-1-89-72 XI-1-86-63 XI-1-86-30 XI-1 -89-60 XI-1-89-67 XI-1-92-35 XI-1-92-35R XI-1-92-55 XI-1-89-28

XI-82-06R XI-1-83-08 XI-1-86-21 R XI-1-92-63 XI-1-92-63 XI-1-92-63 XI-1-89-55 XI-1-89-55 XI-1-92-14 XI-1-86-33 XI-1 -89-55

XI-82-06R XI-1-83-08 XI-1-83-59 XI-1-86-21 R XI-1-89-36 XI-1-89-71 XI-1-89-71 R XI-1 -83-59 XI-1-83-59R XI-1 -83-1 7

File No. -

BC85-2538 IN86-026C BC82-522 lN90-027 IN92-006B IN92-010 IN92-006A IN93-016 IN86-026A IN90-004 lN94-023 IN86-013 lN90-029 BC82-230* BC82-230*' lN90-026 BC82-230 BC82-230' BC82-230** IN90-027 IN86-026A BC82-230 BC82-230' BC82-230** lN86-002 lN86-0268 lN87-008 IN90-009 lN90-032 lN90-035 IN87-004 IN86-013 lN90-029 IN89-017C lN92-023 IN92-023* 1N93-016 lN89-021

BC82-340' BC82-523 lN86-004' lN93-036 lN93-036 lN93-036 IN90-021 IN90-021 lN91-037 BC85-5298 IN90-021

BC82-340' BC82-523 BC83-439 IN86-004' lN89-024 lN90-036 lN90-036' BC83-439 BC83-439* BC82-597

Page No.

105 128

32 233 254 254 257 281 127 209 303 112 229 49 49

228 18 49 49

233 127

18 49 49

110 128 155 210 229 234 147 112 229 232 265 289 281 195

-

5 9

186 284 2 84 284 226 226 251 119 226

5 9

58 186 205 234 281

58 90 20

( 4

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 15: Asme Sec Xi Int Vol 36

Location Interpretation

Subsection I W V (Cont'd) IWV-2200 IWV-3200

IWV-3300 IWV-3400 IWV-3410

IWV-3412

IWV-3413 IWV-3420 IWV-3426 IWV-3427 Table IWV-3510-1 IWV-3511 IWV-3512

IWV-3514 IWV-3520

IWV-3522

Subsection I W X IWX-2 100 IWX-2500

Table IWX-2500-1 IWX-3100 IWX-4000

Appendix I I 1-2000

1-4421 1-4422 1-4430 1-4450 1-7000

Appendix II Form NIS-2

Appendix 111 111

XI-1 -83-62 XI-1-83-14 XI-1-66-60 XI-1-92-1 6 XI-1-92-50 XI-1 -89-1 0 XI-1 -86-60 XI-1 -83-1 7 XI-1 -92-41 XI-1-92-41 R XI-1-63-74 XI-1 -89-1 0 XI-1 -92-50 XI-1 -89-1 0 XI-1 -83-62 XI-1-63-61 XI-1-63-60 XI-1-89-25 XI-1-89-25 XI-1 -89-65 XI-1 -92-37 XI-1-89-65 XI-1-92-41 XI-1 -92-41 R XI-1 -83-73 XI-1 -86-01

XI-1-63-75 XI-1 -83-75 XI-1-66-52 XI-1-86-52R XI-1-86-52R XI-1 -92-59 XI-1 -86-21

XI-1 -89-62 XI-1-89-1 2 XI-1-89-1 3 XI-1 -83-22 XI-1-63-22 XI-1-83-22 XI-1-63-22 XI-1-83-22

XI-1-92-07

XI-1 -89-49

File No. -

BC84-178 BC82-626 IN%-001 IN91-045 IN92-041 IN88-015 IN86-001 BC82-597 IN92-025A IN92-025A' BC82-752 IN88-015 lN92-041 IN88-015 BC84-178 BC84-176 BC84-095 lN89-019 IN89-019 IN90-002 lN92-027 IN90-002 IN92-025A IN92-025AI BC82-665A BC82-6658

BC83-055 BC83-055 BC85-524 BC85-524. BC85-524* lN93-023 lN86-004

lN90-033 IN89-001A lN89-005 BC80-567 BC80-567 BC80-567 BC80-567 BC80-567

lN91-022

IN90-013

Page No. -

59 19

145 252 275 169 145 20

268 273

74 169 275 169

59 59 58

193 1 93 231 266 231 268 273

73 91

75 75

135 187 187 282 107

230 175 1 76

28 28 28 28 28

244

21 7

Location

Ill-1100 111-3230

Ill-3310 Ill-3320 111-3330 Ill-3400

111-341 0 Ill-4420 Ill-4430

Ill-4500

Appendix IV IV-2300 IV-3000 IV-4000

Appendix VI1 Vll-3300 Vll-4240 Vll-4323 Vll-4342 Supplement 1, 9

Appendix Vlll VIII-1 loO(c) Vlll-2100 Vlll-3100 Supplement 4, 1.1 Supplement 6, 1.1

Code Cases N-98 N-308

N-408

N-416

N-460 N-481 N-498

Interpretation

XI-1 -92-58 XI-1-86-61 XI-1-89-1 1 XI-1 -89-1 7 XI-1-69-21 XI-1 -89-23 XI-1 -89-05 XI-1 -92-1 7 XI-1-92-1 7 XI-1-89-1 1 XI-1 -89-1 1 XI-1 -86-28 XI-1-89-23 XI-1 -89-1 1 XI-1-89-21 XI-1-89-23 XI-1-83-84

XI-1-92-67 XI-1-92-67 XI-1-92-67

XI-1 -92-42 XI-1-92-53 XI-1 -92-1 1 XI-1-92-69 XI-1-92-53 XI-1 -95-08

XI-1-92-49 XI-1-92-39 XI-1-95-04 XI-1 -92-09 XI-1 -92-36 XI-1 -92-36

XI-1 -89-09 XI-1 -83-02 XI-1-83-47 XI-1 -89-03 XI-1 -95-03 XI-1-92-25 XI-1-95-1 2 XI-1 -89-32 XI-1-92-26 XI-1 -92-25 XI-1 -92-26

File No. -

lN93-021 lN86-030 lN88-016 lN89-0048 IN89-004A IN89-010 lN88-005 IN92-001 IN92-001 1N88-016 IN89-001A lN86-008 IN89-010 IN89-016 IN89-004A IN89-010 BC83-654

lN94-004 lN94-004 lN94-004

lN92-030 lN93-007 lN91-035 lN94-007 lN93-007 IN94-015

lN93-006 lN92-032 lN94-009 IN91-027 lN92-026 lN92-026

IN87-019 BC81-476 BC84-197 1N88-003 1N93-042 IN92-012 lN94-028 lN89-026 lN92-014 IN92-012 IN92-014

Page No. - 282 146 175 179 190 192 167 252 252 175 175 111 192 175 190 192 80

291 291 291

268 276 246 292 276 302

275 267 300 245 265 265

168 6

52 166 300 256 304 203 256 256 256

Cumulative Index - Interpretations Vols. 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 16: Asme Sec Xi Int Vol 36

SUBJECT INDEX

Subject Interpretation Acceptance Criteria applicable code. ................................................... XI-1-83-75

XI-1 -86-37 XI-I -89-1 6

Class 1 . reactor vessel ferritic material. ............................... XI-1-83-06 constructed to 831.7 ............................................... XI-1-83-07 definition of flaw depth ............................................. XI-1-83-32 fabrication defecb - additional examinations ........................... XI-1-83-04 flaw evaluation .................................................... XI-1-86-52

flaw evaluation - Section XI in lieu of construction code . . . . . . . . . . . . . . . . . . XI-1-92-35

indications outside examination area ................................... XI-1-86-52

leakage .......................................................... XI-1-92-1 9 not specified ...................................................... XI-1-89-45

XI-1-86-52R

XI-1-92-35R

XI-1-86-52R

Applicability corrective measures . of new bolting ................................. XI-1-92-01 fabrication of replacements .......................................... XI-1-83-72 flaws detected outside of an inservice examination ....................... XI-1-89-67 installation requirements ............................................. XI-1-83-85 instrument tubing .................................................. XI-1-83-52 leakage - not found during a system pressure test ....................... XI-1-92-03 material removal process - nonwelded ................................ XI-1-89-70 metal removal to prepare surface for NDE .............................. XI-1-89-56 owner ........................................................... XI-1-83-83 preventive maintenance ............................................. XI-1-89-1 9 redundant canopy seal .............................................. XI-1-89-1 9 repair program - installing replacements ............................... XI-1-83-42 repair/replacement activities - off site ................................. XI-1-95-09 repair subsequent to N-Stamping - prior to N.3 ......................... XI-1-83-10

shot peening ...................................................... XI-1-89-73 small items - replacement of ........................................ XI-1-92-60 storage tank - examination., ........................................ XI-1-89-51 through wall leakage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-89-64 use of AIA for installing replacements .................................. XI-1-83-38

XI-1-83-46

Brazing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-47 procedures and personnel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-85

XI-1-83-86 XI-1-83-86R

Repair/Replacement Program ........................................ XI-1-86-23

Calibration angle beam ....................................................... XI-1-89-1 1 confirmation - period of use ........................................ XI-1-89-05 demonstration of equivalence ........................................ XI-1-86-28

electronic memory ................................................. XI-1-92-1 7 XI-1-86-61

File No .

BC83-055 lN86-022 IN89-001 B BC82-428 BC82-429 BC82-437 BC82-427 BC85-524 BC85-524' lN92-023 lN92-023' BC85-524 BC85-524* lN92-005 I N90-006

IN90-023 BC81-568A IN89-017C BC84-683 BC83-625 IN91 -01 7 IN91 -005 IN90-022 BC83-179 lN88-009 lN88-009 BC84-123 lN94-014 BC82-277 BC83-595 IN91 -006 lN93-024 IN90-017 IN89-0178 BC84-122

lN86-0258 BC84-683 BC85-113A BC85-113A' BC85-525D

IN88-016 lN88-005 lN86-008 lN86-030 IN92-001

Page No .

75 121 1 78

8 8

33 7

135 187 265 289 135 187 253 209

242 72

232 81 55

242 233 227

79 188 188 43

302 17 51

234 283 218 231 41

127 81 82

102 108

175 167 111 146 252

Cumulative Index . Interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 17: Asme Sec Xi Int Vol 36

Subject Interpretation

Calibration (Cont'd) interim check ..................................................... XI-1-89-62 of gages .......................................................... XI-1-83-49 series of test ...................................................... XI-1-83-49 standard ......................................................... XI-1-86-28

Calibration Blocks different specification ............................................... XI-1 -86-61 material . ......................................................... XI-1-86-72 notch reflectors .................................................... XI-1-89-09 reactor vessel . ..................................................... XI-1-86-71 side drilled holes ................................................... XI-1-89-1 1 ultrasonic examination .............................................. XI-1 -89-1 2 Vpath ........................................................... XI-1-89-21

Classification of Systems high pressure safety injection ......................................... XI-1-86-42 instrument tubing .................................................. XI-1-83-78 penetrates the containment .......................................... XI-1 -83-44 piping - visual examination ......................................... XI-1 -86-67

Component Supports associated supports ................................................. XI-1-86-49

coiled wire rope device ............................................. XI-1-92-55 corrective measures - additional examinations .......................... XI-1 -86-1 7 examination requirements - exemptions ............................... XI-1-83-27

integral attachments ................................................ XI-1-89-47

Interfaces ......................................................... XI-1-92-29 integrally attached .................................................. XI-1 -86-69 integrity by analyses ................................................ XI-1-86-30 multiple components ............................................... XI-1 -86-26

not constructed to Section 111 ......................................... XI-1-83-30 preservice examination .............................................. XI-1-86-48

XI-1-86-50

XI-1-92-22

XI-1-89-59

XI-1-86-63

XI-1 -86-50 XI-1 -89-44

removal of insulation ............................................... XI-1-89-69

Repair/Replacement Program ........................................ XI-1-86-23 repair - requirements .............................................. XI-1-89-28 representative sample ............................................... XI-1-89-72 scopeexpansion ................................................... XI-1-89-60 selection of supports for examination .................................. XI-1 -83-12

XI-1 -92-20

XI-1 -83-1 2R XI-1 -83-12R-2 XI-1-86-48 XI-1-86-49 XI-1 -86-63 XI-1-89-61

Construction Code hydrostatic test .................................................... XI-1-83-83

XI-1 -86-22 XI-1-86-52R

material manufacturers and suppliers .................................. XI-1-83-50R

reconciliation ...................................................... XI-1-89-41 repair/replacement - design requirements ............................. XI-1 -95-01 replacement of Section 111 components ................................. XI-1-89-68 replacement pressure vessel .......................................... XI-1-89-46

XI-1 -89-24

XI-1 -89-46R

File No . IN90-033 BC82-776 BC82-776 lN86-008

lN86-030 lN87-0056 lN87-019 lN87-005 1N88-016 IN89-001A IN89-004A

IN86-011 BC84-682 BC83-448 lN87-022

1N86-0268 IN86-026C IN93-016 BC85-253B BC83-437 IN92-010 IN90-009 IN90-026 IN92-006A lN87-008 IN86-013 lN86-002 lN87-004 BC82-522 IN86-026A IN86-026C IN90-004 IN90-027 IN92-006B BC85-525D lN89-021 lN90-035 lN90-029 BC82-230 BC82-230* BC82-230'' IN86-026A 1N86-0266 lN87-004 IN90-032

BC83-179 IN86-010 BC85-524' BC84-175* IN89-014 lN89-025 lN93-003 IN90-015 IN90-008 IN90-008*

Page No .

230 53 53

111

146 156 168 156 175 175 190

124 76 50

154

128 128 281 105 31

254 210 228 257 155 112 110 147 32

127 128 209 233 254 108 195 234 229

18 49 49

127 128 147 229

79 108 187

68 193 207 299 232 210 225

(h) Cumulative Index . interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 18: Asme Sec Xi Int Vol 36

Subject Interpretation

Construction Code (Cont’d) surface examination . acceptance criteria .............................. XI-1 -86-52 use of later editions of .............................................. XI-1 -86-1 2

XI-1-86-38R XI-1-86-39R XI-1-86-44R XI-1-89-20

use of later editions of . stamping .................................... Xi-1-83-21 R

welding requirements ............................................... Xi-1-86-51

Documentation (see Records and Reports)

XI-1 -86-44R

Hydrostatic Test (see also System Pressure Test) after a repair ...................................................... XI-1-83-66

XI-1 -86-75 XI-1-89-18

after a replacement ................................................. XI-1-83-54

alternative test ..................................................... XI-1-86-25

core criticality. .................................................... XI-1-86-53 elevated temperatures .............................................. XI-1-86-34 exempt from ...................................................... XI-1 -83-34 fabricated spool piece - Construction Code ............................ XI-1 -86-58 impractical ........................................................ XI-1-86-25 induction stress improvement ......................................... XI-1 -83-71 inspection interval extension ......................................... XI-1-89-58 nonwelded modification ............................................. XI-1-86-03R NPS 1 and smaller - component connected to .......................... XI-1-66-35 open ended portions of systems ...................................... XI-1-89-30 piping, pumps. and valves - preservice. ............................... Xi-1-86-22 pressurization pressure factors ........................................ XI-1-86-32 removal of a seal weld .............................................. XI-1-83-28 repair to a flange .................................................. XI-1 -89-31 requirements ...................................................... Xi-1-83-37R2

static head considerations ............................................ XI-1 -89-54

system pneumatic test in lieu of ....................................... XI-1-92-04

test pressure ...................................................... XI-1-83-67

test pressure - gage accuracies ....................................... XI-1-89-74 test temperature ................................................... XI-1-92-23 through-wall leakage ................................................ XI-1 -89-40 when performed - order ........................................... XI-1 -89-63

XI-1 -83-66

XI-1 -92-30

XI-1 -83-54R

XI-1 -89-66

XI-1 -92-1 8

Xi-1-92-23

lnservice Inspection Summary Report additional examinations . similar components .......................... XI-1-95-13 pressure retaining components and their supports ........................ XI-1-83-03 pumps and valves .................................................. XI-1-83-08 when performing preservice inspection ................................. XI-1-83-1 5

Inspection Interval extension of ...................................................... extended or decreased .............................................. hydrostatic test - interval extension ................................... inspection completion percentages - calculation of ...................... multiple components - NDE ........................................ scheduling requirements - applied by ................................. support examinations - percentage requirements ........................ visual examination - multiple stream .................................. volumetric examination - successive ..................................

XI-1 -86-54 XI-1 -92-57 XI-1 -89-58 XI-1 -95-1 1 XI-1 -86-26 XI4 -86-74 XI-1 -95-1 0 XI-1-83-68R XI-1-69-50

File No .

BC85-524 BC85-098 BC85-141* BC85-525Cf lN86.015 lN88-014 BC82-434* lN86.015 lN86-027

BC84-652 lN87-032 lN86-031 BC84-321 BC84-652 BC85-528 IN92-015 IN86-017A IN86-0178 BC83-587 IN87-010 BC85-528 BC80-583 iN90-025 BC83-112* lN86-019 IN89-011 IN86-010 BC85-5258 BC83-344 iN89-023 BC82-425** BC84-321* IN90-018B IN90-018A IN91-009 lN92-003 BC82-606 IN86-0178 IN91 -008 IN86-0176 iN89-017A lN90-034

IN93-027B BC82-406 BC82-523 BC82-610

IN87-001 lN93-002 lN90-025 lN94-024 lN86-002 IN86-003A lN94-023 BC83-441* IN90-014

Page No . 135 103 143 144 144 189 117 144 129

61 158 188 55 61

110 258 136 120

39 138 110

71 228 103 120 202 108 119

31 203 185 186 226 232 243 253 62

255 235 255 207 230

304 6 9

19

136 282 228 303 110 157 303 101 218

Cumulative index . interpretations Vols . 12-36 (il

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 19: Asme Sec Xi Int Vol 36

Subject Interpretation

Instrument Tubing ................................................. XI-1-83-52 XI-1-83-77 XI-1 -83-86 XI-1-83-86R

liquid Metal Cooled Plants inspection of inaccessible welds ....................................... XI-3-83-01 preservice system leakage test ........................................ XI-3-89-02 system leakage monitoring ........................................... XI-3-86-01

Material Manufacturer or Material Supplier qualification of .................................................... XI-1-83-50

Quality Assurance Program - update .................................. XI-1-86-44R XI-1-86-55R

Metric Versus Customary ........................................... XI-1-86-76

Nondestructive Examination (see also Ultrasonic. Visual. and Volumetric Examinations) examination of dissimilar metal welds .................................. induction stress improvement ......................................... items NPS 1 and smaller ............................................

for installation welds ................................................ liquid penetrant comparator blocks .................................... longitudinal welds .................................................. multiple stream - pressure retaining bolting ............................ multiple stream - pressure retaining nozzle weld ........................ nonferromagnetic steam generator heat exchanger tubing . . . . . . . . . . . . . . . . . . of emergency core cooling systems .................................... of pipe lugs ....................................................... performance demonstration - thermal fatigue crack ...................... piping - pressure retaining welds ..................................... reactor vessel ...................................................... requirements ...................................................... surface - flaw evaluation ........................................... use of one examination to satisfy two Categories .........................

XI-1-89-57 XI-1-83-71 XI-I -83-86 XI-I -83-86R XI-1 -86-45 XI-1 -86-51 XI-1-83-64 XI-1 -83-51 XI-1-83-68R XI-1-83-53 XI-1-92-67 XI-1 -92-45 XI-I -89-38 XI-1-92-49 XI-1-86-57 XI-1-86-71 XI-1-83-85 XI-1-86-52 XI-1-86-52R XI-1 -83-33

Nonpressure Retaining Welds ....................................... XI-1-83-28R

Nonwelded Work maintenance . requirements ........................................ XI-1-86-21

mechanical tube plugging ............................................ XI-1 -86-41

modification . hydrostatic test ....................................... XI-1-86-03R pressure retaining material . requirements ............................. XI-1-86-21

repair program ............................. I ...................... XI-1-83-42 replacement . documentation ................ I ...................... XI-1-86-14R sleeving of heat exchanger tubes ...................................... XI-1-92-32 sleeving of steam generator tubes ..................................... XI-1-86-41 use of an AIA ..................................................... XI-1-83-13

XI-1 -86-21 R

XI-I -92-44

XI-1-86-21 R

XI-1-83-38

NPS 1 and Smaller connected to a valve . hydrostatic test ................................ XI-1-83-58

XI-1 -86-35 exempted - pressure test ................................... I . . . . . . . XI-1 -83-85R

heat exchanger tube plugging ........................................ XI-1-92-44 heat exchanger tube - sleeving ..................... I ................ XI-1-92-32

XI-1 -83-83

File No . BC83-625 BC84-603 BC85-113A BC85-113A*

BC81-330 lN86-0248 IN86-024A

BC84-175 lN87-002' IN86-015'

lN87-035

lN90-024 BC80-583 BC85-113A BC85-113A' lN86-020 lN86-027 BC84-562 BC83-240 BC83-441' BC83-656 lN94-004 lN92-0228 IN89-007 lN93-006 lN87-007 IN87-005A BC84-683 BC85-524 BC85-524* BC83-589

BC83-344*

lN86-004 lN86-004* lN86-005 IN91-031 B BC83-112* lN86-004 lN89-004' BC84-123 BC85-112' IN91-031 lN86-005 BC82-407 BC84-122

BC84-422 IN86-019 BC83-588* BC83-179 IN91-031B IN91-031

Page No . 55 76 82

102

11 211 159

54 153 144

158

227 71 82

1 02 126 129 60 54

101 55

291 273 206 275 138 156 81

135 187 39

185

107 186 124 273 103 107 186 43

118 263 124

18 41

57 120

67 79

273 263

Cj) Cumulative Index . Interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 20: Asme Sec Xi Int Vol 36

Subject Interpretation

NPS 1 and Smaller (Cont'd) items . exempted from ............................................ XI-1-83-86

XI-1-83-86R XI-1-86-45 XI-I -92-66

piping, valves. and fittings . exemptions ............................... XI-1-83-26 XI-1 -89-04 XI-I -92-68

piping, valves. and fittings - supports for ............................... XI-1-86-65 valve replacements - exemptions . . . . . . . . . . . . . I ....................... XI-1-89-36

Piping component connected to NPS 4 and smaller . NDE ..................... XI-1-86-43R multiloop system - inspection ....................................... XI-1-86-15R NDE . installation welds ............................................ XI-1-86-51 pressure retaining welds - NDE ...................................... XI-1-86-57

supports - examination ............................................. XI-1-86-49

supports - exempted .............................................. XI-1-86-65 supports - multiloop system ......................................... XI-1-86-63 system - visual inspection ....................... , . . . . . . . . . . . . . . . . . . . XI-1-86-67

XI-1-92-56

XI-1-86-63

Preservice Examination ............................................. componentsuppo rts ................................................

edition of Section V ................................................ exemptions - gasket replacements .................................... integrally cast steam generator nozzle .................................. limitedto ......................................................... of Class 2 vessel ................................................... of manways - bolting .............................................. piping, pumps, and valves - hydrostatic testing ......................... pumps and valves - VT-3 prior to service .............................. ultrasonic examination - acceptance standards ..........................

XI-1 -86-24 XI-1 -86-48 XI-I -86-50 XI-I -89-02 XI-1-89-36 XI-I -86-71 XI-1 -86-24 XI-1-89-42 XI-1 -83-1 1 XI-1-86-22 XI-1-86-20 XI-1-86-37

Pressure Retaining bolting . documentation ........................................... XI-1-89-22 bolting . manways ................................................ XI-1-83-1 1 bolting . removal of insulation ....................................... XI-1-89-39R bolting . visual examination ......................... , . . . , , . . . . . . . . . . XI-1-83-68R

XI-1 -86-45 XI-1 -92-64

bolts and studs - examination ....................................... XI-1-83-76 boundary - alternative test .......................................... XI-I -86-25 boundary - flaw evaluation ......................................... XI-1-92-35 component - through-wall leakage ................................... XI-1 -89-64R components and their supports - summary report ... , .... , . . . . . . . . . . . . . . XI-1-83-03 components - exempt from visual .................................... XI-1-89-53 material - nonwelded work ...................... , .. , , .. , , .. , , . ..... XI-1 -86-21

parts - hydrostatic test ............................................. XI-1 -83-83 parts - ordered as spares ........................................... XI-1 -83-21 R welds - examination schedule requirements . . . . , ....................... XI-1-89-14 welds in piping - NDE .......................... , ........... , . , . . . . XI-1-86-57

welds in vessels - examination ....................................... XI-1-86-70 welds - preservice examination ...................................... XI-1-86-24

XI-1 -86-21 R

XI-1-92-56

Procurement of material .......................................................... XI-1-86-55R material - MM and MS qualification .................................. XI-1-83-5OR

XI-I -89-24 parts as material ................................................... XI-1-83-21 R

File No . BC85-113A BC85-113A' lN86-020 lN93-041 BC83-244 lN88-004 lN94-005 lN87-031 lN89-024

lN86-012* BC85.130 * lN86-027 lN87-007 lN93-013 lN86-0268 lN87-004 lN87-031 lN87-004 lN87-022

BC85-526 IN86-026A IN86-026C IN88-001 lN89-024 IN87-005A BC85-526 IN90-001 BC82-304 IN86-010 lN86-006 lN86-022

lN89-009 BC82-304 IN89-013At BC83-441* lN86-020 lN93-038 BC84-390 BC85-528 lN92-023 IN89-0178' BC82-406 IN90-019 lN86-004 IN86-004* BC83-179 BC82-434* lN86-0038 lN87-007 IN93-013 IN87-011 BC85-526

lN87-002* BC84-175' IN89-014 BC82-434'

Page No .

82 102 126 291

30 166 292 147 205

125 135 129 138 281 128 147 147 147 154

109 127 128 165 205 156 109 208

17 108 107 121

191 17

289 101 126 290

75 110 265 241

6 219 107 186

79 117 176 138 281 155 109

153 68

193 117

Cumulative Index . Interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 21: Asme Sec Xi Int Vol 36

Subject Interpretation

Procurement of (Cont’d) parts by nowcertificate Holder ....................................... XI-1-89-29 pipings. valves. and fittings - NPS 1 and smaller ......................... XI-1-89-04 pressure retaining part - Code Data Report ............................ XI-1-83-21 R replacements - later edition, . . . . , . .................................. XI-1-86-1 2 replacements - perform work on it ................................... XI-1-86-59 replacement - stamping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-20 spares . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-21R

spares - transfer of custody ......................................... XI-I -89-07 XI-1 -86-1 8

Pumps instrument accuracy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1 -89-55

testing of - inservice ............................................... XI-1-92-63 visual VT-3 - prior to service ........................................ XI-1-86-20 vibration measurement instrumentation ........................... , . . . , . XI-1-86-33

XI-1 -92-14

Qualification of NDE Personnel certification date ........................................ , . . . . . . . , . . XI-1-86-73 certification examinations ............................ , . . . , . . . . . . . . . . . XI-1-86-56

XI-1-86-66 XI-1 -86-73 XI-1 -89-06

certified to a later edition of SNT.TC.1A ................................ XI-1-83-18 XI-1-83-24 XI-1 -86-40

certified to an earlier edition of SNT-TC-1A ............................. XI-1-83-24 certified to SNT.TC.1A .............................................. XI-1-83-18

XI-1-83-23 XI-1-83-29 XI-1-83-82 XI-1-89-26

color vision examination - frequency .. I .............................. XI-1-83-36 duties of Authorized Inspector I ....................................... XI-1-83-48 examinations scoring . . . . . . . . I ....................................... XI-1-92-54

experience requirements ............................................ XI-1-92-28 eye examination ................................................... XI-1-83-01 for pumps and valves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-82-06R other than to SNT-TC-1 A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-I -83-45 outside agency .................................................... XI-1-92-53 perform examinations to earlier editions ................................ XI-1 -86-40

performance demonstration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-92-39 practical examination requirements - alternatives to ..................... XI-1-92-69 pressure loss, flow change and test .................................... XI-1-92-52 pumps and valves .................................................. XI-1-92-37 recertification - ASNT certification .................................... XI-1-86-66 recertification - examinations ........................................ XI-1-86-1 6 recertification - Level 111 .................................. I . . . . . . . . . XI-1-86-19 supplemental training - Level Ill ..................................... XI-1-95-08 toanothercode ................................................... XI-1-83-40R ultrasonic examination technicians ..................................... XI-1-92-39 ultrasonic examination - annual training ............................... XI-1 -92-1 1 used to perform repair examinations ................................... XI-1 -83-40 visual examination - SNT-TC-1A ..................................... XI-1-83-16

XI-1-92-70

XI-1 -92-70

Quality Assurance Program qualification of plant and contractor personnel ........................... XI-82-06R review of ......................................................... XI-1 -86-64 updating to a later Construction Code .................................. XI-1 -86-44

XI-1-86-44R

File No .

lN89-008 lN88-004 BC82-434* BC85-098 BC85-550 BC82-430 BC82-434* BC85-254 IN88-011

IN90-021 lN91-037 lN93-036 lN86-006 BC85-5298

lN87-029 lN86-028 IN87-015 lN87-029 lN88-006 BC83-060 BC83-178 BC85-571 BC83-178 BC83-060 BC83-056 BC82-050 BC83-176 BC80-231* BC83-585 BC84-177 IN93-015 lN93-022 IN92-019 BC80-582 BC82-340* BC83-535 lN93-007 BC85-571 lN93-022 lN92-032 lN94-007 lN93-005 lN92-027 IN87-015 BC85-142 BC85-071 IN94-015 BC84-043* lN92-032 lN91-035 BC84-043 BC82-775

BC82-340* IN87-028A IN86-015 lN86-015*

Page No . 202 166 117 103 145 27

117 106 167

226 251 284 107 119

157 137 153 157 167

21 29

123 29 21 29 32 78

194 40 52

276 293 257

5 5

50 276 123 293 267 292 276 266 153 105 106 302

67 267 246 42 20

5 147 126 144

(1) Cumulative Index . Interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 22: Asme Sec Xi Int Vol 36

Subject Records and Reports certificate of compliance and CMTR ................................... Code Data Rep0 rt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . designdocumen ts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . documentation - construction code ..................................

documentation . inservice degradation ................................ documentation - installation of replacement ............................ documentation - test temperature .................................... for pressure retaining bolting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . inservice inspection plan - requirements ............................... manufacturer's data report - NIS-2 ................................... NIS forms - signature ..............................................

nonwelded replacement .............................................

replacements ...................................................... Ownersdata form ..................................................

retention of radiographs. ............................................ use of N IS I Form .................................................

useof NlS-2 Form .................................................

weld reference system ..........................................

Interpretation

XI-I -83-21 R XI-I -83-21 R XI-I -89-34 XI-1 -89-20 XI-1 -89-34 XI-1 -89-48 XI-1 -89-64R XI-1 -95-02 XI-1 -95-07 XI-I -89-22 XI-I -92-02 XI-I -92-07 XI-1-83-65 XI-1-83-79 XI-1-86-14R XI-1-83-02 XI-1-86-68 XI-1 -89-48 XI-1-83-47 XI-1-86-14R XI-1-86-31 XI-1-86-31 XI-1-86-68 XI-1 -92-06

Repair/Replacement Program activities . off site ................................................. XI-1-95-09

XI-I -86-41 XI-I -86-62

failure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1 -92-1 5

initiation of . ...................................................... XI-I -95-14 items NPS 1 and smaller ............................................ XI-1-83-86

nonpressure boundary material ....................................... XI-1 -86-23 Owner's responsibility . ............................................. XI-1 -95-09 Quality Assurance Program - review of ................................ XI-1-86-64 use of later rules ................................................... XI-1-86-25

XI-1-86-31

applies to . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-86-36

component supports ................................................ XI-1-86-23

impractical NDE - alternative examination ............................. XI-I -86-51

XI-I -83-86R

Sealants use of . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1 -89-40

Shutdown cold . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1-83-73

XI-1-83-74 extended - valve testing ............................................ XI-1-92-41 R valve testing ....................................................... XI-1-83-74

Spares (see Procurement of)

Stamping installation of replacement parts ...................................... XI-I -83-02 of replacement parts - ordered as spares .............................. XI-I -83-21 R of replacement parts - valves ........................................ XI-I -83-20 Section 111 ........................................................ XI-I -83-72

System Pressure Test (also see Hydrostatic Testing) after a repair or replacement ......................................... XI-1 -83-05 applies to ......................................................... XI-1 -83-34

XI-1-83-37R2

File No .

BC82-434* BC82-434* IN89-012 lN88-014 IN89-012 IN90-011 IN89-017B" lN93-026 IN94-011 lN89-009 IN91-012 lN91-022 BC84-647 BC84-684 BC85-112* BC81-476 lN87-024 IN90-011 BC84-197 BC85-112* BC85-525A BC85-525A lN87-024 IN91-019

IN94-014 lN86-021 lN86-005 lN86-032 BC85-525D IN91-040 lN86-027 lN93-029 BC85-113A BC85-113A* BC85-525D lN94-014 IN87-028A BC85-528 BC85-525A

IN89-017A

BC82-665A BC82-752 IN92-025A* BC82-752

BC81-476 BC82-434* BC82-430 BC81-568A

BC82-425 BC83-587 BC82-425**

Page No .

117 117 204 189 204 21 7 241 299 301 191 242 244

61 77

118 6

154 217

52 118 118 118 154 244

302 121 124 146 108 252 129 304

82 102 108 302 147 110 118

207

73 74

273 74

6 117

27 72

7 39

185

Cumulative Index . Interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 23: Asme Sec Xi Int Vol 36

Subject Interpretation System Pressure Test (Cont’d)

XI-1 -86-1 3 XI-1 -86-1 3R XI-1-86-21 XI-1 -86-21 R

corrective measures ................................................ XI-1 -92-1 9

exempted from - NPS 1 and smaller .................................. XI-1-83-35R leak test - core criticality ........................................... XI-1-86-53 open ended portions of systems ...................................... XI-1-89-30 pressurizing medium ................................................ XI-1-83-25

XI-1-92-51

XI-1 -86-34 XI-1-92-23

reassembled components/breaking pressure boundary .................... XI-1-83-63R XI-1-83-70 XI-1-83-70R XI-1 -86-1 3 XI-1 -86-1 3R XI-1 -86-27 XI-1 -86-27R XI-1 -86-29R XI-1 -89-1 5 XI-1 -89-33 XI-1 -89-37 XI-1 -89-52

reduction of pressure - visual examination ............................. XI-1 -86-46 replacement of bolts. studs. and nuts .................................. XI-1-89-08

systems not required to operate ....................................... XI-1-92-62 through-wall leakage ................................................ XI-1-89-64

through-wall leakage - corrective action ............................... XI-1-92-31

Temporary Repair ................................................. XI-1-83-14

XI-1-92-65

XI-1-89-64R

XI-1-83-57

Ultrasonic Examination calibration ........................................................ XI-1 -92-1 7 detection specimens - orientation .................................... XI-1 -92-36 equalized sensitivity - recording of ................................... XI-1-83-22 evaluation of flaws ................................................. XI-1 -83-29 full penetration weld of nozzles ....................................... XI-1 -83-56 material attenuation ................................................ XI-1-89-1 7 nozzle-to-safe end welds - extent of .................................. XI-1 -89-49 performance demonstration .......................................... XI-1-92-36 piping - outer surface .............................................. XI-1-92-58 .qualified by performance demonstration ................................ XI-1 -92-09 reflectors ......................................................... XI-1 -83-84 requirements ...................................................... XI-1-83-84 search unit overlap ................................................. XI-1-89-1 3 sweep display ..................................................... XI-1-89-23 three-point DAC ................................................... XI-1-83-31 V path ........................................................... XI-1-89-23

Use of Code Cases N-98 ............................................................ XI-1-89-09 N-308 ........................................................... XI-1-83-02

XI-1-83-47 N-408 ........................................................... XI-1-89-03 N-416-1 ......................................................... XI-1-95-12 N-416 ........................................................... XI-1-92-25 N-460 ........................................................... XI-1-89-32 N-481 ........................................................... XI-1-92-26 N-498 ........................................................... XI-1-92-10

File No .

BC85-111 BC85- I l l * lN86-004 lN86-004* IN92-005 IN93-011 BC83-588* IN86-017A IN89-011 BC83-219 IN86-0176 IN86.178 * BC84-31 O* BC84-198 BC84-198* BC85-111 BC85-111* lN86-007 lN86-007* lN86-009* IN88-002A IN88-017 IN88-002C lN88-0028 lN86-023 lN87-018 IN94-001 IN93-030 IN89-0176 IN89-0178* IN91-018

BC82-626 BC84-392

IN92-001 lN92-026 BC80-567 BC82-050 BC84-388 IN89-004B IN90-013 lN92-026 lN93-021 lN91-027 BC83-654 BC83-654 lN89-005 IN89-010 BC82-630 IN89-010

IN87-019 BC81-476 BC84-197 lN87-003 lN94-028 IN92-012 lN89-026 lN92-014 lN91-029

Page No .

104 225 107 186 253 275

67 136 202

30 120 255 101

70 201 1 04 225 111 187 143 178 21 3 205 21 9 127 168 290 284 231 241 263

19 57

252 265

28 32 56

179 217 265 282 245 80 80

176 192

33 192

168 6

52 166 304 256 203 256 246

(n) Cumulative Index . Interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 24: Asme Sec Xi Int Vol 36

Subject

Use of Code Cases (Cont’d)

Interpretation

XI-1-92-25 XI-1 -92-26

Valve classification ...................................................... XI-1-83-59

XI-1-83-62 lN91-026

disc and seat . hard facing .......................................... XI-1-92-35 examination . bolts and studs ....................................... XI-1 -83-76 exercising test ..................................................... XI-1 -89-10 full stroke exercising ................................................ XI-1-92-50 inservice testing program - corrective action ............................ XI-1 -86-60 inservice testing - scope of .......................................... XI-1-89-71

limiting values of stroke time ......................................... XI-1-83-1 7 measured leakage rate .............................................. XI-1-83-60

packing adjustment - seat leakage testing .............................. XI-1 -92-38 replacements - NPS 1 and smaller ................................... XI-1 -89-36 set point adjustments ............................................... XI-1-89-65 stroke time ....................................................... XI-1 -92-16 supervisor qualification - set point testing .............................. XI-1-92-37 supports - exempted .............................................. XI-1 -86-65 test scheduling - extended shutdown ................................. XI-1 -92-41 R test scheduling - outage ............................................ XI-1-89-25

XI-1 -89-71 R

XI-1 -83-61

XI-1 -92-41 visual VT-3 - prior to service ........................................ XI-1 -86-20

Visual Examinations components exempt . volumetric and surface .......................... XI-1-92-40 core support structure ............................................... XI-1 -92-46 exempt from ...................................................... XI-1 -89-53 leakage .......................................................... Xi-1 -92-19

XI-1 -92-48 XI-1-92-51

liquid-metal containing components ................................... XI-3-89-01 multiple stream - pressure retaining bolting ............................ XI-1 -83-68R piping system - classification ........................................ XI-1 -86-67 pressure test - pressure requirements ................................. XI-1-86-46 removal of insulated ................................................ XI-1-89-39 vessels - pressure retaining welds .................................... XI-1-86-70 VT categories - requirements ........................................ XI-1 -89-26 VT-1 - base metal ................................................. XI-1-92-33 VT.l. VT-3 - interchangeable ....................................... XI-1-83-69 VT-1 - pressure retaining bolting ..................................... XI-1-86-45 VT-2 during a functional test ......................................... XI-1-89-75 VT-2 of borated water systems ........................................ XI-1-89-39 VT-2 of buried components .......................................... XI-1-83-19

VT-2 - personnel ................................................. XI-1-83-63R VT-2 - removal of insulation ........................................ XI-1-92-47 VT.2. VT-3 - piping system ......................................... XI-1-86-67 VT-3 - bolted connection ........................................... XI-1-92-48

VT-3 - pumps and valves prior to service .............................. XI-1-86-20

VT-4 - pumps and valves ........................................... XI-1-83-69 VTM-2 - Accessibility .............................................. XI-3-89-01 welds on multiple components ....................................... XI-1-86-26

XI-1 -92-34

XI-1-92-51

VT.3-~~pp0rts ................................................... XI-1-89-26

Volumetric Examinations and surface . exemptions to ........................................ XI-1-86-43R

XI-1-92-40

File No . lN92-012 lN92-014

BC83-439 BC84-178 IN92-016 lN92-023 BC84-390 IN88-015 lN92-041 IN86-001 lN90-036 IN90-036* BC82-597 BC84-095 BC84-176 lN92-031 lN89-024 IN90-002 lN91-045 lN92-027 lN87-031 IN92-025A* IN89-019 IN92-025A lN86-006

IN92-022A lN92-043 IN90-019 lN92-005 IN93-001 lN93-011 IN86-024C BC83-441* lN87-022 lN86-023 IN89-013A IN87-011 BC80-231* IN91-043 BC84-616 lN86-020 IN91 -01 0 IN89-013A BC82-607 IN92-020 BC84-310* lN92-046 lN87-022 IN93-001 IN93-011 lN86-006 BC80-231* BC84-616 IN86-024C lN86-002

IN86-012* IN92-022A

Page No . 256 256

58 59

251 265

75 169 275 145 234 281

20 58 59

266 205 231 252 266 147 273 193 268 107

267 274 219 253 2 74 275 169 101 154 127 206 155 194 264

69 126 235 206

27 2 64 101 274 154 274 275 107 194 69

169 110

125 267

Cumulative Index . Interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 25: Asme Sec Xi Int Vol 36

Interpretation

Volumetric Examinations (Cont'd)

as an alternative to surface ........................................... Code Case N.460 ................................................ fabrication defects - additional examinations ......................... or surface ...................................................... piping . outer surface .............................................. prior to hydrostatic test .............................................. required volume to be examined ..................................... successive inspection intervals ........................................

XI-1 -92-45 XI-1 -95-03 XI-1 -89-21 XI-1 -89-27 XI-1-89-32 XI-1 -83-04 XI-1-89-1 1 XI-1-92-43 XI-1-92-58 XI-1-89-63 XI-1 -89-32 XI-1 -89-50

Weld accessible . preservice examination ................................... XI-1-86-24 additional examinations - similar components .......................... XI-1-92-61 between different P.numbers ......................................... XI-1 -83-39 connecting NPS 1 and less - hydrostatic test ........................... XI-1 -86-35 examination - dissimilar metal welds .................................. XI-1 -92-1 3 examination - full penetration ....................................... XI-1 -89-43 examination of integrally welded attachments ........................... XI-1 -92-05 examination of pipe ................................................ XI-1 -83-80

examination - partial .............................................. XI-1 -92-1 2 examination - partial penetration .................................... XI-1 -89-43 examination schedule requirements ................................... XI-1 -89-1 4

half bead weld repair - automatic .................................... XI-1-83-09

items NPS 1 and smaller - requirements ............................... XI-1-83-86

multiple components - NDE ........................................ XI-1-86-1 5R

multiple loop piping - inspection ..................................... XI-1-86-1 5R NDE examination requirements ....................................... XI-1-86-51 nonpressure retaining ............................................... XI-1-83-28R overlay cladding to replacement parts .................................. XI-1-86-36 piping - additional examinations ..................................... XI-1-95-06 piping - examination of (calibration method) ........................... XI-1-95-04 piping - NDE requirements ......................................... XI-1-86-51

XI-1-86-57 piping supports - examination ....................................... XI-1-86-49 pressure retaining boundary - alternative test ........................... XI-1-86-25 procedure qualification record - sharing of ............................. XI-1 -92-08 procedures - qualification .......................................... XI-1 -83-41

XI-1 -83-80R

XI-1-92-24

XI-1-83-09R

XI-1 -83-86R

XI-1-86-26

XI-1-83-55 XI-1-83-81 XI-1 -89-01

reference system - recording of ...................................... XI-1 -92-06 reference system - identification of ................................... XI-1 -95-05 Repair/Replacement Program ........................................ XI-1-86-23 repair - internal wall thinning ....................................... XI-1-92-59 repair - steam generator tube plug ................................... XI-1 -92-21 temper bead method ............................................... XI-1 -89-1 8 tungsten-inert gas process - automatic ................................ XI-1-83-09

vessels - examination .............................................. XI-1-86-70 XI-1 -83-091

Welder qualification ....................................................... XI-1-83-55 qualification of - simultaneously ..................................... XI-1-89-35 requalification - change in contractor ................................. XI-1-83-43

File No .

lN92-0228 lN93-042 IN89-004A IN89-004C lN89-026 BC82-427 lN88-016 lN92-033 IN93-021 IN90-034 lN89-026 I N90-014

BC85-526 IN93-027A BC83-527 IN86-019 lN91-026 IN90-003 IN91 -01 6 BC84-685 BC84-685' lN91-025 IN90-003 IN86-0036 IN91-014 BC82-604 BC82.604 * BC85-113A BC85-113A' BC85-130* lN86-002 BC85-130' lN86-027 BC83-344' lN86-021 IN94-002A IN94-009 lN86-027 lN87-007 lN86-0268 BC85-528 IN91 -024 BC84-064 BC84-322 BC84-687 lN87-036 IN91 -01 9 lN93-035 BC85-525D lN93-023 IN92-009B lN86-031 BC82-604 BC82-604' IN87-011

BC84-322 lN89-006 BC84-179

Page No .

273 300 190 195 203

7 175 268 282 230 203 218

109 283 42

120 251 208 243

77 241 251 208 176 255

9 10 82

102 135 110 135 129 185 121 301 300 129 138 128 110 245 43 56 78

165 244 301 108 282 254 188

9 10

155

56 204

44

(PI Cumulative Index . Interpretations Vols . 12-36

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 26: Asme Sec Xi Int Vol 36

Subject interpretation

Welder (Cont’d) required qualification . Section IX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . XI-1 -89-01 supervision ....................................................... XI-1-83-81

Cumulative index . Interpretations Vols . 12-36

File No .

lN87-036 BC84-687

Page No .

165 78