ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

15
ASME B31Q UPDATE Michael Gruenberg WRGC August 2013

Transcript of ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Page 1: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

ASME B31Q UPDATE

Michael GruenbergWRGC August 2013

Page 2: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Points to Cover

• Committee Structure• Industry Representation• What has been accomplished

Page 3: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Committee Structure

• Chair - Amy Livingston, Compliance Manager Kinder Morgan

• Vice Chair – Mike Burkhart, Program Manager Nicor Gas

• Secretary – Paul Stumpf, ASME

Page 4: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Committee Makeup

• 30 Voting Members• Representing:– Transmission pipeline companies (10)– Distribution companies (8)– Liquid pipeline companies (2)– State and Federal agencies (3)– Vendors (6)– ASME (1)

Page 5: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Member Locations

Page 6: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Committee Work 2012 - 2013

• Preparation for next release• Ad-hoc meetings• Committee meetings• Balloting Process

Page 7: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Preparation for Release

• Revise Task Guidance:– Several instances where the written guidance did

not match the intent of the task.

• Revise Task Language:– Each task rewritten to eliminate by inclusion the

main AOC’s that could be encountered (PHMSA)

– Additional language inserted to add clarity

Page 8: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Examples

Current• Identify requirements• Perform task equipment check• Test/troubleshoot rectifier• Repair or replace defective

rectifier components• Place in service• Adjust output• Recognize and react to AOC’s• If required, complete

documentation

New• Select task procedure(s)

and appropriate equipment• Perform test equipment

check to verify that equipment functions within specified parameters – Inspect equipment– Verify equipment is calibrated– Test equipment

Page 9: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

ContinuedTest rectifier and troubleshoot problems•Monitor requirements of all impressed current sources•Visually inspect components of the rectifier•Check electrical connections (anode, ground beds, power supply, structure, electrical ground, etc.)•Identify and locate correct test points•Connect instruments and test leads to correct locations•Operate test equipment and take readings

– Rectifier voltage and current output to include current drains, shunt using a high impedance voltmeter, ammeter (direct or indirect), and shunt, if applicable

– Watt-hour reading, if applicable– Internally mounted voltage and amperage meter

•Analyze and interpret test results– Maximum rated outputs

•Common component failures and output indications

Page 10: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

ContinuedRepair or replace defective rectifier components as applicable•AC/DC circuit breakers•Power connection/safety ground•Fuses•Diodes•Disconnects•Rectifying elements•Transformer•Lightening arrestors•Shunts•AC Filters/Chokes•Stack•Meters

Page 11: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Meetings

• Committee Meetings– Three were devoted to the revision

• Ad-Hoc Meetings– Six or more WebEx meetings held

Page 12: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Results

• 109 Tasks have been approved by the standards committee

• 13 have been sent out for a recirculation vote• 20 still being worked• 1 being recirculated in the committee• 2 not yet drafted• 2 tasks were voted on to be removed• 20 diving tasks

Page 13: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

What is left

• 20 Diving tasks• 2 Pump or compressor type tasks• 2 Squeeze tasks

Page 14: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

Path Forward

• Compete the task revision process• Submit all to standards committee• Publish next version ??? • Pick up the items to be completed that were

tabled for the revision

Page 15: ASME B31Q U PDATE Michael Gruenberg WRGC August 2013.

QUESTIONS

Michael [email protected]

702-668-6401