ASK THE INSPECTOR 6 Part Series Basements · was the tar we applied is a damp proofing, not a water...
Transcript of ASK THE INSPECTOR 6 Part Series Basements · was the tar we applied is a damp proofing, not a water...
ALLTECH CONSULTING GROUP
POINTS OF INTEREST
History
Why they fail
Waterproofing
Dig it up
Sumps
Introduction
Each week I select a question from a reader, generally chose one that I may have had more then one similar request. This summer however the number of questions about block basements, damp to outright wet, cracks and repairs, how to fix and not get stung and how to insulate has been a weekly inquiry. It is a sign of a very wet summer I suspect. This booklet will cover some history, pros and cons to block and go on site with a foundation contractor as they repair and waterproof a block basement. I hope you find it interesting and informative.
ASK THE
INSPECTOR
6 Part Series
Block
Basements
Cam Allen L.I.W. RHI
Phone: 613-546-9876
By the Block
Up until the 1980’s concrete block
was the basement of choice.
They are reasonably priced, fairly
simple to lay provided your foot-
ings are level and if you need to
make some adjustments for square
of level it can be “picked up as you
build your rows of blocks.
If you are hiring a mason to build
your block basement he will charge
you “by the block” to assemble it.
Around 1950 we started brushing
road tar or bituminous tar onto the
blocks in the belief that this would
stop water from penetrating the
blocks. We thought we had the
wet basement issue solved……..oh
how wrong we were!!”
more uniform in integrity, but they are still made of Portland Cement, sand and an
aggregate of some form.
Gravel is used, so is shale and slate in some manufacturing processes. The mix for
blocks usually contains more sand than gravel and water, making it a stiffer mix so the
blocks hold their shape. Most modern block manufactures use some manner of com-
paction to help make the blocks consistent. An average run of blocks from mix to
pour, then curing and then put in a steam room to reach an even temperature and
then they are allowed to dry takes about a day. We generally see the grey hollow
concrete block. There is however many other kinds including architectural designs
used on large buildings for example.
If block basements were so good and reasonably priced, why have we moved to
poured concrete and insulated concrete foundations? The answer is longevity, re-
duced water invasion and better insulation values. We started using basements for
living space after WW2 and along came the problems. The first thing we found out
was the tar we applied is a damp proofing, not a water proof coating. It often dried
out, did not seal cracks and on average failed in its intended use. Within 3-5 years
depending upon the soil and water concentration it was sitting in the moisture would
begin to invade the blocks. An average modern block will absorb up to 3-4 lbs of wa-
ter…per block. The hollow cavities will hold up to a gallon and half of water.
We did not use below grade drains with any consistency until the 60’s and even then
they were a clay tile that quickly filled with silt or tree roots.
Improper drainage around the home, lack of eves trough extensions, the movement
of soil due to what is know as the freeze-thaw cycle, lack of proper anchoring at the
sill plates, moving equipment too close to the building, it’s a long list of issues that
Early concrete blocks weighed over 50lbs a piece, today they average anywhere from 25-30 lbs per block
History of the Block
We shall start by explaining the some
of the history of blocks, how they are
made and some of the “quirks” of a con-
crete block basement. While it’s gener-
ally considered that the Romans in-
vented concrete and used it extensively
in their massive buildings the use of a
uniform concrete block did not evolve
until the mid 1800’s. Many contractors
used hand made molds and poured their
own. The first concrete block building in
North America is located in New York
City, it was built in 1837. Thanks to Eng-
lish Inventor Joe Aspidin who invented
Portland Cement in 1824 it allowed the
development of concrete blocks. In 1868
a company in Chicago called G.A. Frear
got the first patent for manufactured
concrete blocks. They were designed
with a stone chiseled pattern to look like
a stone foundation, for a lot less money.
By 1900 a gentleman by the name of
Harmon Palmer had invented a cast iron
machine that mass produced hollow
concrete blocks. Coupled with the devel-
opment of reinforced concrete in 1849,
by World War 1 the use of steel, con-
crete and concrete blocks for large scale
buildings was well under way.
The actual method of making concrete
blocks has not changed dramatically
since it original development. They are
lighter and stronger now and certainly
2
Good blocks go bad
The number one issue with
a block basement is mois-
ture; blocks are not water-
proof…period. Water will
penetrate any mortar crack,
open seam or just about
any opening for that matter
and we all know that the
blocks themselves are po-
rous.
I have seen cases where a
contractor drilled a hole in
the second course of blocks
and the water actually
flowed in.
The CMHC guide to damp
basements has a good list of
reasons why basements
leak. Ineffective or non-
existent eve trough and
downspouts are top of the
list. Lack of slope away from
the building, poorly draining
backfill around the base-
ment, ineffective window
well drains, defective or
missing below grade drain-
age systems are the com-
mon culprits for a wet base-
ment. There are two other
issues which are serious and
very difficult to fix, that is a
basement built in an area of
high water table and one
build in a valley or on the
side of a long sloping grade.
Why they fail
affect block base-
ments. We learned
some time ago they
were only capable
of bearing a build-
ing about five times
less the weight
than a poured con-
crete foundation.
Block basements
were an evolution
in modern home
assembly. After this
many years we
have learned their
shortcomings and
fortunately we have developed ways to improve them, unfortunately at some consid-
erable cost in many cases.
3
Clogged clay drains can’t do the job
If you have a choice in basements between ICF, poured concrete or block I think you
will find most reputable contractors will list them just like that with a block basement
last. Check the yellow pages for waterproofing contractors that are listed, few of them
fixed poured or ICF.
A block basement with moisture issues is usually fairly easy to detect, provided its
not covered in drywall or paneling. If you have a white chalking along the first or sec-
ond row of blocks you can bet you have a drainage issue. This chalking is called efflores-
cence and is not uncommon in a block foundation, especially an older one. Efflores-
cence by itself is not that harmful, what it means is there is a salt content in the blocks
or the external ground water seeping thru and depositing this white crystal like powder
on your block wall.
There are as many reactions from a wet basement as there are terms. Mold, Mildew
and that “Damp Smell” are all signs of a water issue. Mold or rot at the end of your
floor joists or along the sill plate are also a sign. The CMHC publication “A Guide to Fix-
ing your Damp Basement” is a good starter manual. Contact CMHC at 1-800-668-2642
and ask for catalogue number NH15-72/2007E..
Moisture in a block wall can usually be fixed by excavation and installing any number
of membranes around the foundation. We will discuss that next week. The other issue
is foundation failure and this is usually caused by seasonal expansion and contraction of
the soil around the basement which puts pressure on the actual block foundation. Dur-
ing the freeze-thaw cycle this pressure builds up against the wall and often causes hori-
zontal cracks along the mortar lines. This can and does lead to a bow in some block
walls. I generally see this at or near the frost line, anywhere from the fourth to sixth
row of blocks in a standard basement which is usually 11 rows high. The next defect
that I see too often is the lack of anchors in the sill plate and the soil pressure is actually
pushing the wall vertically inward. While not as common, a shear crack at the base or
second row of blocks is usually caused by poorly drained soil that has moved these
blocks inwards. These types of block failure are more common than many people think
and usually mean major foundation restoration or replacement if not caught in time.
“I shake my head to think that less than twenty bucks of eves trough extension could have saved what could quite easily be a five figure repair. “
Another common problem is step cracks that follow the mortar line. These can be the result of settling or a poorly installed
footing base. This is reasonably common in many block basements and if there is no continued movement there are some
reasonable repairs available for this type of crack. A wall with a bulge or a full bow can often be stabilized by means of but-
tress work or infilling the blocks with rebar and concrete slurry. I have seen a Kevlar wrap used on a bowed wall and I have
also seen steel columns installed that were anchored to the pad and the floor joists. The benchmark I have seen used is the
under an inch for a bowed wall. While the rebar and slurry does work it has some drawbacks. Getting an even pour inside a
block wall is difficult and air pockets are not uncommon. Feeding a 6-7 foot long piece of rebar inside a block wall is a daunt-
ing task; it takes patience and a skilled hand. Any block wall with more than a ¾-1” of displacement should be excavated and
brought back to plumb or replaced.
Drainage and eves trough discharge are the two major issue as we have stated and I can’t stress enough how important this
is. Every time I get called to a basement problem it’s often a home that is 25 plus years old, the downspout discharge is the
elbow on the end and the wall has a major crack. I shake my head to think that less than twenty bucks of eves trough exten-
sion could have saved what could quite easily be a five figure repair. If you have a block basement and see activity in your
wall, don’t delay getting a professional foundation company to look at it. Caught in the early stages you can save thousands
of dollars.
This is the third in our series on block
foundations and this week we look at the
numerous kinds of materials, coatings and
membranes on the market that are used
to rectifying a wet block basement. One
thing to get clear from the start, the terms
damp proofing and waterproofing that
are often used by some unscrupulous
contractors as the same thing….they are
not! Damp proofing is coating that applied
to resist water vapor, it’s generally an
asphalt based coating not unlike the
driveway sealer you put on your asphalt
driveway. In an extremely well drained
soil around a home they will have some
effect but those of us in the trades are
fully aware it looses its effectiveness in
less than 5 years. Waterproofing is just
that, a system to effectively prevent wa-
ter from entering your block basement.
This is done by excavating around your
home and applying a waterproof system.
The next myth is the roll on…brush on…
spray on coating that is applied to the
inside of your basement walls. Think of a
plastic cup with a small hole drilled in it. If
you apply the band-aid on the inside and
fill it with water the entire band aid is held
in place by the water. If you apply it on
the outside you are reliant upon the adhe-
sion abilities of the band-aid. In effect if
the porous blocks are receiving the mois-
ture we all know they do then this kind of
coating has a tough job ahead of it, one I
have yet to see as long term effective.
There is one interior water soluble rub-
berize material called Blue Max that ad-
vertises itself as a waterproof paint. If you
read the specs closely you will find they
recommend 2 gallons per 100 sq ft and
application to the thickness of a dime. In
an area of casual dampness it may be
worth a look, for repeated dampness or
water invasion I would be hesitant.
Waterproofing
Coating Options
There are also a number of differ-
ent kinds of brush…roll….spray on
rubberized coatings on the market.
One maker is called “Tuff-N-Dri. Its
product is a spray on coating called
“Code Blue” (there’s that blue
again!) This product is only applied
by installers who have been
trained by Tuff-N-Dri. One of the
largest manufacturers of sealants,
coatings and membranes is Bakor.
They are the makers of Yellow
Jacket and Blue-Skin. They also
manufacture a line of liquid ap-
plied membranes that are very
popular with reputable foundation
companies. Some installers will
cover their liquid membrane with
rigid foam insulation. This has two
benefits, it helps reduce the cold
intrusion into the foundation,
similar to an ICF foundation and
help protect the liquid coating
from any damage from rocks or
lumps of soil in the material used
to backfill the opening around your
foundation. There are other kinds
of waterproofing systems on the
market; Thermadry is a system of
2’ by 8’ tongue and groove panels
that are channeled to deflect wa-
ter for example.
Now that we have got the myths out of the way we can look at the different kinds of actual external coatings and membranes that are
on the market. It is a long list so I am going to stick to the most common types. Bentonite clay is a powdered mix that is also used in some
toothpaste. It was the first recognized waterproofing material and entered the residential market in the mid 60’s.
Once the mix is prepared by a trained installer it swells up to form a sticky gel upon application. It is also available in sheet form. The draw-
back to this material is it must be shielded from rain and if there is any free flowing ground water it will erode it away.
“John McEwen from Eastern Ontario Foundation has fought for years to get this included, as have many other reputable contractors…”
The majority of reputable foundation contractors utilize a rubberized liquid coating
or some form of continuous membrane. There are numerous kinds of membranes on
the market. Yellow jacket is one type that is applied over a preparation coating and is
set into the coating. It is an open weave glass fabric material that is colored so the
installer can see that they have covered it fully. It is applied in layers to form a water-
proofing covering. It seems that the word “Blue” is attached to many foundation ma-
terials. One make is called “Blueskin”, it is a self adhesive membrane that is applied
over a sealing primer compound that has been applied and cured. Another mem-
brane is called dimple wall and is made by a couple of companies. This rubberize sheet
is designed to offset the actual membrane from the wall by 5/16” by means of a dim-
pled surface. The manufacturer claims it keeps the soil away and allows any dampness
in the blocks to condensate outwards onto the membrane and then drain down to the
drainage tile for removal.
Last week we looked at the different kinds of coatings and membranes that are used on block basements to correct dampness and outright water invasion. This week we look at what should happen when it comes time to dig up a basement and correct the problem. Actually we are going to look at how a reputable contractor should begin. Over the years I have had numerous conversations with responsible foundation contractors and every conversation contains the comment about the lack of a permit for this type of work in the building code. The OBC steers clear of this issue and when you consider the cost along with the multiple num-
bers of “quick buck” contractors in the foundation repair and waterproofing business we are always amazed this has never been included. John McEwen from Eastern Ontario Foundation has fought for years to get this included, as have many other reputable contractors, it is a regional responsibility. In my local area, the City of Kingston does not require a permit, yet the township just north of the city does, go figure! The CBO for the individual municipality can mandate this re-quirement and some do. If you are at the stage where this type of work has been recommended for your basement, check with your municipality to see if they require a permit. This can be a very expensive repair job; you should do your homework, check references and talk to neighbours and friends who have had the same problem. Ask them who fixed their basement and were they satisfied. Responsible, reputable foundation contractors are few and far between and the good ones are usually booked weeks and months ahead. The Pro’s have a recognized process and we are going to go thru this step by step so you understand what should be done. I have been on site with Jerry Shea, the patriarch of Shea Construction in Kingston on different occasions. Jerry has many, many years of foundation repair experience to support his company.
6
Waterproofing continued
We Excavate
The first thing that Jerry does is walk around the building, establish the grades and what he thinks may be the ground water issues. I was at a home recently that has a water issue in the basement, Jerry calmly described how a nearby ground water drainage pipe that was installed in the 50’s had plugged years ago, this is where experience counts. He knew where the water would pond in the yard before the owner could describe it. He then goes to the basement and brings out his moisture meter, meticulously checking numer-ous spots on the wall for moisture. He takes his time
explaining the issues to the client, what it will take to fix the problem and how much it will cost. I have seen Jerry talk to a client for more than an hour explaining what has happened and why. I know two other contrac-tors in this business that operate the same way, the Pro’s have a responsible dedicated method, they know this is going to be an expensive repair and want you to understand the process. Once you have decided to “dig it up”, don’t expect the
back hoe to arrive and start moving dirt the next day.
We Excavate
Excavation
Your contractor has some homework to do. His first call will be
to the local utilities company to establish where the under-
ground residential infrastructure is located. Everything is under-
ground today in many cases. Your hydro, water, gas and sewer
lines must all be located. If there are overhead wires that could
cause equipment issues the appropriate utility company should
be advised and if necessary have the lines temporarily moved.
If your home is located in a high traffic area a traffic control
plan should be established. Most reputable contractors have a
strong working relationship with the municipality; they realize
they must work together here. In some cases they may be
aware of an underground tank and this must be attended to
and removed first, especially if it is an abandoned oil or fuel
tank. If the neighbors are close by most reputable contractors
will contact them and advise them of pending work and the
proposed schedule to help reduce any inconvenience.
Preparation of the outside of the home is established, if you
have a favorite tree, tell your contractor so they are extra care-
ful. Equipment like your air conditioner will have to be moved
by a reputable TSSA contractor, steps and decks can sometimes
be moved and replaced, other’s may need to be demolished.
Your contractor should establish all of this before a shovel hits
the ground. I have seen the Excavation Assessment and Proce-
dures list that Shea’s use and it’s impressive. It covers every-
thing from safety, traffic control, and local hazards to necessary
equipment that will be need on site. Most good contractors
operate with similar job site records.
8 Excavating the foundation
The Dig Begins
Last week we listed off the procedures that are needed to properly prepare a site for
excavation around a block basement, in previous weeks we discussed waterproofing
methods and reasons why block basements are known for water issues.
There are a number of advantages to digging up a basement and certainly benefits
from insulating the exterior of the foundation. Some of the companies that manufac-
ture waterproofing coatings and membranes actually require an insulation barrier
applied to the wall after covering is installed. This is done to protect the waterproof
barrier from damage by soil or rocks when the back fill work is done. While it is not
required, unless it’s a manufacturer’s standard, exterior insulation applied to the
foundation is not as common as it
should be. There is the cost factor here
and often times the five figure excava-
tion “hit” on the family budget is
enough that the additional two or
three thousand for rigid foam insula-
tion is beyond available funds. Install-
ing rigid foam insulation will dramati-
cally reduce the level of condensation
in the block walls. It might mean a va-
por barrier on the interior wall may not
be needed. It protects the walls from
additional air leakage provided this
insulation application is installed up the
wall fully including the rim joist or
header areas, whichever term you like.
This insulation will dramatically im-
prove the air quality and temperature
in the basement.
“I won the bet”
A couple of years ago I was on a
major renovation and basement
excavation site and the owner was
hesitating on the cost of the insula-
tion. I took him inside and we took
the temperature of the home’s
main level by using a laser ther-
mometer. We then went to the
unfinished basement and there
was a seven degree difference. I
told him that properly installing
the external rigid foam and includ-
ing the rim joists would close this
gap by around 50%. He bet me a
steak dinner I was going to be
wrong….I enjoyed the dinner….his
basement was 2 degree different
from the main level when the job
was done.
“I told him that properly installing the external rigid foam and including the rim joists would close this gap by around 50%..”
The Dig
9
Caption describing picture or graphic
Now on to the dig and everything was getting ready, I joined Corey Shea from Shea’s Construction on the site. He is the field
boss and one of Jerry Shea’s Sons. Corey was carefully going thru their Excavation Assessment as their crew unloaded the
track hoe. I was pleased to see the size of equipment on site. Some years ago I had a block wall fail because we allowed a full
sized back hoe too close to the block wall. They had put up the stakes for the safety fence and the operator slowly began at
the edge of the foundation removing the soil and piling it away from what became the hole beside the foundation. Large rocks
and any hard clay pieces were separated and removed from the stored soil. Corey said they will use the existing soil provided
it is suitable, if not they replace it with better draining soil. If present, they also removed the old clay drainage tile. Some
homes built before the 80’s when “Big O” came into popularity had a clay tile drain system installed around the foundation.
Corey stated that nearly 100% of those that they dig up are filled with silt and roots, long since failed in their usefulness. All of
this waste is removed from the site.
Once the trench is dug they care-
fully shore up the walls with braces
and plywood to protect their staff.
Corey was adamant at this point
about the crew’s safety in the
trench and watched over this instal-
lation carefully. They now began the
arduous task of scraping down the
walls and checking for any major
cracks or openings in the founda-
tion. Depending upon the severity
of the cracks they use professional
crack sealants or a prep coat and a
mesh type covering that is imbed-
ded into the prep coat. Corey said
each job is different and they come
prepared for different crack and
patch work. The time consuming
work of preparing the walls by
scrapping them down, pressure
washing if necessary and removing
any old parge that is still present
that would be below grade. At this
point they try and establish where
the drain tile will discharge. Corey
said this can be frustrating at times
as many homes never had a proper
discharge to the storm sewers or a
dry well.
Once everything is prepared and
the trench cleaned out the clear stone is brought in. A layer is set at the edge of the foundation to “bed down” the perforated
plastic pipe that will become the drain tile. Corey said this is one of the most important areas, ensuring that it sits beside the
footings and has a proper base for drainage. Shea’s have a policy of adding close to three feet of gravel from the base up the
wall. Corey recognized this may be “over kill” but they feel the extra cost is outweighed by the benefits of proper drainage.
Second Choice
External pumps are not as
common, I know of only
one basement contractor
who uses this installation. I
have seen these used
where the basement is oc-
cupied and the owner
wants access to the pump
at any time. The contractor
must excavate a pit about
20 inches below the foot-
ings, usually in a corner.
They will install a culvert
section as a chamber for
the sump pump. Care must
be taken to ensure the
pump and float is not ob-
structed. The rigid plastic
line should be discharged
on the surface. In this type
of installation you do not
use a check valve; the cover
should be secure, water
resistant and insulated to
reduce the chance of
freezing.
The Final Step
The last step depends upon the water test that they do on the drain tile. If the water
test shows good discharge or they know they have got a storm sewer hookup, then a
sump may not be necessary. Corey Shea noted that a high percentage of basement
waterproofing jobs they do includes a sump pump if they are the least bit unsure of
the drainage. There are two methods of installing a sump pump, internal or external.
Corey commented that they prefer the internal pump for a couple of reasons. He has
seen the external units freeze up if they are poorly installed and if a pump fails this is
Last week we got the block foundation
walls cleaned, covered in a waterproof
coating and reset the drainage tiles, then
installed a bed of washed stone. The
stone acts as the clear base for the soil
that will back fill against the house. Prop-
erly draining soil is the last step and can
consume a large portion of the actual
budget if it has to be removed and re-
placed. The soil that goes back into the
hole has to be pushed in carefully; too
much pressure can crack or bow the
wall. I have seen a basement contractor
do this in layers and slowly raise each
level of soil. Once the trench is filled the
soil should be set with an aggressive
slope away from the building. This allows
for the expected settlement. Casey Shea
made comment during this interview
that they go back to a site some weeks
later and check to see if the soil has set-
tled more than expected and they have
brought in additional soil in some cases
so this all important drainage away from
the building is maintained. They seed it
down for grass and replaced the shrubs
if requested.
10
Sumps
Excavate outside the house to confirm the existence and shape of the tile system
Dig a hole through the floor slab down about 45cm (17 1/2 “) on the opposite side of the wall inside the basement
Dig a tunnel under the footing connecting the two
Have the tiles empty directly into the sump pit
Allow water under the floor slab free access to the pit
If using manufactured plastic “pails” as sump pits, make sure they have enough access holes punched or drilled into them
Secure a sump pump into the pit and direct discharge water in a legal fashion (do not flush water directly into septic tank)
Securely cover the pit
Backfill exterior hole with as much clear stone as possible
To avoid soil gases, sumps should be covered and vented outdoors
When they know they need a sump pump they jack ham-
mer out a spot in the basement floor, usually at a corner
where they can loop in the drainage tile. Most pro’s use the
manufactured plastic bucket designed for a sump installa-
tion. These buckets are about 18 inches deep and are usu-
ally set up on a base of washed gravel. A channel is dug
under the footings to allow the plastic drain pipe to be dis-
charged into the bucket. There are a number of punch out
holes that can be opened to help with the under pad drain-
age too. Shea’s use a submersible sump pump manufac-
tured by Hydramatic. I have also used this brand; they are
known for long term reliability and are far better than the
stem style of sump pump. Once this is all set in place a hard
plastic discharge line should be installed along with a check
valve fitted just above the base of the liner. This check valve
stops the back flow of water reversing the pump; this will
reduce its life span. Once outside the wall with the hard
pipe you must carefully discharge this water, it can create
some amount of erosion. If you are in the city you cannot
discharge this water onto your neighbour’s property. It may
take some thought, don’t bury this line however. I have
seen more than one early spring thaw where the under-
ground pipe froze and caused some considerable damage
when the final spring thaw came.
Back inside the home this sump pit should be finished.
Proper concrete poured around the top edge and the
bucket cover fitted and twist locked into place. This is done
for a couple of reasons. It helps reduce the evaporation of
the water into the basement which only adds to extra hu-
midity and the cover stops anything from falling into the
sump hole and damaging the actual pump. If at all possible
the pump should be on a designated electrical circuit so
that no other tools or appliances could accidentally trip the
power supply.
ALLTECH CONSULTING GROUP
A tip of the hat to John McEwen who co-authored the CMHC booklet “A
Guide to Fixing Your Damp Basement”. It’s an excellent book.
A special “Thank You” to the Shea Family; Jerry, Casey, Corey and their staff
at Shea Construction in Kingston Ontario. They opened up their job sites, al-
lowed me access to their work plans, operational procedures and were pa-
tient with my questions. Without them this series on block basements would
not have been possible.
Many Thanks
Cam Allen L.I.W. RHI
Phone: 613-546-9876