March 2013 NSW Public Works Asbestos in Grounds, Asbestos Management Plan, Muirfield High School, North Rocks, NSW Parsons Brinckerhoff Australia Pty Limited ABN 80 078 004 798 Level 27, Ernst & Young Centre 680 George Street Sydney NSW 2000 GPO Box 5394 Sydney NSW 2001 Australia Telephone +61 2 9272 5100 Facsimile +61 2 9272 5101 Email [email protected] Certified to ISO 9001, ISO 14001, AS/NZS 4801 A GRI Rating: Sustainability Report 2011 2171479A PR_6945

Transcript of Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in...

Page 1: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

March 2013

NSW Public Works

Asbestos in Grounds, Asbestos Management Plan, Muirfield High School, North Rocks, NSW

Parsons Brinckerhoff Australia Pty Limited ABN 80 078 004 798

Level 27, Ernst & Young Centre 680 George Street Sydney NSW 2000 GPO Box 5394 Sydney NSW 2001 Australia Telephone +61 2 9272 5100 Facsimile +61 2 9272 5101 Email [email protected] Certified to ISO 9001, ISO 14001, AS/NZS 4801 A GRI Rating: Sustainability Report 2011 2171479A PR_6945

Page 2: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

2171479A PR_6945

© Parsons Brinckerhoff Australia Pty Limited (PB) [2013].

Copyright in the drawings, information and data recorded in this document (the information) is the property of PB. This document and the information are solely for the use of the authorised recipient and this document may not be used, copied or reproduced in whole or part for any purpose other than that for which it was supplied by PB. PB makes no representation, undertakes no duty and accepts no responsibility to any third party who may use or rely upon this document or the information.

Author: ....................................................................................... Warren Lal

Signed: ............................................................................

Reviewer: ........................................................................................ John Batty

Signed: .........................................................................................................

Approved by: ..................................................................................... Jason North

Signed: .........................................................................................................

Page 3: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page i

Contents Page Number

1. Introduction .................................................................................................................................... 1 1.1 Document Review 1 1.2 Background 1 1.3 Asbestos removal/clean-up works 2

2. Asbestos materials ......................................................................................................................... 4 2.1 Asbestos zone locations 4 2.2 Risk management 4

3. Asbestos register (Grounds) ......................................................................................................... 6

4. Asbestos zone routine management .......................................................................................... 10 4.1 Inspections 10 4.2 Maintenance 10 4.3 Checklist 10

5. Asbestos zone maintenance works management ...................................................................... 12 5.1 General 12 5.2 Sub-soil areas within school grounds 12

6. Permit for work ............................................................................................................................. 14

7. Legislative requirements ............................................................................................................. 16

8. Safe work procedures for asbestos work ................................................................................... 18

List of Tables Table 3-1 Asbestos Register – Asbestos zones only for Muirfield High School List of Figures Site layout plans Appendices Appendix A Grounds management checklist

Page 4: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks,

NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 1

1. Introduction

1.1 Document Review No Activity and/or no Re-occurrence of ACM in grounds on this site since October 2012, as such the following is recommended:

This document is to be reviewed and updated

when works occur on site

when works occur on site which may cause grounds disturbance

when any ACM in grounds is reported

every second year, if no activity.

until ten years of inactivity, when document review and update will occur every five years

1.2 Background In February 2003 and November 2006, fibrous cement fragments were identified on the ground surfaces of the following areas;

Area A – grounds surrounding the front car park to the East of the site;

Area B – grounds to the East of the Administration/Office Block;

Area C – grounds surrounding sports building and to the West of the North/East sports oval;

Area D – stormwater detention basin North/west of the school buildings;

Area E – grounds to the West of the Assembly Hall;

Area F – grounds to the North of the Library;

Area G – grounds to the west of the North/West sports oval;

Area H – grounds to the south of the North/East sports oval;

Area I – grounds to the East of the main entrance road;

Area J – grounds to the south of the sports court;

Area K – grounds to the west of the main entrance road, adjacent to the Administration/ Office Block;

Area L – grounds to the south of Block L

at Muirfield High School, Barclay Road, North Rocks NSW 2150.

Page 5: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks,

NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 2

In order to manage the risk of exposure to asbestos, any fibrous cement fragments are to be removed from the ground surfaces (Refer to Section 1.3). The areas where fibrous cement fragments have been identified within the fill material (and further in-situ asbestos fragments may be present) have been designated as “asbestos zones”.

In the previous ground inspection reports, by Sinclair Knight Merz dated 1 February 2003 and reports produced by PB dated 10 February 2003 and report reference 2115108A/LT_5205/TR/ks dated 25 January 2007, it was proposed that the asbestos zones (i.e. areas of imported fill) located throughout the school were either encapsulated using a mixture of encapsulation techniques such as turfing, mulch garden beds and/or installing hard stand surfaces or monitored on a regular basis. If fragments continue to be identified in these areas which are to be monitored, the areas will be reassessed and appropriate surface treatment measures such as re-turfing, paving and/or mulching implemented.

Another inspection was conducted in April 2011 of areas overlapping those of the original AMP. The results are outlined in the report numbered 2116799B LT_4030/TR/kt. The areas inspected in April 2011 are as follows:

C1-2011 – Garden bed area south of store area

C2-2011 – Grassed area west of basketball court

F-2011 – Area south-east of library

N-2011 – New garden bed within Block C quadrangle

This report outlines the plan for management of the identified asbestos impacted areas (zones), and should be read in conjunction with the existing Department of Education and Communities (DEC) Asbestos Management Plan for all other identified asbestos materials within the school.

1.3 Asbestos removal/clean-up works At the time of updating the Management Plan, March 2011, no further occurrence of asbestos in grounds had been reported to PB.

Based on the information provided by the DEC, it is PB understanding that the asbestos removal/ clean up works completed in 2003 comprised:

Area A – access to this area was restricted and encapsulated with mulch.

Area C – the area was encapsulated with a layer of geo-fabric and covered with topsoil and turf. A concrete path was installed between the Sports Block and the Canteen (Block B) to reduce further erosion by student traffic.

Area F – the area was encapsulated with a layer of geo-fabric and covered with topsoil and turf.

Area K – the grounds were encapsulated with a layer of geo-fabric and covered with a mulched garden bed.

Area L – the ground were covered with a compact road base and landscaped.

Page 6: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks,

NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 3

In November 2006 approval was given by the DEC for the removal of an asbestos contaminated stock pile in the Agricultural plot.

All other area are to be regularly inspected for fibrous cement fragments

It is Parsons Brinckerhoff’s understanding that the areas listed in the April 2011 inspection report were sparrow-picked. No further investigations have occurred since that date.

The remediated areas are shown in Figure 1.

Page 7: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks,

NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 4

2. Asbestos materials

2.1 Asbestos zone locations Asbestos cement fragments may be present as a component of buried fill within the asbestos zone areas. Refer to Figure 1 site plan. A hygienist should be engaged to determine whether the asbestos within the Asbestos Zones is considered non friable or friable in accordance with the NSW WorkCover Authority ‘Working with Asbestos, 2008’. This contains safety guidelines and requirements for work involving asbestos.

2.2 Risk management The in-situ asbestos within the asbestos zones can be classified as low risk provided that the following measures are undertaken:

The control measures installed are fully maintained.

The in-situ asbestos remains undisturbed.

An asbestos management plan remains in effect.

Any works undertaken on or near the asbestos zones are to be under the control of a permit to work where the contractor has acknowledged the presence of asbestos and has prepared a safe work method statement(s) to ensure that asbestos is not disturbed and therefore airborne asbestos fibres are not generated.

Page 8: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 5

Page 9: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 6

3. Asbestos register (Grounds) Table 3-1 outlines the findings of the inspection of the grounds indicating the areas requiring management.

Table 3-1 Asbestos Register – Asbestos zones only for Muirfield High School

Event Location Description of Material Extent Condition Risk

Status Control Priority Control Recommendation/Comments

School Grounds*

A

Grounds surrounding front car park area to the East of the site

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Maintain existing surface/ new surface in a good condition. Do not disturb soil surface. Inspect every three months or after adverse weather conditions for signs of surface wear and possible fragments at surface.

B

Grounds to the East of the Administration/Office Block

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

C

Grounds surrounding Sports Building, West of the North/east sports field

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Maintain existing surface/ new surface in a good condition. Do not disturb soil surface. Inspect every three months or after adverse weather conditions for signs of surface wear and possible fragments at surface.

D

Stormwater detention basin North/west of the school buildings

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

E Grounds West of the Assembly Hall

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

Page 10: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 7

Event Location Description of Material Extent Condition Risk

Status Control Priority Control Recommendation/Comments

F Ground North of the Library

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Maintain existing surface/ new surface in a good condition. Do not disturb soil surface. Inspect every three months or after adverse weather conditions for signs of surface wear and possible fragments at surface.

G Grounds West of the North/west sports oval

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

H

Grounds to the South of the North/east sports oval

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

I Grounds to the East of the main entrance Road

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

J Grounds to the South of the sports court

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

K

Grounds to the West of the Main entrance Road, adjacent to the Administration/Office Block

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Maintain existing surface/ new surface in a good condition. Do not disturb soil surface. Inspect every three months or after adverse weather conditions for signs of surface wear and possible fragments at surface.

L Grounds to the South of Block L

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Maintain existing surface/ new surface in a good condition. Do not disturb soil surface. Inspect every three months or after adverse weather conditions for signs of surface wear and possible fragments at surface.

Page 11: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 8

Event Location Description of Material Extent Condition Risk

Status Control Priority Control Recommendation/Comments

C1-2011

Garden bed area south of Canteen

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

C2-2011

Grassed area west of Basket Ball Court

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

F-2011 Area south-east of Library

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

N-2011

New garden bed within Block C quadrangle

Possible buried asbestos cement fragments

Throughout – below ground surface

Unknown Low Low

Inspect on a regular basis for signs of surface wear and possible fragments at surface. If fragments continue to be found, appropriate remediation measures should be implemented. The initial inspections should be carried out by a Department of Commerce representative.

*Refer to Figure 1 for detail of area locations

Risk assessment factors

Low risk: Asbestos materials that pose a low health risk to personnel, employees and the general public provided they remain undisturbed.

Medium risk: Asbestos materials that pose a moderate risk to people in the area – there is a medium potential for the material to release asbestos fibres, if disturbed.

High risk: Asbestos materials that pose a high health risk to personnel or the public in the area of the material – there is a high potential for the material to release asbestos fibres, if disturbed.

Page 12: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 9

Page 13: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 10

4. Asbestos zone routine management 4.1 Inspections by local staff

In order to monitor the effectiveness of the on-site asbestos zone management, it is essential that the affected areas are regularly inspected. Visual inspections of the asbestos remedial measures should be carried out to ensure that they are maintained adequately. Such inspections should occur on the following occasions:

at three monthly intervals (e.g. a walkover of remediated areas to ensure that applications of mulch and turf, etc. have been maintained)

after a period of prolonged heavy rain (e.g. a walkover of remediated areas to ensure that applications of mulch and turf, etc. have not been disturbed by heavy rain)

whenever damage or disturbance has been reported (e.g. a walkover of remediated areas to ensure that applications of mulch and turf, etc. have not been disturbed by events such as vehicle movements).

whenever works are about to commence that may cause grounds disturbance

Should areas be identified where encapsulating measures appear to be damaged or are no longer effective, these areas should be re-covered immediately. Some remedial measures such as the installation of layers of mulch and top soil will require ongoing maintenance to ensure that a sufficient barrier layer is in place.

4.2 Maintenance All remediation measures carried out in the affected areas must be maintained as per their original application. In particular:

All surface cover/treatments within the asbestos zones must be fully maintained at all times. For example, mulch levels should remain as per their original application, turf should be maintained to ensure full coverage and any other measures should be maintained in a good condition.

All hard standing surfaces must be maintained and re-instated should any works that disturb them be carried out.

If any portion of an affected area is found to be damaged (i.e. the surface cover has been damaged so that it has resulted or may result in the soil becoming exposed), the DEC local Asset Management Unit (AMU) should be contacted immediately.

4.3 Checklist A checklist of site management requirements is presented in Appendix A of this document. This checklist should be used whenever walkover inspections are carried

Page 14: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 11

out and where maintenance issues have been raised. The checklist is specific to the requirements of the grounds at the Murifield High School and sets out the frequency of inspections required. It is recommended that a hard copy of the check-list retained by the school and field copies are taken on-site when required.

Page 15: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 12

5. Asbestos zone maintenance works management

5.1 General An Asbestos Management Plan (AMP) has been implemented for all NSW state schools and educational facilities. The plan includes procedures for managing friable asbestos and working on asbestos. A generic permit to work template will also be included in the management plan which will be able to be used where any work is required that may disturb asbestos materials within an asbestos zone.

5.2 Sub-soil areas within school grounds Any contractor, maintenance person; all Department of Commerce,

Department of Education & Communities personnel or other authorised persons must acknowledge the presence of buried asbestos cement materials within these areas. A copy of the asbestos register must be made available to any such person prior to commencing work.

Any contractor, maintenance person; all Department of Commerce, Department of Education & Communities or other authorised person who may potentially disturb the soil surface must complete a permit to work or similar form that ensures that any work will not disturb the buried asbestos.

If work is to be carried out in grounds that will disturb or potentially disturb the buried asbestos, the contractor, maintenance person; all Department of Commerce, Department of Education & Communities personnel or other authorised person must engage a licensed asbestos removal contractor with a friable asbestos licence to undertake the work. The licensed contractor should prepare a safe work method statement detailing procedures that ensure that personnel working in the asbestos zones and any other persons within the school will not be exposed to asbestos fibres. The work area must be completely enclosed and work undertaken out of school hours.

Work in progress asbestos air monitoring should be carried out during any work that disturbs or could potentially disturb the buried asbestos and/or the soil surface. Air-monitoring should be in accordance with the National Occupational Health & Safety Commission's Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres 2nd Edition [NOHSC: 3003 (2005)] and be conducted by National Association of testing Authorities (NATA) accredited personnel operating from a NATA registered laboratory.

All asbestos management measures originally installed must be re-instated at the completion of work and prior to the removal of the work area enclosure.

Page 16: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 13

Page 17: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 14

6. Permit for work Any contractor who proposes to work in any of the asbestos zones where asbestos may be disturbed or the ground surface may be broken must complete a permit to work form.

Before a permit to work is issued, individuals will be required to read and understand the AMP, as well as copies of the relevant asbestos registers. Individuals must be aware of their legal obligations in relation to health and safety as specified in the Work Health and Safety Act 2011 and the Work Health and Safety Regulation 2011.

Permits to work are designed to ensure appropriate work practices are employed in the vicinity of asbestos-containing materials/products. The permit to work will document what asbestos is to be removed, encapsulated or otherwise protected, prior to the contracted maintenance or building works proceeding. The permit to work will also indicate whether other requirements, such as the use of personal protective equipment (PPE), the installation of barricading and/or airborne fibre monitoring, are necessary.

When the work is completed, or the permit to work expires (whichever occurs first), the permit shall be signed and returned to the DEC Facility Manager for cancellation after that Manager has checked a safe situation exists.

The DEC local AMU shall be advised immediately of any incidents of non-compliance with the AMP.

In accordance with the interpretation of the NSW WorkCover Authority published in ‘Working with Asbestos,’ Guide 2008, a licenced asbestos assessor should be engaged to determine whether the buried asbestos is considered non-friable or friable. Therefore, any fibrous cement materials or other suspected asbestos-containing materials excavated should be inspected by a hygienist to determine if it’s friable. This means that any such asbestos should be worked on only by contractors with an appropriate asbestos licence and a project specific permit issued by WorkCover NSW (in addition to the permit to work, mentioned above).

Page 18: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 15

Page 19: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 16

7. Legislative requirements The following legislative requirements will apply to asbestos zone maintenance works:

All asbestos removal and disposal work shall be carried out in accordance with the requirements of the WorkCover NSW Guidelines for Licensed Asbestos Removal Contractors

The asbestos contractor shall notify WorkCover NSW of the proposed work at least 5 days prior to the commencement of any work in accordance with NSW Occupational Health and Safety Regulation 2011. However this time period may be waived in the case for DEC properties

All work shall be carried out in strict accordance with the NSW Work Health and Safety Act 2011, the NSW Work Health and Safety Regulation 2011, How to Safely Remove Asbestos – Code of Practice 2011, and the Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres, 2nd Edition [NOHSC 3003 (2005)].

Page 20: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 17

Page 21: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW

PARSONS BRINCKERHOFF 2171479A PR_6945 Page 18

8. Safe work procedures for asbestos work The following safe work procedures will apply for asbestos work:

The removal contractor must develop a site-specific asbestos removal plan before commencing the asbestos work. Such a plan must be prepared in accordance with Section 3 of the Work Safe Australia- How to safely remove asbestos: Code of Practice 2011.

Only personnel who have been trained in work procedures for the safe removal of asbestos shall work on asbestos.

A trained, experienced operator must remain on duty outside the removal area and/or enclosure (if installed) at all times that asbestos removal is in progress. Curricula vitae for all persons undertaking asbestos removal works must be submitted to the Principal prior to the commencement of work on the sites.

Removal of asbestos must generally be carried out by wet removal techniques. That is, as the asbestos material becomes accessible during the removal process, it shall be thoroughly wetted down. Care must be exercised to prevent excessive use of water. The contractor will be held responsible for any water damage.

Decontamination facilities and procedures shall be undertaken to the complete satisfaction of a hygienist.

Any signage existing prior to removal must be re-affixed to any new or existing assembly.

The contractor must ensure that persons in the work area(s) are not exposed to fibre levels greater than those stated in the National Exposure Standard for the type of asbestos being removed.

Page 22: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Figures

Site layout plans

Page 23: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Store

C1-2011

C2-2011N-2011

M

F-2011

Figure 1.

Muirfield High School

Key

Previous asbestos zone

New asbestos zone

N

Page 24: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Appendix A

Grounds management checklist

Page 25: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Muirfield High School grounds asbestos management checklist – Routine three monthly inspections Table 1 Routine monthly inspection checklist

Three monthly inspections Initial inspection Subsequent three-monthly inspections

Area Location description Date: Date: Date: Date: Date:

A Grounds surrounding front car park area to the East of the site

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

B Grounds to the East of the Administration/Office Block

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

C Grounds surrounding Sports Building, West of the North/east sports field

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

D Stormwater detention basin North/west of the school buildings

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

E Grounds West of the Assembly Hall

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

F Ground North of the Library

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

G Grounds West of the North/west sports oval

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

H Grounds to the South of the North/east sports oval

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

Page 26: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Three monthly inspections Initial inspection Subsequent three-monthly inspections

Area Location description Date: Date: Date: Date: Date:

I Grounds to the East of the main entrance Road

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

J Grounds to the South of the sports court

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

K Grounds to the West of the Main entrance Road, adjacent to the Administration/Office Block

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

L Grounds to the South of Block L

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

C1-2011

Garden bed area south of Canteen

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

C2-2011

Grassed area west of Basket Ball Court

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

F-2011

Area south-east of Library

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

N-2011

New garden bed within Block C quadrangle

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

Page 27: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Muirfield High School grounds asbestos management checklist – Incident inspections (e.g. after heavy rain or disturbance) Table 2 Incident inspection checklist

Three monthly inspections Initial inspection Subsequent three-monthly inspections

Area Location description Date: Date: Date: Date: Date:

A Grounds surrounding front car park area to the East of the site

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

B Grounds to the East of the Administration/Office Block

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

C Grounds surrounding Sports Building, West of the North/east sports field

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

D Stormwater detention basin North/west of the school buildings

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

E Grounds West of the Assembly Hall

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

F Ground North of the Library

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

G Grounds West of the North/west sports oval

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

H Grounds to the South of the

Surface cover adequate (Y/N)

Page 28: Asbestos in Grounds, Asbestos Management Plan, Muirfield High … · 2020. 2. 6. · Asbestos in grounds, asbestos management plan, Muirfield High School, North Rocks, NSW PARSONS

Three monthly inspections Initial inspection Subsequent three-monthly inspections

Area Location description Date: Date: Date: Date: Date:

North/east sports oval

Suspected asbestos materials visible (Y/N)

I Grounds to the East of the main entrance Road

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

J Grounds to the South of the sports court

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

K Grounds to the West of the Main entrance Road, adjacent to the Administration/Office Block

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

L Grounds to the South of Block L

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

C1-2011

Garden bed area south of Canteen

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

C2-2011

Grassed area west of Basket Ball Court

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

F-2011

Area south-east of Library

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)

N-2011

New garden bed within Block C quadrangle

Surface cover adequate (Y/N)

Suspected asbestos materials visible (Y/N)