Asbestos Assessment - Toronto Catholic District School Board · Toronto Catholic School Board...
Transcript of Asbestos Assessment - Toronto Catholic District School Board · Toronto Catholic School Board...
Asbestos Assessment Immaculate Heart of Mary Catholic School 101 Birchmount Road, Toronto, Ontario Prepared for:
Toronto Catholic School Board 80 Sheppard Avenue East Toronto, Ontario, M2N 6E8
Attention: Kathleen Wilson Safety Officer, Accident Prevention, Occupational Health and Safety
April 2, 2015
Pinchin File: 103167
© 2015 Pinchin Ltd.
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Issued to: Contact: Issued on: Pinchin File: Issuing Office: Primary Contact:
Toronto Catholic School Board Kathleen Wilson Safety Officer, Accident Prevention, Occupational Health and Safety April 2, 2015 103167 50 Wellington Street East, Suite 200, Toronto, ON M5E 1C8 Mike Horobin, Senior Project Technologist (416)-368-6555 Ext. 1917
Author: Mike Horobin Senior Project Technologist (416)-368-6555 Ext. 1917 [email protected]
Reviewer: Scott Cryer, P.Geo. Operations Manager (905) 363-1311 [email protected]
© 2015 Pinchin Ltd. Page i
Asbestos Assessment April 2, 2015 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
EXECUTIVE SUMMARY
Toronto Catholic School Board (Client) retained Pinchin Ltd. (Pinchin) to conduct an asbestos building
materials assessment of Immaculate Heart of Mary Catholic School located at 101 Birchmount Road,
Toronto, Ontario. The assessment was performed on March 19, 2015.
The objectives of the assessment were to document the locations of asbestos building materials, evaluate
their condition and develop corrective action plans as required for the purposes of long term
management. The results of this assessment are not intended for construction, renovation, demolition or
project tendering purposes.
The assessed area consisted of the entire building. The building was vacant at the time of the
assessment work.
SUMMARY OF FINDINGS
Asbestos-containing materials (ACM) were confirmed to be present as follows:
• Plaster, containing chrysotile asbestos in the skim coat, is present throughout the
building.
• Texture finish, containing chrysotile asbestos, is present on walls of the Ground Floor and
Second Floor Corridors.
• Aircell pipe insulation, containing chrysotile asbestos, is present on straight sections of
hot water pipes.
• Parging cement, containing chrysotile asbestos, is present on fittings of hot water heating
pipes.
• 12” x 12” beige with grey streaks vinyl floor tiles, containing chrysotile asbestos, are
present in the building.
• 9” x 9” red with white streaks vinyl floor tiles and associated mastic, containing chrysotile
asbestos, are present within the building.
• 9” x 9” brown with dark brown and white streaks vinyl floor tiles and associated mastic,
containing chrysotile asbestos, are present within the building.
• 9” x 9” green with white streaks vinyl floor tiles, containing chrysotile asbestos, are
present within the building.
• 9” x 9” brown with white streaks vinyl floor tiles and associated mastic, containing
chrysotile asbestos, are present within the building.
© 2015 Pinchin Ltd. Page ii
Asbestos Assessment April 2, 2015
Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167
Toronto Catholic School Board DRAFT
• 12” x 12” beige with brown and white streaks vinyl floor tiles and associated mastic,
containing chrysotile asbestos, are present within the building.
• 12” x 12” beige with grey and white flecks vinyl floor tiles (non-asbestos) and associated
mastic, containing chrysotile asbestos, are present within the building. Due to the mastic
containing asbestos, the composite material (tile and mastic) must be treated as
asbestos-containing.
SUMMARY OF RECOMMENDATIONS
The following is a summary of significant recommendations; refer to the body of the report for detailed
recommendations:
1. Prepare an Asbestos Management Program (AMP);
2. Perform a re-assessment of asbestos materials on an annual basis;
3. Perform a pre-construction assessment and remove all ACM prior to alteration or
maintenance work or if ACM may be disturbed by the work;
4. Follow appropriate safe work procedures when handling or disturbing asbestos;
5. Remediate the following asbestos-containing materials:
• 5 square feet on cracked plaster in Stair B.
• 3 square feet of damaged plaster in Room 210 (Janitor’s Closet).
• 5 square feet of cracked plaster on the wall of the Second Floor Corridor.
• 2 square feet of damaged plaster behind the radiator in Room 204.
• 2 square feet of damaged exposed plaster in Room 204.
6. Refer to Section 4.0 of this report for detailed recommendations regarding administrative
and remedial actions.
This Executive Summary is subject to the same standard limitations as contained in the report and must be read in conjunction with the entire report.
© 2015 Pinchin Ltd. Page iii
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
TABLE OF CONTENTS
1.0 INTRODUCTION AND SCOPE ....................................................................................................... 1
1.1 Scope of Assessment ........................................................................................................... 1
2.0 BACKGROUND INFORMATION ..................................................................................................... 1
2.1 Building Description .............................................................................................................. 1 2.2 Existing Reports.................................................................................................................... 2
3.0 FINDINGS ........................................................................................................................................ 2 3.1 Asbestos ............................................................................................................................... 2
4.0 RECOMMENDATIONS .................................................................................................................. 10
4.1 General ............................................................................................................................... 10 4.2 Remedial Work ................................................................................................................... 10 4.3 On-going Management and Maintenance .......................................................................... 11
5.0 LIMITATIONS ................................................................................................................................. 11
6.0 REFERENCES ............................................................................................................................... 12
APPENDICES
APPENDIX I Drawings
APPENDIX II Asbestos Analytical Certificates APPENDIX III Methodology
APPENDIX IV Photographs
© 2015 Pinchin Ltd. Page iv
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
1.0 INTRODUCTION AND SCOPE
Toronto Catholic School Board (Client) retained Pinchin Ltd. (Pinchin) to conduct an asbestos building
materials assessment of Immaculate Heart of Mary Catholic School, located at 101 Birchmount Road,
Toronto, Ontario.
The assessment was performed by Mike Horobin, Senior Project Technologist on March 19, 2015. The
surveyor was unaccompanied during the assessment. The building was vacantat the time of the
assessment.
The objectives of the assessment were to document the locations of asbestos building materials, evaluate
their condition and develop corrective action plans as required. This assessment is only to be used for the
purposes of long term management and routine maintenance. The results of this assessment are not to
be used for construction, renovation, demolition or project tendering purposes.
1.1 Scope of Assessment
The assessment was performed to establish the location and type of asbestos building materials
incorporated in the structure(s) and its finishes. The assessed area consisted of all parts of the building.
2.0 BACKGROUND INFORMATION
2.1 Building Description
Item Details
Building Use Elementary Catholic School
Number of Floors/Levels 2 stories plus 1 below grade
Total Area of Building (Square Feet) 28,700
Year of Construction, Significant Additions or Renovations
1959 with an addition in the 1960s
Structure Structural steel and concrete
Exterior Cladding Masonry
HVAC Boiler and hot water heating to radiators
Roof Built-up
Flooring Terrazzo, carpet, ceramic tile, vinyl floor tiles, concrete and dirt
© 2015 Pinchin Ltd. Page 1 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Item Details
Interior Walls Drywall, concrete block, speed tile and plaster
Ceilings Plaster and acoustic ceiling tiles
2.2 Existing Reports
Pinchin was provided with and instructed to rely upon, the following reports:
• “Final Report, Asbestos-Containing Building Material Assessment, Toronto Catholic
School Board, Immaculate Heart of Mary Catholic School, 101 Birchmount Road,
Scarborough, Ontario” dated April 29, 2008, by Jacques Whitford
3.0 FINDINGS
Please note references to sample numbers in the following refer to those samples obtained by Pinchin for
asbestos analysis. References to samples previously obtained by Jacques Whitford are indicated as
such.
3.1 Asbestos
3.1.1 Suspect Building Materials Not Found
The following types of building materials may historically contain asbestos but were not observed in the
building and are not discussed in the report findings:
• spray-applied fireproofing or thermal insulation;
• asbestos cement products;
• firestopping;
• sealants, caulking, and putty.
3.1.2 Texture Finishes (Acoustic/Decorative)
Texture finish is present on the plaster walls throughout the Ground Floor and Second Floor Corridors
(Samples 0013A-E) chrysotile asbestos was found to be present in the texture finish. There is
approximately 1,000 square feet of asbestos-containing texture finish that was found to be in good
condition.
© 2015 Pinchin Ltd. Page 2 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Asbestos-containing texture finish on the Corridor walls.
3.1.3 Thermal Systems Insulation (TSI)
3.1.3.1 Pipe Insulation
Parging cement, containing chrysotile asbestos, is present on pipe fittings (elbows, valves, tees, etc.) on
hot water systems (Previously sampled by Jacques Whitford). Parging cement is a friable insulation,
jacketed with canvas and is in good condition.
A white corrugated paper insulation (trade name Aircell), containing chrysotile asbestos, is present on
straight sections of hot water system pipes (Previously sampled by Jacques Whitford). Aircell is a friable
insulation, jacketed with canvas and is in good condition.
A tar layer is present over top of the asbestos-containing Aircell pipe insulation in the Basement Crawl
Space. Three samples of the tar layer (samples 0003A-C) were collected. No asbestos was detected in
the tar layer.
Non-asbestos fibreglass insulation is present on straight sections and fittings of remaining pipe in the
building. There was no asbestos parging cement noted on the seams of the insulation at the locations
inspected.
Pipe System, Type Location Sample
Number Asbestos Type Total Quantity
Quantity Damaged
Hot water heating, Aircell
Basement Crawl Space
Previously sampled Chrysotile 1,000 LF N/A
Hot water heating, Parging Cement
Basement Crawl Space
Previously sampled Chrysotile 100 Fittings N/A
Hot water heating, Aircell
Ground Floor Pipe Chase (behind Janitor’s Closet)
Previously sampled Chrysotile 30 LF N/A
© 2015 Pinchin Ltd. Page 3 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Pipe System, Type Location Sample
Number Asbestos Type Total Quantity
Quantity Damaged
Hot water heating, Parging Cement
Ground Floor Pipe Chase (behind Janitor’s Closet)
Previously sampled Chrysotile 5 Fittings N/A
Asbestos-containing Aircell pipe insulation.
Asbestos-containing parging cement insulation on pipe fittings.
Refer to additional photographs in Appendix IV.
3.1.3.2 Duct Insulation
Ducts are either uninsulated or insulated with non-asbestos fibreglass and jacketed with either canvas or
foil.
3.1.3.3 Mechanical Equipment Insulation
Mechanical equipment is not insulated.
Uninsulated boilers in the basement Boiler Room.
Uninsulated hot water heating tank in the basement Boiler
Room.
© 2015 Pinchin Ltd. Page 4 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
3.1.4 Acoustic Ceiling Tiles
Four (4) distinct types of acoustic ceiling tile are present in the assessed area, as follows:
Size, Type, Pattern Locations (Quantity in Square Feet)
Sample Number or Date Code Asbestos Type
1’ x 1’ glue-on 2-size hole Throughout the Ground Floor and Second Floor Classrooms
Previously sampled by Jacques Whitford
None (glue adhesive on the top of the tiles is presumed to contain asbestos)
24” x 48” lay-in pockmark and random pinhole
Ground Floor Corridor and Ground Floor Vestibule
Previously sampled by Jacques Whitford
None
24” x 48” lay-in 2-size pinhole
Ground Floor Corridor, Room 213, Room 214A, Room 306, Room 307 and Room 305
Previously sampled by Jacques Whitford
None
24” x 48” lay-in pockmark and medium pinhole Room 216 and Room 215 Dated 2012* None
*These ceiling tiles are presumed to be non-asbestos based on the date of manufacture determined from
the date stamp applied to the top of the tiles. The tiles were manufactured after asbestos stopped being
used in acoustic ceiling tiles.
The brown mastic which adheres the 1’ x 1’ glue-on acoustic ceiling tiles is presumed to contain asbestos
until further sampling proves otherwise.
1’ x 1’ 2-size hole acoustic ceiling tiles.
24” x 48” pockmark and random pinhole acoustic ceiling tiles.
Refer to additional photographs in Appendix IV.
© 2015 Pinchin Ltd. Page 5 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
3.1.5 Plaster
Plaster is present on walls and ceilings throughout the building. A total of seven (7) samples of plaster
(Samples 0001A-G) were collected and found that the plaster contains chrysotile asbestos in the skim
coat. Plaster is non-friable while in place, but generates friable dust upon removal.
Plaster was found to be in good condition with the exception of the following area:
• 5 square feet on cracked plaster in Stair B.
• 3 square feet of damaged plaster in Room 210 (Janitor’s Closet).
• 5 square feet of cracked plaster on the wall of the Second Floor Corridor.
• 2 square feet of damaged plaster behind the radiator in Room 204.
• 2 square feet of damaged exposed plaster in Room 204.
Damaged plaster on the wall in Stair B.
Damaged plaster on the wall in the Ground Floor Janitor’s
Closet, Room 210.
Refer to additional photographs in Appendix IV.
3.1.6 Drywall Joint Compound
Asbestos in drywall joint compound was banned in Canada in 1980. Drywall joint compound in Room 204
was installed after 1985 (1980 plus a reasonable non-compliance period based on our experience) and is
assumed to not contain asbestos.
3.1.7 Vinyl Sheet Flooring
Vinyl sheet flooring is present as follows:
© 2015 Pinchin Ltd. Page 6 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Pattern, Colour and Photo Number
Paper Backing (Yes/No)
Locations (Quantity) Sample Number
Asbestos Type
Grey, blue and beige mosaic No Room 216 and Room 217 Not
sampled* None
*Vinyl sheet flooring is presumed to be non-asbestos based on historical knowledge of the date of
installation and known end of us dates for asbestos-containing vinyl sheet flooring.
Non-asbestos grey, blue and beige mosaic vinyl sheet flooring.
3.1.8 Vinyl Floor Tile and Mastic
Vinyl floor tiles are present as follows:
Size, Pattern, Colour and Photo Number Locations (Quantity) Sample
Number Asbestos Type (tile)
Asbestos Type (mastic)
12” x 12” beige with white smudges Room 218 and Room 306
Previously Sampled by Jacques Whitford and 0010A-B
None None
12” x 12” beige with white and black streaks
Room 241, Room 214A, Rom 214B, Room 213, Room 305 and Room 311
Previously Sampled by Jacques Whitford and 0009A-B
None None
12” x 12” pink Ground Floor Corridor
Previously Sampled by Jacques Whitford
None None
© 2015 Pinchin Ltd. Page 7 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Size, Pattern, Colour and Photo Number Locations (Quantity) Sample
Number Asbestos Type (tile)
Asbestos Type (mastic)
12” x 12” orange with multi-colour Ground Floor Corridor
Previously Sampled by Jacques Whitford
None None
12” x 12” beige with grey streaks
Room 209 (500SF), Room 209A (25SF), Room 209B (25SF) and Room 303 (500SF)
Previously Sampled by Jacques Whitford
Chrysotile None
12” x 12” off-white Room 308, Room 309 and Room 312
Previously Sampled by Jacques Whitford and 0011A-C
None None
9” x 9” red with white streaks
Room 208A (10SF) and Room 310 (25SF)
Previously Sampled by Jacques Whitford
Chrysotile Chrysotile
9” x 9” brown with dark brown and white streaks
Room 208A (10SF), Room 310 (50SF), Room 313 (50SF) and 313A (10SF)
Previously Sampled by Jacques Whitford
Chrysotile Chrysotile
12” x 12” blue smears Room 302 and Room 307
Previously Sampled by Jacques Whitford and 0012A-C
None None
9” x 9” green with white streaks
Room 313 (25SF) and 313A (5SF)
Previously Sampled by Jacques Whitford
Chrysotile None
© 2015 Pinchin Ltd. Page 8 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Size, Pattern, Colour and Photo Number Locations (Quantity) Sample
Number Asbestos Type (tile)
Asbestos Type (mastic)
9” x 9” brown with white streaks
Room 208A (5SF), Room 310 (25SF), Room 313 (25SF) and 313A (10SF)
Previously Sampled by Jacques Whitford and 0002A-C
Chrysotile Chrysotile
12” x 12” beige with brown and white streaks
Room 206 0004A-C Chrysotile Chrysotile
12” x 12” red with white flecks Room 206 Closet 0005A-C None
None (same mastic as sample 0006)
12” x 12” grey with flecks Room 206 Closet 0006A-C None None
12” x 12” beige with grey flecks Room 205 0007A-C None None
12” x 12” beige with grey and white flecks Room 204 0008A-C None Chrysotile
The vinyl floor tiles and mastic are non-friable and are in good condition.
Asbestos-containing 9” x 9” red with white streaks vinyl floor
tiles.
Asbestos-containing 9” x 9” brown with dark brown and white
streaks vinyl floor tiles.
Refer to additional photographs in Appendix IV.
© 2015 Pinchin Ltd. Page 9 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
3.1.9 Levelling Compound
The levelling compound associated with the 12” x 12” beige with grey flecks vinyl floor tile was sampled
(Samples 0007B-C). Since only two samples of the levelling compound were found, the levelling
compound is presumed to contain asbestos until further sampling is performed.
Levelling compound is often used in scattered and isolated areas and without removing all flooring may
not always be detected.
3.1.10 Presumed Asbestos Materials
A number of materials which might contain asbestos were not sampled during our assessment due to
limitations in scope and methodology. Where present, these materials must be presumed to be an
asbestos material and are best sampled during project planning and preparation of contract documents
for their removal. Materials presumed to contain asbestos include:
• roofing, felts and tar;
• concrete floor levelling compound;
• moulded plastic components (laboratory bench tops);
• vermiculite in concrete block wall cavities;
• caulking;
• mechanical packing, ropes and gaskets;
• fire resistant doors or metal clad finishes; and
4.0 RECOMMENDATIONS
4.1 General
Perform a detailed intrusive assessment prior to building renovation or demolition operations. The
assessment should include destructive testing (i.e. coring and/or removal of building finishes and
components), and sampling of other hazardous materials (lead, mercury, PCBs, mould, etc.) and
materials not tested in this study (e.g. roofing materials, caulking, mastics).
4.2 Remedial Work
Perform the following remedial work to comply with existing regulations, due to the condition and location
of the material:
© 2015 Pinchin Ltd. Page 10 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Material and Quantity Location Recommended Procedure
Plaster, 5SF Stair B Repair following Type 2 Procedures
Plaster, 3 SF Room 210 Janitor’s Closet Repair following Type 2 Procedures
Plaster, 5SF Second Floor Corridor Repair following Type 2 Procedures
Plaster, 2SF Room 204 behind the radiator Repair following Type 2 Procedures
Plaster, 2SF Room 204 Repair following Type 2 Procedures
4.3 On-going Management and Maintenance
The following recommendations are made regarding on-going management and maintenance work
involving the asbestos materials identified.
4.3.1 Asbestos
Prepare an Asbestos Management Program (AMP). The AMP should address and document asbestos
work practices, worker training, notifications, policies and responsibilities.
Perform a re-assessment of asbestos materials on an annual basis. The next re-assessment of ACM
should be performed prior to March 2016 to remain in compliance.
Remove all ACM prior to alteration or maintenance work or if ACM may be disturbed by the work. Follow
appropriate asbestos precautions for the classification of work being performed.
Update the asbestos inventory report upon completion of any abatement and removal of ACM.
5.0 LIMITATIONS
The work performed by Pinchin Ltd. was conducted in accordance with generally accepted engineering or
scientific practices current in this geographical area at the time the work was performed. No warranty is
either expressed or implied by furnishing written reports or findings. The Client acknowledges that
subsurface and concealed conditions may vary from those encountered or inspected. Pinchin Ltd. can
only comment on the environmental conditions observed on the date(s) the survey is performed. The
work is limited to those materials or areas of concern identified by the Client or outlined in our proposal.
Other areas of concern may exist but were not investigated within the scope of this assignment.
© 2015 Pinchin Ltd. Page 11 of 12
Asbestos Assessment April 2, 2015 Immaculate Heart of Mary Catholic School, 101 Birchmount Road, Toronto, Ontario Pinchin File: 103167 Toronto Catholic School Board
Pinchin Ltd. makes no other representations whatsoever, including those concerning the legal
significance of its findings or as to other legal matters touched on in this report, including, but not limited
to, ownership of any property, or the application of any law to the facts set forth herein. With respect to
regulatory compliance issue, regulatory statutes are subject to interpretation and these interpretations
may change over time. Pinchin Ltd. accepts no responsibility for consequential financial effects on
transactions or property values, or requirements for follow-up actions and costs.
The liability of Pinchin or our officers, directors, shareholders or staff will be limited to the lesser of the
fees paid or actual damages incurred by the Client. Pinchin will not be responsible for any consequential
or indirect damages. Pinchin will only be liable for damages resulting from the negligence of Pinchin.
Pinchin will not be liable for any losses or damage if the Client has failed, within a period of two years
following the date upon which the claim is discovered (Claim Period), to commence legal proceedings
against Pinchin to recover such losses or damage unless the laws of the jurisdiction which governs the
Claim Period which is applicable to such claim provides that the applicable Claim Period is greater than
two years and cannot be abridged by the contract between the Client and Pinchin, in which case the
Claim Period shall be deemed to be extended by the shortest additional period which results in this
provision being legally enforceable.
Information provided by Pinchin Ltd. is intended for Client use only. Pinchin Ltd. will not provide results or
information to any party unless disclosure by Pinchin Ltd. is required by law. Any use by a third party of
reports or documents authored by Pinchin Ltd. or any reliance by a third party on or decisions made by a
third party based on the findings described in said documents, is the sole responsibility of such third
parties. Pinchin Ltd. accepts no responsibility for damages suffered by any third party as a result of
decisions made or actions conducted. No other warranties are implied or expressed.
6.0 REFERENCES
The following legislation and documents were referenced in completing the assessment and this report:
1. Asbestos on Construction Projects and in Buildings and Repair Operations, Ontario
Regulation 278/05.
2. Designated Substances, Ontario Regulation 490/09.
J:\103000s\103167 TCDSB,ImmaculateHea,ASB,ASSMT\Report\103167 - Immaculate Heart of Mary Asbestos Assessment Report.docx Template: Master Report for Asbestos Assessment, Haz, December 10, 2014
© 2015 Pinchin Ltd. Page 12 of 12
APPENDIX I Drawings
ASBESTOS-CONTAINING PIPE INSULATION MAYBE PRESENT ABOVE SOLID PLASTER CEILINGS.
ASBESTOS-CONTAINING TEXTURE FINISH ISPRESENT ON THE CORRIDOR WALLS OF THEGROUND AND SECOND FLOORS.
NOT ALL KNOWN OR SUSPECTED HAZARDOUSBUILDING MATERIALS MAY BE DEPICTED ON THEDRAWING. REFER TO THE HAZARDOUSBUILDING MATERIALS ASSESSMENT REPORTFOR A COMPLETE LIST OF KNOWN ANDSUSPECTED HAZARDOUS BUILDING MATERIALS.
LEGEND IS COLOUR DEPENDENT. NON-COLOURCOPIES MAY ALTER INTERPRETATION.
BASE PLAN PROVIDED BY CLIENT.
ASBESTOS-CONTAINING MATERIALS:
PIPE INSULATION
VINYL FLOOR TILES
VINYL FLOOR TILES & MASTIC
ASBESTOS BULK SAMPLE
STORAGE
BOILERROOM
STORAGE
STAIRS
ELECTRICALROOM
104
103A
103
102
CRAWL SPACEA0003C
A0003BA0003A
DATE:
DRAWN BY:
LOCATION:
CHECKED BY:
CLIENT:
PROJECT # :
DRAWING:
TITLE:
LEGEND:
SCALE:NTS
TORONTO CATHOLICDISTRICT SCHOOL BOARD
IMMACULATE HEART OF MARY C.S.101 BIRCHMOUNT ROAD
SCARBOROUGH, ONTARIO
HAZARDOUS BUILDINGMATERIALS ASSESSMENT
BASEMENT
2015/04/02
DS
MH
103167
1 OF 3
204CLASSROOM
203CLASSROOM
218M.E. CLASSROOM
M.E.WR
218A
VESTIBULE
201
202CORRIDOR
217CLASSROOM
CSTAIRS
216AWASHROOM
216WASHROOM
212CORRIDOR
205OFFICE
206OFFICE
ASTAIRS
207GIRLS
208PRINCIPAL
208AWR
209AWR
208B
209BWR
STORAGE
209STAFF ROOM
210
JANITOR
211BOYS
213HUB ROOM
214BSTAGE
214GENERALPURPOSE
ROOM
BSTAIRS
215SPECIAL EDUCATION
214AGYM
STORAGE
A0008A-C
A0007A-CA0004A-C
A0005A-C
A0006A-C
A0001A A0002A-C
A0009A-B
A0013D
A0001EA0001FA0013CA0001BA0013D
ASBESTOS-CONTAINING PIPE INSULATION MAYBE PRESENT ABOVE SOLID PLASTER CEILINGS.
ASBESTOS-CONTAINING TEXTURE FINISH ISPRESENT ON THE CORRIDOR WALLS OF THEGROUND AND SECOND FLOORS.
NOT ALL KNOWN OR SUSPECTED HAZARDOUSBUILDING MATERIALS MAY BE DEPICTED ON THEDRAWING. REFER TO THE HAZARDOUSBUILDING MATERIALS ASSESSMENT REPORTFOR A COMPLETE LIST OF KNOWN ANDSUSPECTED HAZARDOUS BUILDING MATERIALS.
LEGEND IS COLOUR DEPENDENT. NON-COLOURCOPIES MAY ALTER INTERPRETATION.
BASE PLAN PROVIDED BY CLIENT.
ASBESTOS-CONTAINING MATERIALS:
PIPE INSULATION
VINYL FLOOR TILES
VINYL FLOOR TILES & MASTIC
ASBESTOS BULK SAMPLE
DATE:
DRAWN BY:
LOCATION:
CHECKED BY:
CLIENT:
PROJECT # :
DRAWING:
TITLE:
LEGEND:
SCALE:NTS
TORONTO CATHOLICDISTRICT SCHOOL BOARD
IMMACULATE HEART OF MARY C.S.101 BIRCHMOUNT ROAD
SCARBOROUGH, ONTARIO
HAZARDOUS BUILDINGMATERIALS ASSESSMENT
GROUND FLOOR
2015/04/02
DS
MH
103167
2 OF 3
312SPEC. ED.
311CLASSROOM
310JANITOR
309CLASSROOM
308CLASSROOM
307LIBRARY
306CLASSROOM
304CORRIDOR
UPPERGENERALPURPOSE
ROOM
UPPER STAGE
305STORAGE
303CLASSROOM
302CLASSROOM
313HEALTH
313AWR
314
JANITOR
ASTAIRS
BSTAIRS
CSTAIRS
A0001GA0001C
A0013A A0013B
A0010A-BA0012CA0012BA0012AA0011CA0011BA0011A
ASBESTOS-CONTAINING PIPE INSULATION MAYBE PRESENT ABOVE SOLID PLASTER CEILINGS.
ASBESTOS-CONTAINING TEXTURE FINISH ISPRESENT ON THE CORRIDOR WALLS OF THEGROUND AND SECOND FLOORS.
NOT ALL KNOWN OR SUSPECTED HAZARDOUSBUILDING MATERIALS MAY BE DEPICTED ON THEDRAWING. REFER TO THE HAZARDOUSBUILDING MATERIALS ASSESSMENT REPORTFOR A COMPLETE LIST OF KNOWN ANDSUSPECTED HAZARDOUS BUILDING MATERIALS.
LEGEND IS COLOUR DEPENDENT. NON-COLOURCOPIES MAY ALTER INTERPRETATION.
BASE PLAN PROVIDED BY CLIENT.
ASBESTOS-CONTAINING MATERIALS:
PIPE INSULATION
VINYL FLOOR TILES
VINYL FLOOR TILES & MASTIC
ASBESTOS BULK SAMPLE
DATE:
DRAWN BY:
LOCATION:
CHECKED BY:
CLIENT:
PROJECT # :
DRAWING:
TITLE:
LEGEND:
SCALE:NTS
TORONTO CATHOLICDISTRICT SCHOOL BOARD
IMMACULATE HEART OF MARY C.S.101 BIRCHMOUNT ROAD
SCARBOROUGH, ONTARIO
HAZARDOUS BUILDINGMATERIALS ASSESSMENT
SECOND FLOOR
2015/04/02
DS
MH
103167
3 OF 3
APPENDIX II Asbestos Analytical Certificates
PINCHIN LTD. │ 2470 MILLTOWER CRT, MISSISSAUGA, ON L5N 7W5 │TEL: (905) 363-0678 FAX: (905) 363-0681
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Mike Horobin Date Received: March 20, 2015
Lab Reference No.: b117818 Date Analyzed: March 30, 2015Analyst(s): A. Di Giulio # Samples submitted: 22
# Phases analyzed: 34
Regulatory Threshold Provincial Jurisdiction Regulatory Threshold
0.5% Manitoba 0.1% friable 1% non-friable
0.1% Saskatchewan 0.5% friable 1% non-friable
1% Newfoundland and Labrador, PEI and New Brunswick 1%
Provincial Jurisdiction
All bulk samples submitted to this laboratory for asbestos analysis are retained for a minimum of three months. Samples may be retrieved, upon request, for re-examination at any time during that period.
Pinchin Ltd. is accredited by the National Institute of Standards and Technology, National Voluntary Laboratory Accreditation Program (NVLAP Lab Code 101270-0) for the 'EPA-600/M4-82-020: Interim Method for the Determination of Asbestos in Bulk Insulation Samples' and meets all requirements of ISO/IEC 17025:2005.
This report relates only to the items tested.
NOTE: This test report may not be reproduced, except in full, without the written approval of the laboratory. The client may not use this report to claim product endorsement by NVLAP or any agency of the U.S. Government. This report is valid only when signed in blue ink by the analyst. Vinyl asbestos floor tiles contain very fine fibres of asbestos and may be missed by some laboratories using the PLM method. Internal verification studies performed by Pinchin indicate that the chance of missing asbestos in floor tiles is no higher than about 2%. The vinyl tile study and laboratory documentation on measurement uncertainty is available upon request. The analysis of dust samples by PLM cannot be used as an indicator of past or present airborne asbestos fibre levels.
Ontario, British Columbia, Nova Scotia
QuebecAlberta, NWT, Yukon,
Nunavut
Prepared For:
Method of Analysis:EPA 600/R-93/116 - Method for the Determination of Asbestos in Bulk Building Materials dated July, 1993
103167
Bulk samples are checked visually and scanned under a stereomicroscope. Slides are prepared and observed under aPolarized Light Microscope (PLM) at magnifications of 40X, 100X or 400X as appropriate. Asbestos fibres are identified by acombination of morphology, colour, refractive index, extinction, sign of elongation, birefringence and dispersion stainingcolours. A visual estimate is made of the percentage of asbestos present. A reported concentration of less than (<) theregulatory threshold (see chart below) indicates the presence of confirmed asbestos in trace quantities, limited to only a fewfibres or fibre bundles in an entire sample. This method complies with provincial regulatory requirements where applicable.Multiple phases within a sample are analyzed and reported separately.
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
REVIEWED BY
Page 1 of 7
ANALYST
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
2 Phases:None Detected Cellulose < 0.5%
Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
2 Phases:None Detected Hair < 0.5%
Non-Fibrous Material > 75%
Chrysotile 10-25% Perlite 25-50%Other Non-Fibrous 25-50%
3 Phases:None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
Chrysotile 10-25% Perlite 25-50%Other Non-Fibrous 25-50%
b) Homogeneous, white, hard, cementitious, plaster base coat.c) Homogeneous, off-white, finishing or texture coat.
0001CPlaster - 2nd Floor Corridor
b) Non-homogeneous, beige and green, hard, cementitious material.
0001APlaster - Stair A
a) Homogeneous, grey, hard, cementitious, plaster.
b) Homogeneous, white, finishing or texture coat.
0001BPlaster - Ground Floor Corridor
a) Homogeneous, grey, hard, cementitious, plaster base coat.
ASBESTOS OTHER
Mike Horobin
b117818March 30, 2015
a) Homogeneous, grey, hard, cementitious, plaster base coat.
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)
REVIEWED BY
Page 2 of 7
ANALYST
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
ASBESTOS OTHER
Mike Horobin
b117818March 30, 2015
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)
2 Phases:None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
2 Phases:None Detected Cellulose < 0.5%
Hair < 0.5%Non-Fibrous Material > 75%
Chrysotile 0.5-5% Non-Fibrous Material > 75%
3 Phases:None Detected Cellulose < 0.5%
Hair < 0.5%Non-Fibrous Material > 75%
Chrysotile 0.5-5% Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
a) Homogeneous, grey, hard, cementitious, plaster base coat.
b) Homogeneous, white, hard, cementitious, plaster top coat.
0001EPlaster - Ground Floor Corridor
a) Homogeneous, grey, hard, cementitious, plaster base coat.
b) Homogeneous, white, hard, cementitious, plaster top coat.c) Homogeneous, white, hard, cementitious, plaster top coat.
0001FPlaster - Ground Floor Corridor
a) Homogeneous, grey, hard, cementitious, plaster base coat.b) Homogeneous, white, hard, cementitious, plaster top coat.
0001DPlaster - 2nd Floor Corridor
REVIEWED BY
Page 3 of 7
ANALYST
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
ASBESTOS OTHER
Mike Horobin
b117818March 30, 2015
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)
2 Phases:None Detected Cellulose < 0.5%
Hair < 0.5%Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
Chrysotile 0.5-5% Non-Fibrous Material > 75%
Comments:Not Analyzed
Comments:Not Analyzed
Comments:
0002B9" x 9" brown with white streaks VFT
Analysis was stopped due to a previous positive result.0002C9" x 9" brown with white streaks VFT
Analysis was stopped due to a previous positive result.
a) Homogeneous, grey, hard, cementitious, plaster base coat.
b) Homogeneous, white, hard, cementitious, plaster top coat.
0001GPlaster - 2nd Floor Corridor
Homogeneous, brown, consolidated, vinyl floor tile.
0002A9" x 9" brown with white streaks VFT
A mastic phase is present but was not analyzed.
REVIEWED BY
Page 4 of 7
ANALYST
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
ASBESTOS OTHER
Mike Horobin
b117818March 30, 2015
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)
2 Phases:None Detected Cellulose 50-75%
Synthetic Fibres 0.5-5%Hair 0.5-5%Tar and other non-fibrous
25-50%
None Detected Tar and other non-fibrous
> 75%
Comments:2 Phases:
None Detected Cellulose 50-75%Synthetic Fibres 0.5-5%Hair 0.5-5%Tar and other non-fibrous
25-50%
None Detected Tar and other non-fibrous
> 75%
Comments: Another phase is present but was not analyzed. Cotton fabric reinforcement is present on the surface of this sample.
a) Homogeneous, black, tar impregnated, compressed fibrous material.
b) Homogeneous, black, tar material.
0003AAircell pipe insulation and tar paper
Another phase is present but was not analyzed.
a) Homogeneous, black, tar impregnated, compressed fibrous material.
b) Homogeneous, black, tar material.
0003BAircell pipe insulation and tar paper
REVIEWED BY
Page 5 of 7
ANALYST
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
ASBESTOS OTHER
Mike Horobin
b117818March 30, 2015
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)
2 Phases:None Detected Cellulose 50-75%
Synthetic Fibres 0.5-5%Hair 0.5-5%Tar and other non-fibrous
25-50%
None Detected Tar and other non-fibrous
> 75%
2 Phases:Chrysotile 0.5-5% Non-Fibrous Material > 75%
Chrysotile 0.5-5% Non-Fibrous Material > 75%
Not Analyzed
Comments:Not Analyzed
Comments:
0004C12" x 12" beige with brown and white streaks VFT
Analysis was stopped due to a previous positive result.
a) Homogeneous, beige, consolidated, vinyl floor tile.
b) Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0004A12" x 12" beige with brown and white streaks VFT
0004B12" x 12" beige with brown and white streaks VFT
Analysis was stopped due to a previous positive result.
a) Homogeneous, black, tar impregnated, compressed fibrous material.
b) Homogeneous, black, tar material.
0003CAircell pipe insulation and tar paper
Comments: Another phase is present but was not analyzed. Cotton fabric reinforcement is present on the surface of this sample.
REVIEWED BY
Page 6 of 7
ANALYST
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
ASBESTOS OTHER
Mike Horobin
b117818March 30, 2015
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)
None Detected Non-Fibrous Material > 75%
Comments:None Detected Non-Fibrous Material > 75%
Comments:None Detected Non-Fibrous Material > 75%
Comments:2 Phases:
None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
2 Phases:None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
a) Homogeneous, grey, consolidated, vinyl flooring.
b) Homogeneous, brown, adhesive.
0006A12" x 12" grey with flecks VFT
a) Homogeneous, grey, consolidated, vinyl flooring.
b) Homogeneous, brown, adhesive.
0006B12" x 12" grey with flecks VFT
Homogeneous, grey, consolidated, vinyl flooring.
0005B12" x 12" red with white flecks VFT
Another phase is present but was not analyzed.Homogeneous, red, consolidated, vinyl flooring.
0005C12" x 12" red with white flecks VFT
Another phase is present but was not analyzed.
Homogeneous, red, consolidated, vinyl flooring.
0005A12" x 12" red with white flecks VFT (
Another phase is present but was not analyzed.
REVIEWED BY
Page 7 of 7
ANALYST
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
ASBESTOS OTHER
Mike Horobin
b117818March 30, 2015
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)
2 Phases:None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
a) Homogeneous, grey, consolidated, vinyl flooring.
b) Homogeneous, brown, adhesive.
0006C12" x 12" grey with flecks VFT
PINCHIN LTD. │ 2470 MILLTOWER CRT, MISSISSAUGA, ON L5N 7W5 │TEL: (905) 363-0678 FAX: (905) 363-0681
Project Name: Immaculate Heart of Mary Catholic Elementary School
Project No.:Mike Horobin Date Received: March 20, 2015
Lab Reference No.: b117819 Date Analyzed: March 30, 2015Analyst(s): S. Capsuyen # Samples submitted: 21
# Phases analyzed: 31
Regulatory Threshold Provincial Jurisdiction Regulatory Threshold
0.5% Manitoba 0.1% friable 1% non-friable
0.1% Saskatchewan 0.5% friable 1% non-friable
1% Newfoundland and Labrador, PEI and New Brunswick 1%
Prepared For:
Method of Analysis:EPA 600/R-93/116 - Method for the Determination of Asbestos in Bulk Building Materials dated July, 1993
103167
Bulk samples are checked visually and scanned under a stereomicroscope. Slides are prepared and observed under aPolarized Light Microscope (PLM) at magnifications of 40X, 100X or 400X as appropriate. Asbestos fibres are identified by acombination of morphology, colour, refractive index, extinction, sign of elongation, birefringence and dispersion stainingcolours. A visual estimate is made of the percentage of asbestos present. A reported concentration of less than (<) theregulatory threshold (see chart below) indicates the presence of confirmed asbestos in trace quantities, limited to only a fewfibres or fibre bundles in an entire sample. This method complies with provincial regulatory requirements where applicable.Multiple phases within a sample are analyzed and reported separately.
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
Provincial Jurisdiction
All bulk samples submitted to this laboratory for asbestos analysis are retained for a minimum of three months. Samples may be retrieved, upon request, for re-examination at any time during that period.
Pinchin Ltd. is accredited by the National Institute of Standards and Technology, National Voluntary Laboratory Accreditation Program (NVLAP Lab Code 101270-0) for the 'EPA-600/M4-82-020: Interim Method for the Determination of Asbestos in Bulk Insulation Samples' and meets all requirements of ISO/IEC 17025:2005.
This report relates only to the items tested.
NOTE: This test report may not be reproduced, except in full, without the written approval of the laboratory. The client may not use this report to claim product endorsement by NVLAP or any agency of the U.S. Government. This report is valid only when signed in blue ink by the analyst. Vinyl asbestos floor tiles contain very fine fibres of asbestos and may be missed by some laboratories using the PLM method. Internal verification studies performed by Pinchin indicate that the chance of missing asbestos in floor tiles is no higher than about 2%. The vinyl tile study and laboratory documentation on measurement uncertainty is available upon request. The analysis of dust samples by PLM cannot be used as an indicator of past or present airborne asbestos fibre levels.
Ontario, British Columbia, Nova Scotia
QuebecAlberta, NWT, Yukon,
Nunavut
REVIEWED BY
Page 1 of 6
ANALYST
Project Name:Elementary School, 101 Birchmount Road, Toronto, Ontario
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
2 Phases:None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
3 Phases:None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
None Detected Cellulose 0.5-5%Non-Fibrous Material > 75%
3 Phases:None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
None Detected Cellulose 0.5-5%Non-Fibrous Material > 75%
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)ASBESTOS OTHER
Mike Horobin
b117819March 30, 2015
a) Homogeneous, off-white, consolidated, vinyl floor tile.b) Homogeneous, yellow, soft, sticky material on the back of vinyl floor tile.
0007A12" x 12" beige with grey flecks VFT
a) Homogeneous, off-white, consolidated, vinyl floor tile.b) Homogeneous, yellow, soft, sticky material on the back of vinyl floor tile.c) Homogeneous, beige, levelling compound.
0007B12" x 12" beige with grey flecks VFT
a) Homogeneous, off-white, consolidated, vinyl floor tile.b) Homogeneous, yellow, soft, sticky material on the back of vinyl floor tile.c) Homogeneous, beige, levelling compound.
0007C12" x 12" beige with grey flecks VFT
REVIEWED BY
Page 2 of 6
ANALYST
Project Name:Elementary School, 101 Birchmount Road, Toronto, Ontario
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)ASBESTOS OTHER
Mike Horobin
b117819March 30, 2015
2 Phases:None Detected Non-Fibrous Material > 75%
Chrysotile 0.5-5% Tar and other non-fibrous
> 75%
2 Phases:None Detected Non-Fibrous Material > 75%
Not Analyzed
Comments:2 Phases:
None Detected Non-Fibrous Material > 75%
Not Analyzed
None Detected Tar and other non-fibrous
> 75%
Comments:
a) Homogeneous, off-white, consolidated, vinyl floor tile.b) Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0008A12" x 12" beige with grey and white flecks VFT
a) Homogeneous, off-white, consolidated, vinyl floor tile.b) Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0008B12" x 12" beige with grey and white flecks VFT
Analysis in phase b) was stopped due to a previous positive result.
a) Homogeneous, off-white, consolidated, vinyl floor tile.b) Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0008C12" x 12" beige with grey and white flecks VFT
Comments: Analysis in phase b) was stopped due to a previous positive result.Analysis in phase b) was stopped due to a previous positive result.Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0009A12" x 12" beige with white and black streaks VFT
A floor tile is present, but was not analyzed as requested.
REVIEWED BY
Page 3 of 6
ANALYST
Project Name:Elementary School, 101 Birchmount Road, Toronto, Ontario
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)ASBESTOS OTHER
Mike Horobin
b117819March 30, 2015
None Detected Tar and other non-fibrous
> 75%
Comments:None Detected Tar and other non-
fibrous> 75%
Comments:None Detected Tar and other non-
fibrous> 75%
Comments:2 Phases:
None Detected Tar and other non-fibrous
> 75%
None Detected Non-Fibrous Material > 75%
Comments:
Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0009B12" x 12" beige with white and black streaks VFT
A floor tile is present, but was not analyzed as requested.Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0010A12" x 12" beige with white smudges VFT
A floor tile is present, but was not analyzed as requested.Homogeneous, black, tar material.
0010B12" x 12" beige with white smudges VFT
A floor tile is present, but was not analyzed as requested.
a) Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
b) Homogeneous, yellow, soft, sticky material on the back of vinyl floor tile.
0011A12" x 12" off white VFT
A floor tile is present, but was not analyzed as requested.
REVIEWED BY
Page 4 of 6
ANALYST
Project Name:Elementary School, 101 Birchmount Road, Toronto, Ontario
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)ASBESTOS OTHER
Mike Horobin
b117819March 30, 2015
2 Phases:None Detected Tar and other non-
fibrous> 75%
None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
Comments:None Detected Tar and other non-
fibrous> 75%
Comments:None Detected Tar and other non-
fibrous> 75%
Comments:2 Phases:
None Detected Tar and other non-fibrous
> 75%
None Detected Non-Fibrous Material > 75%
Comments:
a) Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
b) Homogeneous, yellow, soft, sticky material on the back of vinyl floor tile.
0011B12" x 12" off white VFT
Comments: Phase a) is small in size. For more reliable results, a larger sample is required. A floor tile is present, but was not analyzed as requested.Homogeneous, yellow, soft, sticky material on the back of vinyl floor tile.
0011C12" x 12" off white VFT
A floor tile is present, but was not analyzed as requested.Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0012A12" x 12" blue smears VFT
A floor tile is present, but was not analyzed as requested.Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
0012B12" x 12" blue smears VFT
A floor tile is present, but was not analyzed as requested.
a) Homogeneous, black, soft, sticky material on the back of vinyl floor tile.
b) Homogeneous, off-white, levelling compound.
0012C12" x 12" blue smears VFT
A floor tile is present, but was not analyzed as requested.
REVIEWED BY
Page 5 of 6
ANALYST
Project Name:Elementary School, 101 Birchmount Road, Toronto, Ontario
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)ASBESTOS OTHER
Mike Horobin
b117819March 30, 2015
2 Phases:None Detected Non-Fibrous Material > 75%
Chrysotile 0.5-5% Non-Fibrous Material > 75%
3 Phases:None Detected Non-Fibrous Material > 75%
None Detected Non-Fibrous Material > 75%
Not Analyzed
Comments:Not Analyzed
Comments:2 Phases:
None Detected Non-Fibrous Material > 75%
Not Analyzed
Comments:
a) Homogeneous, white, soft, cementitious material.
b) Non-homogeneous, beige, green, and black, finishing or texture coat.
0013ATexture finish - corridors
a) Homogeneous, beige, hard, cementitious material.b) Homogeneous, beige, soft, cementitious material.
c) Non-homogeneous, beige, green, and black, finishing or texture coat.
0013BTexture finish - corridors
a) Homogeneous, white, soft, cementitious material.
b) Non-homogeneous, beige, green, and black, finishing or texture coat.
0013DTexture finish - corridors
Analysis in phase b) was stopped due to a previous positive result.
Analysis in phase c) was stopped due to a previous positive result.Non-homogeneous, beige, green, and black, finishing or texture coat.
0013CTexture finish - corridors
Analysis was stopped due to a previous positive result.
REVIEWED BY
Page 6 of 6
ANALYST
Project Name:Elementary School, 101 Birchmount Road, Toronto, Ontario
Project No.:Prepared For:
Lab Reference No.:Date Analyzed:
SAMPLE SAMPLEIDENTIFICATION DESCRIPTION
Pinchin Ltd. Asbestos LaboratoryCertificate of Analysis
Toronto Catholic School Board, 101 Birchmount Road, Toronto, Ontario
103167
BULK SAMPLE ANALYSIS
% COMPOSITION (VISUAL ESTIMATE)ASBESTOS OTHER
Mike Horobin
b117819March 30, 2015
None Detected Non-Fibrous Material > 75%
Not Analyzed
Comments: Analysis in phase b) was stopped due to a previous positive result.
a) Homogeneous, beige, hard, cementitious material.b) Non-homogeneous, beige, green, and black, finishing or texture coat.
0013ETexture finish - corridors
APPENDIX III Methodology
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Methodology Appendix III
1.0 GENERAL
Pinchin Ltd. conducts a room-by-room survey (rooms, corridors, service areas, exterior, etc.) to identify
the hazardous building materials as defined by the scope.
Information regarding the approximate quantity, location, and condition of asbestos building materials
encountered and visually estimated quantities are recorded. The locations of any samples collected are
recorded on small-scale plans.
As-built drawings and previous reports are referenced where provided.
1.1 Limitations on Scope
The assessment excludes the following:
• Owner or occupant articles (e.g. stored items, furniture, appliances, etc.);
• Underground materials or equipment (e.g. vessels, drums, underground storage tanks,
pipes, etc.);
• Building envelope, structural components, inaccessible or concealed materials or other
items where sampling may cause consequential damage to the property;
• Energized systems (e.g. internal boiler components, elevators, mechanical or electrical
components);
• Controlled products (e.g. stored chemicals, operational or process-related substances);
and
• Materials not typically associated with construction (e.g. settled dust, spills, residual
contamination from prior spills, etc.).
The assessment is limited to non-intrusive testing. Concealed spaces such as those above solid ceilings
and within shafts and pipe-chases are accessed via existing access panels only. Pinchin Ltd. does not
conduct demolition of walls, solid ceilings, structural items, interior finishes or exterior building finishes, to
determine the presence of concealed materials.
1.2 Asbestos
Pinchin Ltd. conducts an inspection for the presence of friable and non-friable asbestos-containing
materials (ACM). A friable material is a material that when dry can be crumbled, pulverized or powdered
by hand pressure.
© 2015 Pinchin Ltd. Page 1 of 3
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Methodology Appendix III
A separate set of samples is collected of each type of homogenous material suspected to contain
asbestos. A homogenous material is defined by the US EPA1 as material that is uniform in texture and
appearance, was installed at one time, and is unlikely to consist of more than one type or formulation of
material. The homogeneous materials are determined by visual examination, available information on the
phases of the construction and prior renovations.
Pinchin collects samples at a rate that is in compliance with Table 1 of O.Reg. 278/05.
The sampling strategy is also based on known ban dates and phase out dates of the use of asbestos;
sampling of certain building materials is not conducted after specific construction dates. In addition, to be
conservative, several years past these dates are added to account for some uncertainty in the exact
start/finish date of construction and associated usage of ACM.
In some cases, manufactured products such as asbestos cement pipe are visually identified without
sample confirmation.
Drywall joint compound is sampled at exterior walls, columns or other locations that are unlikely to have
been renovated in an attempt to determine the presence of asbestos in the original drywall compound.
Delineation of asbestos-containing drywall compound from newer, non-asbestos drywall compound is not
conducted.
Flooring mastic or adhesive is sampled and analyzed if present on the underside of flooring samples
(vinyl floor tile and vinyl sheet flooring).
Pinchin Ltd. submits the bulk samples to a NVLAP2 accredited laboratory for analysis. The analysis is
performed in accordance with Test Method EPA/600/R-93/116: Method for the Determination of Asbestos
in Bulk Building Materials, July 1993.
The asbestos analysis is completed using a stop positive approach. Only one result of greater than the
regulated criteria (0.5%) is required to determine that a material is asbestos-containing, but all samples
must be analysed to conclusively determine that a material is non-asbestos. The laboratory stops
analysing samples from a homogeneous material once a result greater than the regulated criteria is
detected in any of the samples of that material. All samples of a homogeneous material are analysed if no
asbestos is detected. In some cases, all samples are analysed in the sample set regardless of result.
Where building materials are described in the report as non-asbestos, or described as containing no
asbestos, this is subject to the limitations of the analytical method used, and should be understood to
mean no asbestos was detected.
1 Environmental Protection Agency 2 National Voluntary Laboratory Accreditation Program
© 2015 Pinchin Ltd. Page 2 of 3
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Methodology Appendix III
Asbestos materials are evaluated in order to make recommendations regarding remedial work. The
priority for remedial action is based on several factors:
• Friability (friable or non-friable);
• Condition (good, fair, poor, debris);
• Accessibility (ranking from accessible to all building users to inaccessible);
• Visibility (whether the material is obscured by other building components); and
• Efficiency of the work (for example, if damaged ACM is being removed in an area, it may
be most practical to remove all ACM in the area even if it is in good condition).
© 2015 Pinchin Ltd. Page 3 of 3
APPENDIX IV Photographs
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Non-asbestos tar over asbestos-containing Aircell pipe insulation in the Basement Crawlspace (previously sampled by Jacques Whitford).
Non-asbestos 24” x 48” pockmark and medium pinhole acoustic ceiling tiles in Room 216.
© 2015 Pinchin Ltd. Page 1 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Damaged asbestos-containing plaster on the wall of the Second Floor Corridor.
Damaged plaster behind the radiator in Room 204.
© 2015 Pinchin Ltd. Page 2 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Damaged plaster in Room 204.
Asbestos-containing 9” x 9” brown with white streaks vinyl floor tiles (samples 2A-C).
© 2015 Pinchin Ltd. Page 3 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Asbestos-containing 9” x 9” green with white streaks vinyl floor tiles (previously samples by Jacques Whitford).
Non-asbestos 12” x 12” beige with grey streaks vinyl floor tiles (previously samples by Jacques Whitford).
© 2015 Pinchin Ltd. Page 4 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Asbestos-containing 12” x 12” beige with brown and white streaks vinyl floor tiles (samples 0004A-C).
Non-asbestos 12” x 12” red with white flecks vinyl floor tiles (samples 0005A-C).
© 2015 Pinchin Ltd. Page 5 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Non-asbestos 12” x 12” grey with flecks vinyl floor tiles (samples 0006A-C).
Non-asbestos 12” x 12” beige with grey flecks vinyl floor tiles (samples 0007A-C).
© 2015 Pinchin Ltd. Page 6 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Non-asbestos 12” x 12” beige with grey and white flecks vinyl floor tiles (samples 0008A-C).
Non-asbestos 12” x 12” pink vinyl floor tiles (previously samples by Jacques Whitford).
© 2015 Pinchin Ltd. Page 7 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Non-asbestos 12” x 12” orange with multi-colour vinyl floor tiles (previously samples by Jacques Whitford).
Non-asbestos 12” x 12” blue smear vinyl floor tiles (samples 0012A-C).
© 2015 Pinchin Ltd. Page 8 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Non-asbestos 12” x 12” off-white vinyl floor tiles (samples 0011A-C).
Non-asbestos 12” x 12” beige with white smears vinyl floor tiles (0010A-B).
© 2015 Pinchin Ltd. Page 9 of 10
Asbestos Assessment April 2, 2015 Toronto Catholic School Board Pinchin File: 103167 Photographs Appendix III
Non-asbestos 12” x 12” beige with white and black streaks vinyl floor tiles (0009A-B).
© 2015 Pinchin Ltd. Page 10 of 10