asaaw1-1
-
Upload
hadrien-faryala -
Category
Documents
-
view
25 -
download
0
description
Transcript of asaaw1-1
7/21/2019 asaaw1-1
http://slidepdf.com/reader/full/asaaw1-1 1/6
STANDARD
DOCUMENTCLASSIFICATION
CONFIDENTIAL
REFERENCE RE
TITLE: INFRA-RED SCANNING OF HIGH- SCSASAAW1 1VOLTAGE CURRENT – CARRYINGEQUIPMENT
DATE SEPTEMBER2002
PAGE 1 OF 6REVISION DATE:
SEPTEMBER 2005
COMPILED BY FUNCTIONAL RESP. APPROVED BY AUTHORIZED BY
..............................
O E Mutloane
...................................
Peter Busch
Senior Advisor
..............................
CD Smith
for TESCOD
............................
M N Bailey
DTM for MD (DD)
MGM/mm/AS-2/Aug’02
Contents
Page
1 Scope ........................................................................................................................................ 2
1.1 Purpose………………………………………………………………………………………….2
1.2 Applicability……………………………………………………………………………………... 2
2 Normative references................................................................................................................ 2
3 Definitions.................................................................................................................................. 2
4 Requirements ............................................................................................................................ 3
4.1 Responsibilities ...................................................................................................................... 3
4.2 Substations ............................................................................................................................ 3
4.3 Overhead lines ....................................................................................................................... 34.4 Evaluation............................................................................................................................... 3
4.5 Defect (hot spot) reporting...................................................................................................... 3
4.6 Follow-up................................................................................................................................ 4
4.7 Documentation ....................................................................................................................... 4
Annexes
A Infra-red scanning report .......................................................................................................... 5
B Revision information ................................................................................................................. 6
7/21/2019 asaaw1-1
http://slidepdf.com/reader/full/asaaw1-1 2/6
DOCUMENT CLASSIFICATIONCONFIDENTIAL
INFRA-RED SCANNING OF HIGH- REFERENCE REV
VOLTAGE CURRENT-CARRYING SCSASAAW1 1EQUIPMENT PAGE 2 OF 6
1 Scope
1.1 Purpose
The purpose of this standard is to set a minimum infra-red scanning frequency and documentationrequirement.
1.2 Applicability
The standard is applicable to all staff responsible for infra-red scanning of substations and lines.
2 Normative references
The following document contains provisions that, through reference in the text, constitute requirementsof this standard. At the time of publication the revision indicated was valid. All standards are subject toreview and party for agreements based on this standard are encouraged to investigate the possibility of applying the most recent revision of the document listed below. Information on currently valid nationaland international standards can be obtained from the Information Centre at Megawatt Park and onEskom documents from the Eskom Documentation Centre at Megawatt Park.
ESKARAAG4: Rev.6, Operating regulations for high-voltage systems.
3 Definitions and abbreviations
All definitions and abbreviations in ESKARAAG4 are applicable to this standard.
4 Requirements
4.1 Responsibilities
The Designated Person or his delegate shall ensure that this standard is implemented and adhered to.
4.2 Substations
Infra-red scanning of high-voltage (HV) current carrying equipment at substations shall be carried outregularly as a means of detecting hot spots, cooling and flow problems on transformers, transformer conservator oil level and also transfomer temperature problems before they lead to equipment failure.
Infra-red scanning shall be carried out, when possible, when the equipment is at or above its normalload.
The minimum scanning frequency shall be:
In major substations >40 MVA every 6 months.
In other substations every 12 months.
Panels loaded to near capacity or above may require scanning more frequently. This particularlyapplies to those panels loaded abnormally due to emergencies, equipment outages, etc. which, if loston fault, could prove to be critical.
7/21/2019 asaaw1-1
http://slidepdf.com/reader/full/asaaw1-1 3/6
DOCUMENT CLASSIFICATIONCONFIDENTIAL
INFRA-RED SCANNING OF HIGH- REFERENCE REV
VOLTAGE CURRENT-CARRYING SCSASAAW1 1EQUIPMENT PAGE 3 OF 6
In situations where plant is loaded well below its rating RCM/Criticality analysis shall determine the
frequency.
4.3 Overhead lines
Infra-red scanning may be carried out as required by circumstances and local requirements.
4.4 Newly commisioned Substations/Lines
Newly commissioned substations and lines shall be scanned within a week of commissioning to ensurethat quality work has been done.
4.5 Evaluation
The operator shall evaluate the information available and make a judgement as to the degree of urgency for dealing with any hot spot found.
(This shall be done in co-operation with the person responsible for the equipment).
As a rule of thumb:
Temperature Degree of urgency
0 °C to 10 °C above temperature associated/equivalent item Deal with when equipment is nextavailable.
10 °C to 30 °C above associated/equivalent item Urgent.(for connectors, contacts etc.)
Over 30 °C above associated/equivalent item Extremely urgent.(for connectors, contacts etc.)
Over 20 °C above associated/equivalent item Extremely urgent.(CTs, circuit-breaker heads etc.)
4.6 Defect (hot spot) reporting
All extremely urgent hot spots shall be reported immediately to the person(s) directly responsible for the equipment.
A written report shall be submitted within 24 h after scanning even if this report says “Nothing Found”.
Each “hot spot” shall be clearly identified with its “degree of urgency” indicated (see annex A).
4.7 Follow-up
To ensure the defect(s) has been effectively repaired the equipment shall be re-scanned once it isreturned on-load.
4.8 Documentation
All documentation shall be history recorded in a logical and easily retrievable manner and shall cover atleast:
7/21/2019 asaaw1-1
http://slidepdf.com/reader/full/asaaw1-1 4/6
DOCUMENT CLASSIFICATIONCONFIDENTIAL
INFRA-RED SCANNING OF HIGH- REFERENCE REV
VOLTAGE CURRENT-CARRYING SCSASAAW1 1EQUIPMENT PAGE 4 OF 6
a) Programme;
b) Scheduling/actioning;
c) Reports/follow-ups; and
d) Closing off.
7/21/2019 asaaw1-1
http://slidepdf.com/reader/full/asaaw1-1 5/6
DOCUMENT CLASSIFICATIONCONFIDENTIAL
INFRA-RED SCANNING OF HIGH- REFERENCE REV
VOLTAGE CURRENT-CARRYING SCSASAAW1 1EQUIPMENT PAGE 5 OF 6
Annex A(informative)
Infra-red scanning report
INFRA-RED SCANNING REPORT Ref No.
FSC: __________________ TSC: __________________
Scanning date: __________________ Panel: __________________
Substation: __________________ Load of panel: __________________
Sketch Degree of urgency
A — WHEN NEXT AVAILABLE
B — URGENT
*C — EXTREMELY URGENT
*D — District immediately Yes No
ACTION TAKEN BY SUPERVISOR AND DETAIL OF REPAIR
__________________________ Name in block letters
_______________________ Signature
__________________________ Date
CERTIFIED CORRECT AFTER RETEST
___________________ Name in block letters
_______________ Signature
___________________ Date
NOTE — Duplicate book used
Annex B(informative)
7/21/2019 asaaw1-1
http://slidepdf.com/reader/full/asaaw1-1 6/6
DOCUMENT CLASSIFICATIONCONFIDENTIAL
INFRA-RED SCANNING OF HIGH- REFERENCE REV
VOLTAGE CURRENT-CARRYING SCSASAAW1 1EQUIPMENT PAGE 6 OF 6
Revision information
DATE REV. NO. NOTES
Dec.1997 0 Original issue – SCSASAAW1
Aug 2002 1 Original document re-drafted in accordance with the EskomDocumentation System.
4.2. Text refomated and Infra red scanning on Transfomer added
4.2 Text added
4.4 Text added