Artificial Variables, 2-Phase and Big M Methods For the example, go to p. 16. 1.
-
Upload
jeremiah-mantel -
Category
Documents
-
view
215 -
download
0
Transcript of Artificial Variables, 2-Phase and Big M Methods For the example, go to p. 16. 1.
Artificial Variables, 2-Phase and Big M Methods
For the example, go to p. 16.
1
Artificial Variables, 2-Phase and Big M Methods
Facts:1. To start, we need a canonical form2. If we have a constraint with a nonnegative right-
hand side, it will contain an obvious basic variable (which?) after introducing a slack var.
3. If we have an equality constraint, it contains no obvious basic variable
4. If we have a constraint with a nonnegative right-hand side, it contains no obvious basic variable even after introducing a surplus var.
© 2008 MGS2
Compare!
• 2x + 3y 5 2x + 3y + s = 5, s 0 (s basic)
• 2x + 3y = 5 ??????? Infeasible if x=y=0!
• 2x + 3y 5 2x + 3y - s = 5, s 0 (??????) Infeasible if x=y=0! ??????????????????
© 2008 MGS3
One Equality???
• 2x + 3y = 5 2x + 3y + a = 5, a = 0 (E) (a is basic, but it should be 0!)
• How do we force a = 0? This is of course not feasible if x=y=0, as 0+0+0 5!
© 2008 MGS4
One Equality???
• 2x + 3y = 5 2x + 3y + a = 5, a = 0 (E) (a basic, but it should be 0!)
• How do we force a = 0? This is of course not feasible if x=y=0, as 0+0+0 5
• Idea: ! solve a first problem with
Min {a | constraint (E) + (a 0) + other constraints }!
© 2008 MGS5
Artificial Variables
Notice: In an equality constraint, the extra variable is called an artificial variable.
For instance, in 2x + 3y + a = 5, a = 0 (E)
a is an artificial variable.
© 2008 MGS6
One Inequality ???
• 2x + 3y 5 2x + 3y - s = 5, s 0 (I) s could be the basic variable, but it should be 0 and for x=y=0, it is -5 ! • How do we force s 0?
?© 2008 MGS
7
One Inequality ???
• 2x + 3y 5 2x + 3y - s = 5, s 0 (I) s could be the basic variable, but it should be 0 and it is -5 for x=y=0! • How do we force s 0? • By making it 0!
how?© 2008 MGS
8
One Inequality ???
• 2x + 3y 5 2x + 3y - s = 5, s 0 (E) s could be basic, but it should be 0 and it is -5 for x=y=0! • How do we force s 0? • By making it 0! But we have to start with a canonical form… so
treat is as an equality constraint!
2x + 3y - s + a = 5, s 0, a 0 and Min a
© 2008 MGS9
Artificial Variables
Notice: In a inequality constraint, the extra variable a is called an artificial variable.
For instance, in 2x + 3y – s + a = 5, s 0, a 0 (E)
a is an artificial variable.
In a sense, we allow temporarily a small amount of cheating, but in the end we cannot allow it!
© 2008 MGS10
What if we have many such = and constraints?
7x - 3y – s1 + a1 = 6, s1,a1 0 (I) 2x + 3y + a2 = 5, a2 0 (II)a1 and a2 are artificial variables, s1 is a surplus
variable.One minimizes their sum:Min {a1+a2 | a1, a2 0, (I), (II), other constraints}i.e., one minimizes the total amount of cheating!
© 2008 MGS11
Then What?
We have two objectives:• Get a “feasible” canonical form• Maximize our original problem
Two methods:2-phase method (phase 1, then phase 2)big M method
© 2008 MGS12
2-Phase Method
• Phase I: find a BFSMinimize the sum of the artificial variables
If min = 0, we have found a BFSIf min > 0, then we cannot find a solution
with no “cheating”… the original problem is infeasible
• Phase 2: solve original LPStart from the phase 1 BFS, and maximize the original objective function.
© 2008 MGS13
Big-M Method
• Combine both objectives :(1) Min i ai
(2) Max j cj xj
into a single one:(3) Max – M i ai + j cj xj
where M is a large number, larger than anything subtracted from it.
If one minimizes j cj xj
then the combined objective function is Min M i ai + j cj xj
© 2008 MGS14
The Big M Method
The simplex method algorithm requires a starting bfs.
Previous problems have found starting bfs by using the slack variables as our basic variables.
If an LP have ≥ or = constraints, however, a starting bfs may not be readily apparent.
In such a case, the Big M method may be used to solve the problem. Consider the following problem.
© 2003 Brooks/Cole15
Example
• Bevco manufactures an orange-flavored soft drink called Oranj by
combining orange soda and orange juice. Each orange soda contains
0.5 oz of sugar and 1 mg of vitamin C. Each ounce of orange juice
contains 0.25 oz of sugar and 3 mg of vitamin C. It costs Bevco 2¢ to
produce an ounce of orange soda and 3¢ to produce an ounce of
orange juice. Bevco’s marketing department has decided that each
10-oz bottle of Oranj must contain at least 30 mg of vitamin C and at
most 4 oz of sugar. Use linear programming to determine how Bevco
can meet the marketing department’s requirements at minimum cost.© 2003 Brooks/Cole16
The Big M Method
Let x1 = number of ounces of orange soda in a bottle of Oranj
x2 = number of ounces of orange juice in a bottle of Oranj
x2
x1
17
The Big M Method
Letting x1 = number of ounces of orange soda in a bottle of Oranj
x2 = number of ounces of orange juice in a bottle of Oranj
The LP is:
min z = 2x1 + 3x2
st 0.5x1 + 0.25x2 ≤ 4 (sugar constraint)
x1 + 3x2 ≥ 20 (Vitamin C constraint)
x1 + x2 = 10 (10 oz in 1 bottle)
x1, x2 0
The LP in standard form is shown on the next slide.
© 2003 Brooks/Cole18
The Big M Method
Row 1:-z + 2x1 + 3x2 = 0
Row 2: 0.5x1 + 0.25x2 + s1 = 4
Row 3: x1 + 3x2 - s2 = 20
Row 4: x1 + x2 = 10
The LP in standard form has z and s1 which could be used for BVs but row 2 would violate sign restrictions and row 3 no readily apparent basic variable.
In order to use the simplex method, a bfs is needed. To remedy the predicament, artificial variables are created. The variables will be labeled according to the row in which they are used as seen below. The basic variables are in red:
Row 1:-z + 2x1 + 3x2 = 0
Row 2: 0.5x1 + 0.25x2 + s1 = 4
Row 3: x1 + 3x2 - s2 + a2 = 20
Row 4: x1 + x2 + a3 = 10
© 2003 Brooks/Cole19
The Big M Method
If all artificial variables in the optimal solution equal zero, the solution is optimal. If some artificial variables are positive in the optimal solution, the problem is infeasible.
The Bevco example continued:
Initial Tableau
Row z x1 x2 s1 e2 a2 a3 rhs0 -1.00 2.00 3.00 M M 0.001 0.50 0.25 1.00 4.002 1.00 3.00 -1.00 1.00 20.003 1.00 1.00 1.00 10.00
© 2003 Brooks/Cole20
4.10 – The Big M MethodPivot 1 z x1 x2 s1 e2 a2 a3 rhs ratio ero
0 1.00 2M- 2 4M -3 -M 30M Row 0 + M(Row 2) + M(Row 3)
1 0.50 0.25 1.00 4.00 162 1.00 3 -1.00 1.00 20.00 6.673 1.00 1.00 1.00 10.00 10
ero 1 z x1 x2 s1 e2 a2 a3 rhs ero0 1.00 2M- 2 4M -3 -M 30M 1 0.50 0.25 1.00 4.002 0.33 1 -0.33 0.33 6.67 Row 2 divided by 33 1.00 1.00 1.00 10.00
ero 2 z x1 x2 s1 e2 a2 a3 rhs ero0 1.00 (2M-3)/3 (M-3)/3 (3-4M)/3 (60+10M)/3 Row 0 - (4M-3)*(Row 2)1 0.50 0.25 1.00 4.002 0.33 1 -0.33 0.33 6.673 1.00 1.00 1.00 10.00
ero 3 z x1 x2 s1 e2 a2 a3 rhs ero0 1.00 (2M-3)/3 (M-3)/3 (3-4M)/3 (60+10M)/3 1 0.42 1.00 0.08 -0.08 2.33 Row 1 - 0.25*(Row 2)2 0.33 1 -0.33 0.33 6.673 1.00 1.00 1.00 10.00
ero 4 z x1 x2 s1 e2 a2 a3 rhs ero0 1.00 (2M-3)/3 (M-3)/3 (3-4M)/3 (60+10M)/31 0.42 1.00 0.08 -0.08 2.332 0.33 1 -0.33 0.33 6.673 0.67 0.33 -0.33 1.00 3.33 Row 3 - Row 2
The Big M MethodPivot 2 z x1 x2 s1 e2 a2 a3 rhs ratio
0 1.00 (2M-3)/3 (M-3)/3 (3-4M)/3 (60+10M)/31 0.42 1.00 0.08 -0.08 2.33 5.602 0.33 1 -0.33 0.33 6.67 20.003 0.67 0.33 -0.33 1.00 3.33 5.00
ero 1 z x1 x2 s1 e2 a2 a3 rhs ero0 1.00 (2M-3)/3 (M-3)/3 (3-4M)/3 (60+10M)/31 0.42 1.00 0.08 -0.08 2.332 0.33 1 -0.33 0.33 6.673 1.00 0.50 -0.50 1.50 5.00 (Row 3)*(3/2)
ero 2 z x1 x2 s1 e2 a2 a3 rhs ero0 1.00 -0.50 (1-2M)/2 (3-2M)/2 25.00 Row 0 + (3-2M)*(Row 3)/31 0.42 1.00 0.08 -0.08 2.332 0.33 1.00 -0.33 0.33 6.673 1.00 0.50 -0.50 1.50 5.00
ero 3 z x1 x2 s1 e2 a2 a3 rhs ero0 1.00 -0.50 (1-2M)/2 (3-2M)/2 25.001 1.00 -0.13 0.13 -0.63 0.25 Row 1 - (5/12)*Row 3)2 0.33 1.00 -0.33 0.33 6.673 1.00 0.50 -0.50 1.50 5.00
ero 4 z x1 x2 s1 e2 a2 a3 rhs ero0 1.00 -0.50 (1-2M)/2 (3-2M)/2 25.001 1.00 -0.13 0.13 -0.63 0.252 1.00 -0.50 0.50 -0.50 5.00 Row 2 -(1/3)*Row 33 1.00 0.50 -0.50 1.50 5.00
Optimal Solution