Arterial Traffic Models
Ken CourageTTE 6815
![Page 2: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/2.jpg)
Models vs TMSPs
Model: An abstract representation of a real world object or phenomenon
A Traffic Model Software Product (TMSP) employs one or more models (usually many models) to produce useful information
TMSPs are often called models (incorrectly)
![Page 3: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/3.jpg)
Models vs TMSPs
Models and TMSPs both have the same flow chart representation
Inputs OutputsRules of Operation
![Page 4: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/4.jpg)
Software Products to be Discussed
TRANSYT-7F PASSER II CORSIM (NETSIM)
![Page 5: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/5.jpg)
Software Products to be Discussed
TRANSYT-7F Link-node based, Mezoscopic (Flow rates) Time-scan, 60 steps per cycle Queue accumulation by input/output Platoon propagation by exponential
smoothing Optimization (DI or Pros) by “hill climbing”
![Page 6: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/6.jpg)
T7F Flow Profiles (Link-specific)
Step in Cycle1 60
Flow Rate
![Page 7: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/7.jpg)
T7F Link Operations
Platoon
Propagation
Arrival Departure
Upstream Node
Downstream Node
![Page 8: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/8.jpg)
Flow Profile Interpretation 4000+ : : SSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS 3000+ SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSSS 2000+ SSSSSSOOOSSS : SSSSSOOOOOSS : SSSSOOOOOOOS : SSOOOOOOOOOOO : SOOOOOOOOOOOOOI : OOOOOOOOOOOOOOIII 1000+ OOOOOOOOOOOOOOIIII : IOOOOOOOOOOOOOOIIIIII : IIOOOOOOOOOOOOOOIIIIIIIIII : IIOOOOOOOOOOOOOOIIIIIIIIIIIIIIII IIIIII :I IIIOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIIIIIIIIIIIOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII ************* **************************** 123456789012345678901234567890123456789012345678901234567890
Arrivals
Departures
![Page 9: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/9.jpg)
Flow Profile Interpretation 4000+ : : SSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS 3000+ SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSS : SSSSSSSSSSSS 2000+ SSSSSSOOOSSS : SSSSSOOOOOSS : SSSSOOOOOOOS : SSOOOOOOOOOOO : SOOOOOOOOOOOOOI : OOOOOOOOOOOOOOIII 1000+ OOOOOOOOOOOOOOIIII : IOOOOOOOOOOOOOOIIIIII : IIOOOOOOOOOOOOOOIIIIIIIIII : IIOOOOOOOOOOOOOOIIIIIIIIIIIIIIII IIIIII :I IIIOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIIIIIIIIIIIOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII ************* **************************** 123456789012345678901234567890123456789012345678901234567890
Arrival on red (I)
Departure of previousred arrivals (S)
Arrival on green afterthe queue has cleared (O not under S)
Arrival on green before the queue has cleared (O under S)
![Page 10: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/10.jpg)
External link (nearly saturated) : SSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSS 3000+ SSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS 2000+ SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS :IIIIIIIIIIOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII 1000+IIIIIIIIIIOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIIIIIOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIIIIIOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIIIIIOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIIIIIOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIIIIIOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIII
![Page 11: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/11.jpg)
External link (undersaturated) : SSSSSSSSS : SSSSSSSSS : SSSSSSSSS : SSSSSSSSS 3000+ SSSSSSSSS : SSSSSSSSS : SSSSSSSSS : SSSSSSSSS : SSSSSSSSS : SSSSSSSSS 2000+ SSSSSSSSS : SSSSSSSSSS : SSSSSSSSSS : SSSSSSSSSS : SSSSSSSSSS : SSSSSSSSSSS 1000+ SSSSSSSSSSS :IIIIIIOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIIIIIOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIII
![Page 12: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/12.jpg)
Platoon arrives on green after queue has cleared : SSSSSSSS : SSSSSSSS 3000+ SSSSSSSS OO : SSSSSSSS OOOOO : SSSSSSSS OOOOOOOOOI : SSSSSSSS OOOOOOOOOOII : SSSSSSSS OOOOOOOOOOOIII : SSSSSSSS OOOOOOOOOOOOIIII 2000+ SSSSSSSS OOOOOOOOOOOOIIIII : SSSSSSSS OOOOOOOOOOOOOIIIIII : SSSSSSSS OOOOOOOOOOOOOIIIIIII : SSSSSSSS OOOOOOOOOOOOOOIIIIIIII : SSSSSSSS OOOOOOOOOOOOOOIIIIIIIII : SSSSSSSSS OOOOOOOOOOOOOOOIIIIIIIIII 1000+ SSSSSSSSS OOOOOOOOOOOOOOOIIIIIIIIIII : SSSSSSSSS OOOOOOOOOOOOOOOOIIIIIIIIII :I SSSSSSSSS OOOOOOOOOOOOOOOOOIIIIIIIIIIII II :IIOSSSSSSSS OOOOOOOOOOOOOOOOOIIIIIIIIIIIIIII III :IIOOOSSSSSS OOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIII :IIOOOOOOOOS OOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIII
Not stopped
Departure of red arrivals
Arrived on red
Arrived on green but stopped by queue
![Page 13: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/13.jpg)
Platoon arrives at beginning of red : SSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS 3000+ SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS : SSSSSSSSSSSSSSSSSS : II SSSSSSSSSSSSSSSSSS : IIIIII SSSSSSSSSSSSSSSSSSS : IIIIIIIII SSSSSSSSSSSSSSSSSSS 2000+ IIIIIIIIIIII SSSSSSSSSSSSSSSSSSS : IIIIIIIIIIIIIIIII SSSSSSSSSSSSSSSSSSS : IIIIIIIIIIIIIIIIIIII SSSSSSSSSSSSSSSSSSS : IIIIIIIIIIIIIIIIIIIIII SSSSSSSSSSSSSSSSSSS : IIIIIIIIIIIIIIIIIIIIIIII SSSSSSSSSSSSSSSSSSS : IIIIIIIIIIIIIIIIIIIIIIIIIII SSSSSSSSSSSSSSSSSSS 1000+ IIIIIIIIIIIIIIIIIIIIIIIIIIIIIOSSSSSSSSSSSSSSSSSS : IIIIIIIIIIIIIIIIIIIIIIIIIIIIIOOOOSSSSSSSSSSSSSSS : IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIOOOOOOOOSSSOOOOOSSS : IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIOOOOOOOOOOOOOOOOOOO :OOO IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIOOOOOOOOOOOOOOOOOOOOO :OOOOOIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIOOOOOOOOOOOOOOOOOOOOO ******************************
Arrived on red
Arrived on green after queue was serviced
Arrived on greenBut stopped by queue
Queue Departure
![Page 14: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/14.jpg)
TRANSYT–F Optimization
EvaluationProcedures
Optimization Search
![Page 15: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/15.jpg)
TRANSYT–F Optimization
EvaluationProcedures
Optimization Search
![Page 16: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/16.jpg)
Disutility Index
Stops Delay Fuel Consumption Operating Cost
![Page 17: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/17.jpg)
PROs Optimization A progression opportunity (PRO) is the
ability to “see ahead” one signal in the time space diagram
The number of PROs is defined at every intersection on each step of the cycle
The PROs index is the accumulated PROs / the number that would be available if all signals were always green
![Page 18: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/18.jpg)
Bandwidth Efficiency
10 /60 = 0.167
(60 sec cycle)
10 sec
![Page 19: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/19.jpg)
PROs Example
3
21
2
11
(60 sec cycle)
![Page 20: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/20.jpg)
Maximum PROs = 60 (3+2+1) = 360
# sec with 3 Pros 2 Pros 1 ProAt 1 10 10 5At 2 20 5At 3 25Total 30 60 35PROS index= (30+60+35)/360 =0.347BW efficiency = 10/60 = 0.167
![Page 21: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/21.jpg)
Platoon Propagation
Downstream projectionBy S seconds
F(t + S)
Original flow profileF(t)
Exponential smoothing F’(t + S)
F’(t + S) = K*F’(t+S-1) + (1-K)*F(t+S)Smoothing factor, K, depends on speed and link length
![Page 22: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/22.jpg)
Platoon Propagation: Stop line : SSSSSSS : SSSSSSS : SSSSSSS : SSSSSSS 3000+ SSSSSSS : SSSSSSS : SSSSSSS : SSSSSSS : SSSSSSS : SSSSSSSS 2000+ SSSSSSSS : SSSSSSSS : SSSSSSSS : SSSSSSSS : SSSSSSSS :IIIOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIII 1000+IIIOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIII :IIOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIII :IIOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIIII :IIOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIII :IIOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIII :IIOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOIIIIIIIIIIIIII
![Page 23: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/23.jpg)
Platoon Propagation: 1000 ft3000+ : O : OO : OOO : OOOO : OOOOO 2250+ OOOOOO : OOOOOOO : OOOOOOOO : OOOOOOOOO : OOOOOOOOOO : OOOOOOOOOOOO 1500+ OOOOOOOOOOOOO : OOOOOOOOOOOOOOOO : OOOOOOOOOOOOOOOOOOOOO : OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO : OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO : OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO 750+ OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO : OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :O OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO
![Page 24: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/24.jpg)
Platoon Propagation: 2000 ft 3000+ : : : : : 2250+ : OOO : OOOOOO : OOOOOOO : OOOOOOOOOO : OOOOOOOOOOOO 1500+ OOOOOOOOOOOOOOO : OOOOOOOOOOOOOOOOOO : OOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOO 750+OOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO
![Page 25: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/25.jpg)
Platoon Propagation: 3000 ft2000+ : : O : OOOOOOO : OOOOOOOOO :O OOOOOOOOOOO 1500+OOO OOOOOOOOOOOO :OOOOO OOOOOOOOOOOO :OOOOOOOO OOOOOOOOOOOOO :OOOOOOOOOOOO OOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOO 1000+OOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOO 500+OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO OOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO :OOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOOO
![Page 26: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/26.jpg)
T7F Link Numbers for Node N
![Page 27: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/27.jpg)
TRANSYT Timing Plan------------------------------------------------ Intersection 1 Pretimed - Splits Optimized ------------------------------------------------
Interval Number : 1 2 3 4 5 6 7 8 9 10 11 12 Intvl Length(sec): 7.0 5.0 4.0 5.0 22.0 5.0 7.0 5.0 2.0 5.0 18.0 5.0 Intvl Length (%): 8 6 4 6 22 6 8 6 2 6 20 6
Pin Settings (%): 100/0 8 14 18 24 46 52 60 66 68 74 94
Phase Start (No.): 1 2 3 4 5 6
Interval Type : V Y V Y V Y V Y V Y V Y
Splits (sec): 12 9 27 12 7 23 Splits (%): 14 10 28 14 8 26 Links Moving : 110 110 111 102 110 109 106 105 105 104 103 101 108 106 -106 104 -102 112 110 107 103 -108 -104
Offset = 0.0 sec 0 %.
![Page 28: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/28.jpg)
Software Products to be Discussed
TRANSYT-7F PASSER II CORSIM (NETSIM)
![Page 29: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/29.jpg)
Software Products to be Discussed
PASSER II
•Bandwidth optimization•Phasing optimization•Speed Search (+/- 2 mph)
![Page 30: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/30.jpg)
PASSER II Movement Numbers
![Page 31: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/31.jpg)
PASSER Timing Plan*** INT. 1 .0 SEC OFFSET ART ST PHASE SEQ IS LT 5 LEADS (2+5) West .0 % OFFSET CROSS ST PHASE SEQ IS DUAL LEFTS (3+7)
ARTERIAL STREET CROSS STREET CONCURRENT PHASES 2+5 2+6 1+6 TOTAL 3+7 3+8 4+8 TOTAL PHASE TIME (SECS) 22.0 17.0 12.0 51.0 12.0 3.0 24.0 39.0
![Page 32: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/32.jpg)
Software Products to be Discussed
TRANSYT-7F PASSER II CORSIM (NETSIM)
![Page 33: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/33.jpg)
Software Products to be Discussed
CORSIM (NETSIM)
•Microscopic simulation•1 second time scan•Pretimed control•Explicit actuated control emulation•Hardware in the loop feature•Platoon dispersion by speed differential
![Page 34: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/34.jpg)
CORSIM Node Numbers (AAP)
![Page 35: Arterial Traffic Models](https://reader030.fdocuments.us/reader030/viewer/2022013112/56812f7b550346895d94fca5/html5/thumbnails/35.jpg)
Platoon Propagation Comparison
Upstream
Downstream
TRANSYT
CORSIM
PASSER II