Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut...
-
Upload
bryan-hill -
Category
Documents
-
view
220 -
download
2
Transcript of Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut...
![Page 1: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/1.jpg)
Arseny DolgovNick Driver
Galina Dvorkina Kevin EberhartMatt Edwards
Johnny JannettoEric Kohut
John Shelton
Interim Review #1ASEN 4028: Senior Projects II
2/7/06Professor Dale LawrenceProfessor James Maslanik
SOARSSelf Organizing Aerial Reconnaissance System
![Page 2: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/2.jpg)
Presentation Outline
• Resolution of Items from CDR/Final Report• Design Summary• Integration & Test Plan• Current Issues to Be Resolved• Budget Progress• Schedule Progress• Appendix
2
![Page 3: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/3.jpg)
Resolved Issues
3
![Page 4: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/4.jpg)
Design: Hardware & Software Interfaces
• Addressed software/hardware interfacing and definition concerns, Slave:
4
![Page 5: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/5.jpg)
5
Design: Hardware & Software Interfaces
• Addressed software/hardware interfacing and definition concerns, Master:
5
![Page 6: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/6.jpg)
Controls – Resolutions
• “Black Hole”/Sink behavior improvement
Before: After:
6
![Page 7: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/7.jpg)
Controls - Resolutions• Looping Concern
7
![Page 8: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/8.jpg)
Imaging - Resolutions• Vibration isolation
• Foam will be used to dampen vibrations• Image processing can still be used to make up the difference
• Camera choice• A trade study conducted during the Fall lead to our current imager choice
(see Appendix)
• Determination of the picture capture time• Two pictures instead of one
• Relative motion during imaging• Blur and skew are well
within tolerances as calculated last Fall
8
![Page 9: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/9.jpg)
Design Summary
9
![Page 10: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/10.jpg)
Design Summary• Finalized Master & Slave vehicles, component layout:
• Slave:• Miglet Ducted Fan – houses autopilot & camera• No major changes since CDR• Might need to shield camera interface, leave room in dome
• Master• No need to demonstrate deployment, so reduce payload requirements
• Payload < 5 oz for Comm. board• Piper Cub Electric ARF – manually piloted• Ease of transportation, simple to fly,
crashable• Inexpensive
10
![Page 11: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/11.jpg)
Current Issues
11
![Page 12: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/12.jpg)
Electronics Issues
• High-Risk Issues – Bandwidth & Noise• Need to ensure communications integrity
• Camera PIC: 115 kbps off board• Radios PIC: up to 250 kbps over PCB• PC Radio: up to 800 kbps over USB
• Resolution plans• Reduce data rate
• Radio interfaces have about 50% margin to meet requirements• Camera interface is critical – has the lowest margin
• PIC interface tests early on• Shielded wiring, minimizing cable length• Shielded connector?
• Fallback: PCB & cable enclosure – RF shield
12
![Page 13: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/13.jpg)
Electronics Issues• Critical untested signal path: camera to Autopilot
• Autopilot itself has been tested in realistic operating conditions
13
Potential interference problems
![Page 14: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/14.jpg)
Electronics - Current Issues• Preliminary interface tests performed
• PIC PC via Serial-to-USB cable• Reliable communications up to 800 kbps
• Zig-Bee Radio PC via Serial-to-USB cable• Reliable communications up to 250 kbps• No dropped packets in 100 kbyte test
14
Ground Station Master Vehicle Slave Vehicle
800 kbps 250 kbps
Camera Module
MCU
115 kbps
Radio 1
250 kbps
MCU
Radio 2Radio 3
250 kbps800 kbps
Graphical User Interface
MCU
250 kbps
Radio 4
800 kbps
Partially Tested Components
![Page 15: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/15.jpg)
Controls - Current Issues
• Current Tasks• Field Switching• Slave Modeling• GPS test• Simulink• Evaluate and iterate
model, controller, field switching
15
![Page 16: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/16.jpg)
Imaging - Current Issues• Preliminary interface tests performed
• Foam mount design
• Foam glued to the airplane, with camera mounted on foam center in bracket
• Camera dome?• With the addition of the foam mount and a possible lens, the
camera may extend beneath the underside of the wing.
• Testing• Data handling• Flight
16
![Page 17: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/17.jpg)
Integration & Test Plan
1717
![Page 18: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/18.jpg)
Integration & Test Overview
• Integration Plan• Test List• Testing Conditions• Completed Testing• Future Testing
18
![Page 19: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/19.jpg)
Systems Integration and ValidationIntegration and Testing Progression
Level 1: Isolated Component TestingPerformance verification of individual components
Level 2: Subsystems Integration and TestingAircraft, Control System (slave vehicle), Imaging, Communications
Level 3: Systems Integration and TestingTest systems functionality
Level 4: System Validation and VerificationValidate integrated system performance and verify mission objectives met
Subsystems IntegrationIntegrate isolated components into relevant subsystems
Systems IntegrationIntegrate individual subsystems into complete system
Integrated System ValidationValidate complete integrated system performance
1919
![Page 20: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/20.jpg)
Systems Integration Flow ChartAircraft
-Slave avionics/propulsion-Slave battery discharge
-Slave stability-Master/Slave flight test
Communications-Master/slave comm. link verification-Ground station com. link verification-Verify GUI display
Autopilot-Particle vector field sim.-Simulink vector field simulation (Stryker)-Simulink vector field simulation (Miglet)-Autonomous control flight test (Miglet)
Imaging-High frequency motor vibration-Verify camera resolution-Rotational blur test-Camera data output rate-Camera JPEG compression pixel error
Autopilot-Generate target vector fields -Command of elevon servos-Instruct camera to take image-Receive image data from camera and pass to comm. link
Aircraft-Slave controllability (RC from ground)-Master flight capability with slaves-Slave deployment (simulated)
Communications-Verify air-to-air/ air-to-ground comm. links-Verify transceiver ranges-Determine bit error in data transmission -Determine data transmission times
Imaging-Take image per autopilot instruction-Compress image to JPEG-Pass image to slave transceiver
Aircraft/Comm.-Ground station to master comm. link -Master to ground station comm. -Slave to master comm. link
Aircraft/Comm./Autopilot
-GPS coordinate received by autopilot (Zigbee radio)
Aircraft/Comm./Autopilot/Imaging
-Autopilot instructs camera to capture image-Camera compresses image and passes to autopilot (RS232-to-Zig-bee) -Image relayed to master
Aircraft-3 targets imaged in under 8 -99% probability of detection
Communications-Image data received by GUI within 2 sec of time captured
Autopilot-3 target locations navigated to and over flown with 99% probability of detection
Imaging-Image 3 targets - Images have sufficient resolution that a human can discern 1 x 0.5 x 1.5m object
Time
Level 1: Component Testing
Level 2: Subsystems Integration
Level 3: Systems Integration
Level 4: System verification
2020
![Page 21: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/21.jpg)
Major Test List• System Level
• Mission Profile• System Communications Test
• Major Component Level• Ground Station Operations Test• Slave Vehicle Operations Test• Master Vehicle Operations Test
• Subsystem Level• Ground Communications Test• Autopilot Verification• Ground Station Software Verification• Aircraft Oscillation Test
• Individual Components Level• *Battery Discharge Tests• *High Frequency Imaging Verification• Low Frequency Imaging Verification• *Autopilot Particle Simulation• GPS Positioning Verification• *Image Resolution Test• Miglet Simulink Test• Master Transceiver Tests• Slave Transceiver Tests• Camera Interface Test• Master Power Tests * Completed Testing 21
![Page 22: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/22.jpg)
General Battery Discharge Tests
Controls Autopilot Particle Simulation GPS Positioning Verification Miglet Simulink Test
Imaging Slave Camera Interface Test Image Resolution Test
Communications Master Long-Range Radio Range Test Master Long-Range Radio BER (Bit Error Rate) Test Master Long-Range Radio Throughput Test Master Communications PCB Power Test Slave Short-Range Transceiver Range Test Slave Short-Range Transceiver BER (Bit Error Rate) Test Slave Short-Range Transceiver Throughput Test
22
Level 1: Component Testing
![Page 23: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/23.jpg)
Level 2: Subsystems Testing
2323
Ground Station Software/Hardware Communications Verification Software displays images Software communications with transceiver and transmits commands
Master Interface to transceiver
Slave/Autopilot Verification Navigation to pre-programmed GPS coordinates Generation of target vector field Altitude hold Interface to transceiver
Ground Station Master Vehicle Slave Vehicle
800 kbps 250 kbps
Camera Module
MCU
115 kbps
Radio 1
250 kbps
MCU
Radio 2Radio 3
250 kbps800 kbps
Graphical User Interface
MCU
250 kbps
Radio 4
800 kbps
Major Subsystems
![Page 24: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/24.jpg)
Level 3: Integrated System ValidationGround/ Master Ground station to master comm. link
Ground station sends GPS coordinate to master/ master receives GPS coordinate Master to ground station comm.
Master sends picture and telemetry data to ground station and
Master/Slave Master sends GPS coordinate and is received by slave Slave sends picture and telemetry data to master
Slave/Autopilot GPS coordinate received by autopilot (ZigBee)
Autopilot generates flight path and target vector fields Autopilot communicates with elevons and ESC to actively control slave to follow flight path
Autopilot/Camera Autopilot instructs camera to capture image Camera compresses image and passes to autopilot (RS232-to-Zig-bee) Image relayed to master
2424
![Page 25: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/25.jpg)
Level 4: System Requirements Verification
Aircraft 3 targets imaged in under 8 minutes from acquisition of first GPS coordinate
99% probability of detection (Johnson Criteria)
Communications Image and telemetry data received by GUI within 2 sec of time captured
Autopilot 3 target locations navigated to and over flown with 99% probability of detection (Johnson Criteria)
< 15 degree heading error at time of imaging< +/- 6 m deviation from intended altitude< +/- 5 m/s derivation from intended flight speed at time of imaging
Imaging Image 3 targets each with 99% probability of detection (Johnson Criteria) Images have sufficient resolution that a human can discern 1 x 0.5 x 1.5m object
2525
![Page 26: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/26.jpg)
Outdoor Testing Conditions• Duration
• 64-80 hours to completion• 16 hours of testing
• Locations• Table Mountain RC Field• Arvada Associated Modelers (AAM)
• Environmental Conditions• Snow Reduction• Temperatures above 0°C• Low Wind Conditions (Less than 15
mph)
AAM Site26
![Page 27: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/27.jpg)
Critical Testing: Camera Jitter• Test performed again with the aid of low density foam for vibration
damping.• Tests with foam added show decreased blur
• 30% Reduction on “Long Grid” Axis• 60% Reduction on “Vertical Grid” Axis
• Blur will not be an issue during mission profile
No Foam Test
Foam Test – Blur Reduced
27
![Page 28: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/28.jpg)
Future Testing
Test Duration Location
Miglet Simulink Test 4 hours ITLL
Image Resolution Test 1 hour ITLL
GPS Positioning Verification 1 hour E Center
Autopilot Particle Simulation 2 hours ITLL
Low Frequency Imaging Verification 5 hours ITLL
Battery Discharge Test 1 hour ITLL
Aircraft Oscillation Test 1 hour ITLL
Ground Station Software Verification 2 hours E Center
Autopilot Verification 4 hours Arvada AssociatedModelers RC Field
Ground Communications Test 2 hours Arvada AssociatedModelers RC Field
System Communications Test 4 hours Table Mountain RC field
Mission Profile 5 hours Table Mountain RC field
28
![Page 29: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/29.jpg)
Budget Progress
29
![Page 30: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/30.jpg)
BudgetCategory Name/Item Description Unit Price ($) # Total Cost ($) Purchased # Total Price
VehiclesMaster Airframe - Piper Cub 200.00 2 400.00
Slave Airframe - Miglet 180.00 3 540.00 11/3/2006 2 $ 300.00
RC Equipment RC Radio (6-Ch) 180.00 1 180.00 11/3/2006 1 $ 180.00
Micro Servo 15.00 8 120.00 11/3/2006 2 $ 159.99
Receiver 60.00 3 180.00 11/3/2006 1 $ 60.00
Battery 60.00 3 180.00 11/4/2006 2 $ 79.98
Battery Charger 100.00 1 100.00 11/3/2006 2 $ 72.96
Electronic Speed Control 40.00 2 80.00 11/3/2006 1 $ 40.00
Motor 40.00 3 120.00
Electronics CU Autopilot 500.00 2 1,000.00 12/10/2006 1 $ 500.00
Microcontroller Unit 20.00 3 60.00
GPS Receiver 75.00 1 75.00
PCB Manufacturing 100.00 3 300.00
Misc. IC's 50.00 1 50.00
Communications Development Kit ZigBee 220.00 1 220.00 1/5/2007 1 $ 220.00
Development Kit Aerocomm 200.00 1 200.00 1 $ 200.00
Comm modules 90.00 3 270.00 1/23/2007 1 $ 110.00
Imaging Camera 100.00 3 300.00 11/3/2006 1 $ 100.00
Subtotal $4,375.00 Total $ 2,022.93
Total with 25% Margin $5,468.75 Total Left $ 3,877.07 30
![Page 31: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/31.jpg)
Schedule Progress
31
![Page 32: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/32.jpg)
Schedule Overview
32
![Page 33: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/33.jpg)
Schedule Progress
• On-time Progress & Developments:• Camera interfacing • Vector field simulation• Transceiver testing
• Set-backs• Manual Test Flights
• Cause: Weather• Fall-back: Simulators
• Communications Development Board Procurement• Cause: Product backorder/2 week lead time• Fall-back: Continue other subsystems
• PCB Procurement• Cause: Ensuring no issues with RF interference• Fall-back: Testing software using manual wiring
33
![Page 34: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/34.jpg)
Appendix
34
![Page 35: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/35.jpg)
Appendix: Schedule 1
35
![Page 36: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/36.jpg)
Appendix: Schedule 2
36
![Page 37: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/37.jpg)
Appendix: Schedule 3
37
![Page 38: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/38.jpg)
Appendix: Wiring Diagram - Master
38
![Page 39: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/39.jpg)
Appendix: Wiring Diagram - Slave
39
![Page 40: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/40.jpg)
Critical Testing: Camera Jitter (Pre-CDR)
40
• Image blur/distortion due to engine jitter and vibrations is unpredictable and must be tested
• High-frequency (kHz range) vibrations cause CCD to move while rows of pixels are read – resulting image gets shifted between row reads
• Further testing required - attempt to damp out vibrations
Engine OFF
Engine ON, 80% Throttle Engine ON, Camera Rotated 90°
CCDScan Direction
Current Read Row
Camera Movement Direction
Blur – Shutter too slow:
Rolling Shutter Distortion:
Fast Global Shutter:
[1] Electronic Shuttering for High-Speed CMOS. - Dalsa Corp. 40
![Page 41: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/41.jpg)
Critical Testing: Power System (Pre-CDR)• Wingless ducted fan tested at 56mph (manufacturer’s optimal speed) in
the wind tunnel to simulated actual load conditions
• Measured battery discharge voltage and current• ElectriFly: 3 Li-Polymer Cells• 11.1 Volts• 910 mAhr• Ran for 5.5 minutes
• Larger capacity battery required
41
Battery CapacityMass
(g)Volume
(mm)
ElictriFlyGPMP0815
910 mAh 79 20 x 34 x 62
Pro LiteTP20003
2000 mAh
12019 x 47.6 x
63.5
Stock Battery vs. Higher Capacity Battery
41
![Page 42: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/42.jpg)
Critical Testing: Camera Resolution (Pre-CDR)
• JPEG compression might cause loss of effective camera resolution: must be verified experimentally
• Resolution test pattern used to verify actual resolution• Test indicates no noticeable loss in camera resolution• Camera meets design-to specification of >300 lines
42
Lines become indistinguishable at approximately 400 lines of resolution marker
42
![Page 43: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/43.jpg)
Appendix: Camera Choice
43
![Page 44: Arseny Dolgov Nick Driver Galina Dvorkina Kevin Eberhart Matt Edwards Johnny Jannetto Eric Kohut John Shelton Interim Review #1 ASEN 4028: Senior Projects.](https://reader035.fdocuments.us/reader035/viewer/2022081513/56649f555503460f94c790e2/html5/thumbnails/44.jpg)
Aircraft- Outstanding IssuesIssues:
• Current inability of group members to effectively pilot slave vehicle• Determination of approximate roll/pitch angles and rates at which
slave vehicle looses GPS downlink• Insufficient time and experience to build Sig. Rascal
Resolutions:• Utilize experienced RC pilot (James Mack) to assist group in piloting
slave vehicle• Visual inspection of telemetry of slave vehicle to determine maximum
allowable turning angles and rates at which GPS signal is retained• Substitute Hobby Zone Super Cub RTF for Sig Rascal
44