ARIES -ST Study L. Waganer 4 December 1998 Page 1 Revised TF Coil Costing Cost Assessment Changes...
-
Upload
julianna-mitchell -
Category
Documents
-
view
216 -
download
2
description
Transcript of ARIES -ST Study L. Waganer 4 December 1998 Page 1 Revised TF Coil Costing Cost Assessment Changes...
ARIES -ST Study
L. Waganer4 December 1998
Page 1
Revised TF Coil Costing
Cost Assessment Changes• Revised Weights Adjusted to 11/98 Strawman CAD Baseline
– 0.5 m Thick on Mid-Plane, Can Estimate 0.7-m Case When Available
• Increased Material Wastage to 5% on Both Cu and Al• Obtained Raw Material Quotes - Increment above LME Prices
– Suitable Alloys Available with Low Percentages of Adverse Elements– On-Site Recycle of Copper Does Not Seem Practical - Sell to Recyclers
• Included Fabrication Hardware Cost in Estimate– Al : Furnaces, Transfer Pumps, Heated Piping, Atomizing Heads– Cu: Powder Storage, Transport System, Positioning System, Melting Heads
• Estimated Energy Cost to Heat and Melt Metals• Reduced Number of Alum. Spray Casting Heads to Slow Rate
– Reduced Capital Costs More Than Offsets Longer Fabrication Time (6 Mo.)
• Added Costs for Contingency (20%) and Fee (12%)
ARIES -ST Study
L. Waganer4 December 1998
Page 2
Revised TF Coil Costing
Baseline TF Coil Configuration• Centerpost Is Now Inverted
with Large End Down– Weighs 0.85 x Mkg, 85% Cu– 20% Higher Weight
• Outer Shell Has Three Parts– For 0.5 m Midplane Thick Shell
• Upper:1.558 Mkg, 85% Al• Middle: 0.584 Mkg, 85% Al• Lower:0.548 Mkg, 85% Al• Total Weight (2.69 Mkg) is 6% lower
– Lower Shell Components May Be Fabricated Upside Down and Inverted For Installation
– Large Component Weights Complicate Handling and Installation
ARIES -ST Study
L. Waganer4 December 1998
Page 3
Revised TF Coil Costing
Laser or Plasma Arc Forming• A laser or plasma-arc deposits a layer of
metal (from powder) on a blank to begin the material buildup
• The laser head is directed to lay down the material in accordance with a CAD part specification
Beam and PowderInteraction Region
Z-Axis Positioningof Focusing Lensand Nozzle
High PowerLaser
PowderDeliveryNozzle
PositioningTable
PreformFormed Part
Schematic of Laser Forming Process
AeroMet has produced a variety of titanium parts as seen in attached photo. Some are in as-built condition and others machined to final shape. Also see Penn State for additional information.
ARIES -ST Study
L. Waganer4 December 1998
Page 4
Revised TF Coil Costing
Good Material Properties Can Be ObtainedFatigue testing performed on laser formed Ti-6Al-4V, showing performance at the low end of wrought material. Plotted against standard axial fatigue zones of cast and wrought Ti-6Al-4V, Ref Aeromet and DARPA.
ARIES -ST Study
L. Waganer4 December 1998
Page 5
Revised TF Coil Costing
Laser Forming Can EasilyFabricate Simple Passive Cooling Systems
Cool Water Descends to Bottom of Centerpost in Central Passage, Moves Radially Outward to the Risers in Which the Water Is Heated and Rises to Passive Heat Sink
ARIES -ST Study
L. Waganer4 December 1998
Page 6
Revised TF Coil Costing
Forming Centerpost with Laser or Plasma Arc Offers Design Flexibility
Water Content= Approximately 14%
Slots vary from0.4 cm to 2 cm
Holes with Graded Spacing 15% Water Content
Slots with Graded Widths and Lengths
For Background Information, See Centerpost Cooling Options
ARIES -ST Study
L. Waganer4 December 1998
Page 7
Revised TF Coil Costing
Summary of Centerpost Costs• Mass of centerpost with holes 851,000 kg• Including wastage of 5% 894,000 kg• Deposition rate with multiple heads 200 kg/h• Build labor, 24-h operation, 1 operator + 0.5 assistant 6702 h• Inspection and rework 1676 h• Total labor hours 8628 h• Labor cost @ $150/h (including overtime and site premium) $1,294,000• Material cost, $2.86/kg (copper) $2,556,000• Energy cost (20% efficiency) for elapsed time + 30% rework $93,000• Material handling and storage $75,000• Postitioning systems $435,000• Melting and forming heads and power supplies $600,000• Inert atmosphere system $44,000• Process computer system $25,000• Subtotal cost of centerpost $5,122,000• Contingency (20%) $1,024,000• Prime Contractor Fee (12%) $738,000• Total centerpost cost $6,884,000• Unit cost (finished mass = 704,000 kg) $8.09/kg
(~ 6 mo)
Note: New items are green , increased values are red
ARIES -ST Study
L. Waganer4 December 1998
Page 8
Revised TF Coil Costing
Aluminum TF Return Shell • TF shell has three parts• Spray Cast preform will be vacuum vessel • Vacuum vessel will be 0.5” aluminum plate, 5052
or 5002 for low resistance and ease of welding• Remainder of VV shell thickness (0.5 to 2.5 m)
will be spray cast to final shape and thickness• Stainless steel coolant tubes will be embedded in
spray cast material• Flanges and other features can be spray cast
(not costed yet)
ARIES -ST Study
L. Waganer4 December 1998
Page 9
Revised TF Coil Costing
Aluminum TF VV Cost AnalysisContingency and Fee Added
• Mass of 1/2”-thick plates, incl. wastage 41,765 kg• Material cost: $5/kg $208,825• Bump forming: 90 panels x 60 h/panel 5400 h• On-site weld setup: 6 mo x 6 people x 160/mo 5760 h• Weld prep: 90 panels x 2 h/m + setup(10 h/panel) 4776 h• Segment welding: 900 m x 0.13 h/m ÷ 25% efficiency 472 h• Weld inspection: 900 m x 1 h/m 900 h• He leak check: 900 m x 0.5 h/m 450 h• Final cleaning for vacuum service 1500 h• Total labor hours 19,258 h• Labor cost @ $120/h (including site premium) $2,310,960• Subtotal $2,519,785• Contingency (20%) $503,957• Prime contractor fee (12%) $362,849• Total cost of vacuum vessel $3,386,591• Unit cost (finished mass = 39,776 kg) $85.15/kg
2-3 yrselaspedtime
ARIES -ST Study
L. Waganer4 December 1998
Page 10
Revised TF Coil Costing
Schematic of Spray Casting Process
Support Table
T-Bars orSows
MeltingFurnace
HoldingFurnace
LowPressureTransferPump
Track-MountedSpray Robot
w/High PressurePump (1 of 4)
CoverGas Shield
LaunderDistribution
Pump
AnodeUpperShell
Molten Metal Furnace, Courtesy ofSECO/WARWICK, Inc
ARIES -ST Study
L. Waganer4 December 1998
Page 11
Revised TF Coil Costing
TF Return Shell Cost Development• Spray cast aluminum is cooled with room temperature
water, flowing through embedded SS coolant tubes• Part is assumed to be 85% aluminum, 15% coolant• Flanges and fittings not included, but additional cost
would be minimal• Part will be fabricated on site• Cost is 10th of a kind, 1998$, fabrication hardware
cost included • Upper shell built in place• Middle and lower shells built upside down, inverted,
and moved to Power Core area
ARIES -ST Study
L. Waganer4 December 1998
Page 12
Revised TF Coil Costing
Spray Cast Shell Cost Analysis• Mass of three shell components 2,690,000 kg • Including wastage of 5 % 2,820,000 kg• Deposition rate per head (4 heads used) 0.5 kg/s• Build labor, 1 operator+ 1 assistant/inspector, 50% efficiency 1569 h• Inspection and rework 400 h• Total labor hours 2089 h• Labor cost @ $150/h incl. site premium $313,375• Material cost, $1.87/kg (aluminum) + tubes $5,281,815 • Energy cost, natural gas + pump electrical $37,398 or $37,398• Melting and handling furnaces incl installation $2,650,000 $985,000• Other fabrication hardware $1,379,000 $1,379,000• Subtotal $9,715,588 $8,046,588• Contingency (20%) $1,942,318 $1,609,318• Prime Contractor Fee (12%) $1,398,469 $1,158,709• Total cost of spray cast shell $13,052,375 $10,814,615• Unit cost (finished mass = 2,020,000 kg) $4.85/kg $4.02/kg
Note: New items are green, changed values are red
Seco/Warwick Schaefer
ARIES -ST Study
L. Waganer4 December 1998
Page 13
Revised TF Coil Costing
TF Coil Cost SummaryComponent Finished MassTotal CostUnit Cost
Cu Centerpost 0.851 Mkg $6.88 M $8.09
TF Vacuum Vessel 0.040 Mkg $3.39 M $85.15
Al Spray Cast Shell 2.690 Mkg $11.93 M (average) $4.44
TF Coil System 3.581 Mkg $22.20 M (average) $6.20
(minimum) $5.89
(maximum) $6.51
Recommend using low-cost, automated fabrication technique for Centerpost and TF Return Shell with supporting costs.